Manual For Consulting Service

This document provides guidance on the procurement process for trail bridge construction projects. It outlines six sections: 1) procurement planning which involves cost estimates, implementation packages, and engineering services, 2) selection of procurement methods such as community-based or open bidding processes, 3) bidding procedures including standard documents, invitation for bids, and bid submission, 4) bid evaluation procedures to determine the lowest bidder, 5) contract management procedures including performance security, commencement, payments, disputes, and record keeping, and 6) service charges for consulting services provided. The overall purpose is to provide a standardized process for procuring engineering consulting services for trail bridge construction projects.

Uploaded by

Bipin Gyawali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views

Manual For Consulting Service

This document provides guidance on the procurement process for trail bridge construction projects. It outlines six sections: 1) procurement planning which involves cost estimates, implementation packages, and engineering services, 2) selection of procurement methods such as community-based or open bidding processes, 3) bidding procedures including standard documents, invitation for bids, and bid submission, 4) bid evaluation procedures to determine the lowest bidder, 5) contract management procedures including performance security, commencement, payments, disputes, and record keeping, and 6) service charges for consulting services provided. The overall purpose is to provide a standardized process for procuring engineering consulting services for trail bridge construction projects.

Uploaded by

Bipin Gyawali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 26

Trail Bridge Construction Manual for Consultants

Table of Contents:

SECTION-I: PROCUREMENT PLANNING ................................................. 3


1. District Development Plan ........................................................................................... 3
2. Annual Procurement Plan ............................................................................................ 3
3. Cost Estimate ............................................................................................................... 4
4. Implementation and Contract Packages ....................................................................... 4
4.1 Implementation of Long Span Trail Bridge (LSTB) ..................................................... 4
4.2 Implementation of Short Span Trail Bridge (SSTB) ..................................................... 4
5. Engineering Package [EP]............................................................................................ 4
SECTION-II: PROCUREMENT METHODS................................................. 5
6. Selection of Procurement Method ................................................................................ 5
6.1 Community Based Procurement Method ....................................................................... 5
6.2 Open Bid Method for Engineering Services .................................................................. 5
6.2.1 Socio-economic and Technical Feasibility Study Package .............................................. 5
6.2.2 Detailed Engineering Survey & Detailed Design Package .............................................. 5
6.2.3 Construction Supervision & Quality Control Package .................................................... 6
6.2.4 Third Party Technical Audit............................................................................................. 6

SECTION-III: BIDDING PROCEDURES ..................................................... 7


7. Bidding Procedures ...................................................................................................... 7
7.1 Tender Packages ............................................................................................................ 7
7.2 Contract Limits and Re-Bidding .................................................................................... 7
7.3 Two Envelop System ..................................................................................................... 8
7.4 Preparation of Standard Bidding Documents (SBDs) ................................................... 8
7.4.1 Instruction to Bidders (ITB) ............................................................................................. 8
7.4.2 Bidding Data Sheet (BDS) ............................................................................................... 9
7.4.3 General Conditions of Contract (GCC) ........................................................................... 9
7.4.4 Special Conditions of Contract (SCC) ............................................................................. 9
7.5 Invitation for Bid (IFB) ............................................................................................... 10
7.6 Distribution of Standard Bidding Documents ............................................................. 10
7.7 Pre-bid Conference & Site Visits ................................................................................ 10
7.8 Preparation and Submission of Bid ............................................................................. 11
8. Bid-Validity Period .................................................................................................... 11
SECTION-IV: BID EVALUATION ............................................................ 12
9. Bid Evaluation ............................................................................................................ 12
9.1 Confidentiality of Procedures ...................................................................................... 12
9.2 Clarifications of Bids ................................................................................................... 12
9.3 Rejection of Bids ......................................................................................................... 12
9.4 Extension of Bid Validity Period ................................................................................. 12
9.5 Reception of Bids ........................................................................................................ 12
9.6 Bid Evaluation Committee .......................................................................................... 13
9.7 Bid Evaluation Procedure ............................................................................................ 13
9.8 Collection of Information ............................................................................................ 13
9.8.1 Basic Data ................................................................................................................. 13
9.8.2 Public Bid Opening ........................................................................................................ 13

Procurement of Consulting Service (EP) Page - 1


Manual for Consultants Trail Bridge Construction

9.9 Preliminary Examination for Completeness of Bids ................................................... 14


9.9.1 Determination of Responsiveness of Bids ...................................................................... 15
9.9.2 Clarification of Bids ....................................................................................................... 15
9.9.3 Detailed Evaluation of Responsive Bids ........................................................................ 15
9.9.4 Evaluation of Financial Proposal ................................................................................. 15
9.9.5 Determination of Lowest Evaluated Responsive Bid...................................................... 15
9.9.6 Confidentiality of Bid Evaluation ................................................................................... 15

SECTION-V: CONTRACT MANAGEMENT ............................................. 22


10. Notification of Award ................................................................................................ 22
11. Performance Security ................................................................................................. 22
12. Contract Award .......................................................................................................... 22
12.1 Contract Limit.............................................................................................................. 22
12.2 Witness ........................................................................................................................ 22
13. The Services ............................................................................................................... 22
14. Commencement Date ................................................................................................. 22
15. Orientation.................................................................................................................. 22
16. Quality Monitoring .................................................................................................... 23
17. Checking of Engineering Package ............................................................................. 23
18. Payment Procedures ................................................................................................... 23
18.1 Advance ....................................................................................................................... 23
18.2 Payment ....................................................................................................................... 23
18.3 Place of Payment ......................................................................................................... 23
19. Notice of Delay .......................................................................................................... 23
20. Time Extension .......................................................................................................... 23
21. Penalties for Delay ..................................................................................................... 23
22. Evidence ..................................................................................................................... 23
23. Settlement of Dispute ................................................................................................. 23
24. Internal DDC Contract Management Procedure Table .............................................. 24
SECTION-VI: RECORD KEEPING REQUIREMENTS ............................. 24
25. Record Keeping Requirements .................................................................................. 24
SECTION-VII: SERVICE CHARGES ......................................................... 25
1. Service Charge For Consulting Services (Engineering Packages) ............................ 25
1.1 Socio-Economic and Technical Feasibility Study for LSTB ....................................... 25
1.2 Detailed Engineering Survey & Detailed Design for LSTB1 ...................................... 25
1.3 Construction Supervision and Quality Control for LSTB1 (CSQC) ........................... 26
1.4 Third Party Technical Audit for SSTB and LSTB1 (TPTA) ........................................ 26

2 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

SECTION-I: PROCUREMENT PLANNING


Contract management encompasses within it the management and implementation of all activities that are
concerned and related with contract in close coordination with the overall planning of District Development
Committee (DDC) such as acquiring and filing the necessary Bill of Quantities (BOQ), cost estimates and
other relevant documents and publication of bid notice, evaluation of bids, award of contract, signing of
contract agreement, issuing work order and monitoring work executed by the contractors etc. Furthermore,
the problems accruing during the contract administration have to be put forward to the management and
contribute actively towards its solution. As the contract management is incomplete without the quality
control/assurance, supervision of overall construction, coordination in personnel management and other
related activities should be within the scope of contract management.
The procedure to administer any type of contract for any type of work packages within and as defined by the
DDC’s Office, starts from the actual implementation plan or the construction execution in line with the set
target according to the overall planning of the DDC and ends when the final account with the Firm is settled,
the file closed with all the necessary documentation and forwarded for the audit.
Bidding procedures involves all the procedures and steps since the publication of bid notice until completion
of the contracted job and final settlement of account including final check, third party technical audit and
audit of books and account.

1. DISTRICT DEVELOPMENT PLAN


District Development plan for the procurement of Civil Works, Consulting Services and Goods in the district
should be prepared and approved as per Local Self Governance Act and its Regulations.
(1.1) For all Trail Bridges that have to construct, a procurement plan shall be prepared, and such plan
should outline following aspects:
a. Number of trail bridges (new construction and maintenance), that are to be constructed;
b. Slicing and packaging (i.e., list of individual contract packages) for Engineering Package
(EP), Fabrication Package (FP) and Construction Turnkey package (CTP);
c. the method of procurement – bid for Long Span Trail Bridge(LSTB) and through
community for Short Span Trail Bridge(SSTB) procurement scheduling for each package ,
i.e. time table for events such as date of Issue of Bidding SBDs, Opening of bids. Award
of contract Completion of works, etc.;
d. Identification of the critical path (i.e., the most important contract whose delay will affect
the scheduling of other contract packages.
(1.2) The procurement plan shall be updated periodically to reflect realities in the implementation.

2. ANNUAL PROCUREMENT PLAN


Annual Procurement Plan (APP) is the segregation of District Development Plan (DDP) for the procurement
of Civil Works, Consulting Services and Goods in the district. The annual procurement plan of Trail Bridges
should be made as per master or periodic plan of the district and should be prepared and approved as per
Local Self Governance Act (LSGA) and its Regulations.
Primary Considerations given to the annual procurement plan are as follows:

(2.1) DDC's Office shall plan procurement so that it is carried out within available financial resources and
other applicable limitations, and at the most favorable time, and, when possible, in bulk form so as
to achieve economies of scale in procurement.
(2.2) Prior to the commencement of the fiscal year, each DDC's Office shall prepare an Annual
Procurement Plan of the procurement that it intends to carry out during that year for the construction
of trail bridges. This plan shall be made in way that bridges are constructed in one construction
season. The Annual Procurement Plan shall include information on the:
a) types and quantities of the goods, works and services to be procured;
b) the timing of the procurement and the implementation of the related contracts;
c) an indication of possible packages of procurement, and their value;
(2.3) Procurement procedure for "Construction Turnkey Package" and Consultant for "Construction
Supervision and Quality Control" should be initiated in parallel and contract award should be made
simultaneously.
(2.4) As needed, the DDCs' Office shall periodically update and revise the annual procurement plan.

Procurement of Consulting Service (EP) Page - 3


Manual for Consultants Trail Bridge Construction

3. COST ESTIMATE
During the invitation of bids, the estimate amount shall be made apparent to the firms as per Local
Governance Financial Administration Regulations (LGFAR). However, the following considerations shall be
noted by the bidders in advance:
i. The amount thus mentioned is exclusive of the overhead costs.
ii. The estimated amount shall be considered only as a base line for the preparation of bid, its
costing, pricing and fixing the final “lump sum amount”.
iii. Firms intended to bid for EP are to visit the sites or to collect the first hand information
regarding the site condition and the same shall be reflected in their lump sum price of the bid
considering all possible inaccuracy and other risk factors.
iv. Any rates thus quoted and approved by the DDC's Office shall be binding upon both the
concerned parties, and any request for the change in such rates, whatsoever is the reason
shown by the Firm later on, shall not be entertained.

4. IMPLEMENTATION AND CONTRACT PACKAGES

4.1 Implementation of Long Span Trail Bridge (LSTB)


The LSTB construction program is implemented through private sector, i.e. consultants for engineering
works and contractor for bridge construction and erection works under construction turnkey package through
the following contract packages:
A. Engineering Package [EP]
B. Construction Turnkey Package1 [CTP]
The Engineering Packages are executed by the Engineering Consultants.
The Construction Turnkey Package is executed by the Contractor.

4.2 Implementation of Short Span Trail Bridge (SSTB)


A SSTB is basically a Community Bridge. The community initiates, mobilizes resources and manages the
construction of the bridge by forming a User’s Committee (refer to “Social Organizational Support Manual”).
The DDC nominates the NGO to support the communities to build SSTB bridges in the district. A detailed
engineering survey and detailed design of a SSTB is executed by a nominated NGO. The community
manages the construction of the bridge with social and technical support from the NGO. The DDC provides
the Foreign Materials, which are not available at or near the construction site to the communities. Foreign
Materials are steel wire ropes, steel parts, cement, G.I.Wire and tools. Steel wire ropes are procured centrally.
Other materials are procured by the DDC. The steel parts are procured under the Fabrication package [FP].
The [FP] is executed by the Fabricator.

5. ENGINEERING PACKAGE [EP]


Engineering packages may consist of one of the following at a time:

1. Socio-economic and Technical Feasibility Study (SETFS),


2. Detailed Engineering Survey & Detailed Design (DESDD),
3. Construction Supervision & Quality Control (CSQC),
4. Third Party Technical Audit (TPTA).

Except “Third Party Technical Audit”, all engineering packages are applicable only for LSTB.
In case of SSTB/Community Bridges, a nominated NGO shall provide the engineering and social support to
the community for construction of the said bridges from planning phase up to the construction phase.
“Third Party Technical Audit” is applicable for all bridges of the District, which includes both
SSTB/Community Bridges and LSTB.
The detail tasks and responsibilities of the above are given in the Terms of Reference (ToR) of respective
packages and Standard Bidding Documents (SBDs)2.

1
Refer to “Manual for Contractor –Trail Bridge Construction”
2
Refer to Bidding Document for EP.
4 - Page Procurement of Consulting Service (EP)
Trail Bridge Construction Manual for Consultants

SECTION-II: PROCUREMENT METHODS

6. SELECTION OF PROCUREMENT METHOD

6.1 Community Based Procurement Method


Short Span Trail bridge (SSTB) is basically a Community Bridge. So as per LFAR, community based
procurement method is applied for the construction of SSTB.
For detail refer to 4.2.

6.2 Open Bid Method for Engineering Services


A Open Bid system is necessary in order to short list capable consulting firms from among many bidders.
The objectives of the open bid are:

i. To avoid tenuous pre-qualification process;


ii. To discourage the cartel system between the Firms;
iii. To simplify the process both in terms of time and efficiency
iv. To promote professionalism regarding the bid and contract management for both concerned
parties.

This manual is prepared for the application of all open bid procedure only. Open bid method is applied
through the open invitation of bid for all eligible and qualified bidders concerned. The bidders can purchase
the SBDs without any restrictions from the DDC office and can make their bid within the stipulated time. In
order for sufficient number of firms to participate in the bidding process, an Invitation For Bid (IFB) shall be
made from eligible firms. Such invitation shall be made on the National Daily Newspaper with all the
necessary information.

The DDC's Office shall determine to its satisfaction whether the Bidder that is identified as having submitted
the lowest evaluated responsive bid is qualified to perform the contract satisfactorily, in accordance with the
criteria listed in Standard Bidding Documents (SBDs). The determination shall be based upon an
examination of the documentary evidence submitted by the Bidder in accordance with the requirements set
forth in the SBDs. Following packages are procured through open bid method as per LFAR.

6.2.1 Socio-economic and Technical Feasibility Study Package


The objectives of the present socio-economic and technical feasibility study are to investigate/acquire
data/information as per the set criteria for off the Main Trail LSTB bridges and Main Trail LSTB bridges
costlier than Rs. 8 million. In particular, the study will concentrate on following three areas :
• economic and social benefits after the bridge construction;
• technical feasibility to built a LSTB bridge; and
• existing, ongoing and planned development activities (construction of road, hydropower, etc.).

Detailed description of this package consists the works specified in the TOR of respective SBD.

Contract price is fixed on lump sum basis.

6.2.2 Detailed Engineering Survey & Detailed Design Package


The main objective of the assignment is to execute Detailed Engineering Survey and Detailed Design of
LSTB bridges.
• Desk study of maps, preliminary geological reports and other relevant documents,
• Geo-technical, hydrological investigation and site selection, topographic survey,
• Detailed design and Cost Estimate.
Detailed description of this package consists the works specified in TOR of the respective SBD.
Contract price is fixed on lump sum basis.
Procurement of Consulting Service (EP) Page - 5
Manual for Consultants Trail Bridge Construction

6.2.3 Construction Supervision & Quality Control Package

The scope of work includes conducting construction supervision and quality control of trail bridges to ensure
that quality of the constructed bridge, i.e., steel parts and its fixtures, construction material used, civil
structures and erection works meet stipulated design standards, technical norms and specifications according
to sound engineering practices and as per LSTB standard. The job of construction supervision and quality
control of trail bridges includes:

(a) to ascertain that smooth work flow is maintained by the Contractor/Fabricator according to schedule
as agreed in the Contract Agreement.

(b) to ascertain that construction materials of standard quality are used and meet specifications.
- to ascertain that works are regularly supervised on behalf of contractor / fabricator by the
persons as given in the technical proposal of contractor / fabricator or agreed during the signing
of contract agreement or as consented by the Employer.
- to ascertain that all items of work stipulated for the bridge construction are carried out as per
design, norms, specifications and standards.
- to ascertain and make available with recommendation to the EMPLOYER a listing of any
additional works and volume of work, not originally conceived, but necessary in order to make
the bridge safe in a long run, e.g. bank protection, retaining walls, drainage structures and
environmental works etc.
Detailed description of this package consists the works specified in TOR of the respective SBD.
Contract price is fixed on lump sum basis.

6.2.4 Third Party Technical Audit

The primary objective of conducting third party technical audit of all LSTB and SSTB bridges of the district
is to ensure the following:

• proper planning, prioritization and budget allocation,


• proper site selection,
• cost effective design,
• rational cost estimate,
• quality of completed bridges is as per design, norms, specifications and LSTB and SSTB
standards,
• actual cost of the bridge is realistic (not inflated),
• good governance, gender and equity.

Detailed description of this package consists the works specified in TOR of the respective SBD.

Contract price is fixed on lump sum basis.

6 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

S EC TION - II I: BIDD ING PR OCEDUR E S


7. BIDDING PROCEDURES
Bidding for all packages shall be done according to established practices, approved criteria and shall not
contradict with prevailing rules. Bids shall be invited in the lump sum basis for contract ignoring the detailed
bill of quantities of cost estimates. Bids shall be called from eligible and qualified consultants under Double
Envelopes System (DES) and contract shall be signed with the successful bidder for implementation.

Contract management encompasses within it the management and implementation of all activities that are
concerned and related with contract in close coordination with the overall planning of DDC, acquiring and
filing the necessary proposals and other relevant documents and publication of bid notice, evaluation of
SBDs, award of contract, signing of contract agreement, issuing work order and monitoring work executed
by the contractors etc. Furthermore, the problems accruing during the contract administration have to be put
forward to the management and contribute actively towards its solution. As the contract management is
incomplete without the quality control/assurance, supervision of overall construction, coordination in
personnel management and other related activities shall be within the scope of contract management.

The procedure to administer any type of contract for any type of work packages within and as defined by the
DDC’s Office, starts from the actual implementation plan or the construction execution in line with the set
target according to the overall planning of the DDC and ends when the final account with the Firm/s is
settled, the file closed with all the necessary documentation and forwarded for the audit.

Bidding procedures involves all the procedures and steps since the publication of bid notice until completion
of the contracted job and final settlement of account including final check, third party technical audit and
audit of books and account. Consulting Firms interested to bid shall fill in and provide all information
required of them as follows :

Envelope no. 1 should consist of :


• Technical Proposal with all forms duly filled
• Technical Proposal as required for the specific type of package consisting of:
- Company profile
- Recently signed Cvs of proposed personnel for the particular work
package
- Equipments
- Financial status
- Work program
- Firm’s Experience in the related field
• All Bid documents as required for the specific type of package

Envelope no. 2 should consist of :


• Financial Proposal

7.1 Tender Packages


The packages offered can be of any combination, that is, the package may consist of entirely new
construction projects or major maintenance projects or any combination of new construction and major
maintenance projects. However, effort shall be made to consider the spatial proximity, common travel route,
and the similar nature of work, while preparing a package.

7.2 Contract Limits and Re-Bidding


Irrespective of any aforementioned clauses or conditions, the number of packages that can be offered to any
one firm is limited to 3 in numbers of bridges in a single running fiscal year. However, this limitation does
not apply to Third Party Technical Audit. Third Party Technical Audit should cover all LSTB and SSTB
Community bridges of the district and shall be executed by a single Consultant under single Contract. Those
Consultants involved in the “Detailed Engineering Survey and Detailed Design” or Construction Supervision
and Quality Control” of the same bridge is not eligible to bid for “Third Party Technical Audit”

Procurement of Consulting Service (EP) Page - 7


Manual for Consultants Trail Bridge Construction

For the first time, if less than three firms bid or post qualified, the package shall be re-tendered without
opening the earlier financial proposals. In any case regarding the minimum number of bidders required for
opening up of financial proposals, the LFAR rules shall prevail.

7.3 Two Envelop System


In order to ensure a healthy competition between capable firms a bidding procedure with two envelopes, each
separately sealed envelope consisting of technical and financial proposal shall be followed in all packages of
engineering works.

 Envelope No. 1: Technical Proposal


On the opening date mentioned in the invitation of the bid, all technical proposals submitted
shall be opened with or without the presence of bidder's representative.

 Envelope No. 2: Financial Proposal


Financial proposal containing proposed price of post-qualified firms shall be opened with or
without the presence of bidder’s representative on the date fixed by the DDC’s Office
(generally within one week of opening up of envelope no. 1 - technical proposal and duly
communicated to the successful bidders by reliable means).

All sealed envelopes containing financial proposal of firms which are not post-qualified shall be returned
unopened to the respective firms upon their written request. The DDC’s Office shall analyze the data
submitted by firms, evaluate the responsive technical proposal of firms, and establish a short-list of post
qualified Firms (minimum 3 Firms) based on evaluation criteria for post qualification as per Bidding Data
Sheet of respective SBD. Only the firms whose technical proposal fulfill the minimum required score
according to the criteria shall be post qualified. In re-tenders, Local Financial Administration Rule (LFAR)
shall govern.

After post qualification and opening of financial proposal, lowest price evaluated shall be the basis for
contract implementation. However, and whenever required a negotiation can be held in case when all the
financial bids are in the opinion of the Employer unnecessarily higher than the estimate, first, to negotiate a
lower contract amount, second to identify why the bids were high (suggestions with authentic justifications
shall only be considered responsive).

7.4 Preparation of Standard Bidding Documents (SBDs)


The DDC's Office shall use one of the following SBDs for the type of procurement in question. These SBDs
are prepared by Trial Bridge Section (TBS) of DoLIDAR for the use of DDC's specially for the Trial Bridge
related procurement.

1) SBDs for the Procurement of Services for SETFS


2) SBDs for the Procurement of Services for DESDD
3) SBDs for the Procurement of Services for CSQC
4) SBDs for the Procurement of Services for TPTA

The information specific to the procurement in hand shall be inserted in the spaces provided in the brackets
and italics. Local Development Officer (LDO) prior to publication of the invitation for bid should approve
the completed SBDs along with the bid evaluation criteria.

7.4.1 Instruction to Bidders (ITB)


• This ITB section of the SBDs provides the information necessary for Bidders to prepare
responsive bids in accordance with the requirements of the Employer. It also gives much
information on bid submission, opening and evaluation, and award of Contract. So
Consultants are requested to follow the instructions on this section.

8 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

• Matters governing the performance of the Contractor, payments under the Contract, or
matters affecting the risks, rights and obligations of the parties under the Contract are not
normally included in this ITB Section, but rather under General Conditions of Contract
(GCC) and/or Special Conditions of Contract (SCC). If duplication of a subject is inevitable
in the different sections of the documents, care must be exercised to avoid contradiction
between clauses dealing with the same matter.

• These Instructions to Bidders will not be part of the Contract.

7.4.2 Bidding Data Sheet (BDS)


• Section III Bidding Data Sheet (BDS) consists of provisions that complement, supplement or
amend the provision of the Instruction to Bidders (ITB). Whenever there is a conflict the
provision herein shall prevail over those in ITB Clauses. So specify in detail information or
requirements included in this Section and which are specific to each procurement.

• These provisions shall prevail over the Clauses of the Instructions to Bidders.

• Instructions for completing the Bidding Data Sheet are provided, as needed, in the notes in
italics mentioning the relevant ITB Clauses.

7.4.3 General Conditions of Contract (GCC)


• The General Conditions of Contract, read in conjunction with the Special Condition of
Contract and other documents listed therein, should be a complete document expressing fairly
the rights and obligations of both parties.

• The use of General Conditions of Contract for building and civil works will promote
comprehensiveness of coverage, general acceptability of its provisions, savings in cost and
time in bid preparation and review, and the development of a solid background of legal case
histories.

• Matters governing the performance of the Consultant, payments under the Contract, or
matters affecting the risks, rights, and obligations of the parties under the Contract are
normally included in this section of General Conditions of Contract and/or Special
Conditions of Contract. If duplication of a subject is inevitable in the different sections of the
documents, care must be exercised to avoid contradiction between clauses dealing with the
same matter.

7.4.4 Special Conditions of Contract (SCC)


• This section of the SBDs provides the necessary provisions for contract .

• Special Condition of Contract consists of provisions that supplement, amend, or specify in


detail information or requirements included in General Condition of Contract and which are
specific to each procurement. The provisions of SCC that are specific to each procurement
can be used changing the provisions over GCC.

• Matters governing the performance of the Contractor, payments under the contract, or matters
affecting the risks, rights, and obligations of the parties under the contract are normally
included in this section.

• The Special Condition of Contract shall supplement the General Conditions of Contract.
Whenever there is a conflict, the provisions herein shall prevail over those in General
Conditions of Contract. The corresponding clause number in the General Conditions is
indicated in parentheses. Where sample provisions are furnished, they are only illustrative of
the provisions that the Employer should draft specifically for each procurement.

Procurement of Consulting Service (EP) Page - 9


Manual for Consultants Trail Bridge Construction

7.5 Invitation for Bid (IFB)


1) Invitation for bid shall be published in the national daily newspaper with all the necessary
information as per sample Invitation For Bid as specified in SBDs. Such an invitation to bid
shall be displayed at the office of the DDC's Office, the concerned District Administration
Office, Land Revenue Office, DDC, the District Treasury and Comptroller Office and at the
Office of construction enterprises or FNCCI; if any, at the head quarters of such district.

2) The IFB provides information that enables potential Bidders to decide whether to participate.
Apart from the essential items listed in the SBDs, the IFB should also indicate any important
Bid evaluation criteria (for example, the application of a margin of preference in Bid
evaluation) or qualification requirement (for example, a requirement for a minimum level of
experience in releavnt job).

3) The IFB should be incorporated into the SBDs. The information contained in the IFB must
conform to the SBDs and in particular to the relevant information in the Bidding Data Sheet.

7.6 Distribution of Standard Bidding Documents


1) Bidders are required to pay NRs................................for each package of these SBDs. In
response to a written request and payment of the cost and postage, the DDC's Office may
mail/courier the documents; however the DDC's Office shall not be responsible if the
documents are not received in time or not at all.

2) However, the competitive bidding is open to any Firm, the bidding document have clearly
disclosed the following eligibility requirements applicable to bidder in the procurement
proceedings, and the documentation required to prove conformity with those requirements.

• registered in HMG/N with valid License;


• Tax and VAT registration;
• Firms should be enlisted by Trail Bridge Section/DoLIDAR.
• at least previous experience of minimum three bridges successfully completed LSTB
type (former SBD type) bridges within last five years are eligible to apply individually.

3) However, to encourage the new comers to work and acquire the required experience, they can
bid for any such bid, but in a joint venture (JV) with any eligible firms. In case of a Joint
Venture (JV) or support from another firm, a JV agreement or a Memorandum of
Understanding (MOU) signed between the concerned parties shall be made available. The
leading firm shall be defined and it shall submit its letter of intent in consensus with other
firms, if there are any, along with the proposals.

4) The details of sale of SBDs and submission of the bid shall be recorded in a register
maintained for the purpose. After the expiry of the time for submission of the bids, the Local
Development Officer or office employee designated by him shall close the entries having
signed it. The account of the revenue obtained from the sale of bids be maintained and shall
be deposited in the bank account of District Development Fund (DDF).

7.7 Pre-bid Conference & Site Visits


1) The DDC's Office will organize a conference on the specified date and place in the bidding
document for the purpose of briefing bidders and taking their questions on the SBDs,
including the technical specifications and other requirements so as to allow bidders to take
the information they obtain at the conference into account in preparing their bids. Agenda for
pre-bid meeting shall be mainly:

• Bidding procedures,
• Terms of Reference,
• Other relevant information,
• Clarification, if any confusion to the bidders.

10 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

2) The DDC's Office shall prepare minutes of the meeting containing the questions submitted at
the meeting and its responses to those questions, without identifying the sources of the
questioner. The minutes shall be provided promptly to all bidders to which the DDC's Office
provided the SBDs, so as to enable those bidders to take the minutes into account in preparing
their bids.

3) The DDC's Office shall issue an amendment to the bidding document if the pre-bid
conference or other requests for clarification submitted in writing result in a modification of
any technical or commercial aspect of the SBDs. The amendment shall be mailed to all those
who purchased or received the SBDs.

4) The DDC's Office shall not arrange for site visits during or after the pre-bid conference,
bidders may arrange site visits at their own cost.

7.8 Preparation and Submission of Bid


(1) The invitation to bid shall provide bidders with a period of at least 30 days from the date of
publication to prepare and submit bids.

(2) Bids shall be submitted in only one place, in accordance with the instructions in the SBDs.

(3) The bidder shall submit the bid signed, and accompanied by a power of attorney, if so
required, and in a sealed envelope, as prescribed in the SBDs. Bidders shall submit their
technical and financial proposals enclosing both proposal separately in each envelope and
enclosed both envelope in a single envelope (two envelop system).

(4) The bidder shall have the option to submit the bid by post/mail, courier or personal delivery.
If the bid is delivered by hand, the DDC's Office shall provide a receipt showing the date and
time when its bid was received.

(5) Before the submission of Bid, Firms that are interested to bid shall check in and provide all
information required of them as follows :
 Technical Proposal of the Bid should consist of:
• Bid Form with all forms duly filled
• Technical Proposal as required for the specific type of package consisting of:
- Company profile
- Recently signed CVs of proposed personnel for the particular work package
- Equipments
- Financial status
- Work program
- Firm’s Experience in the related field
 Financial Proposal of the Bid should consist of:
• Financial proposal.

8. BID-VALIDITY PERIOD
The SBDs shall specify the bid-validity date. Such date shall be 90 days from the deadline of submission of
bids. The DDC's Office shall complete the examination, evaluation and comparison of bids and to obtain all
the necessary approvals of the proposed award within 90 days from bid opening date.

Procurement of Consulting Service (EP) Page - 11


Manual for Consultants Trail Bridge Construction

S EC TION - IV: BID EVA LUA TION


9. BID EVALUATION
The main purpose of bid evaluation is to determine the lowest evaluated bid among the bids submitted before
the bid closing time on the date specified in the SBDs. The lowest evaluated bid may or may not necessarily
be the lowest priced bid. In order to determine accurately the lowest evaluated bid in accordance with the
terms and conditions of the SBDs. Following principles and practices in bid evaluation must be clearly
understood and observed in the bid evaluation process:

9.1 Confidentiality of Procedures


After the public opening of bids, no information relating to the examination, clarification and evaluation of
bids, and recommendations concerning awards, shall be communicated to any person not officially concerned
with these procedures until the announcement of the award of the contract to the successful Bidder has been
made.

9.2 Clarifications of Bids


Clarifications, which do not change the substance or price of the bid, may be requested or accepted by DDC's
Office. The request for clarifications and the response by the Bidder shall be in writing or by fax (the term
"fax" is deemed to include electronic transmission such as facsimile, email, cable and telex). Any response
to an inquiry, which leads to a change in the bid price shall be considered as an alteration and shall not be
considered in the bid evaluation. The records of all clarifications sought and received must be kept.

9.3 Rejection of Bids


All valid bids received shall be evaluated in accordance with the terms and conditions of the SBDs and only
those bids which do not substantially meet the specifications or the bidding requirements may be rejected.

A bid received by the DDC's Office after the deadline for the submission of bids shall not be opened and
shall be returned to the bidder that submitted it after noting the date and time of arrival.

The rejection of all bids is justified when the bids submitted are not responsive or where none of the bids
received meets the specifications or where there is evidence of lack of competition or Where all bid prices
have exceeded by ten percent of the cost estimate. Where all bid prices have substantially exceeded the cost
estimate.

9.4 Extension of Bid Validity Period


The DDC's Office shall make every effort to complete bid evaluation and contract award before the
expiration of bid validity. The validity of bids may only be extended in exceptional circumstances. If, prior
to the expiry of the validity period of bids the DDC's Office feels that additional time will be required to
complete all steps and notify an award, it should request all responsive bidders to extend the validity by the
minimum period required to do so. Bidders who are willing to extend the validity of their bids shall not be
permitted to modify the substance or price of their bids. Extension of validity is a decision of the bidder. A
refusal to extend the bid-validity period shall not result in forfeiture of the bid security. Extension of the bid-
validity period shall, however, be subject to extension of the bid security if one was required in the first
place. Without such an extension of the bid security, a bid shall be deemed not extended.

9.5 Reception of Bids


(1) The DDC's Office shall receive bids and keep them in a secured manner that does not permit the
bids to be opened by accident or viewed and handed over to the bid opening committee at the bid
opening time.

(2) Prior to opening of bids, disclosure of the number of the bids received shall be made only to public
officials who as part of their official duties require that information.

12 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

9.6 Bid Evaluation Committee


Bidder’s Envelope containing Application Form, Technical Proposal and bid documents will be evaluated by
a committee consisting as per LFAR but including minimum of below listed personnel.

- DDC Engineer
- DDC Account Officer
- Representative of Donor Agency, if applicable

9.7 Bid Evaluation Procedure


Bids should be evaluated to determine the lowest evaluated bid in accordance with the terms, conditions and
specifications stipulated in the SBDs. Further, the evaluation procedure, will provide fairness to all Bidders
as it will produce a transparent, fair and accurate outcome of the bidding. There are four distinct stages in the
bid evaluation process, which should be followed in a logical sequence.

Following categories of tender packages are to be evaluated separately based on a set of criteria for each
category because of the different nature and kind of work involved in each package. It is intended to keep the
guideline for evaluation simple, relevant and easy. A standard criteria is set for evaluation of each package.
These criteria incorporate within them requirements for each said package in order to make a rational
selection of capable firm according to the Terms of Reference (ToR) of corresponding packages.

The entire job for a specific package shall be undertaken by a single firm (in case of JV, a leading Firm),
which shall be accountable for all the responsibility bestowed to them, and has to organize, manage and co-
ordinate all the activities included in any package by itself, a default on which shall entirely be accredited to
the firm’s account as a liability towards the Employer. In order to post-qualify for any package, a firm has to
acquire a minimum number of 70.

Considering the importance of study/engineering phase in any project cycle, the quality in this package is of
utmost importance. The quality depends on the performance of a team involved in the actual work. Thus the
emphasis is given to the experience of the proposed team of personnel in the technical proposal the
replacement for whom with personnel of higher competence can only be realized with approval from the
Employer.

9.8 Collection of Information

9.8.1 Basic Data


Before starting the actual evaluation it is necessary to collect all the key information pertaining to the bidding
so that it is readily available and the evaluation process is kept in proper perspective.

9.8.2 Public Bid Opening


(1) Bid opening shall follow immediately after the closing time for the submission of bids or
exceptionally very soon thereafter allowing time for logistics,
(2) Bids should be opened in the presence of bidders' authorized representatives who choose to attend at
the time, date and place specified in the SBDs.
(3) Bidders' and their authorized representatives alone shall be allowed to be present and shall sign the
record to ensure that the data have been read out and recorded correctly,
(4) Bids shall be segregate in a following manner:

(a) Late bids


(b) Modification envelope
(c) Withdrawal envelope
(d) Bids received in time

(5) Bids for which an acceptable notice of withdrawal has been submitted shall not be opened.
(6) All bids received prior to the deadline for submissions shall be opened.
(7) At the opening, the committee shall open first envelopes marked "Withdrawal" and "Modifications"
and all bids received prior to the deadline for submissions and read out the name and address of the
bidder, the bid price, discounts if any,

Procurement of Consulting Service (EP) Page - 13


Manual for Consultants Trail Bridge Construction

(8) Any other important infirmity noticed shall be announced and recorded in the minutes which shall
be signed by those present such as:

• discrepancy between figures and words,


• absence of signature, unsigned corrections,
• any other material deviation from the SBDs.

(9) The read out matter shall be circled.


(10) The committee shall prepare minutes (MUCHULKA) of the bid-opening proceeding, which shall
contain the information read out at the bid-opening and be signed by all those present.
(11) No decision as to the acceptance or rejection of any bid shall be taken or announced in the bid
opening session.

9.9 Preliminary Examination for Completeness of Bids


The purpose of this step is to examine whether the bids received were complete as required by the SBDs
before further detailed evaluation. The areas to be covered by the examination are:

Examination for Completeness of Bids

Completeness Name of Bidder


requirements Bidder 1 Bidder 2 Bidder 3 Bidder 4 Bidder 5 Bidder 6
Yes No Yes No Yes No Yes No Yes No Yes No
1. Bid form was
purchased from the
concerned DDC's office
2. The person or firm
submitting the bid
purchased the bid form
3. The bid is sealed
4. Bid documents are
properly signed by the
bidder or authorized
representative
5. A power of attorney for
the authorized persons
is submitted, if
authorized
representative has
signed the bid
6. Joint venture
agreements are
submitted, if joint
venture proposed
7. Documents establishing
the eligibility of
Bidders are furnished
7.1 Registered in HMG/N
with valid License
7.2 Tax and VAT
registration
7.3 Enlisted by Trail Bridge
Section/DoLIDAR
7.4 Previous experience of
minimum three bridges
within last five years

14 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

9.9.1 Determination of Responsiveness of Bids


The scrutiny of bids for responsiveness to the provisions of the SBDs is one of the most important aspects of
the evaluation of bids. If a bid fails to meet any of the above tests, it shall be rejected and excluded from
further consideration. Those bids that contain minor deviations or reservations, but that may be considered
responsive, shall be included in the detailed evaluation and comparison of bids.

9.9.2 Clarification of Bids


In the process of evaluation, Bidders may be requested to provide clarifications of their bids where such
clarifications are deemed necessary. Bidders are not permitted, however, to change the substance or price of
their bids. The records of all clarifications sought and received must be kept by DDC's office for bid
evaluation.

9.9.3 Detailed Evaluation of Responsive Bids


Following the preliminary examination of bids, the DDC's Office shall proceed to the detailed evaluation and
comparison of the bids that have not been rejected in the preliminary examination stage. In order to ensure
that a thorough check of the responsiveness of all bids is carried out, a Table of Responsiveness to Technical
Requirements should be prepared. The tables should list all major conditions for Technical Requirements,
which the Bidders must meet for their bids to be considered responsive. The responsiveness of each bid
received should then be checked against this list and its conformance to each item should be entered in the
tables. All bids must be checked for responsiveness to the technical requirements (evaluation criteria) of the
SBDs. Non conformance to technical requirements shall be justifiable grounds for rejection of a bid.
Technical Evaluation Format for post-qualification based on Technical Evaluation Criteria for all five type of
package separately and these format for Technical Evaluation are given in the Form No. 9.9.3.1, 9.9.3.2,
9.9.3.3 and 9.9.3.4.

9.9.4 Evaluation of Financial Proposal


The lowest evaluated bid shall be awarded the contract to execute the said work as per LFAR. The financial
evaluation of bids involves the determination of the cost to the DDC's Office of each bid so that it may select
the bid with the lowest cost, though not the lowest price. Such evaluation of each bid shall be carried solely
in accordance with the criteria and methodology disclosed in the SBDs.

For all tender packages of Consulting Services, the financial proposal shall be given weightage of 30%.
Financial evaluation of Firm shall be performed based on proposed bid prices submitted by the Firm. The
ranking based on the merit list of evaluated bid amount of the Firm shall be prepared on the basis of amount
quoted on the financial proposal and their evaluation. This might be helpful in two ways: first, to expedite a
further negotiation, if required, and second to invite the next on line bidder, in case the lowest bidder defaults
to enter into a legal agreement of the said contract. Financial evaluation format 9.9.4.1 to be filled after post-
qualification has been made based on financial proposal format to be submitted by bidders. It shall be
compatible with the lump sum amount quoted in financial proposal.

9.9.5 Determination of Lowest Evaluated Responsive Bid


After completing the above evaluation, and comparing the evaluated cost of each bid, the lowest evaluated
responsive bid shall be determined in accordance with the provisions of the SBDs in consideration of Final
(Technical and Financial Combined Weightage) Evaluation . The final evaluation (total score) is made giving
weightage to both technical and financial proposals as per following formula.

Total Score (Points) = Points on Technical Proposal x 0.7 +100 x 0.3 (Lowest Bid Amount / Bidder’s
Amount)

Final evaluation format 9.9.5.1 to be filled after post-qualification has been made based on technical proposal
and evaluation of financial proposal. The contract will be awarded to the Firm with highest total score.

9.9.6 Confidentiality of Bid Evaluation


Information relating to the examination, clarification, evaluation and comparison of bids shall not be
disclosed to bidders or to any other person not involved officially in the process or in the decision on which
bid should be accepted, except as provided in the LFAR.

Procurement of Consulting Service (EP) Page - 15


Manual for Consultants Trail Bridge Construction

9.9.3 TECHNICAL EVALUATION FORMAT FOR EP


9.9.3.1 Socio-Economic and Technical Feasibility Study

Bridge No. and Name:…………………………………………………………………………….

Points Firm (1) Firm (2) Firm (3) Firm (4) Firm (5) Firm (6) Firm (7) Firm (8)
Selection Factors for Evaluation min. max.
1 Personnel :
Team Leader (Coordinator) 5 10
Socio-Economist 13 15
Engineer Geologist 12 15
2 Equipments 7 10
3 Financial Status 8 10
4 Work Programme 5 10
Firm's Experience and
5 Performance 20 30
Total Points for Technical Proposal 70 100
Technical Ranking of Firm

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Name of Firm (6)
Name of Firm (7) Chief
Name of Firm (8) AO/DDC DDC's Office

16 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

9.9.3 TECHNICAL EVALUATION FORMAT FOR EP


9.9.3.2 Detailed Engineering Survey and Detailed Design

Bridge No. and Name:…………………………………………………………………………….

Points Firm (1) Firm (2) Firm (3) Firm (4) Firm (5) Firm (6) Firm (7) Firm (8)
Selection Factors for Evaluation min. max.
1 Personnel :
Team Leader (Coordinator) 5 10
Survey/Design Engineer
(Engineer Geologist) 18 20
Geologist (optional) 7 10
2 Equipments 7 10
3 Financial Status 8 10
4 Work Programme 5 10
Firm's Experience and
5 Performance 20 30
Total Points for Technical Proposal 70 100
Technical Ranking of Firm

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Name of Firm (6)
Name of Firm (7) Chief
Name of Firm (8) AO/DDC DDC's Office

Procurement of Consulting Service (EP) Page - 17


Manual for Consultants Trail Bridge Construction

9.9.3 TECHNICAL EVALUATION FORMAT FOR EP


9.9.3.3 Construction Supervision and Quality Control

Bridge No. and Name:…………………………………………………………………………….

Points Firm (1) Firm (2) Firm (3) Firm (4) Firm (5) Firm (6) Firm (7) Firm (8)
Selection Factors for Evaluation min. max.
1 Personnel :
Team Leader (Coordinator) 5 10
Quality Control Engineer (Civil) 25 30
2 Equipments 7 10
3 Financial Status 8 10
4 Work Programme 5 10
Firm's Experience and
5 Performance 20 30
Total Points for Technical Proposal 70 100
Technical Ranking of Firm

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Name of Firm (6)
Name of Firm (7) Chief
Name of Firm (8) AO/DDC DDC's Office

18 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

9.9.3 TECHNICAL EVALUATION FORMAT FOR EP


9.9.3.4 Third Party Technical Audit

* Bridge No. and Name:…………………………………………………………………………….

Points Firm (1) Firm (2) Firm (3) Firm (4) Firm (5) Firm (6) Firm (7) Firm (8)
Selection Factors for Evaluation min. max.
1 Personnel :
Team Leader (Coordinator) 5 10
Socio-Economist 12 15
Quality Control Engineer (Civil) 13 15
2 Equipments 7 10
3 Financial Status 8 10
4 Work Programme 5 10
Firm's Experience and
5 Performance 20 30
Total Points for Technical Proposal 70 100
Technical Ranking of Firm

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Name of Firm (6)
Name of Firm (7) Chief
Name of Firm (8) AO/DDC DDC's Office
* Attach list of bridges to be audited.

Procurement of Consulting Service (EP) Page - 19


Manual for Consultants Trail Bridge Construction

9.9.4 FINANCIAL EVALUATION FORMAT FOR EP (Engineering Package)


9.9.4.1 Description of EP* …………………………………………………….

S. Bridge Cost Firm (1) Firm (2) Firm (3) Firm (4) Firm (5)
N. No. Name Estimate Rs. Rs. Rs. Rs. Rs.

5
Sub-Total
Discount
Total

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Chief
AO/DDC DDC's Office
*Socio-Economic and Technical Feasibility Study/Detailed Engineering Survey and Detailed Design/Construction Supervision and Quality Control/Third Party Technical Audit.

20 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

9.9.5 FINAL EVALUATION FORMAT FOR EP (Engineering Package)


9.9.5.1 Description of EP** …………………………………………………….

S. Bridge Cost Firm (1) Firm (2) Firm (3) Firm (4) Firm (5)
N. No. Name Estimate Rs. T. Score* Rs. T. Score* Rs. T. Score* Rs. T. Score* Rs. T. Score*

5
Ranking as per merit

Name of Firms : Results : Remarks : Evaluated by : Approved by :


Name of Firm (1)
Name of Firm (2)
Name of Firm (3)
Name of Firm (4) DDC Engineer
Name of Firm (5)
Chief
AO/DDC DDC's Office

* Total Score = Points on Technical Proposal x 0.7 + 100 x 0.3 x (Lowest Bid Amount / Bidders Amount)
** Socio-Economic and Technical Feasibility Study/Detailed Engineering Survey and Detailed Design/Construction Supervision and Quality Control/Third Party Technical Audit.
** For Third Party Technical Audit attach list of bridges to be audited

Procurement of Consulting Service (EP) Page - 21


Manual for Consultants Trail Bridge Construction

SECTION-V: CONTRACT MANAGEMENT

10. NOTIFICATION OF AWARD


(1) Following the identification of the successful bidder the DDC's Office shall then provide
notification of award of the contract to the successful bidder in writing.

(2) Award of the contract shall be made within the validity period of the bid.

11. PERFORMANCE SECURITY


Performance security equivalent to 1% of contract amount shall be required. The performance security is to
be valid up to 6 months after the completion of the job. Initial validity period for performance security should
be minimum of 6 months.

12. CONTRACT AWARD


The successful bidder should be present within the time thus stipulated to enter into legal commitment by
signing an agreement. The Firm should provide the Employer with a performance security either in the form
of a Bank voucher of a deposit in the specified Bank A/C or in the form of a valid performance security
issued by an authorized Bank in favor of DDC’s Office,…… ……… prior to signing the agreement.

Upon submission of performance security by the Firm the office shall immediately process the document and
make arrangement for signing the Agreement. In the event of a failure of the bidder whose bid has been
accepted to sign a contract in accordance with the SBDs, to provide security for the performance of the
contract, the DDC's Office shall select a successful bid in accordance with the evaluation criteria set forth in
the SBDs from among the remaining bids that are in force.

12.1 Contract Limit


Irrespective of whatsoever have been said earlier, the number of contracts which can be offered to any one
Consultant is limited to 3 in numbers of bridges in one fiscal year, except for “Third Party Technical
Auditing”. Third Party Technical Auditing shall include all new and major maintenance bridges of the
district.

12.2 Witness
From DDC Office witness for Contract Agreement shall be DDC Engineer and the Account Office

13. THE SERVICES


The services for the packages described in Instruction to Bidder under these Contracts in accordance with the
Terms of Reference set forth in the respective SBDs shall be performed professionally and accurately by the
Firm.

14. COMMENCEMENT DATE


Services shall be commenced not later than seven days after the Employer notifies the Firm to proceed with
the work. On the contrary case, if the firm does not commence work within aforesaid time without any
reasonable cause, the contract may be terminated by the Employer.

15. ORIENTATION
An orientation program to the Firm, to whom job was awarded, shall be conducted by the Employer. The
main objectives of the orientation program shall be to brief the Firm about the Scope of Works and ToR,
methodology and quality requirements

22 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

16. QUALITY MONITORING


Over all quality monitoring of all engineering work packages has to be performed as per ToR of respective
engineering work and “Quality Control Manual for Trail Bridges”.

17. CHECKING OF ENGINEERING PACKAGE


Responsibility of checking and approval of Engineering Package lies with the DDC Engineer.

18. PAYMENT PROCEDURES

18.1 Advance
As the contract is comparatively small, no advance payment shall be made.

18.2 Payment
Payment for work done shall be according to the “Mode of Payment” as per “Condition of Contract” for each
package. Provision for advances shall be governed by the LFAR, accepted practice and the contract
documents.

18.3 Place of Payment


Payment for all contract packages shall be done at DDC Office.

19. NOTICE OF DELAY


In the event that the Firm encounters a delay in obtaining the required services and facilities set forth for the
provision of service, the Firm shall promptly notify the Employer of such delay with documentary evidence
and may request for time extension for completion of the project before expiry of the stipulated time.

20. TIME EXTENSION


Time extension will be granted according to prevailing fiscal rules of LFAR only if the reasons are
acceptable to Employer.

21. PENALTIES FOR DELAY


In case of reported delays in the performance of the service beyond the specified time of completion due to
Firm’s default, the penalty will be determined on the basis of prevailing LFAR.

22. EVIDENCE
Evidences regarding contractor and its representative’s presence at site all the time and photographs to
supplement the physical progress achieved have to be submitted to the Employer.

23. SETTLEMENT OF DISPUTE


Any dispute or difference arising out of the Contract which can not be amicably settled between the parties
shall be finally settled under the prevailing rules of arbitration and litigation in Nepal.

Procurement of Consulting Service (EP) Page - 23


Manual for Consultants Trail Bridge Construction

24. INTERNAL DDC CONTRACT MANAGEMENT PROCEDURE


TABLE

S. Job Bill Reporting Payment Approval Pay- Quality


N. type Sub- & Procedure of ment Control
mission Checking payment at
1. EP Firm DDC Account Chief, DDC’s DDC Engineer
Engineer Section DDC’s Office Office

SECTION-VI: RECORD KEEPING


REQUIREMENTS

25. RECORD KEEPING REQUIREMENTS

(1) DDC's Office shall open a special file for every procurement proceeding. All the documentation
relating to the proceeding such as the invitation to bid, decision of award, work take-over certificate
and any other information on the method of the Contractor or Supplier's completion of his
commitment shall be kept in the file. A contract file index shall be established for each contract file.

(2) Contract files shall include, at a minimum, the following documentation:

i. contract file index;


ii. invitation to bid,
iii. SBDs;
iv. requests for clarification and responses thereto, and record of circulation of responses to all
participating bidders;
v. minutes of pre-bid meeting with bidders
vi. minutes of bid opening;
vii. bids;
viii. bid evaluation report
ix. documentation of requests for and responses to clarifications of bids;
x. copies of notice of acceptance sent to winning bidder;
xi. procurement contract;
xii. minutes of Orientation meeting;
xiii. documentation related to contract implementation, including progress reports, invoices and
other documents such as inspection reports and any supporting documentation;
xiv. documentation related to change orders and contract modification ,if any;
xv. documentation related to inspections, acceptance and receiving, including any exercise of
the DDC's Office’s right to reject defective performance;
xvi. copies of all correspondence with the Consultant;
xvii. requests to subcontract and responses thereto; and the record of the procurement
proceedings, as well as all of the documentation referred to therein.

24 - Page Procurement of Consulting Service (EP)


Trail Bridge Construction Manual for Consultants

SECTION-VII: SERVICE CHARGES

1. SERVICE CHARGE FOR CONSULTING SERVICES


(ENGINEERING PACKAGES)
The Service Charges for Consulting Services is fixed as below.

1.1 Socio-Economic and Technical Feasibility Study for LSTB3

Personnel :
Socio-Economist 5 Man Days @ Rs…………… = …….…………… (1)
Engineer Geologist 5 Man Days @ Rs…………… = …….……….……(2)
Traveling :
Socio-Economist ……. Days @ Rs…………… = ……..……………(3)
Engineer Geologist ……. Days @ Rs…………… = ……..……………(4)

Sub Total (A=1+2+3+4) = ………………….(A)

Supporting Staff and Labour: 10% of Sub Total (A) =………………….(5)


Equipment and Stationary : 10% of Sub Total (A) =………………….(6)
Report Preparation : 10% of Sub Total (A) =………………….(7)
Sub Total (B=A+5+6+7) =………………….(B)
Overhead (15%) and VAT (…….%) of (B) =…………...…… (C)
Total (B+C) =…………………….
Transportation : As per actual
(Public Transport and by Air where road _______________
transport is not available)

1.2 Detailed Engineering Survey & Detailed Design for LSTB1

• Desk study
Personnel :
Engineer Geologist 3 Man Days @ Rs…………… = ………………… (1)

Detailed Geological Study and Survey


Personnel :
Civil Engineer 5 Man Days @ Rs…………… = …………………(2)
Engineer Geologist 4 Man Days @ Rs…………… = …………………(3)

Traveling :
Civil Engineer ……. Days @ Rs…………… = …………………(4)
Engineer Geologist …….. Days @ Rs…………… = …………………(5)

Sub Total (A=1+2+3+4+5) =………………….(A)


Supporting Staff and Labour: 20% of Sub Total (A) =………………….(6)
Equipment and Stationary : 10% of Sub Total (A) =………………….(7)
Report Preparation 10% of Sub Total (A) =………………….(8)
Sub Total (B=A+6+7+8) =…………….……(B)

3
LSTB = Long Span Trail Bridge

Procurement of Consulting Service (EP) Page - 25


Manual for Consultants Trail Bridge Construction

Detailed Design

Personnel :
Design Engineer 10 Man Days @ Rs… ……… = …………………(9)

Supporting Staff : 10 % of Sub Total (B) =…………..…….(10)


Equipment and Stationary : 10 % of Sub Total (B) =…………..…….(11)
Drawing and Report Preparation :20 % of Sub Total (B) =…………..…….(12)

Sub Total (C=B+9+10+11+12) =………………….(C)

Overhead (15%) and VAT (…….%) of (C) =…….……………(D)

Total (C+D) =…………………...

Transportation : As per actual


(Public Transport and by Air where road _______________
transport is not available)

1.3 Construction Supervision and Quality Control for LSTB1 (CSQC)


Consultant ‘s service charge per running
meter bridge span for “CSQC” service = 1.5 x NGO Service Charge4 per running
meter bridge span for technical support for
SSTB

1.4 Third Party Technical Audit for SSTB5 and LSTB1 (TPTA)
Consultant ‘s service charge per running
meter bridge span for “TPTA” service = 0.40 x NGO Service Charge4 per running
meter bridge span for technical support for
SSTB

4
Refer to website, www.nepaltrailbridges.org or Trail Bridge Section of MoLD/DoLIDAR
5
SSTB = Short Span Trail Bridge

26 - Page Procurement of Consulting Service (EP)