QSSW - 1 - Unit - 1
QSSW - 1 - Unit - 1
ESTIMATION - l
UNIT - l
Introduction to Subject
Purpose of Estimating
Data for Estimate
Accompaniments of an Estimate
Qualities of an Estimator
Spot Items
Contingencies
Prime cost & Provisional sums
Provisional Quantities
Extra items of work
Different types of Estimates their uses and characteristics
Schedule of Quantities.
Schedule of Rates and its uses.
Stages of work
Complete Estimate of a project.
Methods of taking out quantities.
Measurement sheet
Abstract sheet
Bill of Quantities.
Introduction to subject
Thus he needs to get a fair idea regarding the cost of the project
This subject has direct relation with other subjects like specification writing ,
professional practice , working drawing and Architectural design
In todays era client expects an all inclusive service from an Architect in which quantity
surveying and cost estimation play a vital role
To ascertain the necessary amount of money required by the owner to complete the
proposed work.
To ascertain quantities of materials required in order to programme their timely
procurement.
To calculate the no. of different categories of workers.
To fix up the completion period of work.
To invite Tenders & prepare bills for payment.
For Valuation
Data required for Estimate
Working Drawings with schedules of door , window etc
Specifications of materials
Unit of measurement
He should have ability to visualize three dimensional projects by looking at the drawing
Qualities of an Estimator
He should have ability to interpret the risks and then neutralize as much as possible
So that he can communicate his estimate in logical and clear presentation to the client
He should have ability to use the construction company’s job costing system
Qualities of an Estimator
Estimator should have ability to develop strategy for being successful in bidding and
negotiation phase of the project
Estimator should have ability to meet deadlines and still remains calm
The term ‘spot items’ refers to items of existing buildings that require alteration
and repair
In order for quantity surveyors to be able to price spot items, they need to be inspected
on site to gain an understanding of the extent of work that will be involved.
In a bill of quantities, the measurement unit will be stated as ‘Item’, although quantities
may be given if they are considered more appropriate.
Items that have quantities are generally much easier for an estimator to price.
Typically, spot items will be set out in progression from location to location in the
building, as this makes monitoring and estimating easier and clearer.
Contingencies
Contingencies refer to costs, and are amounts that are held in reserve to deal with
unforeseen circumstances.
It is a plan than can be enacted to mitigate project risks, such as adverse weather, an
industrial dispute, supplier failure and so on.
The percentage contingencies applied are at their greatest in the early stages of the
project when there are the greatest number of possible risks.
Prime cost and provisional sums
Prime Cost
The Architect prepares a bill of quantities based on the specifications of items which
have been decided by discussion with the owner.
However there are many items whose exact specifications cannot be decided at the
start of the project.
For example many finishing items such as floor tiles, dado tiles, sanitary and plumbing
fittings etc.
The owner takes the decisions on these items as the work reaches the finishing stage by
going through the choice of materials available at that time.
Prime cost and provisional sums
Prime cost
The problem is how to get an estimate for these items at the start of the work?
For such items the contractor is to mention the cost of the materials he has considered
in giving the estimate.
The prime cost serves as a basis for deciding the addition or deduction in cost due to the
materials selected by the owner.
Prime cost and provisional sums
Prime cost
Cost of tiles = Rs A
Cost of labor = Rs B
Profits = C
Overheads = D
The item rate contract for vitrified tiles is A+B+C+D
Out of these, cost of tiles (A) is variable as it will depend on the selection of the tile
hence while giving the item rate the contractor will mention the cost of tiles assumed
(A)
If the cost of the tile selected by the client is Z then
Cost of item = Z+B+C+D, here the cost of installation has remained the same only the
cost of tile is variable
Prime cost and provisional sums
Provisional sums
In some cases the item involves a specialist agency or vendor such as for example a lift
manufacturer or security system etc.
In such as case the contractor will keep provision for tentative price of such items in the
quotation. This is called the 'Provisional Sum’.
The contractor will take quotations for such items from the vendors after which the
owner can take a decision on the same.
Provisional sums
At the time of execution of this item quotations from various vendors supplying the
solar panels will be taken and actual cost of the item will depend on the rate given by
the vendor.
If however the work is done without the involvement of the contractor he cannot claim
any charges for the same.
The provisional sums are important to give the client a fair idea of the total cost of the
project.
Provisional quantities
Where work can be described and given in items in accordance with the tabulated rules
of measurement
But the quantity of work cannot be accurately determined, an estimate of the quantity shall
be given and identified as a ‘provisional quantity’
The ‘approximate quantity’ shall be substituted by the ‘firm quantity’ measured, and the
total price for that item adjusted to reflect the change in quantity
Extra items of work
“Extra work” is work that was “entirely independent of the contract and not contemplated
by the parties”.
“Extra work” entitles the party performing it to extra compensation for the work
Types of Estimates and its characteristics
This is an approximate estimate to find out an approximate cost in a short time and
Thus enables the authority concerned to consider the financial aspect of the scheme, for
according sanction to the same.
During Preparation of the estimate detailed surveying, design, drawing, etc. are not
required.
Purpose of an Approximate Estimate :-
3. Administrative approval.
Such an estimate is framed after knowing the rate of similar works and from
practical knowledge in various ways for various types of works such as:
The floor area of the proposed structure is worked out, and then multiplied by a suitable rate.
This rate of construction per square meter of floor area is worked out by dividing the known
cost of construction of a similar building by the floor area of that building.
This method is more accurate than the square meter of floor area method because the
depth of foundations and the height of the structure above the ground level are the additional
dimensions taken into consideration. The American Institute of Architects recommends
considering the actual cubic space enclosed within the outer surfaces of the outside walls
and contained between the outer surfaces of the roof and 15 cm below the finished surface
of the lowest floor.
By this method, the volume or cubic content of the proposed building is worked out
and multiplied by the rate per cubic volume of similar building in that locality
constructed recently.
Service unit or unit rate method :-
Buildings are constructed to serve a specific purpose. For example hospitals are designed to
accommodate certain number of beds. Each bed is then considered a service unit. Hotels
are designed to accommodate certain number of guest rooms. each guest room is
considered a service unit. Same applies to offices, residential houses, etc. Whenever a
building is constructed the Engineer or the architect keeps the record of the place, actual
cost, number of service units, and the year of construction. From this record, it is possible to
work out the cost per service unit. This cost is then adjusted to account for inflation, and
peculiarities of the project under consideration. Then the adjusted cost per service unit is
simply multiplied by the number of service units in the proposed project to get an approximate
cost estimate.
Bay method :-
This method is particularly suitable for buildings which consist of repetitive bays, such as a
garage, a workshop building. Detailed quantities are taken out of all the different items of
work involved in a typical bay and finding out the cost of such items using suitable rates.
In this method, multiply the total length of the walls of a building in running meter by the cost
of construction per meter length of such a wall. The total length of the wall of a building is
worked out from the plan. Different sections of walls in a building are considered separately.
A section of a wall includes all items of works from foundation concrete to roofing. Thus the
cost of excavation, foundation concrete, brickwork, D.P.C., proportionate cost of flooring and
woodwork, R.C. roof, lime concrete on roof, parapet, plastering and finishing on walls etc.,
per meter length are accounted. The cost of a wall below and above the plinth level should be
kept separate.
Cost comparison method:-
The approximate cost of the proposed structure is found out by modifying the known cost of
similar existing structure with due consideration to price fluctuation between the dates of
construction of the old and proposed structure.
This method gives the best results but it is only applicable to structures which are repetition of
similar works.
Types of Estimates and its characteristics
2) Detailed Estimate
This includes the detailed particulars for the quantities, rates, and costs of all the items
involved for satisfactory completion of a project.
Quantities of all items of work are calculated from their respective dimensions on the
drawings on a measurement sheet.
Multiplying these quantities by their respective rates in a separate sheet, the cost of all
items of work are worked out individually and then summarized, i.e. abstracted (which is
the detailed actual estimated cost of work).
All other expenses required for satisfactory completion of the project are added to the
above cost to frame the total of a detailed estimate.
Types of Estimates and its characteristics
2) Detailed Estimate
Report
Specifications
Detailed drawings showing plans, different sections, Key or Index plan etc.
Design data and calculations
The basis of rates adopted in the estimate.
Such a detailed estimate is prepared for technical sanction, administrative approval and
also for the execution of a contract with the contractor.
Revised Estimate :-
A revised estimate is a detailed estimate for the revised quantities and rates
of items of work originally provided in the estimate without material deviation
of a structural nature.
ii) When the expenditure of work exceed or likely to exceed by more than
10% of the administrative approval (for work more than Rs. 5 lakhs).
iii) When there are material deviations from the original proposal but not
due to material deviation of structural nature.
Supplementary Estimate :-
The abstract must show the amount of the original estimate and the total of the
sanction required including the supplementary amount.
Types of Estimates and its characteristics
This is a complete estimate or list of quantities for all items of work required to complete
the concerned project.
The quantity of each individual item of work is worked out from respective dimensions on
the drawing of the structure.
To find the cost of an item its quantity is multiplied by the rate per unit for that item.
The purpose of the bill of quantities is to provide a complete list of quantities necessary for
the completion of any engineering project and when priced gives the estimated cost of the
project.
Schedule of Quantities
It provides a simple means of adding a complete Activity to a Job Order in a single action.
Schedule of Rates and its uses
Normally for arriving at cost of building two basic things are required:
1) Quantity of each and every item of work
2) Prevailing market rates of each particular item.
The quantities can be easily worked out by an engineer based on the drawings and
specifications.
The rates would however, vary from place to place depending upon the rates of
construction materials, labour, working environment etc.
Hence all government departments publish standard rates for all building items collectively
and all the estimates have to be worked out based on those rates only.
It would thus be very easy to compare offers / quotes from different contractors.
Stages of work
Site clearance
Setting out of site
Making arrangements for electricity , water connections , watchman's cabin, site office etc
Substructure
a) Foundation work – PCC , DPC , Brick wall for foundation , backfilling of soil
b) Work up to plinth level – Murrum and rubble soling packing
Superstructure
a) Work upto 1st slab level ….. Continued up to last slab , Casting RCC staircase
b) Construction of walls – Brickwork , Casting lintels , chajjas for windows , Door / window
frames
c) Waterproofing and laying water supply and drainage pipes
d) Installation of grills
e) Plaster – Internal and external
f) Painting – Internal and external
g) Flooring
h) Installation of railings , glass panels etc.
i) Compound wall , security system , water tanks , parking pavement , gas bank etc
Measurement sheet
The quantities of various items involved in the structure are calculated using plan,
elevation and section of the structure.
For calculating the quantity of various item of the structure, a Measurement sheet is
used.
Abstract sheet
The cost under item of work calculated from the quantities already computed at
workable rate, and the total cost is worked out in a prescribed from known as abstract
sheet.
Bill of quantities
The bill of quantities is a document prepared by the cost consultant that provides
project specific measured quantities of the items of work identified by the drawings and
specifications in the tender documentation.
The contractors will fill in rates for items of work based on the quantities and
specifications mentioned in the BOQ
The quantities may be measured in number, length, area, volume, weight or time.