Paper / Subject Code: 53701 / Software Project Management
A 6 -
B 8 -
C 3 A
D 5 B
E 4 C, D
i) Create a precedence activity network
ii) What is the total project duration?
iii)Calculate earliest start date, latest start date and float of all the events.
iv) Identify the critical path.
b. Define activity. Discuss three approaches to identify the activities.
c. Suppose four risks namely R1, R2, R3 and R4 have been identified and assigned the
probabilities of occurrence of 0.1, 0.2, 0.3 and 0.4 respectively. The likely damages due
to the four risks are Rs. 50, 000; Rs. 1, 00,000; 70,000; 60,000 respectively. Calculate
the risk exposure of al the risks.
d. Define Risk and discuss the ways of dealing with them.
e. Explain the process of scheduling resources.
f. Discuss the factors to be taken into account while allocating individuals to task.