Offshore Grid NL: Document Title
Offshore Grid NL: Document Title
Document Title:
Standard Offshore Substation
Cable Pulling Methodology
This document and all its content is protected by copyright which is owned by TenneT TSO B.V.
This document has been provided only for the purpose of preparation to the SDE+ tender
regarding Hollandse Kust Zuid sites I and II by or on behalf of the acquirer. Reproduction and/or
adaptation is only allowed for this use. Any other use or further use is not allowed. Without prior
written permission of TenneT TSO B.V., it is furthermore not allowed to distribute, communicate
to the public or otherwise disclose of this document or any part of it. The acquirer is obliged to
impose the same conditions as mentioned above to any user on his behalf.
Any acquirer should be aware of the fact that this document is subject to change and no rights
whatsoever can be derived from it.
ONL-TTB-00188
Intended for
TenneT
Document type
Report
Date
February 2016
Ramboll ref.
1100015665/ROGE-Z-RA-000420, Rev. 1
OFFSHORE GRID NL
Ramboll
Willemoesgade 2
DK-6700 Esbjerg
Denmark
T +45 5161 1000
F +45 5161 1001
www.ramboll.com/oil-gas
Standard offshore substation
Cable Pulling Plan
CONTENTS
1. Introduction 1
1.1 Final deck configuration 1
2. Regulations, Codes and Standards 2
3. Basis of Design 2
4. Cable Pulling methods 3
4.1 General 3
4.1.1 Cable pulling layout 3
4.1.2 The cable ‘sledge’ method 3
4.1.3 The Samson post method 4
4.1.4 The cable pulling frame 5
4.2 Cable pulling winch 5
4.3 Sequence of cable pulling 5
4.4 Rigging equipment 6
4.5 Escape routes 6
4.6 Jacket structure 6
4.7 Screenshots from the 3D model 7
5. Field layouts 9
Standard offshore substation 1 of 9
Cable Pulling Plan
1. INTRODUCTION
This document outlines the general methodology regarding the pulling of HV sea cables on the
standard 700MW AC offshore substation. It’s main purpose is to prove the feasibility of the HV
sea cable pull-in.
This methodology will be the basis for the detailed cable pulling methods which will be
established by the various cable contractors in close cooperation with the platform contractor
during the detailed design phase of the project.
This document does not outline the scope demarcation between TenneT and the Offshore Wind
Farm (OWF).
Both documents are the result of the consultation process between TenneT and Offshore Wind
farm developers. The consultation process and the documents could be found at:
http://www.tennet.eu/nl/grid-projects/projects-in-the-netherlands/grid-at-sea/consultation-process.html
The basic design of the standard 700MW AC offshore substation is based on the following deck
designations and elevations:
However, the effective cable deck height to be considered during detail design follows from the
preliminary drawings, which shows the current foreseen height of the cable deck so far:
• ONL-TTB-03556_01-MA--Cable Deck 66kV Infield Cable Routing
During detailed design, construction and installation, the following deck designations and
elevations shall be used as basis:
During detail design the Offshore Wind Farm(s), the export cable contractor and the platform
contractor shall optimize the cable deck height. The following requirements shall be taken into
account when detailing the cable routing:
• Bending radius for all cables during pulling and permanent installation
• It shall be possible to pull sea cables both before and after placement of the topside on
the jacket.
• Crossing of cables
• Sufficient space for repair of cables
• Storage of cables on the cable deck before the installation of the topside
Offshore Wind Farms shall follow these codes when establishing their detailed cable pulling
method.
3. BASIS OF DESIGN
This chapter states the relevant parameters used and the number of cables to be pulled:
• No. 2 off 220kV export cables
• No. 18 off 66kV array cables
The following cable specifications have been used for the basic cable pulling methodology and
determination of the deck height and cable routes:
For the detailed design, Offshore Wind Farms shall use the specifications of their intended cable
supplier, which shall be above (bending radius) or below (diameter) the specifications given
above.
Standard offshore substation 3 of 9
Cable Pulling Plan
The preliminary layout drawing only indicates one placement of a cable pulling winch, but the
detailed design phase shall determine two locations on the cable deck (one for each OWF), see
chapter 4.2 for further information.
Furthermore the cable pits area has been shown with a dotted line, to indicate where the cable
pits will be located underneath the 66kV GIS areas.
All cable ways sizes and deck penetrations are estimated and shall be detailed designed in the
next phase.
The sledge guiding system shall be sized and designed by the (OWF's) cable contractor(s)
according to the minimum bending radius of their cable(s), having in mind the maximum height
and other requirements to be fulfilled.
The T.O.S. (Top Of Steel) elevation of the J-tubes will be positioned at a suitable elevation for
using the sledge. A clearance of 300 mm between the Top of Grating (T.O.G.) and the flange is
reserved for the installation of the cable clamp upon the flange. It assumed the flange will fit with
standard type of hang-off clamps, which are compliant with DIN 2642. Nevertheless, the (OWF's)
cable contractor(s) shall review and design the flange detail for fitting with the cable clamp
chosen during detail design.
The structure of the cable deck is sized in order to carry the lifting equipment and its related
design loads.
The structure supports a sledge guide, which may be oriented around the required directions; a
pad eye, which is used for the installation of the snatch block and a winch. The sledge guide is
bolted to the structure. If it is deemed necessary, due to local loads, the grating has to be
replaced with plating.
Jack-up
cable
Post
Design factors
The pulling force is multiplied by the following design factors:
• Weight contingency 1.05
• Dynamic effect 1.1
• Consequence factor 1.3
• ULS load factor 1.3
The dynamic effect makes reference to cable pull-in operation in other similar platforms. The
weight contingency and consequence factor refer to Noble Denton guidelines for marine lifting &
lowering operations, 0027/ND.
J-tubes shall be located in such a way that one side of the Substation is kept free of cables, to
allow a Jack-up vessel at that side. Furthermore the J-tubes shall be located so that the cables
can be separated as much as possible on the seabed close to the Substation. Due to Remote
Operating Vehicle “ROV” cable pull-in operations, the distance between J-tubes and seabed
during cable pulling operation has to be coordinated with ROV supplier to ensure that the ROV
can manoeuvre freely also with dynamic sand banks in mind. 2.5 meters between J-tubes and
sea bed is a conservative approach and can be used as a guideline.
J-tubes will have minimum bending radius required for the cables, with single curvature and will
be able to withstand the cable pulling forces with no jamming.
The J-tube inner surface shall be smooth, free of obstructions, sharp and cutting edges. The J-
tube shall be checked by pigging or other suitable operation.
J-tube entrance shall be characterized by the presence of suitable smooth bell-mouth opening.
The bell-mouth shall be suitably sealed allowing for an easy opening at the time of the pulling by
means of a ROV. A simple example of a possible solution is shown in below sketch.
Design and construction of the bell-mouth shall include the following requirements:
• Bell-mouth elevation above seabed: 2.5 m, bell-mouth angle (from horizontal): 15°
• Bell-mouth exit angle: +/- 30° (see Figure 3-4)
• Bell-mouth exit angle shall guarantee the minimum bending radius of 3.4 m in the 66 kV
J-tube and 5.6 m in the 220 kV J-tube.
• Bell-mouth shall be aligned with the exit direction of cable (route of the cable
approaching the Platform)
• Bell-mouth exit point shall be outside the platform footprint for the ROV access
• Area in front of J-tube entrance shall be free of obstacles and shall allow safe approach
of the cable laying vessel and ROV and ease pulling of the cable.
1. Screenshot in Figure 3.5 shows an overview of the entire cable deck including the two
placement of cable pulling winches, the two sledges and the Samson post pulling method.
The pulling A-frame has not been inserted in the 3D model
2. Screenshot in Figure 3.6 shows the large sledge suitable for pulling of export cables
3. Screenshot in Figure 3.7 shows the small sledge suitable for pulling of array cables
4. Screenshot in Figure 3.8 shows the Samson post mounted on one of the array J-tubes
5. FIELD LAYOUTS
In the principle field layout the platform is located such that it is surrounded by the two wind
park areas. The array cables enter the platform from three sides (north, west and south). The
export cables to shore can optimally be connected to the platform on the north side, but
connection on the south side will be kept open. The east side shall be kept free from cables on
the seabed to secure future accessibility for a jack-up-based heavy lifting crane vessel for
potential replacement of a main transformer, GIS or shunt reactor.
• ONL-TTB-04016-MA-EN_00--Field_Lay_Out_HKZ_Alpha_(1-10)
• ONL-TTB-04017-MA-EN_00--Field_Lay_Out_HKZ_Beta_(1-10)
• ONL-TTB-04018-MA-EN_00--Field_Lay_Out_HKZ_Alpha_(1-20)
• ONL-TTB-04019-MA-EN_00--Field_Lay_Out_HKZ_Beta_(1-20)
These drawings show a preliminary lay-out. The lay-out shall be the basis for further optimization
during detailed design between TenneT, Offshore Wind Farm, Platform Contractor and Cable
Contractors.