2..loading Unloading and Installation of Piping

The document provides a job safety analysis for loading, unloading, and installing piping. It identifies potential hazards such as traffic accidents during crane mobilization, crushed body parts from improper crane positioning, and crane collapse or hitting materials during loading and unloading of pipe spools. Preventive measures are outlined like securing work permits, barricading work areas, using flagmen and personal protective equipment. Failure of slings or shackles and fall hazards are also identified for the erection and installation of pipe spools. Proper lifting methods, inspection of lifting devices, and use of safety harnesses to prevent falls from elevated areas are emphasized. Supervisor monitoring and toolbox talks are required to

Uploaded by

Francis Vinoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
405 views3 pages

2..loading Unloading and Installation of Piping

The document provides a job safety analysis for loading, unloading, and installing piping. It identifies potential hazards such as traffic accidents during crane mobilization, crushed body parts from improper crane positioning, and crane collapse or hitting materials during loading and unloading of pipe spools. Preventive measures are outlined like securing work permits, barricading work areas, using flagmen and personal protective equipment. Failure of slings or shackles and fall hazards are also identified for the erection and installation of pipe spools. Proper lifting methods, inspection of lifting devices, and use of safety harnesses to prevent falls from elevated areas are emphasized. Supervisor monitoring and toolbox talks are required to

Uploaded by

Francis Vinoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

EPC -3 Gasoline package

DAELIM CO.

JOB SAFETY ANALYSIS

JSA Title: Loading/Unloading and installation of piping JSA Control No: RCL-JSA-009 DEPARTMENT : PIPING
Location : EPC-3 Sulfur Area Revision Date: July 2013
Task Description
Work Description Hazards Identified Preventive Measures

crane Mobilization Traffic Accident  Secure all necessary work permits prior to execute the job.
 Fix the traveling route and make sure the ground resistance satisfies traveling
requirement of crane.
 Flag man should be assigned to direct and guard when traveling
 All employees involved in the operation to be aware of hazard
 Foreign materials within lifting area should be clear
 Crane should be positioned on hard and level ground to settlement
Crushed body parts, cut
Crane positioning  Barricaded the swing radius
fingers/hands, crushed
 Flag man required
fingers/Hands
 Use proper PPE
 Tool box meeting to be conducted by supervisor before start job.

Loading/ Unloading of pipe spool Crane Collapse  Crane operator must be physically fit and no mental illness.
 Crane shall be checked in order to ensure that there is no leak of hydraulic oil
or any other defects, before starting job
 Crane must have valid 3rd party test certificates.
 Crane operator shall have Saudi equipment operator license in addition to third
party.
 Crane load chart to be checked.
Hitting the materials.  Capacity and position of the crane has to be checked.
 Crane out rigger pad to be conforming per DIC/discription standard.
 Only authorized signalman to be give signal to crane operator.
 Barricaded the swing radius.
 Set the crane on a firm and level ground close to the load.
 Tool box meeting to be conducted by concerned supervisor before start of
job.
 No erection allowed during harsh weather e.g. wind exceeding 20mph, thick
fog, heavy sandstorm, rain etc.
 Crane load chart to be checked.
 Capacity and position of the crane has to be checked.
 Authorized signalman to be give signal to crane operator
 Pipe shall be stacked properly and it shall not be blocked the main access.
 Stopper must be provided to avoid rolling.
 Materials shall be stacked off the ground using wooden piece.
 pipe Storage area shall be properly barricaded
 Nobody is allowed to stay or pass under suspended load.
 Two tag line to control the Pipe from the safe distance.
Erection/Installation of Pipe spool at Failure of sling/cut  Lifting methods will be correctly followed as safely and mechanical lifting will
elevated area Breakage of D-Shackle be with crane,

 Check the condition of sling, D-Shackle


 Check all the tools to be certified and color coded as per the monthly.
 Use correct size of the sling and D-shackle
 All lifting device must be valid test certificates and must be inspected before
use.
 Supervisor/foreman must be continuously at job site until the job is finished.
 Safety officer must be monitor continuously.

personnel injury  Proper PPE must be wear.


cut  Two tag lines must be used to control the structure materials.
Fall hazards  Do not allow to jump, walk on structure while controlling the tag line.
Human fall  Physical barricaded the working area
 Only personnel involve in lifting activity are allowed inside the barricaded
area.
 Arranging /lifting must be sequence.
 Avoid over stacking of pipes to prevent materials from tripping over. It
necessary to stack the materials not higher than the reach of a person, this is to
avoid climbing over the materials during hitching that will expose the rigger to
fall hazards.
 Audible reverse alarm to be installed to all mobile equipment.
 Pipe spool should be tide with two ropes to control from safe distance.
 Proper access to be provided.
 Scaffolding green tag must be checked while going elevated plate form.
 Wear safety harness and anchored on fixed structure.
 All lifting job is done under the guideline of rigging supervisor.
 Proper access to be provided.
 Supervisor/foreman must be continuously at job site until the job is finished.
 Safety officer must be monitor continuously.
 Check the condition of sling, D-Shackle
 Check all the tools to be certified and color coded as per the monthly.
 All lifting device must be valid test certificates and must
be inspected before use(Chain Blocks, Lifting belts and Shackles.)

Prepared and Reviewed By:


Approved By:

RAJESH KUNTA
Signature
RCL Permit Receiver
In- charge of the work