Pokhara Sub - Metropolitan City Office: Rate Analysis of Electrical Works (F/Y 2069/070)
Pokhara Sub - Metropolitan City Office: Rate Analysis of Electrical Works (F/Y 2069/070)
16 Supply &Fixing 2x3/22 P.V.C. copper wire for Light, fan, wiring per mtr.(6.0-13)sq.mm.
Norms:26/11b.1/274 Per 100 mtr
Discription items unit rate amount Remarks
Skilled lab. 0.75 Md 620.00 465.00
Semi-skilled Lab. 1.30 Md 475.00 617.50
Unskilled Labour 1.20 Md 425.00 510.00
HDP Pipe 3/4" 100.00 mts. 31.49 3149.00
2x3/22 copper wire 100.00 mts. 0.00 0.00
Nails,grips,cement and paints etc… L.S L.S. 200.00
Sub total 4941.50
Contractor's profit and Overhead(15%) 1.15 5682.73
Rs. 56.83 per mtr
17 Supply & Fixing 2x3/20 P.V.C.copper wire for jun to jun wiring.
Per 100 mtr.
Norms:No26/11(b-1)page-274
Discription items unit rate amount Remarks
Skilled lab. 0.75 Md 620.00 465.00
Semi-skilled Lab. 1.30 Md 475.00 617.50
Unskilled Labour 1.20 Md 425.00 510.00
HDP Pipe 3/4" 100.00 mts. 31.49 3149.00
2x3/20 copper wire 100.00 mts. 0.00 0.00
Nails,grips,cement and paints etc… L.S L.S. 200.00
Sub Total 4941.50
Contractor's profit and Overhead(15%) 1.15 5682.73
Rs. 56.83 per mtr
18 Supply & Fixing 2x7/20 & 1x1/18 P.V.C. copper wire for DB to DB .
Norms:No26/11(b-2)page-274 Per 100 mtr.
Discription items unit rate amount Remarks
Skilled lab. 1.00 Md 620.00 620.00
Semi-skilled Lab. 1.50 Md 475.00 712.50
Unskilled Labour 2.00 Md 425.00 850.00
HDP Pipe 3/4" 100.00 mts. 31.49 3149.00
2x7/20 & 1x1/18copper wire 100.00 mts. 0.00 0.00
Nails,grips,cement and paints etc… L.S L.S. 200.00
Sub Total 5531.50
Contractor's profit and Overhead(15%) 1.15 6361.23
Rs. 63.61 per mtr
19 Supply & Fixing 2x7/22 & 1x1/18 P.V.C. copper wire for power pt.
Norms:No26/11(b-2)page-274 Per 100 mtr.
Discription items unit rate amount Remarks
Skilled lab. 1.00 Md 620.00 620.00
Semi-skilled Lab. 1.50 Md 475.00 712.50
Unskilled Labour 2.00 Md 425.00 850.00
HDP Pipe 3/4" 100.00 mts. 31.49 3149.00
2x7/22 & 1x1/18copper wire 100.00 mts. 0.00 0.00
Nails,grips,cement and paints etc… L.S L.S. 200.00
Sub Total 5531.50
Contractor's profit and Overhead(15%) 1.15 6361.23
Rs. 63.61 per mtr
S. Norms Rate
Description unit
N. no. Dept. Cont.
1 Supply & Fixing Main distribution Board Per set 5475.20 6296.48
2 Supply & Fixing Tube light Per set 622.00 715.30
3 Supply & Fixing Wall Bracket Per set 542.75 624.16
4 Supply & Fixing Bulk head Per set 642.75 739.16
5 Per set 341.54 392.77
Supply & Fixing 6/16 Amp. CPL Power Socket ( N.G.)
6 Per set 422.50 485.88
7 Supply & Fixing Celing Fan 48" with regulator Per set 3775.76 4342.12
8 Supply & Fixing Exhaust Fan 9" Per set 3239.50 3725.43
9 Supply & Fixing 6 gang switch Per set 437.50 503.13
10 Supply & Fixing 4 gang switch Per set 393.40 452.41
11 Per set 371.35 427.05
12 Supply & Fixing 2 gang switch Per set 332.76 382.67
13 Supply & Fixing 1 gang switch Per set 305.20 350.98
14 Supply & Fixing 1 gang two way switch (N.G.) Per set 315.00 362.25
15 Per set 114.19 131.31
Supply &Fixing 2x3/22 P.V.C. copper wire for
16 Light, fan, wiring per mtr.(6.0-13)sq.mm. RM 49.42 56.83
Supply & Fixing 2x3/20 P.V.C.copper wire for jun
17 to jun wiring. RM 49.42 56.83
Supply & Fixing 2x7/20 & 1x1/18 P.V.C. copper
18 wire for DB to DB . RM 55.32 63.61
Supply & Fixing 2x7/22 & 1x1/18 P.V.C. copper
19 wire for power pt. RM 55.32 63.61
20 Per set 6236.50 7171.98
21 Per set 5712.15 6568.97
22 Per set 10129.13 11648.50
Remarks