Labor Estimate: Work Description Manpower Concreting
Labor Estimate: Work Description Manpower Concreting
CONCRETING
1 Plain Flooring 2 men
2 Reinforced Flooring 2 men
3 Column and Beam 2 men
FINISHING
Rough Flooring 2 men
CHB Joints 2 men
PLASTERING
CHB 2 men
LAYING
CHB 2 men
Glazed Tile 4" x 4" 2 men
Glazed Tile 6" x 6" 2 men
BREAKING
Breaking Old R-C Flooring 2 men
INSTALLATION
Water Closet 2 men
Lavatory 2 men
GI Sheets 32" x 8" on Steel Frames 2 men
GI Sheets 32" x 8" on Wooden Frames 2 men
GI Sheets 32" x 12" on Steel Frames 2 men
GI Sheets 32" x 12" on Wooden Frames 2 men
Fabricating & Installation of Gutter
2 men
Downspout Ridge Roll 32" x 8" GI Sheets
GI Pipe 1/2 dia x 20" 2 men
Doors and Windows Jamb 1 man
Door (Complete of Hinges and Knob) 1 man
Plywood Board 4" x 8" 2 men
Wooden Post 4" x 4" x 18' 2 men
Wood Jalousies Windows 30" x 45" 1 man
FABRICATION
Doors (Excluding Planning of Frames) 1 man
PLANNING
Rough Lumber (including Alignment) 2" x 4"
1 man
x 18'
Rough Lumber (No Alignment) 1 man
MANHOUR
1 set wc / day
1 set lav / day
11 sheets/ day
20 sheets/ day
10 sheets/ day
15 sheets/ day
5 sheets/ day
20 lights/ day
340 bd ft/ day
2 pcs door/ day
15 sheets/ day
6 pcs or 96 bd ft/ day
2 pcs or 18.75 bd ft/ day
3 pcs/ day
II. FORMWORK
a. Footing, grade, column 2.5 manhour/ sq.m.
b. Beams, bond beams, floor slab 2.8 manhour/ sq.m.
c. Roof beams and bond beams 3.01 man hour/ sq.m.
d. Roof Slabs 3.34 man hour/ sq.m.
e. Retaining Walls 2.4 man hour/ sq.m.
f. Stairs and Landing 2.48 man hour/ sq.m.
g. Form Oil application 6.0 man hour/ 10 sq.m.
III. REINFORCEMENT
a. Footings up to roofing ave. 9.0 manhour/ 100 kilos
b. Grade slab EWP 13.0 man hour/ 100 sq.m.
c. Floor membrane 15.0 man hour/ 100 sq.m.
d. Roof beams and bond beams 2.88 manhour/ cu.m.
e. Stairs 2.6 man hours/ cu.m.
f. Roof Slab 2.91 manhour/ day for 7 days
g. Equipment
1. Vibrator 16 min/ cu.m.
2. Crane with concrete bucket 4 cu.m./ man hour
1 mason & 1
a. Laying of CHB and adobe 22 pcs
helper
b. Cement Finish 28 sq.m.
1 Carpenter &
a. Erecting Forms 1.86 sq.m.
1 helper
b. Removing Forms 1.86 sq.m.
CAPABILITIES OF MANUAL LABOR PER HOUR
Tractor -
Drawn Roller a. Vibratory Rolling ( 6 passes - 20 cm lift) 240 cmph
( 1-d)
No. 3w road
a. Static rolling (6 passes - 20 cm lift) 24 cmph
roller
5-T dump
a. Hauling Common Borrow 3.5 cmpt
truck
b. Hauling Selected borrow base course 5 cmpt
Note: 1 metric ton of asphalt conc. Covers 8 sq.m. Of pavement 0.005m. Thick or 0.43 cu.m.
Asphalt concrete
UNIT MANHOUR ITEM OF WORK
PVC Pipes
1/2 " Ø 20 MH/ 100 BF
3/4 " Ø 20 MH/ 100 BF
1"Ø 22.5
1 " - 1/4" Ø 22.5
1 " - 1/2" Ø 25
2" Ø 25
2 " - 1/2" Ø 30
3" Ø 33
3 " - 1/3" Ø 35
4" Ø 40
5" Ø 50
6" Ø 75
CONCRETE FOUNDATION AND ELEVATED CONCRETE UNIT MANHOURS
1 GRADE MEMBER
Formwork 2.54 MH/ SQM
Concreting 8.54 MH/ SQM
Rebars Work 0.071 MH/ KG
Finishing 0.4 MH/ SQM
2 SUSPENDED MEMBER
Formwork 3.28 MH/ M
Concreting 16.70 MH/ CU.M.
Rebars Work 0.08 MH / KG
Finishing 0.80 MH/ SQM
3 ROOFING AND SIDING
Metal Roofing 0.09 mh/ sq. Ft
Non-Metal Roofing 0.10 MH/ CU. FT
Metal Sidings 0.117 MH/ SQ. FT
Non-Metal Sidings 0.133 MH/ SQ FT
4 ARCHITECTURAL SPECIALTIES
2 WINDOWS
Fixed Glass on Steel Frame 0.286 MH / SQ FT
Fixed G.I> Louver 0.429 MH / SQ FT
Fixed Asbestos Louver 0.429 MH / SQ FT
Metal Louver 0.286 MH / SQ FT
TRUSSES
Truss Fabrication 46 bf/ md
Truss Erection 40 bf/ md
Posts 60 - 90 bf/ md
Girts 50- 75 bf/ md
Plates 90 - 120 bf/ md
Purlins 40 - 60 bf / md
Facia Boards 25 -35 bf/ md
CABINETS
Framing 30 - 60 bf / md
Boarding 40 - 80 bf / md
Plywood Sheating 75 - 150 sq ft / md
Cabinet and Doors 40 - 80 sq ft / md
STRUCTURAL LUMBER
SUB-FLOORING
T & G Laid Regular 15.00 4.66 19.66
T & G Diagonal 16.88 4.66 21.54
Plywood Sub-Flooring (sqm) 0.10 0.04 0.14
Plank Flooring 10.79 4.19 14.98
INTERIOR TRIM