Bangui Complete Documents
Bangui Complete Documents
7 May 2004
Dear Sir/Madam:
Reference is made to letter dated March 31, 2004 and mail dated Apnrl
8, 2004.
Please find the following documents and information for your assessment.
APPENDIXES:
INFORMATION:
The piles are drilled into the ground and the pile cap is attached to the piles by
reinforcement bars/concrete as detailed in the drawing.
The total volume of excavation is 12,500m 3 /tower most of which will be used as
back fill while excess soil will be disposed to areas designated by DENR.
Tower sections, nacelle, rotor and blades will all be delivered to site via LCT's.
2
The erection of each turbine is performed in four (4) steps, button tower section,
top tower section, nacelle and rotor including of blades. The erection is done with a
450T crawler crane.
The contract with the EPC contractor requires the contractor to meet all Philippines
environrmental requirements and regulations including requirements specified in
the ECC as well as such requirements imposed by DENR and or other national
agencies.
Service and maintenance of modem wind turbines are very minimal. Two (2)
scheduled service shutdowns per year is the only requirement.
During a service shutdown, the various safety and shutdown function are checked,
in addition a gear box oil analysis is performed and a number of bearings are being
greased.
The turbines are sealed to the surroundings and internally all equipment containing
oil are provided with fail-safe containment which will guide and contain any spills
intemally.
National Standards:
International Standards
The existing INEC right-of-way will cover the entire new 69kV line.
Aside from the sub station area which already acquired by NorthWind, no other
additional acquisition is required.
As the new 69kV line is overbuild to the existing 13.8kV line, no displacement,
demolition, clearing of obstruction will take place.
Best regards,
Niels caobsen
Presdent & CEO
4
ANNEX 1
7,
NorthWind Bangui
Bay Project Phase I
mc -
30 MVA Substation
69 KV "Overbuild"
-~ ^n - -Transmission Line
Initial Environmental
Examination
Checklist
February 2004
A. GENERAL INFORNIATION
1. Project Ownership
_ Corporation
Cooperative
Other, specify
Page I of 22
2. Project Cost
Bank Loan
Government Financing
3. Project Objective
3.1 To transmit generated power by the 25.5MW Wind Farm to the local cooperative
INEC at Laoag substation
To reinforce the Northern Paft of Ilocos Norte's transmission system and thereby
eradicate poor power electrical quality.
Page 2 of 22
S02 802.0 Tons/year
NO 2
CO2 76,218.5 Tons/year
Particulates in suspended particulate 1,604.0 SPM/year
matter (SPM)
NorthWind Bangui Bay Project - Phase I has been targeted as a priority on New
and Renewable Projects in the Philippines which will pave the way for additional
wind power projects which will ultimately reduce oil and fossil fueled energy
production and further diversify the country's energy mix.
The Project would not only be the first of its kind in the Plilippines, in fact it will
be the first in the whole ASEAN.
World Bank through its PCF (Prototype Carbon Fumd) has entered into an
agreement with NorthWid on the purchase of Carbon Credits. World Bank
believes that NorthWind's emission reduction will be the first Carbon Credit
trading from ASEAN Countries and entry of NorthWind will pave the way for
additional carbon trading from the Philippines. Signing of the Emission Reduction
Purchase Agreement (ERPA) is targeted for June this year.
Page 3 of 22
B. PROJECT DESCRIPTION
1. Project Components
2.2 Approximately 57 kin. 69KV transmission line will be overbuilt to the existing
13.8KV transmission line utilizing INEC's existing right of way. Document attaclhed
hereto.
3. How do you describe the general location of the project? (Vicinity Map)
Page 4 of 22
Electrical Monitorin E iii ment NA Lot
Protection Eqtuipment _ NA_ Lot_ _
Power Line Carrier NA __Lot
Area of Control Center 300 sq. m.
Total Project Area Covered 4,432 sq. m.
Power generated from the wind turbines are delivered througlh underground cables to the
substation. From the substation, the power (voltage) is transformed firom medium tension
voltage 13.8KV to hiigh tension voltage 69KV suitable for direct connection to the 69KV
overhead transmission line.
A 300m2 switchgear, storage and control center including office shall contain switchgear,
SCADA (Supervision Control and Data Acquisition), power line carrier and office
facilities for safe operation of wind turbine farm, substation and transmission line.
The substation will be built fully in accordance witli the Philippine Grid Code, Philippine
Electrical Code and International recognized standard such as ANSI/IEEE (American
National Standards Institute), ASTM (American Society for Testing and Materials), IEC
(International Electrotechnical Commissioning), ISO (International Standards
Org,anization).
Nominal Voltage 69 KV
Stuctitre (Concrete/Steel Poles) 65/80 feet
Post Insulators 69- KV Post/Suspension
Conductor 795 MCM ACSR
Existing Transmnission Line 13.8 KV
(to be underbuild) _ _l__ _
Pole Class 2 Class
_ ____ I _ _ _ I ____
The transmission line will follow the existing 13.8 transmission line of INEC (Ilocos
Norte Electric Cooperative) starting uomr NorthWind Powers sabstatian locate&at Suya,
Bangui, Ilocos Norte ending at Transco substation located North of Laoag, Ilocos Norte.
The whole line is 57k-rn and the number of poles is 622 pcs excluding of stud poles.
The line will be constructed in between the existing 13.8KV line which will then be
transferred to the new concrete poles througfh cross arms and insulators.
Page 5 of22
In this manner, the new upgraded line will not need additional right of way nor will it need
tree cutting or relocation of existing stTuctuires.
Page 6 of 22
The new transmissioni line is following the same route as the existing 13.8 KV line. The
total length is approximately 57km. transversing various land use classification as
described above.
Page 7 of 22
Buyon Bacarra
Dilaan Bacarra
Barit Laoag
The proposed 69KV transmission line will follow the existing 13.8KV transmission line of
INEC. The existing 13.8KV transmission line will be underbuild to the new 69KV line
once the 69KV pole structures are erected.
I. Physical Environment
Components/Parameters Y N Remarks
What is the elevation of the area
(masl)?
<100 masl if
100-300 masl f
300-500 masl i
500-1,000 masl /
t1,500 masl i
Slope and topography of the area
Is the terrain flat or level (0-3% slope)? f
Gently sloping or undulating (3-8%
slope)?
Undulating to rolling (8-18% slope)? i
Rolling to moderately steep (18-30% iO
slope)?
Page 8 of 22
Steeply sloping (30-50'%slope)? /
Very steep to mountainous (>50% /
slope)?
What is the general geology of thie Mixed area - See 5.2
area?
Are there indications of landsliding in
the area?
Page 9 of 22
Are there natlral drainageways/creeks
along the area that drain towards NA
communities downstream?
Is the area frequently visited by Typhoons are coming from South
typhoons? / East and is weakened by the
._______________________________ mountain area
When was the last typhoon whiclh July 22, 2003
visited the area? Typhoon Harurot
Average number of typhoons per year:
1999 = 4 Based on PAGASA records
1998 = 2
1997=1I
1996 = 1
1995 = 2
Is there a record of tornadoes/twisters
which occurred in the area?
What is the nearest earthqtuake, fault
zone or volcano, etc. in the area? West Ilocos Fault System
V
Identify the name of the zone: Approximately 2km. West
What are the present uses of the water bodies being drained/affected by the project site?
E N Use Remarks
I Bathing NA
I Fishing NA
I Pebble picking at Brgy. Baruyen only NA
I Washing NA
/
____ Source of drinking NA
I Irrigation NA
1. Biological Environment
Components/Parameters Y N Remarks
Are there existing tress and other types The 69KV transmission line will be
of vegetation in the project area? V "overbuild" to the existing 13.8KV
l line. As stclh it will not require tree
Page IGoF22
If yes, indicate the forest cuttillg or tnmining.
type/vegetation.
Are there birds and other forms of The transmission line will serve as
wildlife found in the area? resting area for birds.
Are there fishery resources in the water NA
bodies found near or in the project .
area?
Is the area in a waterslied or forest
reservation area?
/
If near only, how near? n/a (m or
km)-_
If across, indicate name of the
watershed or forest reservation area. /
If answer is yes to any of the above questions, please list down these species (common or local
name) in the table provided below.
NA NA NA
What are the existing forest resources in the proj'ect area that are important to the community?
_______ I
Forest Resource ! Remarks
NA Timber l
NA Fuelwoodl
NA Non-timber products
NA Food Plants
NA Medicinal plants
NA Wild animals
NA Others (specify) ,_-_,_
Page 11 of22
If yes, hiow many househiolds or families? The transmission line is
lhow many are legitimate land owners? transversing all typical
how many are tenants? areas in Ilocos Norte
how many are caretakers?
how many are squatters?
2. What is the total population of the The transmission line is
barangay (s) covered by the project? transversing all typical
___
_ __ areas in Ilocos Norte
Average family size The transmission line is
transversing all typical
areas in Ilocos Norte
How many of the houses are made of concrete?
Made of wood?
Made of concrete
and wood?
Made of brick?
Made of adobe?
The transmission line is
What are the sources of livelihood? transversing all typical
areas in Ilocos Norte
Livelihood Type:
Farming I
Fishing /
Backyard and poultry and piggery /
Vending/buy and sell /
Sari-sari store 1
Other, pis. Specify: /
Employees /
Barbers, drivers, etc. /
Professionals (doctors,
engineers, Accountants, etc.)
Pebble picking /
How many of the total population lhave reached
the
Elementary level? NA
I) Abaca NA
2) Baruyen
3) Taguiporo
4) Masikil Primarv
Page 12 of 22
Hi-gh School Level?
I) Bangui Nat'l High School
2) Banguii Schiool of Fisheries
If yes, please list down these organized groups e.g. associations, cooperatives, etc. below:
1.
Page 13 of 22
Are there other social infrastructures in the
barangay?
3 Y N
Pre-ConstructionlConstruction Period
Project Activities Affecting the Y N Impact Description Mitigation/
Physical Environment Enhancement
Measures
Will there be land clearing? The new line will
If yes, what is the total area to be follow the existing
cleared? line
Area to be cleared: None
Will there be stockpiling of soil, No impact
sand and gravel materials in the I
project area? ___
Will there be drillings, No impact
hanmering, boring activities?
Will there be earthmoving Minimal excavation
activities e.g. excavation works, works for the
cut and fill, etc.? If yes, how electrical poles
deep is the excavation and hIow e
much is the estimated volume of No Impact
cut and fill?
Ave. deptlh of excavation: Approx. 2.5-3 m.
Estimated volume of cut and fill /
Page 14 of22
Will temporary quarters or Minim-al impact due Coordination with
barracks and a field office be to domestic waste LGU re: disposal
provided for construction
workers in the project site?
Will there be topsoil removal and / No impact
replacement? If yes, how much
of the removed topsoil will be
replaced?
Z I Enitire volume
Partial only
Concrete
z Asphalt
Lengtlh (in)
Width (m) . ._.
Pre-Construction/Construction Period
Project Activities Affecting the Y N Impact Description Mitigation/
Biological Environment Enhancement
______________________________ lM
easures
1. Will there be vegetation No Impact
clearing?
2. Will trees be affected (e.g. No Impact
clea ? , ,, N. I,pact _ of2-.
Page 15 of'22
cut down or removed) during
the clearing? If yes, howl
many and wrhat are thiese
species of trees?
of trees
species of trees:
[Pre-Construction/Construction Period
g Project Activities Affecting the Y N Impact Mitigationl
Socio-Cultural Environment Description Enhancement
__ __ __ __ _ __ __ _ __ __ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ e a sures
1. Will there be settlements to , No Impact
be affected? If yes, how
many households will be
affected?
Total no. offamifies/hlousefiolds:
none
2. Will the preject provide NA NA
reasonable payment terms to
the affected settlements? _
/
l_l_
Substation area
is private
property witlh no
l
PRme 26 or22
residence? Transmission
line is
public/private
fand with access
___
_ _ _to public
6. Will there be increase in Positive impact Increase in economic
economic activity in the area activities will be due to
or rise in associated projects? local hiring, local
purchase of goods and
services and generation
of small scale business
7. Will the project cause an Limited increase Coordination with LGU
increase in traffic or disrupt in traffic due to in connection with the
traffic in major routes due to / transportation of arrival of equipment
entry or exit of construction equipment
equipment?
8. Are there prevailing peace / No impact
and order problems in the site
which can affect the project?
9. Will the project destroy/ No impact
impose hazards to
historical/ctultural instniments?
Page 17of22
Operation and Maintenance Period
Project Activities Affecting the Y N Impact Mitigation/
Biological Environment Description Enhancement
Measures
1. Does the design take into No Impact
account hazards to wildlife
2. Does the design take into V No lInpact
account possible blockade of
wildlife passageways? _
Page I8 of22
PROPONENTS CONIMITMENTS Answer
Yes No
Are you committing yourself to...
I. Comply with existing environmental rules and
regulations, guidelines and criteria?
2. Comply with all mitigation and enhancement measures
that have been identified in the report?
3. Abide and conform to the prescribed rules an
specifications for power transmission lines as contained in
the Electrical Code of the Philippines?
4. Construct, operate ad maintain well-designed transmission ,
line and substation?
5. Establish adequate buffer zones from the project area?
6. Comply with all stipulations indicated in any agreement
forged with private or public authorities?
7. Report to proper government authorities any illegal forest
activities that may be present or happening in the project
area?
8. Immediately replace/rehabilitatelrepair damaged /
structures/lines resulting from nalural or man-made
calamities?
9. Organize and conduct information, education and _
communication (IEC) activities on safely and potential
hazards of the project?
10. Properly brief or orient the proponent's staff about the
ECC conditions, commitments and agreements made
about the project?
I1. Others, please specify
Ilage 19 of 22
E. LIST OF ANNEXES
1. Location Map
Photocopy of TCT/OCT/CLT, etc. (S/S
only)
2. Transmission Line Location Plan /
3. Pole Design and Layout /
Page 20 of 22
ACCOUNTABILITY STATEMENT
This is to certify that all the information and commitmnents in the Initial Environmental
Examination (IEE) Checklist are true, accurate and complete. Should we learn of any information
to the attention of the appropriate DENR Regional Office.
We hereby bind ourselves jointly and solidarily to any penalty that may be imposed
arising from any misinterpretation or failure to state material information in this IEE Checklist.
ATTY.FERDINAND A. DUMLAO
Chairnman, Board of Directors
North Wind Powver Development Corporation2
Page 21 of 22
ACKNOWLEDG EIENT
And acknowledged to me that this TEE is his/ler voltuntary act and deed, of the entity lie/slie
represents. This document, whichi consists of pages, including the page on
which acknowledgement is written is an Initial Environment Examination (IEE) Checklist.
Witness my lhand and seal on the place and date above written.
Notarv Public
Until
PTR No.
Issued at
On
Doc. No.
Page No.
Book No.
Series of
I'age 22 of 22
i ; . '0
0~~~~~~~~~
0~~~~~~~~~~~ .....
.:4
. ,
......:.P"0,._
.T
'.,
0~~~~~~~~
This Contract to Buy and Sell is macfe, executed and entei-ed into by and
between:
We, Spouses FELIZARDO GACES and ELENA B. GACES, both of legal age,
Filipino citizens, and residents of Barangay Utol, Bangui, Ilocos Norte, hereilnafter
referred to as the "SELLERS";
-AND-
WITNESSETH;
That the SELLERS are the absolute owners in fee simple of parcel of [and,
<2_--cated at Barangay Baruyen, Municipality of Bangui, Province of llocos Norte with an
rea of Sixteen Thousand Three Hundred Eighty Six Square Meters (16,386 sq. m.),
ore particularly described and covered by the Original Certificate of Title No. P-55671
&
A / issued by the Registry of Deeds for the Province of llocos Norte;
That the SELLERS offers to sell and the BUYER agrees to buy a portion of the
afore-mentioned and above-described property limited to an area of Four Thousand
Four Hundred Thirty Two Square Meters (4,432 sq. m.) as earlier identified and agreed
by the parties herein, at a net amount of Sixty Pesos per Square Meter (PhP60.00/sq.
-m.) or a total amount of Two Hundred Sixty Five Thousand Nine Hundred Twenty Pesos
(PhP265,920.000):
That the parties herein further agree on the following terms and conditions;
1. That the BUYER will shoulder the cost of surveying and subdivision,
capital gains tax, transfer fees, titling, documentation and other
N miscellaneous expenses;
5. That after all documents that are needed for the consummation of the
Deed of Sale and Partition, failure on the part of the BUYER to pay the
SELLERS, on or before January 30, 2003, the balance of One Hundred
Sixty Five Thousand Nine Hundred Twenty (PhP165,920.00), the
SELLERS will have the right to forfeit the BUYER's downpayment.
IN WITNESS WH-IEREOF, the par-ties lhereto lhave arlix their sigilatules tllis
day of December 2002.
ACI OWLEbGMENT
BEFORE ME, a Notary Public for the Province of Ilocos Norte, tlis day of
December 2002, personally appeared:
FELIZARDO GACES
ELENA B. GACES
all known to me and to me known to be the same persons who executed the
foregoing
Contract to Buy and Sell, consisting of two pages, including this page on
which the
acknowledgement is written and acknowledged the same to be their voluntary
act and
deed.
WITNESS MY HAND AND OFFICIAL SEAL on the date and place first above
written.
NOTARY PUBLIC
Doc. No. ;
Page No. _ ;
Book No._;
Series of
~~~~r
r ~~~~~~~~~~~~~~~~
.1 Ban~~~~~~~~~~~~~~~~
;,k ....
i zll t~,n:y 1985) _ _ ___ ] 9 1agc.
,- r'e .. . wo
......
TO ALL WVI
1om TilESE PRESEN ITSSI IALI, COMrE, GREETINGS:
t | @E ., -- , -; ' -' 16 ;S'; ' ' ' '; ' j .Xu Iiori eI
, CIT ilcPrl 1 e,-l
eE
L pj.'
|% 1= ' 't ,' .;,-, , l, I ! fi .s >.' i < ~~~~~Trmm;lt. i n t1,. 7ft V.rIrarlP Sot"!r th,e Provinice f
iS~~~~~~~~~~~~~~RO
6;
{Q>,!,,,Lt,,,
<,,,mA'_'iu
. ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~............
~~
-~~ ~ ~~ ~ ~ ~ ~ -. o- -
be3n nflg
i ,at a point
, mm I 21126, -CaJ-34-D,
be
inn SI.,
S 8-56 8405.£3 m .rg. 34-P
4 Dthence|
,
S. 31-35 W., 43.30 in. to point'jti N 64- V.in.:,-IX; i 1 m
m.o.point..3;
N;- 62-45 W., 15,.84 m. -to point 4, 34.74 i. to' point
S. 86-38 E., 34.31 Tn.t point 1,- pbint,fllieginnina.
Containina an area of CNE THOUSMZCDWaE HUNDREID 'ID THIRTY
NIN
1, 139) SQUARE METERS ';; L*
, I .r,Al~~~~~~~~~~l_i
'IL() G . I EeI l
I, \Distri(r
..
1.I,nd f fi(er
. ". \A
~~~~~~~~~~~~~~~~~~~~. D S ll IG
I l!!11-llil.l
l1 ddZ ionasl s liedt ................
zItI(-IiA Page ..... ...... .... ..... .. ;|.|:... ... .h*.
; ...-1''s
t- . gisler of Deeds|
|~~~~~~~~~~~~~~~~~~~~I
~~
II ~ ~ ~ ~ ~ .*.'.
..
.'' f
l ( l S*b + * --
1
J M~~~~~~EMORA!ND[UM~ OF E~NCUMBRAIhNCES;
Eizfiy No.. .1 1
the amount of
l 2671Q.
1tr.t ftAILIMD of tMo
accunjd tiestor faloalep i
56,nO.o00o (t80ooo.oo each)-in Grim. Onse N n. 7668,76G),
67076;?,7691f,7693 nd f1ed in thc flogional Trial Gourt ef Iloce'
a ,1 liort,
rirst Judicial Regiont lag (OitY of the parffslandl dencribed*in
OCT Nos, P-55715 and P_55671 inI s30 fa msn Lat 2114f1 S. ceacerned.
I Daite of instrument- l:gnrch 4,1997
Dato of inecription ^lMjrch !7,1997
-- FITilelp i55715 '
, jl~. I Arp. 1 I, '-
-0 I lRegistrar of Deeds 'i
r ,ntryNo. 159806
5r. &Ori l- r bot-1-
Upon nrl ono'ei oFr -le U rl-r io iuii1
j] I 1 1 'wi e ,
P1 lir3t
-- JulTic-ti ; ;ifi,
' *ti.l:v,
l>uii li% "-'j I 1 wi
1
-
un ler Eni lry No. 1 (i,71 I) iLs herePby cance1l Hi.
Date o0 insL.rumiinit - - - -Jrintary 2, 22001
Jate o' in.;cripLion-- - - Jnonuary
- ile [o. 1-55'7 1 5
,, I201
d3 ' --
J * /\01~~~~~~~~~~~~TTY.
.Irrw;I\,P ILI;. .j
_. . _ .-- : -- 1 - /| : ;.-.i!~~~~~~/
*
. , . !-- i
~~~~~'
~ ~ ~ A
..
1'~~~~~~~~x
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~.. |lQ;g.t..
...........................................- ..-. .
S~~~~~~~~~~~~~~~~~~~~~~~~~~~~Rgse of Ded
-~~~~~~~~~~~~~~~~~~~~~~~g
j~~~~~~~~~~~~~~~~~~~
I ,I
I21546 14
21547 D
CAD. 734 D CAt. 7 I4
CAD. 7340D
C____734 _______ \5_ __
_ \ Ot03 4 \ vr
3
1X 5 -'<4
o8 5RE
1 "
N~~~~~~~~~~~~~~~~~~~~~~~~1
oto
32 *~ - : ,.-
-- t\
N 4
--
tAGV _5 --- i
: ;TRAN MISSION -LIN
- ^:-ALOCATION PLAN ---- :
I ~~~~~~~~~~~~~~~~Pagudpud
lQ7cD
.,-S,t,Xi~~~
. I
S-/0'-'t'Sn'#~~~~~~~~~~~~~~~~~if.M
jL,AOAG . , , . . . . . _. _ , _
X l fl
; : - s r
/ / ^ r r
1.
H , . - . .
. . '.
. , .
I
'- [ crgto-w:1 ses-:v-Xn
'~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-
i*
,-¢j
I~ ~ ~ ~ ~ ~ 00 I=.-> 00
0~~~~~~~~~~~~~~~~~~~~~~ .~ .. . -.. i
PROFESSONAL
E / TK)N ELECMCALENGINEER | 1 PROIECr
LHEET
TIT ,CONTEN,T,S,., , _ _ | IARK | _ RMSIONS | DATE 1 BY [ORA!NG FILE NO. _ 10WNER _ | SHEET NO.~~~~~~~~~~~~
: s : :
4
b , ' . 0 0 $ $ f ; s ;
d lff'V000 t 000
u' 0 'X ';0005z '0 0''V 0'TL f t ;l
- .: Z -.- ... . ,\., :. - '- . . - . -- ; -
. . . .- .- . - - . - ;
: . . . . .. .
, -
.. . . . .
;
.
.
.
.. .
> . . ,
. . .
£000 p0 0
BILL of MATERIALS
I I itemd i
(@
®i) litennOnl ~~~~~~~~~~~~~~~~~~~~~~~~
4 armor rod, preformed for 795 MCM acsr, Drake
5 clevis-eye, twisted
7 Bolts, nuts, washers & other hardware - galvanized
8 Bolt, oval eye, with square washer, 5/8" x 12", hot dip
9 clamp, parallel grove, 2 bolt, for 3/8" OHGW
10 clamp, pole band, heavy duty
13 clamp, suspension 3/8"
16 insulator, post, 72 kv, w/ clamp for 795 MCM acsr with
20 Pole, 18m, 201mm tip, 417mm butt
25 wire,# 4 copper, bare, stranded (grounding)
300
_E:C,C4/
5,.'P!CL?t ENG<T~
** .RCjeZ= 'IL / JiCTQ". SHEET CONTENl36:
ON__R__N__Y_R
K REVIS[SI-S yE DRWNG PkE NMJ -_______________________
-L
1>5 ~~~~~~~~~~~~~~~~~~~~~~~~~ARWi
ASt:.. a
6000 2000
BILL of MATERIALS
item descr i ptin
1 anchor log, creosoted, 10Odia x 5' or concrete equivaier
2 anchor rod, 3/4" x 10', twin thimble eye, wI 4"x4" curvec
3 anchor shackle, 5/8", Joslyn 1082 NGK
4 armor rod, preformed for 795 MCM acsr, Drake
22 ~~~~~~~~~~~~~~~~~5
clevis-eye, twisted
7 Bolts, nuts, washers & other hardware - galvanized
8 Bolt, oval eye, with square washer, 5/8" x 12", hot dip g9
9 clamp, parallel grove, 2 bolt, for 3/8" OHGW
10 clamp, pole band, heavy duty
13 clamp, suspension 3/8"
16 insulator, post, 72kv, w/ clamp for 795 MCM acsr with .
18 insulator, strain, 506 heavy duty
20 Pole, 18m, 201mmm tip, 417mm butt
22 preformed guy grip, 7/16"
24 nut, eye, oval, heavy duty, 5/8" hot dip galvanized
25 wire,# 4 copper, bare, stranded (grounding)
27 wire,guy, 7/16" HS, G I
28 wire, OHGW, 3/8" HS, G I (utility grade)
3 00
PE EL T?C CNG. E
-ECRI4 Fr.iE PR -- 7.ThE LOA:,:EH C"VE-NTS: .4R T
DA,5~f3 BY i DRAWNG F-LE NO.
top
j237<
6 00
BILL of MATERIALS
item
a_a
description
>| / 1 anchor log, creosoted, 10"dia x
2 5'
anchor rod, 3/4" x 10', twin thimble or concrete equivalen
17 / (4
3 anchor shackle, 5/8", Joslyn 1082 eye, wl 4"x4" curved
armor rod, preformed for 795 MCMNGK
acsr, Drake
O 5 clevis-eye, twisted
U 6 clevis-y ball
section a a se
\ ction a - -
a
/ / ~
7
8
Bolts,
6 nuts, washers & other hardware - galvanized
Bolt, oval eye, with square washer, 5/8" x 12",ohotadip1hd
.10
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~9
clamp, parallel grove, 2 bolt, for 3/8"
pole band,
clamp, duty heavy
11 clamp, strain, for 3/8" OHGW,
OHGW
NGK or equivalent
13 clamp, suspension 3/8"
14 clamp, suspension, for 795
15 extension link 18" heavy duty,MCM acsr w/ armor
hot dip galvanized
17 insulator, suspension, 10", b&s type
18 insulator, strain, 506
20 Pole, 18m, 201 mm tip, heavy duty
417mm butt
22 preformed guy gnp,
P2 / 7/16"
23 socket eye
224 nut, eye, oval, heavy duty, 5/8" hot
/ 25 wire,# 4 copper, bare, dip galvanized
stranded (grounding)
27 wire, guy, 7/16" HS,
GI
3000
_ _ _ _ __ s FDCFESCOHAL
AL E_E_TRIC_rf4os'8EEi } r ?RDvE r,-E /FE :LNTENT TEqAMNG
:
jIARE< FEHASIC
ThENS
,, ,, ~~~~~~~~~~ja
Stit:ATn-.Us
A.;
i ........
.L
AI
72j.I.A
.ZSL
.....
5l Q 'r A h 1CAA1C1- -
6 00#1
BILL of MATERIALS
item description
no.
1 anchor log, creosoted, 10"dia x 5' or concrete equivalei
2 anchor rod, 3/4" x 10', twin thimble eye, w/ 4"x4' curvei
sectionn aa _- a
a' a a
sectiont a a X6 anchor
63 shackle, 5/8", Joslyn1082NGK
clevis-y ball
7 Bolts, nuts, washers & other hardware - galvanized
8 Bolt, oval eye, with square washer, 5/8" x 12", hot dip c
9 clamp, parallel grove, 2 bolt, for 3/8" OHGW
10 clamp, pole band, heavy duty
11 clamp, strain, for 3/8" OHGW, NGK or equivalent
12 clamp, strain, for 795 MOM acsr, NGK or equivalent
15 extension link 18" heavy duty, hot dip galvanized
17 insulator, suspension, 10", b&s type
18 insulator, strain, 506 heavy duty
20 Pole, 18m, 201mm tip, 417mm butt
21 preformed guy grip, 3/8"
22 preformed guy grip, 7/16"
23 socket eye
24 nut, eye, oval, heavy duty, 5/8" hot dip galvanized
25 wire,# 4 copper, bare, stranded (grounding)
27 wire, guy, 7/16" HS, G I
- -/
-
_ C,'~
~ A E~
ZTR~4L
~NC3 300.E
section w 1
a
a a-
o
- a
rst
a a
Gla/
i a
2 anchor rod, 3/4" x 10', twin thimble eye, w/ 4"x4" curve(
3 nn_ anchor
|n n shackle,
w 5/8", Joslyn 1082 NGK
cZ 6 clevis-y ball
7 Bolts, nuts, washers & other hardware - galvanized
8 Bolt,-oval eye, with square washer, 5/8" x 12", hot dipg
( S ) Cg + / ; ..... 9 clamp, parallel grove, 2 bolt, for 3/8" OHGW
18 10 clamp, pole band, heavy duty
/ 1 clamp, strain, for 3/8" OHGW, NGK or equivalent
12 clamp, strain, for 795 MCM acsr, NGK or equivalent
15 extension link 18" heavy duty, hot dip galvanized
17 insulator, suspension, 10", b&s type
18 insulator, strain, 506 heavy duty
20 Pole, 18m, 201mm tip, 417mm butt
21 preformed guy grip, 3/8"
22 preformed guy grip, 7/16"
23 socket eye
24 nut, eye, oval, heavy duty, 5/8" hot dip galvanized
25 wire,# 4 copper, bare, stranded (grounding)
27 wire, guy, 7/16" HS, G I
3000
=R.C . .N
-
6_ 00 /2000_
section a - a' a a
BILL of MATERIALS
item d e s c ri p t i on
no.
1 anchor log, creosoted, 10"dia x 5' or concrete equivalent
2 anchor rod, 3/4" x 10', twin thimble eye, w/ 4"x4" curved sqr
3 anchor shackle, 5/8", Joslyn 1082 NGK
5 clevis-eye, twisted
6 clevis-y ball
7 Bolts, nuts, washers & other hardware - galvanized
8 Bolt, oval eye, with square washer, 5/8' x 12', hot dip galvar
9 clamp, parallel grove, 2 bolt, for 3/8" OHGW
10 clamp, pole band, heavy duty
11 clamp, str-ain, for 3/8" OHGW, NGK or equivalent
: 1 )____________________ 12 clamp, strain, for 795 MCM acsr, NGK or equivalent
-f 15
j Wextension
< link 18" heavy duty, hot dip galvanized
- - ~~~~1
6 insulator, post, 72 kv, w/ clamp for 795 MCM acsr with armoi
- - .- ~ 17 insulator, suspension, 10", b&s type
18 insulator, strain, 506 heavy duty
1934 ~ ~~~~~~~~~~~~~~~~~~~~~~20
Pole, 18m, 201 mm tip, 41 7mm butt
3 uuu21pefr 3o22
|preformed guy gnp, 7/16'
23 socket eye
24 nut, eye, oval, heavy duty, 5/8" hot dip galvanized
25 wire,# 4 copper, bare, stranded (grounding)
27 wire, guy, 7(16" HS, G I
28 wire, OHGW, 3/8" HS, G I (utility grade)
_0 'NT' S_ F- 'B Y
consiant 0 O.OOOOU0 U.uUUUuu l.UUl
Sag Profile
rated 20 0.048711 0.004871 1.001
ACSR diameter Weight 40 0.194846 0.009742 1.001
in inches #11000ft strenght
1,899 4105.84 60 0.438408 0.01 4613 1.001
336.4MCM LINNET 0.72 462.5 14,000
4,500 4105.84 80 0.779402 0.019484 1.001
795 MCM DRAKE 1.11 1,096.0 31,500
100 1.217838 0.024356 1.001
120 1.753725 0.029227 1.001
140 2.387076 0.034098 1.001
160 3.117906 0.038969 1.00'
180 3.946232 0.043840 1.00
200 4.872074 0.048711 1.00
220 5.895455 0.053582 1.00
Catenary Calculations for 336.4 & 795 MCM ACSR 1.00
240 7.016397 0.058453
ruling span = longest span = 1000 ft. = 304meters 260 8.234929 0.063324 1.00
280 9.551078 0,0681 96 1.00
9.5508
280 10.964877 0.068 9 .00
The exact catenary equation uses hyperbolic function i.e. catna_equatio300 0.073067 1.00
320 12.476358 0.077938 1.00
340 14.085557 0.082809 1.00
y(x) = w Ecosh- _ 1] 360- 15.792514 0.087680 1.00
] ' ! 2.SO US
2.50 M.
| ~~~~~~~~~~~~~~~~~~~~~~~~PREUM
DRAWINGONLY
j~~~~~~~~~i II I I
I , i, - . 1 1 b\~1
] ~~ ~ ~ ~ ~
__-____;__= __ _ _ _ _ _ _ ___ __ _____
500 +
I9S L C.R.
CONTROLPANELS
CONTROL
ROOM
RECEPTION
___ ~I _._________________ r
_______I___-____r___ __________
_____ M.
M.___ _12.00 , 4.00 M. 4.00 M.
. NORTHWIND POWERDEVELOPMENT CORPORATION
_______ __ _ 20.00 M. __ _310 immmamd."
Ch_CkedOr. OFFICES
FP S. 11/20/KW
I14 9
I-- - - - - -- - - -- - - - - - - - -- - -- - - - - - - -
----
5-25230/: A
;7
NW9
SS xv, 6,, 'k
_:712 L-21,
C9
ki. 8M A 1*3
L I PT
20/1,731 - 'I' vll 732 Np
10 kA
Kw;
T 1:z
ANSPORHER
Ju ;I
Buc:
ON LIN TAP
ie
- - - - - - ---- -
(PRELIMINARY)
xII,/;.._I, i",v
'T
-7.
MP3
CS MPS --';A4
Vf_. Tpi= ,4w,
M A
L- -
J-
K:W.
4!
- - - - --- --- - ------ - - - - - - - - - - - -
- --
- - - - - - - - -- - - - - - - - - - - - - -
o.,,z
DA7 NO OWNER-
h--a A PS7,M717
(D
c3rTU7t, V40 N
- ; Wa--s, - - - c-. -V.
bi-- t .2 -- t )i .t , , -
, _ ....._...
..
I~~-
-~ ~ ~ ~~~~~~~~~~~~~~~~~~N-
-,
LEGEND:
_- ._ ._ . . .~ . - . jF P .i L Z ,' OC\ ., ~ 5 *
F
-P 0 7*
T -T-D
- , ' , r.
__~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ E
______ - r s i __ -- i .- -- . --- ---
---
*--,--- 2-_~Z,
b , N'_E
ZLF
_AT _I _WWN _ I-C;sQ
L~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~E
OT,"' I,
_ j ,. : v . ___
- __ . NOTES :~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~"
; V r E r
X,rr ' PR
r z-:- J - + :,,-
;~-~ 'R
i,,,
-- TH - cROUN~NL MAT 5" A ' .,
II
L~~~~~~~~~~~~~~~~~~~~~
__
I~~~~~_
4* I
F~ ~ ~~I
'-,1,-$9
~ --
2.32'
StOck
Yard
_~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ / XI
CouL
Bagkeoh. /
/ _ _ ! t1 .S:: e
->-Mv*~.
'- 1 ! . __j!/ , I! -
~~~~~~~
~~~~~~~~~
~
OWN
s.;- ,..t r.f !-
;. .rc
§-< <':-tb i ! f .;
_________ ~3-POLE' SINGLE-POLE H-FRAME T3-POLE
_ _ SINGLE POLE
PI H
H- - FRAME
RAE SINGLE
INLE DOUBLE
DOBL DOUBLE
DUBE DOUBLE~~~~~~~~~
OUL
_ _ _ SINGLE CRCIT
CIRCUIT SINGLE CIRCUITj CKT.
SIGLECICUT KT CIRCUIT
CRCITCICUT
__________ ___________
_______ _________ ___________
CIRCUIT CIRCUIT~~~~~~~~~
IRUI
F~~~~~~~~~~~~~~~~~~~~~~~~~
-I 120 120 120 1201-1 220
So~~~~C,
5C0 600L
2 2220C 3Z
3230 17
3200os 90 I so 160 200 2023
20
____________
100 000 1030 1200
MA.s''
IC
-32
3 0, 3 0 130 130 F320 320 375 375
200
130
300
130
-~~~~
503-
32
500 0 0 I.F S00
30 375 I
OE,ALiUES STRIC7LY M.1NIM.UM:
__________
______________
_____________ ______________
I C~~~~~~~~~~~~~~~~~W~~
: OVER AT 700F'INAL
C (1550 F'~~~~~~~~~~CR
NO
Q WWIND.T
ND.FIN LRSSAOG
__________ ____________
_______________ C EAREC
'PA~~~~~~~~~~~~~~~~~~~~~r~
AiLS OF RAILR
RAILROAD0S
ADS
j3737. 2fr.
0.:
l~ 32.5 Fr1.
FI ' I' -' ~~~TARE'A ACOE'SSI2LE ONLY T~ ~:'r.`TIANz 7.0 mr.
LO 3A,-- 24.50 Fr.
IN
Pt L DISTRPICT73 . 22...95Ft
-- - "' ~~~~~~~~~~~~~~~~~ ~~~~~~~~~~
'~~~~~~TI0N ~~~~zcordafnce w[th PEG
SPAN. M. 100
~ ~
___________________________________ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
200 300 L.-0-..~~~~~
~~. .~~~ m. 3') LOO ANCHOR-4,550
e ----
----- 1(D03
S (10,000--
1~'000 Lzs.)K
3. 0 .
-~~~~~~~~~~~~~~~~~~~
~~~~~~~~SPAN, M.
C7 '_RDSARI-STEE-------------------------'OR
FBRLS
STRESS ~~~~~~~~~(i/m
-- PSI
2EN~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
DING --------------------------
____________________ 5S 5.0
_________
OOVFRESS2N, END ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~--
-- -- -- -- -4.I40010 10---
I f ~~~~~~~~~~~~~~~~~~~~~~~~~~~3 PROPORT IONA11
AT~~~~~~~~~~~~~ VLiMIT'I
I ~~~~~UNLOADED LOADED
FINAL AT 15 C'(59 F) FINAL ATIS C-(59 F)____
- - :.:~~~~~~~~':'-
- -~~~~~~~~~
i~~~i
DEPTH OF POLE SETTING
LENGTH OFF POLE'
OL IN EARTH
INEATHOC IN ROCK~~~~~~~~~~ENGH
- -- .1;
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~METER
[FEET METER FEET IMETER FEET
I 1 3~~~~~~~~~~~~~~~~~~~~~~S
21 . 1.5 5,0
I ______ ______5 "29 7.5 1.68 5.5
4 .02
g~~. '-i3 7.0
w4
____ .. 'I0 ___ __229
7 I
F 3 7 'g-
''W '' -
C
ll~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
5. .EGEND
s - e 'etOC
r37B - r
r5us c;rercr'ne
D j;t Z-i
s t e tv~-! ri's
S/e/ S a
EsSrruit;cic
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~_ _
:___ -- ______ _ ___-__ _
-~~~~~ - I~~~~~~7
/~~~~~~~~~~7 1TC
H0fXi''S~~~~~~~~~~j - 'I
''DI~~~~~~~~~~~~~~~~~~~~~~~~~~-
i'
I -
,1/
!, I 'i ;
I .I I " 1 | | .
N...
LEGEND:
e
-F
62
.
r r - r
O
._s i-
GROUNDING ROD
CONNECTION: EQUIPMENT
TO SCTEELSTRUCTURES
rrtr Z :
X
5-4, +I2~
9T .L.A, Lift U-
I1
Circuit
..|it. Breaker Other equipment
Disconnect sv.6tcih
Lightning Arrester
VIEW A
pplSC~ -l`_ N
Q, -
_EC cAr-
! SNE ONTENT.T
- _______
. r
EDGARDO - cRac
G:raq
iT ASANNSTR ;RP'
AAtVTSI~5ONS I DATE I Y
IL 9-ULrAS IOFSERICE I DRAWND- ',E 'NC
SSliE PRWrr Tl OWNER-
I A N A.
- r -
' 40 ^ ' - ; . - r
' : - \', ,''L' ''" ."' /.. -' "'',.,'; ;'" - ' ' -, '''j'
e -
-' :-
;
."','' " "',,' '.
e i's \0 t L ) F '.' h % 9 { _
a a _ r ,
; . X, '
> _ # X v _ 4 X _ . .
4 _ 1 t i . . $
. ,
' .
_
_
. _ _
,: . ' e ' .
.' _ .
' j .
. |
' , , . , e
24.75 MW NorthWind Power- Project
Substation and Transmission
Nlanpower Requirenient
Total 220
11. PROJECT OPERATION PERIOD
r; ~ -- ctivities)- :
Transmission LItl.svrziSd Substationfor Norlt windIBvni1
ui Bay Project- Phase I Section II
Teneder Docuiments
Activity Schedule
10-20-2003
TIME SCHEDULE
The following charts show the Employer's project schedule for the 69KV transmission lines and the 30MVA Bangui
Substation.
2004
ACTIVITY Dm
(Days)
t Weight (%) Feb Mar Apr May Jun Jul Aug Sep
1. Mobii zation 15 1.4
2. Manufacturers Drawings 60 5.4
Approval ____ __
Plage 1 of 2
Tra,ismission Lines intd Suibsitctiof
lit8 Vo-thi, rdlla,ii'n
IJ 3,I,nProject - Phase I Section 11
7Tender DocuImenls
Actiiitv Schedule
i0-)0-2003
_ __________________ 2004
Duration Relative
ACTIVITY (Days)" Weight Feb Mar Apr May Jun Jul Aug Sep
1 Mobilization 15 2-10
2. Site Development 90 12.55 -
3. Manufacturers Drawings Approval 60 8.36
4. Eqpt. Manufacture, Tests & Delivery 120 16 73
Period
5. Preparation of Construction Drawings 60 8.36
6. Finalization of Construction Drawings 60 8.36
7. Equipment Foundation 60 8.36
8. Equipment Installation/Erection 75 10.46
9. Conductor Installabon/Cable Pulling 90 12.55
10. Transformer Installation/Related 30 3.81
l'age 2 of 2
PHxOTOCOPIES OF
*AGRIEEMIENTS/RIGHT OF'WAY
-GRANTS
ILOCOS NORTE ELECTRIC COOPERATIVE, INC.
SUYO, DINGRAS, ILOCOS NORTE 2913
29 .Ianui;iry2003
In line with our Electric Sales `Ag2reelmlenlt Of Julyz 19.2002, Ilocos Norlc
Electic
Cooperative (INEC). Hereby allow NortlhWind Power Development Corporationi (NP'DC)
the use of our existing, right of wrav from NPC Laoag substation to Nomlliwincl's project
site in Bansui, in particular thle 13.8 k-\V line extendin-Lg from the main highway
to tlh
proposed 2 x 20 MAZ\ti substation facility.
WNVe have no objection in NorlhWind revising tiNs particular line/system vhercin our
13.8 kV linc shall be "'undeibuilt" to NortlhWind's 69 kV tranismiiissioni line
R inillas C. Pascual
v telleral AIanager
_ FES
_ __ .3
i~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~L
-
-
;
-
- -
: '
; >
t *s
a C *
-
t
- i: = ' C.
- 3
b -
-e
: +- - '
f j
f - :
s
} i * Y -s - l
s w
* , ' r
; ' z 0
.
- GEOLOGICAL :FAULT- MAP - - . . . . . .
.
. .
. .
'
.
. .
.. ..
. . . .
- : -': . ....
,
.'. . . .
. .
. .
.
.
. .
.. .
-. -
. .
.
/ (
!/ -
/ / ,r .
P,Q1IV(J_ '.
I C-Jan-01-023
25 January 2001
CERTIFICATION
This is to certify that the Proposed 20 MW Wind Power Project located along the
shoreline of Bangui, Ilocos Norte, as indicated in the vicinity map provided, is
approximately 2 kilometers west of a splay of West Ilocos Fault System, *the
nearest known active fault in the area, based on the map currently available in
PHIVOLCS. The buffer zone against surface rupturing recommended by this office
is at least 5 meters on both sides of the fault trace or from the edge of the
deformation zone.
This certification is being issued upon the request of Mr. NIELS JACOBSEN for
whatever purpose it may serve and supersedes any previous certification issued by
this office regarding the area.
R MUNDO S. PUNONGBAYAN
Director
.. '-J (
_17 _0/ '73dcl
121 00 t200
1
Roads/highways
Cityrrown
C
Babuyan Islands
1900'
0 15 30
Kilometers
-~~~~~-p
' t- I o ::/ ff /; s
k Abe stTabuk
ItLL _ifaT
5~~~~~~~~~~I OFVOLCAO
2000~
GoA~~~~~~~~~~~~.y o
LY
.OCY SEMMOLO(rY
I
ENDORSEMENT OF TILE
M--UNICIPAL OR CITY
PROVINCIAL COUNCIL-
Republic of the Philippinies
PROVINCE OF ILOCOS NORTE
Municipalitv of Bangui
To All Concerned:
Done in the Municipality of Bangui, Ilocos Norte, this (ot. day of February
2 002.
WIL . GACES
Municipal Mayor
Republic of the Philippines
Municipality of Bangui
fl
Ilocos Norte
BARANGAY MASIKIL
. EXCERPTS FROM THE MINUTES OF THE REGULAR SESSION OF THE SANGGUNIANG
; ;, BARANGAY OF BARANGAY MASIKIL, BANGUI, ILOCOS NORTE HELD ON
Al"', ' /a, AT_(_ __ HALL.
'OCLOCK_AT_ITSSESSION
PRESENTS:
WILLIAM R. TOMAS Barangay Chairman
ELMER TQMAS Baragay Kagawad
ROSARIO VALIENTE -do-
LUCRECIA MAGANA -do-
EDGARDO MALLARI -do-
EMILIO ACOB -do-
EDWARD MARTINEZ * - do -
ANGEL MABINI -do-
s: .~ FROILAN MAGANA SK Chairman
ARTEMIO TORRADO Orgy. Secretary
B
EDROLFO ACOB Brgy. Treasurer
Resolution No. _ 2b6o
WHEREAS, Barangay Masikil, Bangui, llocos Norte have a constant source of renewable
ff w energy in the form of wind power and also have available foreshore areas suitable for the
establishment of a commercial windmill power plant;
secured WHEREAS the Northwind Power Development Corporation, a private corporation has
secured a foreshore lease from the Government of the Republic of the Philippines through the
Department of Environment and Natural Resources over the foreshores located In the aforesaid
> ~~~~barangay;
WHEREAS, the Northwind Power Development Corporation has proposed to develop the
r
W said leased government land into a large-scale commercial windmill power plant using wind
power as a renewable source of energy;
RESOLVED FINALLY, to furnish copies of this resolution to the offices concemed for
information and recommending approval.
ARTEMIO TORRADO
Barangay Secrelary
Walna RChi
TOMAn
Ft _^ - ~~~~~Barangay Chairman
Republic of the Philippines
A Municipality of Bangui
Ilocos Norte
BARANGAY ABACA
,e ~ EXCERPTS FROM THE MINUTES OF THE REGULAR SESSION OF THE
SANGGUNIANG
; ; BAJANGAY OF BARANGAY ABACA BANGUI, ILOCOS NORTE HELD ON
= v,' 4 A3 'aAT (b) i OCCOCKAT ITS SESSION HALL.
NC' , PRESENTS:
ELMER R. ACOBA Barangay Chairman
RODOLFO TRINIDAD Baragay Kagawad
V RUBEN LAURETA
,4tERNESTO -do-
RIOGA -do -
ABRAHAM ACOBA -do-
ROY VISITASION
- do -
RODOLFO ACOBA
-do-
-,- JULIO ALABA
-do-
MELCHOR TRINIDAD SK Chairman
TERESITAAGUSTIN Brgy. Secretary
ROSALINDAVILLANUEVA Brgy. Treasurer
VOTING PROFILE:
UNANIMOUSLY CARRIED
I HEREBY CERTIFY to the correctness of the foregoing resolution.
TERE A GUSTIN
APPROVED.__________________ lBarangay SecretaryC'
APPROVEDC n 4) mr
SX Bara~~~~~~ngay Chairman
r sa * \~0
Republic of the Philippines
Municipallty of Bangui
j ri
,locos Norte
BARANGAY MANAYON
EXCERPTS FROM THE MINUTES OF THE REGULAR SESSION
4;, BARANGAY OF BARANGAY MANAYON, BANGUI, ILOCOSOF THE SANGGUNIANG
--AtVw
NORTE HELD ON
_ . S . an AT 69) /Z O'CLOCK AT ITS SESSION HALL.
PRESENTS:
ROGELIO A. PEDRONAN Barangay Chairman
,,.' JERRY RAGUDO Baragey Kagawad
JOSEPH GUIRA
.stEDWIN - do -
-4 RAMOS -do-
MAXIMO ANCHETA
-do-
ISMAELA VALIENTE
MENANDRO ALUPAY -do-
- do-
CECILIO OMMAYON
* ;: -do-
CYNTHIA HIDALGO - SK Chairman
ARTEMIO APOSTOL Brgy. Secretary
FROILAN ALETA Brgy. Treasurer
Resolution No. /P-
VOTING PROFILE:
c ,NCUNANIMOUSLY CARRIED
4 t .PEDRONAN
> k tzS~~~~~~rangay
Chairman
A Republic of the Philippines
Municipality of Bangui
Ilocos Norte
BARANGAY TAGUIPORO
EXCERPTS FROM THE MINUTES
BARANGAY OF BARANGAY OF THE REGULAR SESSION OF
TAGUIPORO, BANGUI, ILOCOS THE SANGGUNIANG
E'Th- NORTE
O'CLOCK AT ITS SESSION HALL. HELD ON
' ''1 D AT (/o)
PRESENTS:
EDGAR GUMALLAOI
NELSON BULUSAN Barangay Chairman
INOCENCIO ACOBA Baragay Kagawad
SARIKEDKED ABALOS -do-
ROMULO MOLINA -do -
EDGAR MARTINEZ - do-
ALEX GACES -do-
JEMEI ACACIO -do-
JONEL GACES -do-
NELY GACES SK Chairman
JOSUE GUMALLAOI Brgy. Secretary
Brgy. Treasurer
Resolution No. °?
A RESOLUTION ENDORSING THE
WINDMILL POWER PLANT IN BARANGAY ESTABLISHMENT OF A COMMERCIAL
TAGUIPORO, BANGUI, ILOCOS NORTE
a a0
',,,
WHEREAS. Barangay Tagulporo,
renewable energy in the form of wind Bangui, llocos Norte have a constant
power and also have available foreshore
Ithe establishment of a commercial windmill
power plant;
source of
areas suitable for
--
0 it
' WHEREAS,
? the operation and establishment of
Corporation will redound to the economic the Northwind Power Development
benefit
by way of collection of fees, licenses, business of the local govemment of Barangay Taguiporo
permits and other local taxes;
WHEREAS, the long-term benefits
windmill power plant will lead to the'developmentof the establishment of a large-scale
commercial
.T within the municipality of Bangui and and modemization
llocos Norte as well. ultimately redound to the benefit ofof Barangay Taguiporo,
the whole province of
t: VOTING PROFILE:
UNANIMOUSLY CARRIED
-
,s.Je&/
I HEREBY CERTIFY to the correctness
of the foregoing resoluti
-PROVED:Bore NL
ga
CES
ecrelary
I r (iafZMGUMALLACI
C .2n9Bay Chairman
1e _
_~~~~~
Republic of the Philippines
Municipality of Banguil
llocos Norte
BARANGAY BARUYEN
PRESENTS:
ALEXANDER C. CALAPINI Berangay Chairman
FERNANDO LABRADOR Baragay Kagawad
SAMUEL VELASCO -do-
AMELITO JAMON -do -
*# MEDEL SAMBRANO -do -
ALLAN LABRADOR -do-
ROBERT GUZON -do-
ROQUE FERRERIA -do-
WILLIE VELASCO . SK Chairman
JALIBERT MALAPIT Brgy. Secretary
REY BALOALOA Brgy. Treasurer
WHEREAS, the Northwind Power Development Corporation has proposed to develop the
aiw c.I,. said leased government land into a large-scale commercial windmill power plant using wind
power as a renewable source of energy;
%
g
plant will provide new jobs and offer employment opportunities to the nearby residents and
constituents of Barangay Baruyen;
WHEREAS,
l the operation and establishment of the Northwind Power Development
Corporation will redound to the economic benefit of the local govemment of Barangay Baruyen by
way of collection of fees, licenses, business permits and other local taxes;
RESOLVED FINALLY, to furnish copies of this resolution to the offices concerned for
f
___
Information and recommending approval.
| E VOTING PROFILE:
UNANIMOUSLY CARRIED
a4 ~ ~~ ~ ~ ~ ~ ~ JA 1~~~~iBA e PIT.
ecT &
'Brangay ~ecrelary)ft1, 7
.4 APPROVED:
MEMpRANDUM
rTNVIAQNMEN-TAL IMPACT AS
iSM1ENT
A. General Information:
1. Nam4 and Address of Project
Proponent rorthwind
I Power Dev't. Corp.
Fap. byAtty. Ferdinand A. Dumiao
2. Type ond Location of Proposed
Project : 3 9 MVA Substation
6 ? KV 'Overbuild'" Transmissiorn
Pvun. of Pasuquin, Buwgos and Line
II ices Norte Bangui,
3. Date and Purpose of Inspection
A )nl 15, 2004
S te Verification subject to the
o0i issuance
Environmental Compliance
C Wrt1ficate (ECC)
4. lnspec*or/Position
Ei gr. Alberto B. Baguio
LI fQ 111/01C, EMS
8. FINDINGS AND OBSERVATIONS:
1. General Description of
the Project:
1.1 The project aims to supply
electrical power from he Wind
Substatlon via the proposed Power Plant to NPC Laoag
thtu the existing power post 30 MVA Sulstation 69 KV "Overbuild" transmission line
of )NEC.
2 Genenal Description of the Project
Location:
2.1 ThU project is located within
Note, the Municipalities of Flasuquin,
Burgos and Bangui, Ilocos
2.2 The generally categorized
as undeveloped areas tt be traversed
ab6ut 57 kilometers in length by transmission line of
Bobon, Paayas, all of Burgos,are Brgy. Suyo, E angui, Brgys. Saoit, Ablan, Bayog,
Sukwngan, Estancia, Susugaen, liocos Norte; a id Brgys. Davila, Dilavo, Carwan,
Ng6bangab, and Carusipan, Salpad, Sulbec, FobIacion 4,
all of Tabungao, Dadaeman,
the Municipaliti of Pasuquin,
exitting power post of INEC; llocos Norte thru the
and
2.3 The entire 57 kilometers
length of transmission line, traverses
agricultural, commercial, residential land use such as:
and open spac' ts.
3 Project Site and Scale.
3.1 The project will be composed
of the following comp meents:
a. Around 622 pieces of poles
b. 69 kV substation at the Windtransmission towers
c. Aluminum stranded, steel coredPower Project Site
d. Line hardware and accessories; cable,
e. Transmission towers foundation;
f. $uspension and strain insulators and
P.03
C. REMA RKSIRECOMMENDATiONS.'
Prepared By,
ENGR. AL t,Uo
LMC I/jOCE
AU4d by:
BEJJAXNN
.
CEtR Officer
I,
fn IC tnmslsoa roc
AB Jrocefyn
'pages 101-10?
F t 7 v l.7 -
04
P-.04
MEMORANDUM
Enclos d: As stated.
Copyf rnished:
CKEXtI(FIO IrOW
%nEff
.
his is to certify that the 30 MVA SL bstation 69 KV "Overbuild"
Transknission Line (identical to the existin! I INEC transmission line) of
NORtHWIND POWER DEVELOPMENT CORPOZRATION represented
by ATTY.
FEROlNAND A. DUMLAO, located in the Munici Dality of Pasuquin, Burgos
and
Bangyi, lotcos Nsorte as shown in the attached loc, ition t-nap has been determined
to be within the typhoon prone area an identifieil Environmentally Critical
Area
( ECA)
CgR Officer
DENR-CENRo No.
1. That the proponent shall secure prior to project implementation, all necessary
permits/ clearances from concerned agencies with administrative jurisdiction over
such project i.e. LGU, MGB, DPWH, DOTC, etc.;
4. That any affected landowners and residents shall be properly compensated and/or
relocated in accordance with Transco Relocation and compensation policies and
guidelines prior to project implementation;
6. All trees to be cut shall be covered by a Permit from DENR Region 1, disposition of
cut trees shall be in accordance with Forestry Laws and Regulations; and
BENEDICTO MOLANO
OIC, Regional Director
Recommending Approval:
NICANOR C. ESTEBAN
OIC, Environmental Impact and Monitoring Division
P 2,100 00 O.R No. . 1658021 Date 04-19-2004
Processing Fee Date 04-19-2004
460.00 0 R. No. 1658021
Filing Fee Date 04-19-2004
. 240.00 O.R. No 1658021
Legal/Research Fee 1658021 Date 04-19-2004
200 00 O.R. No
Procedural Screening Fee .
l~~~~~~~
INITIAL ENVIRONMENTAL
EXAMINATION CHECKLIST
I I I I I I
Bangui Bay 60 MW
Wind Power Project
Ilocos Norte
~
.%~~~~~) ~~~ ~Initial Environmental
. . .
Examination
~~~~~~~Nvebr r2-.00D;
[ . 'Checklist
~
* >*~~ ,. ..
A. GENERAL INFORMATION
1. Project Ownership
Single Proprietorship
Corporation
Cooperative
Other, specify
iee-chk/revO/Page I of 20
2. Project Cost
Bank Loan
Government Financing
3. Project Objective
B. PROJECT DESCRIPTION
1. Project Components
1.1 Around 30 turbines with 660 kW rated capacity each. Alt. 12 turbines rated
1.75 MW each.
1.2 Control Center/Office
1.3 Sub-station, warehouse/switch gear room
1.4 Transmission line - a separate [EE will be submitted. Survey of TIL route on-
going.
As of IEE submission date, approval of Foreshore Lease is in the process which was
filed at the CENR Office, Bangui, Ilocos Norte on September 11, 2000. Documents
are hereto attached. Survey of final lay-out of wind towers is still on-going.
3. flow do you describe the general location of the project? (Vicinity Map)
iee-chk/revO/Page 2 of 20
V Foreshore Land, Underdeveloped Area (relatively far from the urban center
with predominant absence of utility system)
Towver Height - the height from the ground level to the top of the towver
Rotor - solid steel hub wi'ith 3 rotor blades
The turbines will automatically start to generate electricity when the wind speed reaches 4
m/s and will achieve a maximum output at around 15 m/s. These will shut down on an
individual basis when the wind speed exceeds 25 m/s (90 kph typhoon speed)
Power output from the turbines is delivered through underground cables connected to a
substation within the vicinity. From the substation, the power (voltage) is transformed from
medium tension voltage (13.8 kV) to high-tension voltage (69 kV), suitable for direct
connection to a 69 kV high-tension transmission line. A separate IEE for the transmission
line and substation components will be submitted pending completion of transmission line
route survey.
iee-chk/revO/Page 3 of 20
A 300 m sub-station switchgear and storage room and a control center and office of 20 x 15
shall contain a fully equipped office with data collection equipment and modem for
telephone transmission.
iee-chk/revO/Page 4 of 20
C. DESCRIPTION OF EXISTING ENVIRONMENT
I. Physical Environment
Components/Parameters Y N Remarks
What is the elevation of the area (indicate the area of each elevation
(masl)? range)
Brgys. Baruyen to Abaca
<100 masl
100-300 masl
300-500 masl
500-1,000 masl
> 1,500 masi
(refer to the topographic map which
shows the elevation per contour line,
Annex 8)
Slope and topography of the area (indicate the approximate area per
slope category)
Is the terrain flat or level (0-3% slope)?
iee-chk/revO/Page 5 of 20
Are there indications of landsliding in
the area?
iee-chk/revOlPage 6 of 20
Is the area frequently visited by _ Typhoons are coming from South
typhoons? East and is weakened by the
mountain area
When was the last typhoon which
visited the area? October 2-6, 1999
Typhoon Pepang (signal#3)
Average number of typhoons per year:
1999 = 4 V Based on PAGASA records
1998 2
1997 - 1
1996= 1
1995 = 2
Is there a record of tomadoes/twisters _ _
which occurred in the area?
What is the nearest earthquake, fault The Wind Turbine Generators
zone or volcano, etc. in the area? I (WTG) are designed to withstand
the effects of an intensity 10
Identify the name of the zone: V/ earthquake in the Modified Mercalli
Intensity Scale. Further, the
Distance: expected earthquake intensity in the
V/ area is about 7. (See Geological
Bangui fault, though nearer, is inactive. Fault Map, annex 9)
Had there any incidents such as No records available.
lightning strikes at or near the site? Lightning arresters is installed at
the turbines and tall structures
_. . . .
What are the present uses of the water bodies being drained/affected by the project site?
Use Remarks
Bathing
/ Fishing The Turbines occupy a small area and will not
affect fishing.
V/ Pebble picking at Brgy. The Turbines occupy a small area and will not
Baruyen only affect pebble picking.
Washing
Source of drinking
Irrigation _
iee-chk/revO/Page 7 of 20
I. Biological Environment
Components/Parameters |Y N Remarks
Are there existing tress and other types
of 'vegetation in the project area?
If answer is yes to any of the above questions, please list down these species (common or
local name) in the table provided below.
What are the existing forest resources in the project area that are important to the
community?
i_ Resour
__ ceRemarks <Forest
n/a -- Timber l
n/a Fuelwood |_-
n/a Non-timber products __ __
n/a Food Plants l_11
n/a Medicinal plants !_11
|/ Wild animals 1sea birds only
n/a Others (specify) l 11
iee-chk/revO/Page 8 of 20
II. Socio-Cultural and Economic
Environment 1
iee-chklrevO/Page 9 of 20
Elementary level? 1995 Census
1) Abaca 199
2) Baruyen 271
3) Taguiporo 84
4) Masikil Primary 44
High School Level?
1) Bangui Nat'l High School 1,091
2) Bangui School of Fisheries 517
ff yes, please list down these organized groups e.g. associations, cooperatives, etc. below:
iee-chklrev0/Page 10 of 20
Are there other social infrastructures in the barangay? Y Z N
Pre-Construction/Construction Period
Project Activities Affecting the Y N Impact Description Mitigation/l
Physical Environment Enhancement
Measures
Will there be land clearing? Of the 808,630 square
If yes, what is the total area to be meters bounded by the
cleared? project, only the tower
Area to be cleared: None foundation area,
underground cables
and access roads are
clearedl
Will there be stockpiling of soil, / Minimal impact due to
sand and gravel materials in the temporary excavation
project area? works
Will there be drillings, / Short-term impact. Avoid operation of
hammering, boring activities? Noise emission high noise emitting
heavy equipment
at nighttime.
Will there be earthmoving / Excavation for wind
activities e.g. excavation works, Turbine generators
cut and fill, etc.? If yes, how foundation and
deep is the excavation and how underground cables at
much is the estimated volume of the foreshore land
cut and fill?
Ave. depth of excavation: 4.0 m ___[ Low dust emission Sprinkling of water
iee-chk/revO/Page 11 of 20
Estimated volume of cut and fill to minimize dust
60 cu.m. pr foundation l_l
Will there be any slope
modifications or ground leveling
to be done? I
Will temporary quarters or Minimal impact due to Coordination with
barracks and a field office be domestic waste LGUJ re: disposal
provided for construction
workers in the project site?
Will there be topsoil removal and V/ n/a Foreshore land
replacement? If yes, how much
of the removed topsoil will be
replaced?
Cz Entire volume
Partial only
If partial only, where will the rest n/a Foreshore land
of the topsoil go?
If no, what will happen to the n/a Foreshore land
excavated topsoil?
Will there be demolition of /
existing structures? If yes, what
types of structures will be
demolished?
Concrete
L Asphalt
Length (m)
Width (m)
iee-chk/revO/Page 12 of 20
Pre-Construction/Construction Period
Project Activities Affecting the Y N Impact Description Mitigation/
Biological Environment Enhancement
Measures
1. Will there be vegetation n/a
cleaning? _
2. Will trees be affected (e.g. V/ n/a
cut down or removed) during
the clearing? If yes, how
many and what are these
species of trees?
# of trees
species of trees:
Pre-Construction/Construction Period
Project Activities Affecting the Y N Impact Mitigation!
Socio-Cultural Environment Description Enhancement
L _ ~~~~~~~~ ~~~~Measures
l
1. Will there be settlements to n/a
be affected? If yes, how
many households will be
affected?
Total no. of families/households:
none
L -- ~~~~~~~~~~n/al
2. Will the project provide n/a
reasonable payment terms to
the affected settlements?
iee-chklrevOPage 13 of 20
3. Will there be locals to be Positive impact It is the Cooperative's
hired during the construction? policy to prioritize local
l ~~~~~~~~~~~~~~~~~~hiring.
4. Are there existing public trails / No impact Access for fishing
or routes (regularly used) that activities and pebble
traverse the property? picking will be
maintained. Public will
be allowed continued
access to project area.
5. Will the public or local / No impact Public will be allowed
community still have access to continued access to the
the property in terms of project area.
passing through or entering it
to reach their house or
residence? __
6. Will there be increase in / Positive impact Increase in economic
economic activity in the area activities will be due to
or rise in associated projects? local hiring, local
purchase of goods and
services and generation
of small scale business
7. Will the project cause an - No impact Transport of heavy
increase in traffic or disrupt equipment will be by
traffic in major routes due to sea.
entry or exit of construction
equipment?
8. Are there prevailing peace No impact
and order problems in the site
which can affect the project?
9. Will the project destroy! No impact
impose hazards to
historical/cultural instruments?
iee-chk/revO/Page 14 of 20
strikes in the area. with lightning arresters.
3. Does the project have Nighttime noise Use of modem turbines
significant noise emissions level theoretically with low sound
may reach up to emissions.
45dBA at The Turbines are
distance up to 200 placed close to the sea,
meters from the and as such the
row of turbines background noise will
due to rotation of mask the Turbine noise.
blades and
mechanical noise
of turbines
iee-chk/revO/Page 15 of 20
2. Will the project create a Positive Impact Only tourist/transient
significant increase in the visitors are expected
existing population in the area? initially.
Businesses/industries
which will locate in the
area may attract migrant
workers.
3. Will the prevailing land value / Positive impact Increase in land value is
in the area increase with the a natural market
project? consequences when
projects are established.
4. Does the design take into Occurrence of Towers are designed to
account hazards to humans due accidents is withstand storms,
to accidental failure of the wind unlikely. There is typhoons and
turbines? no record of such earthquakes of 10
accidents in wind magnitude. Blades will
projects in 37 automatically reorient to
countries. stop rotation at wind
speeds from 30 m/sec
and up.
5. Is there a team formed for the / No impact
proper responsibilities in
repairing damaged poles/towers
resulting from natural
(typhoons, earthquakes) or man-
made calamities? l
6. Will there be an increase in / Positive impact. Need LGU initiatives.
economic activity or rise in The project is
associated projects? expected to attract
tourist and other
investors the area.
iee-chkl/revO/Page 16 of 20
4. Construct, operate ad maintain well-designed wind
turbines and other related structures?
5. Establish adequate buffer zones from the project area?
6. Comply with all stipulations indicated in any agreement /
forged with private or public authorities?
7. Report to proper government authorities any illegal forest /
activities that may be present or happening in the project
area?
8. Immediately replace/rehabilitate/repair damaged
structures/lines resulting from natural or man-made
calamities?
9. Organize and conduct information, education and
communication (IEC) activities on safely and potential
hazards of the project?
10. Properly brief or orient the proponent's staff about the /
ECC conditions, commitments and agreements made
about the project?
11. Others, please specify /
E. LIST OF ANNEXES
1. Location Map Vl
Photocopy of TCT/OCT/CLT, etc. (S/S Filed and on the process at CENR office,
only) Foreshore Lease Bangui, Ilocos Norte
2. Location Plan /
3. Tower or Pole Design and Layout V/
4. Power Output Layout of Wind Farm
5. Control and Storage Station Layout /
6. Listing of Manpower Requirements /
7. GANTT Chart (Schedule of Activities) /
Photocopies of Agreements/Right-of-Way n/a
Grants
8. Topographic Map /
iee-chklrevO/Page 17 of 20
9. Geological Fault Map l
10. List of Trees and other Important n/a
Vegetation
11. Noise Emission Impact Assessment l
F. LIST OF ATTACHMENTS
iee-chk/revO/Page 18 of 20
ACCOUNTABILITY STATEMENT
This is to certify that all the information and commitments in the Initial
Environmental Examination (IEE) Checklist are true, accurate and complete. Should we
learn of any information to the attention of the appropriate DENR Regional Office.
We hereby bind ourselves jointly and solidarily to any penalty that may be imposed
arising from any misinterpretation or failure to state material information in this IEE
Checklist.
ATTY.FERDINAND A. DUMLAO
Chairman, Boardof Directors
North Wind Power Development Corporation
iee-chk/revO/Page 19 of 20
ACKNOWLEDGEMENT
And acknowledged to me that this TEE is his/her voluntary act and deed, of the entity he/she
represents. This document, which consists of pages, including the page
on which acknowledgement is written is an Initial Environment Examination (IEE)
Checklist.
Witness my hand and seal on the place and date above written.
Notary Public
Until
PTR No.
Issued at
On
Doc. No.
Page No.
Book No.
Series of
iee-chk/revOlPage 20 of 20
. ~~~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 1
Location Map
L ~~~~~~~~~~~~~~~~~~~~~~~~
NorthWind Power Development Corporation
Bangui Bay, llocos Norte
121°00'O
3.'..,,. ., , ;, ,
-* 3A -ITE-;
H ;
... ~ .R ~ ~ -. l < - z .
rn-~~~~~~~~~~~~~~~~~
S; * v!ltf
.s- . T
5.,!,z f :._ .\i
t \'( ,
*- . Ii 1*.~tw
w~.
*t-
Itt
<t
- , I !"V
It '\ l
I 'I~~~~~~
ILOCOS
IL Utl.---.;;--.i' -6s-;;.. t ~ ..... / s' -/
LOCTIO
>-- _'
MAP
LOCATION -.
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
-~~~~~~~~~~
MINA:! OOdMNI
,^.^- 7 ..
IN
JIL
-~~~~~~~~~~Xt sd£ 4 s| - Pll
l~~~~~~
21 ~~~~~~~~~~~~VISAYAS
LOCATIONMAP
/ --
J1
. '.s
f '10;,NORTHWIND ;' 1 POWER DEVELOPMENT CORP.
Project: Station
I WIND TURBINES BANGUI
Proj. No. Sheet Contents
Drawn By:
_EA___ OWH
aumnOla_ ~ BAEM DrNE .L
B L,~u
___VICINITY
111201/0(1
111201CO
NWPDC
PLAN
2 ff 48V 1028 ii. I 12 NiW 2rW 123 iL Checked By:
2 3 MF 48'W 140.71 M. 12 13 NUlW .OBU.h
3 4 NU21W 264.11 . 13 14 Nl 34W 141.86iL F.P.S. 11r00
48 NMrO - 486..02IL 14 11 NW lWw 304. M.
6 NW 54W 36074 kL 15 1 NWI l'W 226-36M.
8 7 N1'r 46W 344.7 k. 16 17 SW 2r5 M. .praved by: Drawing No. Shaet
7 e s-- 357.k. 17 16 N8 46V 1I0 .* N 11/2ZWO0 SD-CW-oOOO
a fl6W .74kM. 15ig N1V l7W 86.80k. NI. Sae
6 10 NW 25- 72.8 IL 1i 20 MZ74
SW M. S .S.
10 1 SWM 5i*W 62.26M. 20 21_ 67V
lIE 84.67 M. _ _iUMDE/fia /NWi2oc
U N -/W W -N.T.S. A
I
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
IPRELIMINARY DRAWING ONLY
I - §~~~~~~~~~~~~----
-
E.
i ffi i | | .~~~~~~~~~~~~~~~~~~~~~~~~~~
400
Hub helght 50 rI
._ __ . 2 = ------ _
|~~~~~~~~ ~~ ~~~~~~~~~~~~~~~~~~
Rd. D1 ProAS
5 DX
TUFNE3
Pmed VINND ~~~~~~~~~~
station BANOUI
Chedkd Of FOUNDATION
690V - Ib';
13.8KV 69KV
Step-down -. -
- ,. Transformer
J.~~~~~~~~~~~~.
- ~ ~ ~ ~ ~~5KM 69KV
Transmission Line
Bangui Bay to Laoag
Ilocos Norte
Electric Cooperative
PRELIMINARY DRAWING ONLY
NORffrNDEPOWER
DEVELPMENT
CORPORATION~
DM" W. ~SUBSTATION
NOTES _ LAYOUT
L_
1. GENERAL TOLERANCES FOR SUBSTATiON
ACCORDING TO DIN 43t5 _ F.P.S. 1t/17/ZX
2. DO NOT SCALE WORKINGDIMENSIONI Apu' br OMN
1/17 ~ ~ ~~1WTENUMO2
N.J. 11/I7/XSal : 3
PRELIMINARY DRAWING ONLY
SECTION A-A
PHASE B&C
L~,
_~~~~~ W
l ce -Th -CO
-00P -08 -00 -Fl
-SA -OS/Es -PT -PC8 -as -1./IES -PCB -SA -TR
3000 3000 1 3000 2000 2000 I 2000 1 2500 1 4000 1 3000 1 4000
29500
NORTHWfLN0 DEVELOPMENT
POWER CORPORATION
NOTES 3 io wWd
1. GENERAL TOLERANCES FORSUBSTATION 0..IT AN-4
ACCORDING TO DIN 43658 Rd. D-g. Na. Pnj.dt. UAND TURBINE '
Stao EANGU
2. DO NOT SCALE WORKING DIMENSIONI _ = - -___
WD;. DaeINaeSet Conftanh
DrawnBy SUBSTATION
_ ______ SSECTION
Ch.hahdW).
_ 1/17/ = F.
ppxa~ / m W1E-OO2
,NNORTHW1ND POWERDEVELOPM~ENT
OORPOFRATION
=PrN
Nm Shlet CWnTnts
m E_Drw SUBSTATION
ISOMETRIC
F.P.S. Il/17/2 _
1/Il/
o - W~-E-ON.J.
O_
II AL
4
A-
wvwmt- 1
~~b1
I1
CuWkW DhUL&AMMM
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
5,00 M. 7.00 . 4.00 U. 4.00 M.
. . _ . L .' 4 | ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~C.R.m
900 ' i X |- .
CONTROLPANELS
i, _ '''''' CONTROL
S ~~~ROOM
.'
~CANTEEN
,~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~.
STORAOE & SNACK
ROOM ROOM
RECEI10N
12.00 U. 4.00 U.
410.00
r~~~ NORTHWIND POWERDEVELOPMENTCORPORATION
20;O .0 I I3OstNOs_
U.
W
-,20
.-
_~~~~~~~~~~~~~~~~~~~~~
. >d. P.*n
31 __
~=:
.d
-, =.0.Orn-r
Rd. Dwg. No. Project : INSiaUion s
WINDTUJRBINES B1GI
Pro].No. Do gamShee Conft.nts
Droun CONTROL
CENrER
-FLOOR PLAN _EL 1120_ AND
ChockedBr: OFFICES
COFFEE
.. ~
ROOIM/
.I
C.R. ROOM
/
lPSUPERVISORS 11
4.00 M ...... . ....... 4.00 M. __ _ 4.00GM -..... ..
CONFERENCE 7
q ROOM
. WIRGENERAL
ci~~~~~~~~~~~~~~~SICGA STORAGE a
ROOM~~~~~~~~~~~~~~~~~~~~~~~~~~~RO
F
-~~~~~~~ L .. -R -------
.O°M
....
- ...... ....._.....
PHASE I
PHASE II PHASE III\~j.1dNo4444 I -~f h.4431 m
Pmoj.No. Dt lniueSotCne
0001 _1
Orown E 1/ SUBTATION
_ _ _ _ AND
Chocked Or. ROOM
STORAGE
n
t
- I~~~~~~
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
20 MW NorthWind Power Project
Manpower Requirement
I. DEVELOPMENT PERIOD
Total 42
Total 220
Total 62
I
I~~~~~~~~~~~~~~~
I.
I I
__ ~~~~~~~Wind Turbine Project Implementation
Jun '01 Jul '01 Aug '01 Sep '01 Oct'-01 Nov '01 Dec '01 Jan '02 Feb '02 IMar'02 Ap'2 Ma Jun
J0 '702
ID Task Name Duraton Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25
1 Effective Date of Contract 1day 2
2 Start 1day
3 Wind Turbine Project Implementation 302 days
4 Site Preparaton 131 days
5 Equipment manufacturing 131 days
6 Shipment to site 39 days
7 Erection 104 days
8 Testing and Commissioning 28 days
9 Substation 236 days
10 Design and Procurement 155 days
11 Shipment to Site 39 days
12 Erection 26 days
13 Testing and Commissioning 13 days
14 Transmission Line 247 days?
15 Staking and Design 26 days? .....
Page 1
-Aom
-
~~~~~~~~~~~~~~~~
i~~
X~~~~~~~~~~~~
Topographic Map
LS D=CI
~~ aJ8.
NOR-TH
~~ ~~~~~~~~------- -----------
:
7 - - - - ------ ........ . ... ..............-- BA
---
----- -_--_ _- _--
- = :-- ~~-~ ~ ~
-~~ _ I_ _ _ _ _ _ _- _
A _ _ _ _ 'E_ _ _ _ _ _ _ _C_ _H _ _
m CFD 4&12
120 41 2112 42f'W
LEGED
MUNICIPAL
BOUNDAo HMARKER4-
BETWEEN
BURGOS
& BANGUI~~~~~~~~~~~~- --- Sk q
flZj~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~*rA
COOR-NATS:-N------8
-1~~~~~~~~~~~~~~~~~~~~~~~~~~~~~117
~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 01Dt
~~WIND TURBINE~10 ------ _
4~~~~~~~~~~~~~~~~~~.~~~~rw y
tiw 4e
ElXr 111'
M'
3e E12ff 4V EIWZe42' OrEIW 41' OrFlW 42'W E12(r
4.TOr Eiw 4r 3r EIWWOr ~WI
LEEGEENS DSNDS:IE ERNS DSA4ES LNS BAIG ITNES LNS BAIG ITNES LNS BAIG ITNCS LNS BAIG ITNCS LNS BAIG I~JIE -BEL Il2O
1 N
M2 ICIPAL1.0
B UNDARY 12MARK1ERU 2 2 22EE 216 U 13 W3E 71.3U 14 l 0E 0.4U I1 21 ia . 6 2 435 1.2I. - -
2 B2ETWEEN BURGOSWl.
14.7 0.6U 2 3 N E 23.6U 3 3 N 3E 4621U 34 S 36 13.4BANGUIIS 317 U 26 50I' f3 .Chce y
-u
ri
I-
--------
d ---- -- t --- ~
------- --------- ---- I--
>
61~~~
a ~ I z Y z
L- - . . -c
.
, 185 mm q. X L P E , 50mo M
In01-ges e
Q En~~~~
002
t~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Iat
F6 M ~ ~ ~
z +~~~~~~~~~~~~~~~~~~~~~~~~
M+M~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ f
nlnl 8 mmqXE.00
lE|0a taz _g
(A CA
-
NORTH 4~
-
1 -
o 23~~~~~~~~~~~~~~~~~~~~~~~~~~2
23
: ".23~ii
ia3 NA3
/ . (BANGUI~~~~~~~~M4
-L BAY)
a = ..-- .---- __ '- 3 lv ~~~~~~~~~~~~~~~~~~~~~~~~~~~~
I v~~~~~~'A
J~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
- -,- I .~~~~9
4C
SA A~~~~~~~~~EM4 l 1~ l 1 ~ EM4 EM4 l 1M
A 4, G~~~~~~~~~~~~~~~~~~~~~~~~~~~RhWN PWRDVLP
Jaguipuro 31 ,JdhbePe.BId
Donao ~ ~ ~ ~ ~ '/~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~UI
EwidA. aCut.MtnM
-oto~~~~~~~~~~~~~~~~~~~~~~~~~~~~01Dt
0~ ~~~~~~ ~ ~~~~~~~~~~~~~~~~~~~~~~rw y
Qat, Cadagasan.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~1wao
LiNS
BARIGS
BARNGSDISANES
DISANES INS
INE BARIGS DISANCS INE BARIGS ISANCS LNE BERIGS ISTNCS LNE BERINS ISTNCS LNES BERINS ISrNCE BE.LLO
2 17 IBL4WIi ¶2.0II22 ii II12
2 SE W 21.0
0'WM 3122 W 2~ ~ ~ 4 42 Ut~E ~ - - - - Caenedan
-~~~~~~~Al -
''-. W1~~~~~~~~~~~ 1l
l~~~~~~~~~~~1 ."F
wmv<
!~~~~~~~~~~~~~~~~~~~~~Z~
121W 122 W
Legend
ActiveFault: Sld Ine- tracm crttain;
appranite
------- " mm projecion:
dashed in- trace appWwmimata
RoadsJhighways
6City/Tam 9.
0 1i 30
KometerA
A ~- /
oa~~ ~
~ ~ ~ ~~~~~~~~p
_ / s~~~~~~~~~~~~~(Tuguegarao
Banguedm
< T Tabuk
' &--f
4IIL XB OF 1
G..bw
R&D a O.-~~~~~~~~~~~~~~~~~~~
0.0,Mm
I
I 10
djj&r- 1
I ImotatVeeato
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
I
I~~~os EmissoImd
lIsesmn
I
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
TURBINE SOUND EMISSION IMPACT ASSEMBLY
1.0 Summary
Sound produced from turbines are aerodynamic (wind impact on blades) and
mechanical in nature. As such, noise issue on wind turbines is now addressed
through advances in turbine blade design and mechanical design, plus siting of
turbines away from residential areas. Modem turbine designs aim to avoid
aerodynamically emitted pure tones and audible sounds frequencies of 20-20,000
hertz. Modem designs include smoother blade tips and trailing edges, larger and
slower rotational speeds of blades, and upstream orientation of rotors.
Mechanical noises are reduced through improvements on gearboxes, fastenings
and couplings, avoidance of vibration of components, and to certain extent sound
insulation. Background noise sources and barriers help reduce the impact of
sound from turbines.
Daytime 55 dBA
Moming/Evening 50 dBA
Nighttime 45 dBA
Noise emission measurements from the Proposed Wind Turbine has been
performed and is attached hereto.
Analysis of the noise in a distance of 75 m shows that the noise from the turbine
contains no clearly audible tones or impulses.
The Proposed Turbine site is located outside residential areas and along the
seashore line as such the background noise will generally mask the turbine noise
completely.
2.1 Definition
L = 10 log [I/Ir]
Where I is the sound intensity in watts/M2 and Ir is the reference intensity. The
watt is the standard unit of power in electrical or mechanical usage.
Sound level is given with the class of the weighting network (i.e. A, C and F).
The dB(A) scale is used for environmental regulations. It measures the sound
intensity over a range of audible frequencies, and then uses a weighting scheme
which accounts for the fact that the human ear has a different sensitivity to each
different sound frequency. The reference intensity is 1 x 10-12 watts/M2 , the
minimum intensity for the human ear can sense at 1,000 hertz. Attachment 1
shows common sound intensities from various sources.
In general, medium or speech range frequencies are heard better than at low or
high frequencies. In the dB(A) system, the sound pressure at the most audible
frequencies (200-15,000 Hz) are to be multiplied by high numbers while the less
audible frequencies (20-200 Hz and 15,000 - 20,000 Hz) are multiplied by low
numbers, and everything is then added up to get an index number.
2
The "C" weighting network (20-20,000 Hz) is also used to determine the
presence of low and high frequencies. A small difference between the "C" and
"A" levels indicate a large number of higher frequency components within the
normal range of human hearing. A large difference suggests the presence of a
large number of lower frequency components (20-200 Hz).
Sound is produced when wind hits an object and causes vibrations, such as in
buildings, house, cars and other structures. If the object is sharp, a pure tone
such as from musical wind instruments may be produced. A pure tone can be
annoying to a listener. In another case, wind may hit the leaves of trees and
shrubs, or water surface creating a random mixture of high frequencies, often
called white (random) noise which is hardly noticeable.
There are two kinds of noise produced from the windmill, i.e. the aerodynamic
noise produced from the blade and the mechanical noise produced from the
gearbox and hydraulic pumps in the nacelle (generator housing).
3
As discussed in the following sub-sections, aerodynamic noises have been
reduced through use of smooth blade shape, larger blade to reduce rotational sped
which in turn reduces sound frequency to lower non-audible frequencies.
Sound pressure will increase with the fifth power of the speed of the blade
relative to the surrounding air, other factors being equal. Thus, aerodynamic
noise can be reduced by maintaining a slower rotation of blades, attainable using
large rotor diameters. Rotor rotation increases slightly with increase wind speed.
Also, the increase in noise from wind turbine is slight compared with the increase
in sound emission from the wind.
Except near the source, low frequency noises from wind turbine is not detectable,
unless the noise has an impulsive character. It is not clear if low frequency
impulse are actually heard or felt or combination of both. The impulsive nature
of the emitted low-frequency energy may allow interaction between the incident
acoustic impulse and the resonance of the homes which magnify the stimulus by
creating vibrations as well as transforming the energy into the audible frequency
4
range. Thus, the nuisance is often connected with the periodic nature of the
emitted sounds rather tan the frequency of the acoustic energy.
Sounds from waves and winds can be heard near the seashore. At winds around
4-7 m/s and beyond, the noise from the wind in leaves of shrubs and trees will
gradually mask (drown out) any potential sound from wind turbines. At wind
speeds around 8 m/s and beyond, background noise will generally mask turbine
noise completely.
The sound of the wind in nearby trees and hedgerows, houses and structures and
over local topography increases with wind speed, but at a faster rate than that of
the wind turbine. It is likely that turbine noise would then be completely masked
by wind-generated background noise. This is possible at high wind speeds, but
not at cut-in speed, which can be the most critical. As the sound level meets the
45 dB(A) nighttime standard, the sound intensity level is likely to still be lower
inside the houses, even with windows open.
A narrow band frequency analysis (Hz) was carried out for the wind turbine
during periods with wind velocity of approximately 8 m/s, to determine whether
the noise contains clear audible tones. The test showed no dominant tone
components in the Hz range. Calculations were done in the frequency range Hz
to analyze a small peak at Hz. The findings show no clear audible tone
emanating from the wind turbine.
5
Attachment 1
6
1 ~~t~~E5 Vestas 660 kW Variable Slip Wind Turbine, V47-660 kW and V47-66012o0 k-W
Date: 30. J 1998 Clss: I Item no.: 943111.Rl Page: 22jof25|
Acoustica as
Fxlledvej 3
8800 Viborg
2. This resume has been worked out on September 3, 1996 by Vestas Wind Systems A/S.
3. The noise measurements have been reported in Acoustica report no. P4.010.97 dated August
6, 1997. The noise measurements has been carried out July 28, 1997.
4. The measurements were carried out to determine the noise emission from a VESTAS V47-
660 kW.
5. The noise emission has been determined according to statutorial order no. 304 of may, 14,
1991, and relevant parts of Guideline no. 6/1984, "Noise from Industrial Plants", from the
Danish Ministry of the Environment.
6. Results of Measurements:
6a.
Vestas V47-660 kW, 0ster Gammelby, OptiTip
x Turbine noise + Background noise
S- p _ en, -d p4.d t
655
s5o
6 65 710 I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
7.5
W.-
60
.-
a3 90 5 10
111
t25__j Vestas 660 kW Variable Slip Wind Turbine, V47-660 kW and V47-660/200 kW
Date: 30. Ian 1998 Class: I hem no.: 943111.R1 | Pagc: 3 o 25
The apparent A-weighted sound power level can be calculated from the equivalent continuous
A-weighted sound pressure level, using the following expression:
Where, d = distance from the base of the wind turbine to the measurement position
(d= 75m).
h = hub height (h = 40,5m + 0,5m).
6b. The measurement show the following results at a wind speed of 8 m/s. The measurements is
given respectively, as the A-weighted sound pressure level LACq.ref and the A-weighted sound
power level Lw'A,ref.
According to statoturial order no. 304 of May 14, 1991, from the Danish Ministry of the
Environment, the degree of accuracy on the results is +2 dB.
6c. An analysis of the noise in a distance of 75 meter show, that the noise from the turbine
contains no clearly audible tones or impulses. The analysis has been performed according to
guideline no. 6/1984, "Noise from Industrial Plants", from the Danish Ministry of the
Environment.
6d.
V. V47 .440 kW. Hue hI.SQa '41 I
I 4I Ia Ia II
a -
a~~~~~L a -- - -- - - L -- -
50 ---
4_I.… … …
_____'_____.___.______...___4… … …____I …
,s4 _____ ____L___..
-0 - - - ---------- r
- 1- - a- - I e A a a
- -- O 1 1 -- A - -4e -
-- -I -
300 350 00 5 0 50 000
50 S.
'0 200 250
0..... of.. . .no
=~~~~~~~
I
I I AMf
I Endorsenment of
Ii~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
I W
A RESOLUTION ENDORSING THE ESTABLISHMENT OF A COMMERCIAL
WINDMILL POWER PLANT INBARANGAY BARUYEN, BANGUI, ILOCOS NORTE
VWHEREAS, Barangay Baruyen, Bangui, Ilocos Norte have a constant source of
renewable energy in the form of wind power and also have available foreshore areas suitable for
the establishment of a commercial windmill power plant;
WHEREAS, the Northwind Power Development Corporation, a private corporation has
| .-.-
t ~secured a foreshore lease from the Government of the Republic of the Philippines through the
Department of Environment and Natural Resources over the foreshores located in the aforesaid
barangay;
-e WHEREAS,the Northwind Power Development Corporation has proposed to develop the
said leased government land into a large-scale commercial windmill power plant using wind
power as a renewable source of energy;
WHEREAS, the proposed establishment of a large-scale commercial windmill power
plant will provide new jobs and offer employment opportunities to the nearby residents and
constituents of Barangay Baruyen;
:::;i;
WHEREFORE, it has been moved and duly seconded,.be it;
RESOLVED, as it is hereby resolved to endorse and fully support the establishment of a
| *, ~~~commercial windmill power plant in Barangay Baruyen, Bangui, llooos Norte;
i>- RESOLVEDFINALLY, to furnish copies of this resolution to the offices concerned for
information and recommending approval.
VOTING PROFILE:
UNANIMOUSLY CARRIED
< I HEREBY CERTIFY to the correctness of the foregoing resolution.
lBR
rJa AiPIT,.
i APPROV ED:;:
I
of Barangay Taguiporo|
by way of collection of fees, licenses, business permits and other
local taxes;
1, WHEREAS, the long-term benefits of the establishment of a large-scale
windmill power plant will lead to thc development and modemization commercial
.t;I within the municipality of Bangui and ultimately redound to the of Barangay Taguiporo,
12 : Ilocos Norte as well. benefit of the whole province of
I*~.,.
RESOLVED, as it is hereby resolved to endorse and fully
support the establishment of a
commercial windmill power plant in Barangay Tagulporo, Bangui,
Ilocos Norte;
RESOLVED FINALLY, to fumish copies of this resolution to
information and recommending approval. the offices concerned for
VOTING PROFILE:
4 :6s UNANIMOUSLY CARRIED
= , c/ "' /
I HEREBY CERTIFY to the correctness of the foregoing resoluti
s - . ~~~~~~~~~~NfLYG
tCESi
APPROVED
jit ~~APPROVED: 4 Bara ga ecretary
I. . ~ ~~~~
~
74< -.
(EI G9G,JYkGMALLAOI
fangay Chairman 3
Republic of the Philippines
Municipality of Bangui
Iilocos Norte
BARANGAY MANAYON
.4 v EXCERPTS FROM THE MINUTES OF THE REGULAR
BARZANGAY OF BARANGAY MANAYON, BANGUI,SESSION OF THE SANGGUNIANG
£ ¢G7?sa4
ILOCOS NORTE HELD ON
b AT ' Af/
W9
A O'CLOCKAT ITS SESSION HALL.
PRESENTS:
ROGELIO A. PEDRONAN Barangay Chairman
JERRY RAGUDO
JOSEPH GUIRA Baragay Kagawad
EDWIN RAMOS -do-
MAXIMO ANCHETA -do-
ISMAELA VALIENTE -do-
MENANDRO ALUPAY - do -
- do -
CECILIO OMMAYON
CYNTHIA HIDALGO - do -
- SK Chairman
7%.iS, ARTEMIO APOSTOL
FROILAN ALETA Brgy. Secretary
Brgy. Treasurer
g *t, Resolution No.
A RESOLUTION ENDORSING THE ESTABLISHMENT
WINDMILL POWER PLANT INBARANGAY MANAYON, OF A COMMERCIAL
BANGUI, ILOCOS NORTE
WHEREAS, Barangay Manayon, Bangui,
renewable energy in the form of wind power and also llocos
have
Norte have a constant source of
the establishment of a commercial windmill power plant; available foreshore areas suitable for
4i WHEREAS,'the
-s s, secured a foreshore leaseNorthwind Power Development Corporation,
from the Govemment of the Republic of thea private corporation has
'; Department of Environment and Natural Resources over the Philippines through the
barangay; foreshores located in the aforesaid
VOTING PROFILE:
UNANIMOUSLY CARRIED
41
APPROVED: Barangay Secretary
,PEDRONAN
;rangay Chairman
Republic of the Philippines
Municipality of Bangui
Ilocos Norte
BARANGAY ABACA
EXCERPTS FROM THE MINUTES OF THE REGULAR SESSION OF THE SANGGUNIANG
BARANGAY OF BARANGAY ABACA BANGUI, ILOCOS NORTE HELD ON
" ;, "> '3 -sWAT (A') 7 O'CLOCKAT ITS SESSION HALL.
PRESENTS:
ELMER R.ACOBA Barangay Chairman
_v .';>RODOLFO TRINIDAD Baragay Kagawad
RUBEN LAURETA -do-
ERNESTO RIOGA - do-
ABRAHAM ACOBA - do -
ROY VISITASION - do -
RODOLFO ACOBA -do-
JULIO ALABA -do-
MELCHOR TRINIDAD SK Chairman
9A TERESITA AGUSTIN Brgy. Secretary
ROSALINDA VILLANUEVA Brgy. Treasurer
Resolution No. A 3d
A RESOLUTION ENDORSING THE ESTABLISHMENT OF A COMMERCIAL
WINDMILL POWER PLANT IN BARANGAY ABACA, BANGUI, ILOCOS NORTE
WHEREAS, Barangay Abaca, Bangui, llocos Norte have a constant source of renewable
energy in the form of wind power and also have available foreshore areas suitable for the
establishment of a commercial windmill power plant;
_4.,.vWHEREAS, the Northwind Power Development Corporation, a private corporation has
-4. secured a foreshore lease from the Govemment of the Republic of the Philippines through the
Department of Environment and Natural Resources over the foreshores located in the aforesaid
barangay;
VWHEREAS, the Northwind Power Development Corporation has proposed to develop the
said leased govemment land into a large-scale commercial windmill power plant using wind
power as a renewable source of energy;
WHEREAS, the proposed establishment of a large-scale commercial windmill
plant will provide new jobs and offer employment opportunities to the nearby residentspower
and
constituents of Barangay Abaca;
WHEREAS, the operation and establishment of the Northwind Power Development
Corporation will redound to the economic benefit of the local govemment of Barangay Abaca by
way of collection of fees, licenses, business permits and other local taxes;
WVHEREAS, the long-term benefits of the establishment of a large-scale commercial
windmill power plant will lead to the development and modemization of Barangay Abaca,
the municipality of Bangui and ultimately redound to the benefit of the whole province of within
Ilocos
Norte as well.
WHEREFORE, it has been moved and duly seconded, be it;
*16 ;RESOLVED, as it is hereby resolved to endorse and fully support the establishment of a
commercial windmill power plant in Barangay Abaca, Bangui, llocos Norte;
RESOLVED FINALLY, to furnish copies of this resolution to the offices concemed for
information and recommending approval.
VOTING PROFILE:
UNANIMOUSLY CARRIED
Y"' I HEREBY CERTIFY to the correctness of the foregoing resolution.
TEREOAGUSTIN V A
Barangay Secretary
APPROVED & DIR J
;. .> ~~~ELME AOBA
u ~~*n ~~~~i Bar§ ay ma
CFr-- Republic of the Philippines
Municipality of Bangui
llocos Norte
BARANGAY MASIKIL
4 i EXCERPTS FROM THE MINUTES OF THE REGULAR SESSION OF THE SANGGUNIANG
BARANGAY OF BARANGAY MASIKIL, BANGUI, ILOCOS NORTE HELD ON
AiS. A /) AT ( ) *P`o O'CLOCK AT ITS SESSION HALL.
PRESENTS:
I
tS ,. WILLIAM R.TOMAS Barangay Chairman
ELMER TOMAS Baragay Kagawad
ROSARIO VALIENTE -do-
LUCRECIA MAGANA -do-
EDGARDO MALLARI -do-
IL
EMILIO ACOB -do-
EDWARD MARTINEZ - do-
ANGEL MABINI -do-
FROILAN MAGANA SK Chairman
ARTEMIO TORRADO --
Brgy. Secretary
EDROLFO ACOB Brgy. Treasurer
Resolution No. el 2b6b
A RESOLUTION ENDORSING THE ESTABLISHMENT OF A COMMERCIAL
WINDMILL POWER PLANT IN BARANGAY MASIKIL, BANGUI, ILOCOS NORTE
WHEREAS, Barangay Masikil, Bangui, llocos Norte have a constant source of renewable
energy in the form of wind power and also have available foreshore areas suitable for the
establishment of a commercial windmill power plant;
jWHEREAS, the Northwind Power Development Corporation,
51 ; ~~~secured a foreshore lease from the Government of the Republic of thea private corporation has
Philippines through the
seuDepartment of Environment and Natural Resources over the foreshores located in the aforesaid
S ,: barangay;
WHEREAS, the Northwind Power Development Corporation has proposed to develop the
said leased govemment land into a large-scale commercial windmill power plant using wind
power as a renewable source of energy;
WHEREAS, the proposed establishment of a large-scale commercial windmill power
*.. plant will provide new jobs and offer employment opportunities to the nearby residents and
constituents of Barangay Masikil;
WHEREAS, the operation and establishment of the Northwind Power Development
Corporation will redound to the economic benefit of the local govemment of Barangay Masikil by
way of collection of fees, licenses, business permits and other local taxes;
ARTEMIO TORRADO
aO L Barangay Secretary
*: :, ~APPROVED: ,
JOW6NR. TOMAS
Barangay Chairman
- ~~~~~~Foreshore Lease Application
i 11 ~~~~~~~Certification i
I I
NORTHWIND POWER DEVELOPMENT CORPORATION
Room 310, Jolibee Plaza, EmeraldAvenue,
Ortigas Center, Pasig City, Philippines
Initial consultations with barangay and municipal officials of Bangui, llocos Norte
regarding the proposed project have indicated their support thereon, taking into
consideration the following benefits and advantages:
a.) The project produces cleaner and cheaper electricity. Other kinds of power
plants are dependent on oil or bunker fuel which is imported and subjected to
price fluctuations.
b.) It will encourage infrastructure development, not only in Bangui but the whole
province of llocos Norte.
c.) It will generate employment.
d.) Wind farms are tourist attraction as well, thus, it will enhance many other
livelihood projects to support the tourism aspect of the project.
,' i2^ The foreshore being applied for lease is not utilized for any business or livelihood
activity except for stones/peable-picking by three to five individuals in the whole span of
4-,&. -.>> the identified area, hence, the project will develop idle, unutilized and unproductive lands
generating additional revenue for the government.
It has been observed further that, there is very limited fishing activity in the area
applied for, as conformed by the barangay officials, since the area is very windy
throughout the year and making it not to conducive to fishing.
In view of the foregoing considerations, may I respectfully formalize our application
for foreshore lease, as I have earlier indicated our firm reservation for the same,
X: t$; covering the area of 808,630 sq. m. located in the foreshorelines of Barangays Baruyen,
Taguiporo, Manayon, Masikil and Abaca, all in the Municipality of Bangui, llocos Norte.
-:'
j4'-^i Enclosed as Annex "A" for your reference, are copies of Sketch/Survey Plan of the
Foreshore Land indicating its Technical Description.
Thank you and I look forward to your usual prompt action on this request.
Very truly o s,
CE1Z TI FI CA TIO N
That the afore-mentioned land sought to he leased is not within any previously issued
lease, patent, decree of title; that it is free from any adverse claim or conflict; and that there is
no subsisting lease application filed by any other person or entity.
<iJO,EFINO L. DAQUTOAG
CELYR Officer
m
4m
coo &-
W am
am m
.9an 4w
qmww
dwa
mw
IL
X-~~~ 1 ~~~~~~~~~~
11IJt,H
NOfHWINDIPOWER '-\
DEVELOPMENT CORPORATION . I .
N 18"35 0
N' I n3
-1 _, E 12',O JF ,
12)
P4udodB~ Mach.
tt ,,, ~~~~~~. \
-- ' ' '* .'*
. -
;. D,'
>S~~~~~~~I
-i - !--1uo>, 1y
I- -tz*- o l -',L-htCn
0 5,000 10,000 En.EL
E 01rW
-E - vICNrry PLAN
Odhd W.
F.P.S. lOhiDdO
. Wo_
_ d ky I Iowni No. | Shot
_t c _ N.J 10W
ceo~~ ~ ~c-4 I
20 NIW NorthWind Power Project
rom Bangtii View Deck
I_
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
I
20 NIWV NorthlV'ind Po-wer Project
roin llangtii View Dleck (105 mm Zoom)
... s -fi __
I l
Iif Mr~~~~~~~~~~~~~~~~~~~~AA1.,
20 MW NorthWind Power Project
Vest Tower looking towards West
I ___ - i,_
I v -t ,aY
--. ''
T
I'
20 MW NorthWind Power Project
From Pagudpud Beach looking towards the site (105 mm Zoom)
' . ' -
20 NIWI\NorthWind Power Project
-roiu Center Tower looking towards XVest
IL
20 NfW NorthWiind Power Project
roni West Tower looking towvards East
~~~~~~~~~
~~~~~~~~~~~~~~~~,
~ ~ ~ ~ ~ ~ 7
r *46.
20 NIW NorthiWin(d Powver Project
-enter ToNver
-~~~~ i
I~~~~~~~~~~~~~~~
- A ' A- -
?7)"_'tS~~ .A
eT~ ~ f
..
OF
NoWind PowNOt
Bird Impact study on
10 MW Wind Fam doLa Pa
(TARFA)
BIRD IMPACT STUDY ON THE 10 MW WIND FARM OF LA PENA (TARIFA)
ABSTRACT: This paper shows the conclusions of a 16 month study of the possible impacts on the local and migrating popu-
lation of birds of a wind farm located in the passageway of migrating birds between Africa and Europe. On the whole, the wind
farm did not prove to represent an important impact on the birds present in its surroundings and, on the contrary, created a new
habitat for some species of birds not present in adjacent areas.
Keywords: Birds, environmental aspects.
.I
.I
'l
Table II: Roosting birds frequency Flight behaviour in the proximity of wind turbines was
registered by direct observation and by video cameras. All
Area Observation Recorded Expected changes in flight, direction, altitude and wing movements,
time frequency frequency were recorded. Aspect and number of changes observed
Wind Farm 273 792 840 could not be related to wind speed or direction, but
Comparable changes in altitude were positively related to temperature.
area nr. 1 31 144 95 Birds made changes in flight direction more often when
Comparable crossing the wind-farm than when crossing the other areas
area nr. 2 23 70 71 without wind turbines. Although this higher number of
direction changes could probably be entirely ascribed to
2.3 Migrating birds. the wind-farm, the number of operating turbines did not
Nearly one thousand hours were spent watching migrat- influence the frequency of changes in flight.
|i ing birds from several fixed observation points in the three
areas. A total of 72.000 birds were recorded, most of them 2.5 Collision accidents of birds.
passing above the wind-farm, but at a higher altitude than Weekly visits were made to all the wind turbines to
over the other two areas (see Table III). check any collision incidents. The visit frequency was
_ ii actually higher when other activities near the turbines, not
directly related to bird collision registration, were con-
Table III: Migrating birds frequency ducted. Two birds, a Griffon Vulture and Short-toed Eagle
(Circaetus gallicus), collided with a turbine in.the course of
Area Observation Recorded Expected the 16 months of study at the wind farm. Annual passage of
time frequency frequency vultures over the farm is estimated to be about 45.000, and
Wind Farm 408 56.423 30.572 annual passage of eagles about 2.500.
5j11 Comparable
area nr. 1 285 9.397 21.355
Comparable 3. CONCLUSIONS.
_ ~~area nr. 2 269 6.263 20.156
Thcrcforc collision rate at the wind-farm was consid-
Average flight altitudc at the wind-farm was more than ered to be low. The figure of Griffon Vulture collision ratc
100 m, while in the other two areas birds flcw at about 60 with power lines is higher than the observed rate at thc
m above the mountain ridgc. Flight altitudc was positively wind-farm and even so it is considered to be low.
| D related to temperature. but ncgatively to wind speed. Wind On the whole, the wind-farm did not provc to reprcscnt
II direction also showed its influence; with the prevailing an important impact on the birds present in its surround-
eastern wind the number of birds crossing over the wind- ings. On the contrary, the wind-farm crcated a new habitat
farm increased. Morc than 100 hours were spent recording for some species of birds not prcsent in adjacent areas.
noctumal flights, but no significant number of birds was Although a reaction to the wind-farm could be observed in
recorded crossing the wind-farm at night. bird flight behaviour, differences in flight frequency were
such that there were no indications of the wind-farm ob-
2.4 Local and wintering birds. structing the passage of birds at all. Bird mortality was
Flight movements of local or wintering birds, mostly recorded but could be considered insignificant when
Griffon Vultures (Gyps fulvus), had a slightly different weighted against other bird mortality causes.
character than those of the migrating birds. Although, as in
the former comparison, a higher frequency of birds flying
above the wind-farm was observed and a relationship
between temperature and flight altitude was established, no
difference in flight altitude was observed among the three
areas and no relationship with wind speed was found.
The apparent relationship with atmospheric conditions
and flight altitude is an important instrument to prevent
collision incidence. Under certain meteorological condi-
tions stopping the operation of wind turbines would be
advisable. At the Ecotecnia wind-farm, wind turbines are
locked when winds reach high speeds.
91i
-J
ah SE AR
t
I NorthWid PowePrjc
I ~ ~~~~Coroae Bylaws
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
iI
ill dll Ill I
|Zor11''11lll~~~~~~~~11=Al--- -- 'I
7 -
il r.' IIIII II IIII II illI-,-II'-1--
:III'-:--!i i !-
- iilg1lll--U Sl< X--lil A j:MK!
-eIpIll f% r tll I I lU III iii l I
IIIW
,~~~~~~~~~~~~~~~~~~~~M III 'fitaIIiIII
91c
s---lfi
I 1I l l lii Il
Nl UI II
0~~~~~~5 1-!
Hv~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~1
111
II II~ ~ 1 ~ ~~I I I II - II I IIill II
l'~~~~~~~~~~~~~~~~~~~~~~~~~~I
1= '~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-7j1
- -
(STOCK)
BY - LAWS
OF
ARTICLE I
No silare of stock against whiichi the corporation 11olds unpaid claim shiall be
transferable
in the hooks of the corporation.
S4
|S i i i9 > _ - .t AtsL;
.v>sJ:irs:O. . >
e.:. - - .
ARTICLE II
MEETINGS OF STOCKIIOLDERS
Sectioni 1. Aninual / Reguiar Meetings - The annual I regular meetings of stockbolders shall be
lheld at the principal office on any day in March of each year, if a legal holiday, theni on the
day following.
Section 2. Special Meeting - The special meetings of stockholders, for any purpose or
purposes, may at any time be called by any of the following: (a) Board of Directors, at its own
instance, or at the written request of stockholders representing a majority of the ouitstanding
capital stock, (b) President.
Section 4. Notice of Meeting - Notices for reguilar or special meetings of stockholders may be
sent by the Secretary by personal delivery or by mail at least two (2) weeks prior to the date of
the meeting to each stockhiolder of record at his last known address. The notice shall state the
place, date and hiour of the meeting, and the ptirpose or purposes for whiichi the meeting is
called.
Wlhen the meeting of stockholders is adjourned to another time or place, it shall not be
necessary to give any notice of the adjourned meeting if the time and place to whiicih the meeting
is adjouirned are announced at the meeting at whiichi the adjourinmenit is taken. At the reconvened
meeting, any business may be transacted that might liave been transacted on the original date of
the meeting.
Section 5. Quorium - Unless othierwise provided by law, in all regular or special meeting of
stockholders, a majority of the outstanding capital stock muist be present or represented in order
to constitute a quorumn. If no quoruim is constituted, the meeting sliall be adjourned until the
requisite amouint of stock shall be present.
Sectioni 6. Conduict of Meeting - Meeting of the stockholders shall be presided over by the
President, or in hiis absence, by a chiairman to be choseni by the stockholders. Tlle Secretary,
shiall act as Secretary of every meetings, but if not present, the chairman of the meeting shall
appoint a secretary of the meeting.
ARTICLE HII
BOARD OF DIRECTORS
BL-S-97-01
p, 3 conformed copy
ga) ro delegate, from tiine to time, any of the powers of the Board whichi mlay
lawfully be delegate(d in tile course of tile cuirent businiess of the corporation to any
st8nding or special comimittee or to any officer or agent aud( to appoint any person to
be agent of the corporationi with suchi powers and uiponi sucil terms as may be
(Ieelied fit;
h.) To iilplement these by-laws and to act on any matter not covered by these by-
laws, provided such1 matter does not requiire the approval or consent of the
stocklholders unider- the Corporation Code.
fr
Section 2. Election and Tern - The Board of Directors sliall be elected durinlg each regular
meetinig of stockholders and shall hold office for one (1) year and unltil their successors arc
elected and qualified.
Sectioni 3. Vacancies - Any vacancy occurring in the Board of Directors other thani by removal
by the stockholders or by expiration of term, may be filled by the vote of at least a majority of
the remaining directors, if still constittiting a quorum; otherwvise, the vacancy must be filled by
the stocklholders at a reg,ular or at any special meeting of stocklholders called for the purpose. A
director so elected to fill a vacancy shall be elected only for the unexpired term of his
predecessor in office.
The vacancy resulting from the removal of a director by the stockholders in the manier
provided by law may be filled by election at the same meeting of stockholders withouit fulthier
notice, or at any regular or at any special meeting of stockholders called for the purpose, after
giving notice as prescribed in these by-laws.
Section 4. Meetings - Regular meetinlgs of the Board of Directors shall be hield once a monhil
on suchi dates and at places as may be called by tihe Chairman of the Board, or upon the request
of a majority of the Directors.
Section 5. Notice - Notice of the regular or special meeting of the Board, specifying the date,
time and place of the meeting, shiall be communicated by the Secretary to each director
personally, or by telephione, telegram, or by written message. A director may waive this
requirement, either expressly or impliedly.
Section 7. Conduct of the Meetings - Meetings of tihe Board of Directors shall be presided
over by the Chairmani of the Board, or in his absence, by any othier director chosen by the Board.
The Secretary, shall act as secretary of every meeting, if not present, the Chairman of the
meeting, shall appoint a secretary of the meeting.
ARTICLE IV
OFFICER
The Board may, from time to time, appoint such other officers
as it may determine to
be necessary or proper. Any two (2) or more positions may be held
concurrently by the same
person, except that no one shall act as President and Treasurer or Secretary
at the same time.
Section 2. President - The President shall be the Chief Executive
Officer of the corporation
and shall exercise the following functions:
_._~~~Lw:lL-~~~ ...... . . .:
..........
.=-:-
h .) To exccute on belialf of the corporation
all, contracts,' agreements and othier
insirutiments affecting the interests of the corporationl
wilich require tile approval of
the Bo3ard of Directors.
BL-S-97-01
p. 6 conformre( copy
Sec(loi 6. The Treasurer - The Treasurer
of the corporation slhall have the following
duities:
a.) To keep fuill antd accurate accounts of
receipts and disburseinclts in the books of
the corporationi;
ARTICLE V
OFFICES
BL-S-97-01
P 7 confomied copy
*~ j4> -. ...Z....-
, .,* . . .....
..
.. . .......
....
-.F-f>r;e
,<o--r ........................
.................. . r:- -: .:
1.~~~~~~~~~~~~~~~~~~~~~~~~~~
ARTICLE VI
ARTICLE VII
SEAL
Section 1. Form and Inscriptionis - Tlle corporate seal shall be detenrined by the Board
Directors. of
ARTICLE VIII
AMENDMENTS
I ,i;W1i7S
- ...- h,
IN WITNESS
foregoinig WIIERIEOF,
by-laws anid we, the nidersigned
rlty lhereuniito affixed stocklholders lhave
199 ZOOat our signatuires adopted thle
,
"4l1LMYOU th)is t
C¢tiY day of
(Nole: J. Iffiled wsith
incoiporalor5; Articles of Inicorporation,
these by-laws should
2. Jffiled after he signed by all
incorpor-ation,
shouild submlit director's should be signed by majority
certificatefor the of the subscribers
adoption of the and
by-laws.)
. ~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~DIN F. B. LECAROS
l ~~ \ ~~~~
''
...
,r~az,r. ~~~~~
r--…__________
BL-S-97-01
P. 9
confo.e copy
RDS 96- 1
GENERAL INFORMATION
COMPANY TYPE
( DS - DOMESTIC STOCK |
[ I DN - DOMESTIC NON-STOCK - ] DP - DOMESTIC PARTNERSHIP DATE REGISTERED
PRINCIPAL OFFICE ADDRESS
rJ
COMPANY RELATIONSHIP - List all companies related to registrant. (Use additional sheets, if necessary)
RELATIONSHIP TYPE C - DISSOLVED COMPANY (If due to consolidation) S - PARENT COMPANY (Il registrants a subsidiary) 0 -OTHERS
(RELN TYPE) V -DISSOLVED COMPANY (If change in company type) A -AFFILIATE (Of the registrant)
SHARE P/ PAR
AUTHORIZED
_
SUBSCRIBED 1 PAID-UP '~~~~~~PAID
-IN
CODE SHARE TYPE N VALUE NO. OF SHARES
F /
AMOUNT N NO. OF SHARES AMOUNT
I
] C 1100 25,000 p 25,000,000.00 _O 62,500 P 6,250,000.00 P 1,562,500.00
AMOUNT
IW'_ _ _ ii _ _ _ _ _ _ _ 1 _ _ __ ._ _ I_
EERINALA[D
TYE
A.DPMTAf_ I iFeb.23,1952
_ __ __ _l_ _ _ _ _ _ _ _ _ _
iSARES I
!
L F-B. CE-RS
_ _ _ _ __ _ _ _ i'__ _-
I I ,______LI
_____I
IJ1 -- ______
815
1 IiliDim
llDn
_ = 'I__
21,875 2rl87r500-00 I__
5146t875.00
_C 2-1,875 2,187,500.00
A L d__ _ _ _ _Filipino
25 1936 _ ____C
|546,875.00
IAPbLON
2li;/250 625rOC?0.00 | 156_250_00
(FRE;barZ
DOrS GAY- C. {~~~Feb.
09,1949 . Filipin; _ _ C | 6,250 625,000.00 156,250.00
_____________ CENT______ ___________Oct. 05,1955_ Fili_in_
_ I
NAME'' | C 6r250 625,000_00 | 156,250.00
' 'RlNCI
PAGE2 OF 3
FILL-UP INSTRUCTIONS: Type or print legibly. Light-shaded boxes
and codes are to be filled up by the SEC,
including the SEC number.
COMPANY NAME
INCORPORATORS / STOCKHOLDERS
/ DIRECTORS / OFFICERS
= T =
NAME =
(Company Name: If company)
SEC NO. /
.
(Last Name, First Name, MI, Maiden Surname, if CODE NATIONALITY BRD INC OFR SHAR
person) BIRTHDATE R
SHARE NO. OF SUBSCRIBED CAPITAL
CODE TYPE SHARES PAID-UP CAPITAL
f,FRDDfAND A D!An O
- Fi. _ _ _5 C 21,875
A A BOB. . ._____ 2,187,500.00 546,875.00
07-28-55
i__
C 21,875 2,187,500.00
JESUS N. ALM0 | 546,875.00
12-25-36 Fi.__ C 6,250 625,000.00
CER%F=L C. DCNAY 156,250.00
| 02-09-49 Fil. C 6,250 625,000.00
MARLON M. CENTEN0 |"'156,250.00
10-05-55 | Fil. C 6,250 625,000.00 |156,250.00
._
~ ~~~ __l _ _i_ _ __ . ___I
_I_____
_______
- - siIi
l ~ ~ l !_ __ _ _ _ _ _ _ _ _ _______1_
1
E . _ ___
__
_ _ _
__ _ _ _ _ _I_I_
1----_i{jtI~ _SUBTOTALS162
______ ________________________________
--
PG C00 I
_____,[P.
Yl
, 2 000 6,500
69 ~o, oO
}'
j RE( T10. ASH_..
LAPIIAL STOCKICNCORPORATORS/DIRECTORS/OFFICERS
(FOR DOMESTIC STOCK CORPORATION
INFORMATION
ONLY)
0~~~~~~~~~~~~~~~~~~~~~I
Y B II CI_
_ __ _ _ _ _ _ _ _ _ _ _ ___1
INDIVIDUALS
COMPANY (IES)
I p
p p jp . p
TOTAL SUBSCRIBED CAPITALp i
_
p
PAID-UP CAPITAL OF - p
iINDIVIDUALS|p|p
COMPANY (IES) P
|
|TOTAL PAID-UP CAPITAL |
rp|PjP'.
' | ~PERCENTAGE OF FOREIGNf4&T`(:, ,
CERTIFIED CORRECT
iNSRUCiON A~A (SI5na2ureo0v
nmnmed
nanm( POSITION
PROCESSING ATTORNEY: DATE:
i
PROCESSING EXAMINER: -.
DAE ~o
DATA CONTROL CLERK: I
DATTEREVIEWED:I DATA ENCODER:
:
INSTRUCTIONS FOR FILLINS DATE REVIEWED
-
UP TTrE COLUMNS: DATE ENCODED:
PAR
NO PAR (P / N) FILIPINO / FOREIGN (F/N)
- VALUE
INDICATOR - WITH PAID-IN BOARD (BRD)
OWNED INDICATOR - SURPLUS? INCORPORATOR (INC'R)
p- PAR
2 F - FILIPINO INDICATOR - OFFICER (OFR) INDICATOR -
Y - YES INDICATOR LEG - LEGAL COUNSEL
^>_N_NO PAR N - NON-FILIPINO/ C - CHAIRMAN PRE - PRESIDENT
N - NO I - INCORPORATOR AUD - EXTERNAL AUDITOR
M- MEMBER CEO - CHIEF EXECUTIVE OFFICER
FOREIGN S - STOCKHOLDER GOV - GOVERNMENTREPRESENTATIVE
N - NEITHER CFO - TREASURER
N - NEITHER OTH - OTHERS
_____________,_____ COO - CHIEF OPERATING OFFICER
N - NONE
COS - CORPORATE SECRETARY
Republic of the Plilippinles
COMNIISSION
SECURITIES AND EXCHANGE
SEC Bldg., EDSA, Greenihills, City of ivandaluyong
-- ~
VERIFICATION CERTIFICATE
Date. 05/23,'2000
,
N POR.H VI 7i PO(.%AR DEV . CO P.
* VerifiedBy: LIMIUCO
LTRiTA
R E NI A R KS
~ CLD Action When Applicable
-
O Allowed
ldAvailable for use
Q Refer to Corporate and Legal Dept.
3 Not Allowed
O Modify; subject to reverification
RESERVATION NOTICE
| §)1k X
0 to 0 6/ 2 2 / 2 0 00
C
has been reserved from 0 5,' 3/ 2 )
I'' In IdoIrsellzent
I J'llaher 21()()(
ta\orahle
1u01inloIlla.tmOnl and12 .l5cuitosmdrtlc ion
ARTE 11 I UXILA()
SsEIIS/OICl', P YR (ffice
I~~~ ~~/U1~~~~~~~/
Republic of tie Philippines
Department of Environment and Natural Resources
.)A WlT XI:\'lRC)NAET A NIA)
INE 'N7 NA TIR I?,RS(lhJRCES OFFICE
Manayon, Bangul. llocos Norte s r;
~\,' ~
.\/(!/d.'N1)/ \1 ~ ~ ~ ~ ~ ~ ~ ~ A -
IA N' I0
IN I le Regional 1irector V, /4i,
I
Environmental Management Bureau
I i Rt e P'1;,jVl? Officerl
PENRO-liocos Norte -- ; _2. : .
Respectfully forwarding herewith the EIA Inspection Report together with the
mIlalnIdatory requil-ements leading to the issuance of an Environmental Compliance CerTificate
i elative to the above-mentioned subject.
-.m1\Ferdmnand A Dtuiilko
hairman. Board of Director
oItlTt\ itd Pom\ cr DcN clopnieilt (orporainon
^'1 ( Jlllbc. Pli/a Buildlinig
BI 3it
i mcrald X\,:cim. ()ri ;,s (OUter
69;!t:w49T-EN-f OF ENVIRONMEN!
sg'
:s {'i's' t^ V'A' Rt-5OUkCES
T' ENVIRONMe-Ni I
J4L RESOURCE5
JA OF' ."
_4Nt0tI . ILOCOS NOPTP
I. I Conduct of actual survey at the proposed project-site of about-808,630 square meters afea
for the final lay-out of wind tower is on-going during the time of inspection. Around 30
unit turbine with 660 kW rated capacity each will be built on selective site along the bay;
according to Mr. Allen Dumlao, the representative of the Northwind Power-Development
Corporation;
1.2 There was no sign of equipment mobilization nor excavation activity was noticed during
the time of inspection Only survey team members were present at the area; and
1.3 The project proponent has submitted the ECC mandatory requirements except for the
Locational Viability and Engineering Geological and Geohazard Assessment Report
(EGGAR) in consonance with DENR DAO 2000-28 which is the "Implementing
Guidelines on Engineering Geophysical and Geohazard Assessment as additional
requirement for ECC applications covering Subdivision, Housing and other Land
Development and Infra Projects". More so that the project proponent wishes to construct
a 15.0 m x 20.0 m Control Center/Office building and a 10.0 m x 30.0 m
warehouse/switch gear room.
2 I The proposed project site of about 808,630 square meters underdeveloped foreshore area
which ranges from 0-3% slope or maybe considered as flat terrain has a black core, beach
sand type of soil;
-~~~~~-1
Re: EIA Report on the Applicationfor Bangui
Bay 60 MWNorthwind PowerProject; Page 2
2.2 The identified project site is located along the underdeveloped foreshore area of
Barangays Baruyen, Taguiporo, Manayon, Masikil and--Abaca all at Bangui, Ilocos Norte.
Foreshore lease covering the whole area is in the process which was filed at the CENR
Office, Bangui, Ilocos Norte on September 11, 2000. Said Lease Application have
already been indorsed by this Office to the Offices of Department of Tourism, Philippine
Ports Authority and Department of Public Works and Highways;
2.3 It was observed that there are no indications of landslide prone area. Excessive soil
erosion is unlikely to occur since the shoreline moves seasonally, while run-off during
rainy days will drain off to the sea; and
2'4 There are no existing timber type of trees in the proposed project area, only few seabirds
(haliastur indus) were noticed during the time of inspection.
3 1 The proposed project site of about 808,630 square meters underdeveloped foreshore areas
of Barangays Baruyen, Taguiporo, Manayon, Masikil and Abaca is located south of the
town proper of Bangui, flocos Norte. Brgy. Baruyen lies of about five (5) kilometers
from the town proper while Brgy. Abaca is adjacent to the town proper. The subject
foreshore area has an average of 300 meters horizonital distance from the existing national
road towards west.
4.1 The proposed Bangui Bay 60 MW Wind Power Project covers a total foreshore land area
of 808,630 square meters. About 600 square meters will be occupied "v
ControUCenter/Office and warehouse/switch gear room buildings- and, an area to -be
occupied by 30-unit windmill towers; and
4.2 The proposed project is intended to generate a- total of 60 MW electricity from wind
power in three phases.
Negative:
Positive:
I. Existing access road to the vicinities of the proposed project site may be improved
where public may be allowed access;
2. The project is expected to attract tourists and other investors in the area;
-2-
Re: EIA Report on the Application for Banguii
Bay 60 A'!W ANorthwind Power Project;Page 3
4. There will be an increase of economic activities due to local hiring, local purchases of
foods and other services, and
2. The project proponent is advised to acquire sand and gravel quarrying permit from
the agency concerned with corresponding ECC from the DENR;
3. Sprinkling of water to stockpile of soil, sand and gravel materials in the- project area
should be maintained to minimize dust;
4. The project proponent is advised to furnish this Office copy of Locational Viability
and Engineering Geological and Geohazard Assessment Report (EGGAR);
5. The project proponent shall comply with all the mitigating measures that have been
identified in their IEE report under consideration; and
6. The proponent shall not allow his conVeyan-ces for the transport of illegally cut
lumber, mines and quarry resources and other DENR controlled/regulated products
without the necessary permit therefrom.
Based on the foregoing, the project proponent is recommended for the issuance of an
Environmental Compliance Certificate (ECC).
Prepared by:
ENGR GRIO
SpL InvestA,ator:OIcX EMS
Attested by.
8klJOSEFIO L. AOUOA
CE'NR Officer
: eja.
f,lI,,,i 3oc
December 5, 2000
ECA CERTIFICATION
Ihlis is to certify that the proposed Bangui Bay 60 MW Wind Power Project
(indicate name of project/undertaking)
ott Northwind Power Development Corporation represented by
Atty. Ferdinand A. Dumlao-
(indicate name of proponent/applicant)
located in Barangav Baruven to Barangay Abaca. Bangui. flocos
Norte (as shown in the
attached location map) has been determined to be within the Bangmi
Bay/Foreshore Area an
(state ECA category)
identified Environmentally Critical Area.
b JOSIEF L. AQUIOAG
(CENROfficer
DEN R-CENRO No ___
CEIRTIFICATTON
A1vemlL', ()relcs ( nt
li elr, I'asig Cl has complied with the requirement to secure an
Environmental Compliance Certificate (ECC) for his Ban.cui Bav 60 AMW Witd Power Projec
(tIype of project) located at Brgy. Baruyen to Brgy. Abaca, Bangui, Ilocos Norte.
l) JOSEFINO L.jA4 OA /
''Cl,
,,, 1'/ ,
ENVIRONMENTAL COMPLIANCE
CERTIFICATE
_ _
-2 18 0036 - 1405
3> > Department of
Republic of the Philippines
Environment and Natural Resources
Regional Office No. 1
City of San Fernando, La Union
Tel. Nos. 888-38-33 * 888-29-75
KALYAA
KALAYAAN
I*VU*AN NC
Pursuant to the provisions of Presidential Decree No. 1586 and the Department
Administrative Order No. 96-37, the Department of Environment and Natural Resources
(DENR), Region 1, hereby grants this Environmental Compliance Certificate (ECC) to
the NORTHWIND POWER DEVELOPMENT CORPORATION (NWPDC) for the
proposed Infrastructure Project (40 MW Wind Power) located at Bangui Bay from
Brgy. Baruyen to Brgy. Abaca, Bangui, llocos Norte, which has been identified as
within the Environmentally Critical Area (ECA) subject to the following conditions:
1 That the proponent shall secure prior to project implementation all necessary
permits/clearances from concerned government agencies with administrative
jurisdiction over such projects/operations, i.e., DENR-EMB, MGB, LGU, DPWH,
PPA, DOTC, etc.;
2. That this Certificate covers the construction and operation of the proposed 40 MW
Northwind Power Project consisting of 30 units turbines with 660 KW rated capacity
and/or alternative 12 units turbines with 1.75 MW each, transformer station equipped
with switch gear room/warehouse, and control center office;
4. That the proponent shall apply for a Foreshore Lease Permit within ninety (90) days
after the issuance of ECC, and shall properly coordinate with the CENRO concerned
for the adoption of measures to prevent overlapping of projects within the foreshore
area;
5. That the proponent shall submit a modified Geological Fault Map as guide/reference
in the construction/installation and design of wind towers and similar activities and
appropriate measures be adopted to prevent hazards, accidents etc.;
6. The proponent shall not allow his conveyances for the transport of any mine and
quarry resources and other DENR regulated products without the necessary permits
therefrom;
8 That all applicable mitigating and enhancement measures embodied in the IEE
documents submitted (Section D Impact Assessment and Mitigation) shall form an
integral part of the ECC Conditions which shall be undertaken in all phases of project
implementation;
9. That the proponent shall appropriately locate the row of turbines closed to the sea to
prevent significant sound emissions; and
10. All damages or adverse impact to the environment resulting from non-adoption of
appropriate or adequate mitigating measures during the implementation of the
project shall be the sole responsibility or liability of the proponent.
Non-compliance with any of the above conditions shall be sufficient cause for the
suspension or cancellation of this Certificate andior a fine in the amount not to exceed
fifty thousand pesos (P50,000.00) for every violation thereof, at the discretion of the
Department (Section 9 of PD 1586).
Given under the seal of this Department at City of San Fernando, La Union this
8th day of December, Two Thousand.
Recommending Approval:
J . SAVADOR
Regional Director
Environmental Management Bureau
Processing Fee P 3,600.00 O.R. No. 6963883 Date 12-05-2000
Filing Fee : 1,560.00 O.R. No. 6963883 Date 12-05-2000
Legal Research Fee: 240.00 O.R. No. 6963883 Date 12-05-2000
Procedural Screening Fee 600.00 O.R, No. 6963883 Date 12-05-2000
TIN
. >s', , ~~~~~~~~~~~~~~~~~~~~~~~~~-3/8"
0 bCs'N/A
,
F9W4rO'>W>tB s
,
e~~~~~~~~38 F'3t
IE o W/AS'
GROUNDW,RE- =
FABMIK
CONSTRUCTION CO.,INC.
C EOUIPMENT
aYF.d P.a.DVT-,
20\ FI-Cooe
- ~~~~D.I
CH..O A.*M"Clv
000.
= o031
F.. N.oM102
N. 1321 02
OMI2
Of PROPOSED
PMSFBCTIVB 09 kV T'lL
15.2KVL*3ERStiLT LINE
WITHEXISTING1
I CEIOIO
FI 0204 _ _ _ _ _ _ _ _ _ _ _
601 NTS
~~~~
r- -
oM o 69 sV T/L
o
o ' E0_ 4 o - Gl~UfI4
I I ~~~~~~g
z
0
1-I
l ~~~~~~~~~~C,'
CONSTRIJCTION a,
EoUIPrEtr co.., MN.
ar_|
z e-K - rlSial FMFBMIKt
OF PROPOSED 69 KV 1 -/L Gn __
S Cl~~~~~~~~~tz. HO IA VGWIEW Aff___ C
1-ui
cn
w ~~SIGNATURE:
~ (.
BACK FILL
CD (~~~~~ACH SAND) 0 0 ~~
~ ~~ ~ ~ ~ ~ ~ ~~~~~~~~~~~~~C £SUBBA
C)~
E r | . o-t | ¢ ^ [ <
E
1 L= BEACH SAND
1 0 300 7 300 700
CONCRETE ENCAS
0 MV CABLES
CABLE TRENCH
WIDTH OF TRENCH
00
TYPE NO. OF CABLE SYSTEM
00 CONTROL AND M\
|D' 70 300 150
- cstRTac.s En
p~ETPACIFCCONSUTANTS
_
nNTERJHA
a2in PACKAGEI A HW
lmrim ,t )
-@
NTERNATDNAL ~~~~~sU.it
D@I ________ _PROJECT,