Permit To Work Proceduce
Permit To Work Proceduce
PROCEDURE
This Permi to work (PTW) is designed to ensure that all elements of risk in work activities are considered in the
planning, approval, preparation, execution and completion of the strictly activities in Hayat area.
It is aims to create a safe working condition by providing management control over the work activities. The PTW
procedure serves as a tool to:
All PTW issued for the work activities shall be documented and the records maintained for the duration of takes
place. HSE team will save this docs in 3 months.
This management plan applies to all project personnel and Subcontractors working at Hayat site and all
employee of Hayat Kimya Vietnam .
2. DEFINITIONS
PTW: a written document that authorizes certain people to carry out specific work at a certain time and with
stated precaustions to complete the job safely.
Safety requirement: safety measures to be observed in the acvitities
3. RESPONSIBILITY
The following roles and responsibilities are assigned to all personnel involved in the planning,
approval, preparation, execution and completion of work at the construction site.
Before conducting work that involves entry into confined space, work on energized systems, ground disturbance
in locations where buried hazards may exist, or hot work, a permit will be developed by the Sub-constructor Site
Manager/HSE officer and submit to Hayat department Manager who requested that activities to review and sign
off in a form including information of:
PERMIT TO WORK
PROCEDURE
Defines scope of work;
Identifies hazards and assesses risk (risk assessment matrix);
Establishes control measures to eliminate or mitigate hazards;
Specifies the PPE to be used;
Links the work to other associated work permits or simultaneous operations;
Is authorized by the responsible person(s) within HAYAT’s management team;
Communicates above information to all involved in the work; and
Ensures adequate control over the return to normal operations.
PTW form is attached in Appendix.
The PTW will be issued for the duration of one week. New PTW will be issued when the current PTW expired.
PTW number will be recored in a log.
When issued, the original copy must be kept at the work site. One copy will be kept at related Section Office and
one copy will be kept at the HAYAT HSE Department.
PTW will be closed at the completion of the work.
Document to be attached
Supporting documents including risk assessment and method statement. Specific documents need to be
attached based on specific works (for example lifting plan etc).