How To Add Resources Dictionary To Primavera Using Excel
How To Add Resources Dictionary To Primavera Using Excel
Make sure that you have effective date in the (unit and Prices).
1
How to Add Resources dictionary to Primavera using Excel.
Prepared By: Shareef Makhool
5- Now go back to the Excel sheet and make filter on your unit of measure
Make only one unit of measure to one resource (it means if you have 6 unit of
Measures, you assign only 6 resources, each resource with one unit of measure)
2
How to Add Resources dictionary to Primavera using Excel.
Prepared By: Shareef Makhool
8- Paste them on new Excel sheet and keep the selection in the Notepad.
9- If you notice here we have some categories in the selection :
rsrc_name : Resource name that we will change it according to our resources names .
rsrc_short_name : Resource ID
3
How to Add Resources dictionary to Primavera using Excel.
Prepared By: Shareef Makhool
Now try to understand that P6 is using Unit-id (100, 150, 151, 152, etc.) instead of unit
description.
So you will go back to the excel sheet that you have prepared in the beginning and add
new column beside unit of unit of measures , then you will make filter to each unit of
measure and type its ID according to the given ID by primavera :
d- To assign the Prices for these resources , if you see that we have another part in our sheet ,
which contains
Each resource here has a Primavera ID (rsrc-id), you will match the previous list with the
resources prices in the prepared sheet and to fill the prices in the column E, (cost-per-
qty).
Most of times the order of the resources are matching with the above list so no need to
make lookup matching but you need make sure for that .
4
How to Add Resources dictionary to Primavera using Excel.
Prepared By: Shareef Makhool
e- Now we have inserted everything needed for our resources, so we will replace all of these
data in the sheet with the selection that we made in the Notepad, save the changes in
Notepad and Close it. (to paste the selection > use Edit and then paste / Don’t use Ctrl+V )
Make sure that the selection from Excel is containing all rows till column (AF)
f- Go back to P6 and import that file again and set the option (create new ) while importing
As you see, after we import the project, we got all our resources with prices and units of
measure.