2009 June
2009 June
ltlll !ilil
city$p
Guilds
616s-O23 JUNE 2009 Technician Diploma in Construction Constru ction tech n iques 2
Wednesday 1 0 June 2009 09:30 - 1 1:30
You should have the following for this examination
. a multiple-choice answer sheet . a pen with black or blue ink . a non-programmable calculator
This question paper is the property of the City and Guilds of London lnstitute and is to be returned after the examination.
Read the
following notes before you answer any questions . You must use a pen with black or blue ink to complete all parts of the answer sheet. . Check that you have the correct answer sheet for the examination. . Check that your name and candidate details are printed correctly at the top of your answer sheet. . lnform the invigilator if your name or examination details are not correct. . Each question shows four possible answers (lettered 'd','b', 'c'and 'd'); only one is correct. . Decide which one is correct and mark your answer on the answer sheet with your pen.
For example if you decide 'a' is correct, mark your answer like this
mlo
If
[c**i
e
t
@
I
lf you want to change your answer, cancel your first choice by filling in the 'cancel' box below the circle like this
mo
f
@o
crcr ttc-*r
@
lc"m
I
Then mark the answer which you have now decided is correct. For example if you now decide 'c' is correct, mark your answer like this
,l' o o o
trc"r"o-"r""r
\!/
I l-c-""1
t
l-c*r
Any other marks on the form may invalidate some of your answers.
. Any calculations or rough working can be done on the question paper. . Attempt all questions. lf you find a question difficult, leave it and return to it later.
This paper contains 60 questions. Answer them using the ,boxes' numbered 1 to 60 on the answer sheet.
lllilt
l]ililil
067 7 64a
Corrugated metal or plastic roofing sheets on angle iron purlins are normally fixed with
a b c d
a b c J
Cavity ties in cavity walls are normally spaced at not less than
,/
high-rise flats large span storage areas dwelling houses multi-storey offices.
'? b c d
5 per m2
6perm' Tperm'
8 per m2.
The purpose of using trial holes on site before commencing construction of a building is to
a
c d
assess the type of excavation needed investigate the nature of the site substrata decide on the foundation excavation sequence assess the need for trench timbering.
c
d
A mechanical backactor with a 600 mm wide bucket is most likely to be used for which type of excavation work?
q ,directly onto the sub base concrete \&' on a polythene damp-proof membrane c on a coating of bituminous paint d over an asphalt membrane.
How many thicknesses of tile do interlocking concrete roofing tiles require at the lap?
a b c d
11
A plain concrete stepped strip foundation is likely to be used on which type of ground?
6 b c d
Clay.
mild steel bolts with clearance holes high tensile steel bolts in holes with no clearance riveted con nections only welded connections only.
12
Figure
IS
067 7 647
13
20
a b c d
14
The first coat of paint applied to an unpainted surface to provide adhesion for further coats is termed
a b
c
d
21
/a b c d
15
conceal the joint between lining and plaster cover the edge of wallpaper conceal the planted stop on the lining cover the joint between lining and door.
22
a b c d
a b c O
16
ln a hot water system which includes a hot water storage cylinder, the draw-off pipe to the hot water taps is located
a b c d
23
at the top of the cylinder midway up the cylinder near the hot water inlet.
a b f d
17
prevent rising damp break capillary action disperse driving rain prevent water retention.
A wall built between the land of one landowner and the next is termed a
The location of basic reinforced steel in a cast in situ concrete stairway supported at top and bottom only is
a b c d
24
a b c d
18
close to the soffit of the stairway across each step only at the connection to the landing only at the junction between tread and riser.
a b c d
25
Balusters on a stainvay are fixed between riser and tread handrail and stringboard c - ,rise and going 6 newel post and trimmer.
1-
horizontal support wires between the posts vertical support wires between the posts no support wires between the posts diagonalwires between the posts.
a. '
19
Ceramic tiles used as a floor finish to concrete floors are considered to be which type of finish?
a b
C
v
a
c d
067 7 64l-
26
When contractors get smaller companies or trades people to undertake work in their specialist areas, it is known as
a
32
.V
C
"t c
d
Excavating a trench. Reduce levels over a large area. Loading a lorry. Moving spoil across site.
27
a b c {
28
a
is restricted in the type of work that it is allowed to undertake works to the limits of its ability has a limited annual turnover has limited liability status.
Pedestrians prohibited everywhere. Professional people exit. Personal protection excluded. Personal protective equipment.
_ts
c d
29
Figure
34
a , "b c d
30
craftsperson who is responsible for the day-to-day building work person who provides assistance to the craftsperson to enable them to perform their work supervisor in charge of the building team person who controls the deliveries of materials onto the building site.
,{ b {
d
hard hats must be worn on this site hard hats may be worn on this site workmen only past this point beware of falling objects.
Which item of mechanical plant would normally be used to excavate a foundation trench?
a
d
d
31
The most appropriate mechanical plant required to reduce level dig down to formation level for a motorway is
a
Figure
35
"V c
d
a b c d
0677 64L
b
c
d
multi-storey blocks single-storey, wide span structures monolithic structures two-storey office blocks.
I
I
. s.so, ,l
Figure 6
a b c d
40
12.57 m2
a
b
C
3m 4m 6m 7m.
The net area of facing bricks in a wall 7500 mm x 4000 mm with two windows size 1200 mm x 1200 mm is
a b c d
41
PLAN
The area of facing bricks required for the external skin of a wall with an overall plan size 7500 mm x 3500 mm and a storey height of 2700 mm is
a
l, -4L600Jzeoo J
Figure
sEcloN eA
5
b
C
38
m3 m3 m3 m3.
Area of brickwork 150m x 23m Area of doors and windows 1 125m2 Net unit rate per m2 for brickwork $30.55
Figure 7
42
Using the information given in Figure 7, calculate the cost of brickwork for the wall.
a b c d
0677 64L
43
47
have written in requesting to quote for all kinds of work b wish to quote for work that only they 7 CeIt do have been selected by the client or "/ building team as being capable of undertaking the work proposed d wish to select the type of work to quote for.
a b ./ ,d -d
estimator to price the most appropriate plant and method of working for a major operation foremen to tell the bricklayers how to lay bricks architects to present their plans quantity surveyor to create a checklist for'taking off' quantities.
Area of wall 985 Area of doors and windows 92 m2 Net unit rate per m2 $27.59
i0 i5
Figure
4B
I @ $12.00 per
10ur
Calculate the cost for the net area of brickwork as shown in Figure 9 (nearest full unit of cost).
a b
Figure 8
44 How many hours (nearest hour) does it take a team of bricklayers to lay the bricks in Figure 8?
a
v
49
$ $ $ $
,{
c
d
Which one of the following is a bar chart typically used for construction programmes?
45
The process required to calculate the quantities needed for a contract is known as
a b c d
46
Bricklayer
a
-v c
d
1: 2: 3: 4:
Labourer
1 1 1 1
0677 64L
Centre line of trench 23.40 metres Width of trench 0.60 metres Depth of concrete in trench 0.225 metres Output for placing concrete 1.75 man hours per m3 Number of operatives 3
54
Which one of the following must be included in a simple bar chart construction programme?
-{b
C
Figure 10
50
Using the information given in Figure 10, how many gang hours does it take to lay the in situ concrete in the foundation trench?
55
/
51
b c d
c
d
The manpower and equipment requirements for a particular operation are stated in
-{ d
52
Centre line measurement. Site manager's name. Parties to the contract. Cashflow statement.
57
a b c d
An order of materials is received on site. Which document would the supplier send for signing to acknowledge receipt of the goods and advise what has been delivered?
a b
c
a b y' d
A contract for a subcontractor is issued by the client architect ,,y'main contractor nominatedsubcontractor.
Date of commencement, duration of operations, date of completion. Quantities, duration of operations, sequence. Quantities, duration of operation, date of completion. Date of commencement, duration of operations, sequence.
by
a b
-.Xb c d
weekly site meetings interim valuations cost in use calculations cosUvalue analysis.
0677 64a
59
.y
c
d
totals are automatically changed when altered it is easier to read everyone can use it.
.{ b c d
calculation of total operative costs rate of pay operatives receive tax and deductions from an operatives wage cost of plant and machinery on site.
IMPORTANT Are the details at the top of the answer sheet correct? Have you filled in your answers in INK in the appropriate boxes on the answer sheet?
0677 64l-