Building Contract Procedures in HK
Building Contract Procedures in HK
'
t
[
I
t
'-
;
~
i
L
i
f•
~
f
!
Building Contract
f
t Procedures
,
[
"
in Hong Kong
Fourth Edition
1993
)
I,.
~ Martyn J ames Hills
r
,r MSc MCIOB
! Lecturer in Construction Management
Hong Kong Polytechnic
I.
,
r
i
'
HONG KONG POLYTECHNIC
LIBRARY ..._
1/ .'
"
Copyright © Martyn James Hills 1993. All rights reserved. No part of this publication may be reproduced or
transmitted, in any form or by any means, electrical or mechanical, including photocopying, recording or any
information storage and retrieval system, without permission in writing from the author.
ISBN 962-367-013-3
Published by
Printed by
.-
~.
' ..'hod
-.".
"
For my sister
Jenny
-~--
ACKNOWLEDGEMENTS
A special debt of gratitude is due to Mr. John S. Ratcliffe, Head of the Department
of Building and Real Estate from September 1987 to July 1993. As a result of John's strong
backing for my study leave application, I was given the opportunity to pursue, and
successfully complete, a full-time Master of Science degree programme' in Construction,
Management at the University of Bath. The intellectual stimulus provided by that course of
study had a direct bearing on my decision to produce afourthedition.
Finally, my sincere thanks are extended to the many friends and colleagues who, over
the years, have provided the necessary moral and practical support that has made the
production of this book possible. In particular, 1 am very grateful to MaTian Wu, Peter
Smith, and David Peart for their invaluable contribution to the third edition, and Derek
Lane-Smith for his assistance in the production of both the third and fourth editions.
v
CONTENTS
Page
ACKNOWLEDGEMENTS v
INTRODUCTION Xl
3.1 Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
3.2 Agreement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
3.3 Frustration . . . . . . . . . . . . . . . . ". . . . . . . . . . . . . . . . . . . . . . 26
3.4 Breach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
4.1 Damages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.2 SpecifIc Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4.3 Injunction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.4 Rescission . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.5 Quantum Meruit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.6 " Limitation of Action . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
vii
page
10.1 Insurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
10.2 Building Contract Insurances .......-. . . . . . . . . . . . . . . . . . 79
10.3 Indemnity and Insurance Clauses . . . . . . . . . . . . . . . . . . . . . . 82
10.4 Surety Bond . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
VllI
,
page
ix
page
APPENDICES
GLOSSARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 164
BIBLIOGRAPHY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 180
INDEX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
x
-...,---
INTRODUCTION
It is co=on practice in the building industry to use standard forms of contract. A standard
form is simply a document setting out the rights and duties of each party, which may be used
for any contract of a similar nature. For the purposes of clear explanation and consistent
analysis, one particular standard form of building contract has been chosen for reference
throughout this book. This is a standard form of contract widely used in the private sector
of Hong Kong's Building industry, and is termed throughout the book as the HK Standard
Form. The full title of this contract is:
This form, issued by The Hong Kong Institute of Architects, has traditionally been referred
to as the HKIA Form. The other edition of the same form - First RlCS (HK Branch) 1986
Edition - is issued by The Royal Institution of Chartered Surveyors (Hong Kong Branch).
Both Editions are issued under the sanction of The Hong Kong Institute of Architects, The'
Royal Institution of Chartered Surveyors (Hong Kong Branch), and The Society of Builders,
Hong Kong.
In order to appreciate the logic behind the structure of building contracts, it is necessary to
have in understanding of the principles -of contract law; the fIrst section 'of the book is
devoted to providing that understanding. The law of contract - a branch of civil law as
opposed to criminal law - imposes a liability based on a legally enforceable agreement
between the parties. Another branch of civil law is the law of tort, under which liability is
based on the concept of a legal duty of care not to injure persons or their property. Under
certain circumstances, particularly in cases of negligence, tort may interface with and even
overlap contract. Tort is therefore referred to at relevant points in the text, although
comprehensive coverage is beyond the scope of this book. However, for those who wish to
discover more, the bibliography provides an extensive guide to further reading.
Xl
t
Much of the law of contract, particularly concerning the formation of contracts, has been
derived from case law. Case law is the area of law that has evolved as a result of decisions
handed down by the courts over the years but it should be remembered that the establishment
of precedents is not purely historical, it is a continuing process~ These decisions are
subsequently adopted as the rules to be followed, in other words, they es~blished precedents.
Due to the special relationShip that exist between Hong Kong and the United Kingdom, Hong
Kong law closely follows that of the English system of law which is why decisions handed
down by courts in England, as well those in Hong Kong, often establish precedents which
are followed in Hong Kong. As court cases are referred to throughout this book, by way of
example or to show where precedents have been established, it is important to be aware of
terminology applied to tIie parties in a case. All court cases have a party bringing the action,
known as the plaintiff, and a party defending, known as the defendant. The ruune of the
plaintiff will always be given fIrst in a case. Appeal cases use the terms appellant and
respondent.
Note: The terms builder and contractor, and client and employer, may generally be used interchangeably.
However, throughout this book the terms emplayer and contractor (and where appropriate main contractor)
are used, to be consistent with the terms used in the HK Standard Form ...
1
ONE FORMATION OF A CO~'TRACT
The essential requirements which must be present in a valid contract are as follows:
• Consideration - must be given by both parties except for contracts under seal
(See 1.4 for details)
• Contractual capacity - each party to the contract must have the legal capacity
to enter into a contract and in some cases this is limited (See 1.5 for details)
• Genuiness of consent - the parties must intend to enter into legal relations and
must do so of their own free will (See 1.6 for details)
• Legality of object - the contract must not be for an illegal purpose (See 1.8
for details)
In the absence of one or more of these essentials, the contract may be void, voidable,
or unenforceable.
Void contracts are destitute of legal effect; that is they are not contracts, and
agreements of this kind do not confer legal rights on the parties .
. Voidqble contracts are those which may be made void' at the instance of one of the
parties. For example, a. contract which is induced by fraud, can be avoided by the
party deceived. - • -
Unenforceable contracts are those which are valid but are unenforceable at law
because of the absence of either evidence of the contract or the form required by law.
For example, some contracts which are not evidenced in writing are unenforceable I
at law.
i
1.3 Offer and Acceptance
Offer
2
...i
There is no requirement that the word offer must be used, and an offer is no
less an offer because some other word such as estimate, quotation or even
order is used, which are terms frequently used in the building industry.
If the offeror gives a time for acceptance it will end when that tiple
has passed without acceptance. If no time is specified it will lapse
when not accepted within a reasonable time. The court will decide
what is and what is not a reasonable time.
III Rejection
III Revocation
Invitation to Treat
3
ONE FORMATION OF A CONTRACT
-'
l
Examples of invitation to treat are as follows:
The customer by taking the goods from the shelf and presenting them
at the cash desk is making an offer. which the cashier may accept or
reject.
These are normally invitations to treat because the law does not
consider there is an intention on the part of the advertiser to sell at the
price stated (unless the word offer is used). Generally •..adyertisements
-Dnly invite offers; price indicates the lines along which an offer may
be made.
11 Auctions
Tender
A tender is an offer. Companies often invite tenders, that is they ask oth~rs
. to submit details of prices at which goods or services may be bought. There
are two types of tender: where the tender is an offer to supply a specified or
definite quantity of goods or services known as a single tender; where the
. tender is an offer to supply goods or services as required over. a period of
time, knciwJ,1 as astandjng tender
Acceptance
Just like offer, acceptance may be oral, in writing or by conduct. The offeree
must accept all the terms of the offer without any qualification or amendment.
Th~ptance must beco=unicated to the offeror •.. However, under some
circumstances conduct may be sufficient evidence of acceptance.
4
ONE FORMATION OF A CONTRACT
'" For example, if a person owning a flat asks a builder to call around to the flat
I to carry out certain repairs, and the builder does so, there is a legally binding
contract; the builder having accepted the flat owner's offer by conduct.
The reason for this exception is that the offeror, by either expressly or
implicitly authorising an acceptance by post, implies that the postal
authorities are acting as his agent for the purpose of receiving
acceptance. Legally, co=unication to the agent (in" this case the
postal authorities) is deemed.to be co=unication to the principal (in
this case the offeror). However, the postal authorities cannot be held
j responsible for the consequences of loss or delay of letters of
acceptance. Under the terms of their contract with customers, the
postal authorities exclude liability for loss or delay of any item.
5
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ;! -
" L
ONE FORMATION OF A CONTRACT
in England. It was held by the court that the contract had been made
in London, since the defendant's acceptance of the plaintiff's offer was
not complete until it was actually received by the plaintiff.
Consideration
Consj\leration is essential to the. formation of all contracts not under seal and
has been defmed as: Some right, interest, profit or benefit accruing to one
party, or some forbearance, detriment, loss or responsibility given, suffered
or .undertaken f7y the other.
In the case of a building contract, the contractor constructs a building for the
employer who in turn pays the contractor an agreed sum of money. The
contractor has given consideration to the employer by constructing the
building 2nd the employer has given consideration by paying the contractor.
Over the years certain rules have evolved concerning consideration, these are
as follows:
6
.,.I .
I ONE FORMATION OF A CONTRACT
The court will not inquire into the value of the consideration given to
the other party, providing it is valuable consideration, meaning that it
has some monetary value. For example, a contract will be binding if
a Rolls Royce is exchanged for a bicycle as both have value, even
though not equivalent.
* ~ 0\. aml~ 121 To carry out an existing contractual obligation does not provide
consideration
~ To a;v..A~--t.2
i kl'- ~ l5V\ In the case of Stilk v. Myrick (1809), the plaintiff, Stilk, was a seaman
i· )(- '1-Pf )A.n& ~ who had contracted to work on a voyage for £5 a month. There were
I {~I \I\,~I
eleven men in the crew. During the voyage two seamen deserted. The
captain agreed to share the wages of the two deserters between the rest
I itT>ob~~ of the crew, providing they worked the ship back to London. Stilk
, 'vvt- ~v..o'v to'"M~ asked for his share of the extra money upon their return, but did not
~Cb Ifi7lII:s. (71'\. 1T1M.l1.. receive any, and so he sued the captain. It was held by the court that
Stilk was already under a contractual obligation to work on the ship
~d~~~
and was therefore not entitled to receive any extra money.
-to £1\. Ir-e. ~tW' ALL- \
tlJ",-c;- -\: ~ :..tk 0 ~la.v,-t
Only a person who has himself given consideration will be able to
t;lo. 'Mic ~ tW-. - enforce a contract
I w.,,(,o
" av:.., unt -"> ~
, S'V) The relationship which existS between the parties to a contract is
1 ' known as pn'vity of contract, since only the parties to the contract
provide consideration.
I
I
I _.
I~ 7
1 r
ONE FORMATION OF A CONTRACT·
A party may make a promise under seal which is enforceable, even though
there is no consideration. In other words, a party could carry out some act
. or promise, and providing the contract is under seal, would receive nothing
from the other party. This would be accepted by a court of law and is the
major difference between a contract under seal (a deed) and a simple contract,
which does require consideration.
Adult citizens have full capacity to enter into any kind of contract they wish, but a
few groups of persons do not have this power in full; they are said to be, under
incapacity. The groups concerned are minors, persons mentally disordered or under
thdnfluence of drugs, and companies.
8
ONE FORMATION OF A CONTRACT
III Minors
III Companies
A company which has been properly formed, following the procedures laid
down in the Companies Ordinance, is a statutory corporation. It is recognised
by the law as having a legal personality of its own, quite separate to that of
its members, and has the same contractual powers as a person of full age and
capacity. The memorandum of association contains details of the company's.
business and defines the objects of the existence of the company. Any action
taken by the company which is either outside the provision of these objects or
not closely related to them is said to be beyond the power of the company
(ultra vires). It is through this doctrine that a company may lose its capacity
to enter a valid contract.
A contract may become void if there is no genuiness of consent between the two
parties. Consent may render the contract void by mistake, misrepresentation, or
duress and undue influence.
Mistake
9
-;
-'
ONE FORMATION OF A CONTRACT
However, a mistake over a matter of fact may occur during the formation of
an agreement which at co=on law may make it void as a contract. This
does not apply to a mistake of law as we are all presumed to know the law.
A mistake of fact is confmed to four cases:
If the parties are mistaken as to the identity of the subject matter of the
contract, the contract will be void. For example, if Mr. Leung owns
two plots of land, plot X and plot Y, and offers to sell plot X to Mr.
Poon, and Mr. Poon accepts in the belief that Mr. Leung is offering
him plot Y. The minds of the parties are not as one; there is a mistake
as to the identity of the subject matter.
If one party is mistaken as to the identity of the other, the contract will
be void. For example, Mr. Au, by mistake, makes an offer to Mr.
Yip believing him to be Mr. Tang, and Mr. Yip (who is aware of Au's
mistake), accepts. It is for .this reason that a forged signature will
make a contract void.
This occurs where the parties agree, under a mistaken belief co=on
to both, as to the existence of a specific thing or state of facts which
forms the basis of the agreement. For example, if both parties are
under the mistaken belief that a property, which is the subject of the
contract, can be used for industrial development, when in fact it is for
residential development only, then the contract will be void.
Misrepresentation
10
...
ONE FORMATION OF A CONTRACT
11 Innocent misrepresentation
If for example one party makes an untrue statement to the other party
believing it is wholly true, then it is up to the court to decide whether
the contract is void.
Duress is limited to actual violence or threats to the person while the contract
is being carried out.
Undue influence requires that the party seeking to stop the contract must
prove that he was-subject to influences which excluded free consent. For
example, in the case of blackmail, where one person threatens to divulge
damaging information about another if he does not enter into a contract.
In most cases, with regard to simple contracts, it does not matter which of the various
forms of simple contract is used, and a contract made orally or by conduct will
usually be just as effective as a written one. However, in some circumstances written
formalities are required.
11
,
ONE FORMATION OF A COr..'TRACT
• Share transfers
,.
• Hire purchase contracts
• Contracts of guarantee
12
...
ONE FORMATION OF A CONTRACT
Proof of Contract
This has nothing to do with criminal law. There are some contracts which may be
void at civil law because such contracts are considered detrimental to society as a
whole; these are:
13
·'
,;
i~
:
I
Contracts consist of various statements, promises, and stipulations, written or oral, which are
grouped together under the word terms. It is the'ter-ms ,of a contract that specify the extent
of each party's duties, obligations, and rights. However, it should be noted that the phrase
terms and conditions is co=onIy used in contracts. This phrase is used in order to convey
that there are terms in the contract (conditions) which are considered to be more important
than others. ' ' ''
When it is clear that a valid contract has been formed, it is necessary to determine
precisely what it is the parties have undertaken to do. This is necessary in order to
be able to determine whether each has performed, or not performed, their part of the
agreement. Statements made by each of the parties (oral or written), which are
intended to be incorporated jnto the contract, are known as express terms.
Where the contract is wholly oral and the terms are in dispute, it will be a matter to
be decided by the court from evidence presented to it. However; problems may arise
where evidence is conflicting and difficult to substantiate. Therefore, in the case of
_building contracts, where there are generally many terms, it is essential to have
t -- everything in writing to prevent disputes of this nature arisin~
Where the contract is in writing it is usually obvious what the parties have written,
although there may be probJems of jnterpretation, arising from ambig]lity, which the
court has to resolve. Also, in most cases where the terms of a contract are in
writing, the court may refuse to allow oral evidence to be admitted if it has the effect
of adding to, varying, or contradicting the written agreement.
15
\
TWO TEIU.!S OF A CO:t-."TRACT
Not all of the terms created by a contract are of equal importance; consequently, the"
courts have adopted various approaches in assessing their relative importance. The
following terminology has been identified which may be used for the purpose of
classifying the" terms of a contract: condition, warranty, and intermediate term.
• Condition
This is the word used to denote a vital term; one that goes to the root of the
contract. A condition is so essential to the nature of the contract that its"
non-performance may fairly be considered by the other party as a substantial
failure to perform the contract at all.
So if certain cunditions are not carried o'qt in a contract, the injured party may
repudiate (refuse to accept the contract) and sue for damages. For example,
in the case of a building contract, if the employer refuses to pay the contractor
for work which has been properly executed (carried out), the contractor can
take the employer to a court of law, sue for damages and repudiate the
contract.
• Warranty
• Intermediate term
16
! ,
nvo TERMS OF A CONTRACT
Certain statutes may imply terms into particular types of contract. For
example, under the Sale of Goods Ordinance there is an implied term, that the
goods shall cooe5pond with the description, that the goods shall be reasonably
fit for the pumos~ for which they are required, and that they shall be of
merchantable quality.
III _ _ T""e",rms""""--",im"""p",li",e""d,--,b<JY,-",th",e"-",co,,,urts,,,,-,,"-o
In particular types of contract such as landlord and tenant, and hire of goods,
the courts have, over the years, had to imply terms, not on the presumed
intention of the parties but according to what is reasonable in the
circumstances.
Where a building contract makes no reference to such matters as time price etc., the
the terms outlined below will be implied.
Terms that the employer will: give possession of the site; supply all necessary pJans
and other details within a reasonable tjme; not obstruct the contractor in the
performance (If.the work; and pay a reasonable price for the work done.
r Terms that the contractor will: do the work in a workmanlike manner; proceed with
reasonable diligence; complete the work within a reasonable time; and supply
materials that are reasonably fit for the purpose for which they are to be used and are
of merchantable quality. Note: the warranties on materials may be excluded by
express provision or under the ruling in Young & Marten v. McManus Childs Ltd
(1968) which exc~ses the contractor for ·liability if the material· specified by the
k(it
17
roD TER.M:S OF A CONTRACT
employer proves to be unsuitable for the purpose. However, if, as happened in the
Young case (which centred on latent defects in roof tiles), the material used proves
to be defective, then whether the defect is immediately apparent or latent, the
contractor is liable for the cost of replacing the defective material.
A party to a contract may insert a term (clause) excluding or limiting their liability
under the contract. For example, airlines limit their liability for death or injury to
a specified amount of money as stated in the conditions written on the ticket. Car
parks usually exclude their liability for damage or loss of property, by placing a
notice to that effect at the entrance.
Although the courts accept the validity of exclusion and limitation of liability clauses,
they have evolved certain rules to be applied in order to determine whether they can
be enforced.
The rules that are applied by courts to determine the validity of exclusion and
limitation of liability clauses are as follows:
In written contracts which are signed, the exclusion clause is binding whether
it is read or not. If the contract is not signed, then the test is whether the
exclusion clause was reasonably brought to the attention of the other party.
In the case 'of OiltO' Y. Milr/howugh Court lintel (19-~, Olley booked in at
the reception desk, and later found a notice in the hotel bedroom, containing
an exclusion clause, which read, no liability faT loss of belongings. When the
plaintiff (Olley) sued for the loss of a coat, that had been stolen from his
room, the defendant (Hotel) pleaded the exclusion clause as a defence. It was
held by the court that the exclusion clause was not enforceable as it had been
co=unicated after the contract had been made.
18
1WO TERM:S OF A coNTRACT
In the case of Adler v. Dickson (1955), the plaintiff fell from a faulty
gangplank into the harbour whilst boarding a ship. The plaintiff sued the
shipping' company, but an exclusion clause in the contract which read,
Passengers are carried at Passengers' risk, excluded the company from
liability. The plaintiff then sued the captain of the ship. It was held by the
court that as the captain was not a party to the contract he could not claim the
benefit of the exclusion clause.
The party inserting the exclusion or limitation of liability clause should make
it very clear as to what liability is being excluded or limited. If there is any
doubt, due to vague or ambiguous wording, then the court will rule against the
party who inserted the clause i.n thp, "ontract.
In the case of Harbutt's Plqsticine v. Wayne Tank & Pump (1970), the
defendant installed a plastic pipe-work hot water system in the plaintiff's
factory. ,When the system warmed up the pipes melted, the plastic material
caught fire, and burnt the factory to the ground. The plaintiffsued, and the
defendant pleaded a limitation of liability clause as a defence, which limited
liability to £2,300., ~ It was held by the court that the defendant was in
fundamental breach of the contract and could not rely on the limitation clause.
A simple contract may be validly changed by the subsequent agreement of the parties
so long as there is consideration to support the variation agreement. A Contract
.'
1WO TERMS OF A CONTRACT
under seal can be varied without the need for consideration, provided that both parties
agree to the variation. A simple written contract may be varied by a subsequent oral
agreement, just as a simple oral contract can equally be varied by a subsequent
written agreement. A simple contract can also be varied by a contract under seal, in
such a case there is, of course, no necessity for any consideration to support the
variation. The following is a detailed explanation of the situation when an employer
requires variations to the work required under the original contract.
Having ascertained what the parties wrote or said, it is necessary to decide whether
such statements are representations or actual terms of the contract. Representations
induce (cause) the contract; terms are part of the contract itself and make up its
contents. Certain tests are applied by the courts in order to decide whether a
statement is a representation or a term of the contract.
1WO TER1iS OF A CONTRACT
III A statement is not likely to be a term if the person making the statement
!! . asks the other party to check or verify it
For example, in a case where a vendor (the person selling) makes a statement
that the item he is selling is in good condition, but then goes on to advise the
buyer to have it checked. The statement will only be considered a
representation.
Where there is a clear interval of time between the making of the statement
and the concluding of the contract, the statement is most likely to be a
representation. In the event of a dispute, the court will rule on what is, or is
not; a clear interval of time; according to the circumstances.
III Where a contract is in the form of a written document, the court tends to
take the view that the written document is the whole contract
21
'., ~.';'.';'.'.'.'-'.'.'.' .. ~. ' ' ..
-'
L
,; - ,
Once each party's contractual obligations have been fulfIlled, the contract is considered to
be discharged; this is known as discharge by peifonnance. However, there are ways in
which a contract may be discharged without the parties fulfIlling their obligations; these are
by agreement, frustration, and breach of contract.
3.1 Performance
The case of l.1oore & Co. v. Landauer & Co. (1921), involved a contract for a
quantity of tinned fruit which contained thirty tins to a case. On delivery, half the
. cases only contained twenty-four tins, although the overall total was correct. Landauer
refused to accept delivery, and Moore sued for specific performance (a court order
forcing acceptance). The court held that Landauer was justified in rejecting the
delivery because Moore had not performed his exact obligation.
II 23
THREE DISCHARGE OF A CONTRACT
With regard to building contracts, if a supplier fails to provide the contractor with the
exact goods that have been ordered, the contractor may refuse to accept them and also
refuse to pay the supplier.
This is a very harsh rule which depends very much on interpretation. Certain
exceptions have therefore evolved; these are:
• Part performance
If one party accepts the part performance of the other, the law brings in a
promise to pay on a quantum meruit basis, meaning to be paid as much as is
deserved for the work completed. Once part performance is accepted, both
parties' liabilities are discharged and the original agreement cannot be
enforced. However, part performance must be willingly accepted as was
established in the following case:
In the case of Sumpter v. Hedges (1898), the plaintiff agreed to erect stables
and houses on the defendant's land for £565. Sumpter did part of the work
valued at £333 and then abandoned the contract. The defendant completed the
work himself. The plaintiff claimed on a quantum meruit basis for the amount
of work done, on the basis that the defendant had accepted part performance
by completing the work. The court held that the plaintiff could not recover
the £333 because the defendant had not willingly accepted the part
performance. The only reason Hedges had completed the buildings himself,
was that in their partly completed state they would have been a nuisance on
his land.
24
¥-..
.'
THREE DISCHARGE OF A CONTRACT
If a party substantially performs the contract, then he can sue for the contract
price and a sum will be deducted to cover the small defects in performance.
In the case of Hoenig v. Isaacs (1952), the plaintiff agreed to paint and
decorate a flat and provide certain items of furniture. He did all this but a
wardrobe door and a shelf did not fit properly. The defendant refused to pay
any money at all because the contract had not been properly performed. The
court held that the plaintiff had substantially performed the contract; therefore
he could recover the contract price less a sum to cover the defects.
With regard to building contracts, this is one of the reasons why retention
money is withheld by the employer. The employer can use this money to
compensate for any defective work that the contractor has failed to rectify.
3.2 ~greeD1ent
Sometimes a contract makes provision for its own discharge. For example, contracts
of employment provide their own discharge by requiring a minimum notice to be
given by the employer or employee, usually one week or one month. Longer periods
can of course be provided for expressly in particular-contracts.
With regard to the form of discharge, a contract which is made in writing may be
discharged by oral or written agreement.
25
11;
-' !L
THREE DISCHARGE OF A CONTRACT
3.3 Frustration
This applies where an agreement is possible to perform when made, but due to
unforeseeable circumstances, the fundamental purpose of the contract becomes
impossible to perform. The court will decide whether the circumstances responsible
for the frustration were foreseeable or unforeseeable at the time the contract was
entered into. Where such circumstances are determined by the court to be
unforeseeable, both parties may be discharged from their obligation of further
performance. Such circumstances may be: total or partial destruction of some object
necessary to the performance of the contract; change in the law which renders any
attempted performance illegal; where an event fundamental to the contract does not
occur.
In the case of Davis Contractors v. Fareham UDC (1956), the plaintiff agreed to
build seventy-eight houses for £92,000, all of which were to be completed within
eight months .. There was a shortage of materials and labour and the plaintiff took
twenty-two months and incurred an extra expenditure of £17,000. However, the
V.D.e. paid only the price according to the contract and refused to pay the extra
costs that Davis had incurred. The plaintiff claimed that the original contract was
frustrated by the shortages and that he was therefore entitled to be paid on a quantum
meruit basis for the extra £17,000. The court held that under the circumstances the
shortages were foreseeable, and the fact that performance of the contract had become
more onerous for the contractor, did ·not result in the contract being frustrated.
Contracts of employment
The death or illness of a person who has been employed under a contract to provide
a persona! service (such as an entertainer may provide), may frustrate the contract if
consequently the contract is impossible to perform,
It should be noted that the doctrine of frustration will not apply if the contract
contains an absolute undertaking to be performed in any event.
26
"'f
3.4 Breach
A breach of contract may take one of two forms: either anticipatory breach - an
express declaration of intent not to perform, before time for performance arrives; or
executionary breach - failure to fulfIl obligations during the execution of the contract.
In both cases, the injured party may sue immediately the breach becomes apparent.
Even in the case of anticipatory breach, it is not necessary to wait until time for
performance has passed in order to take legal action. A claim for breach of contract
may be made for the whole contract, or of a part only.
Note: A breach of contract entitles the injured party to an action for damages,
amongst other remedies, and possibly the right to treat the contract as discharged.
I Whether the contract can be considered discharged depends on how serious the breach
is; whether it is a breach of condition or whether it is a breach of warranty. For a
breach of condition, the injured party may treat the contract as being discharged and
claim damages. Warranty is a less important term, a breach of which only gives rise
to a claim for damages; the contract may not be discharged.
27
There are a number of remedies available to the injured party upon the occurrence of a
breach of contract. These remedies are: damages, specific peiformance, injunction,
rescission, and quantum meruit. Different remedies will be appropriate, depending upon the
circumstances of the breach and the requirements of the injured party.
4.1 Damages
".;:
29
FOUR REMEDIES FOR BREACH OF CONTRACT
The relief afforded by the court where a penalty is found to exist, is to excuse
payment of that amount. The court has t)J.e power to substitute its own award
of damages, computed on the basis of compensation for the loss sustained.
On the other hand, where an agreeg sum is in the nature of liquidated
damages, no greater sum will be awarded by the court, even if it is proved
that the consequences of breach have been more serious than foreseen.
• Unliquidated damages
These are damages not specified in a contract, and should there be a claim for
a breach, it will be up to the court to decide not only whether a breach has
occurred, but also on the assessment of damag~. The word unliquidated
means that there is no agreement in principle to pay compensation. The
plaintiff will have to first prove that a breach of contract has occurred, and
then provide evidence to support the value of the claim. .
.
4.2 Sp(;\cific Performance
Specific performance is an order made by the court to force the party in breach to (.
~~~ ~,~- --~----
perform their obligations under the contract. It will only be awarded if it is fair and
reasonable to <Io -;0, or if the court declcres that damages are inadequate. It is a
discretionary remedy and is not awarded as of right. It is usually used in contracts
for the sale of land, as each plot of land is uniquely situated.
30
FOUR REMEDIES FOR BREACH: OF CONTRACf
4.3 Injunction
4.4 Rescission
Rescission is a remedy which is generally used in cases where one of the parties to
, a contraCf has been misled, and so occurs mainly in cases of fraudulent or negligent
misrepresentation. ReSCISsion gives the misled party J;1;1e 9J)tipn of aygiding 9Fe
accepting the contract. The iJijured party may either obtain an order from the court
"for rescission, or he can rescind without assistance of the court, by informing the
other party that he is repudiating the contract. Normally re~cission. must be
co=unicated to the other party, but it will be sufficient if all reasonable steps are
taken to co=unicate rescission, even if this is not possible.
@ Rescission requires that the parties shall be restored to their original positions as
though there had been no contract, that is a giving back,and a. taking back. If this is
not possible, rescission will not be given. However, where exact restitution cannot
be made but it is possible to substantially restore the parties to their original position,
restitution can pe llladetogether witha.finahcial.adjustrnent. For example, where a
contract for the sale of property has been induced by fraud, the purchaser may wish
to rescind the contract, yet has carried out some minor improvement. Restitution can
be made by returning the property to the original owner, and returning the purchase
money to the purchaser, along with a financial adjustment to take account of the
improvement.
th~e~r~e~~~~i~~~~~~~i'~biu~tin(quasi
j i:n.eaIDng as if it
the circumstances ofwere a cottract),
the case the law
igr the bsm;fit of services rendered.
is a contract.
31
FOUR REMEDIES FOR BREACH OF CONTRACT
Assessment of a reasonable sum The courts have laid down no rules limiting the
way in which a reasonable sum is to be assessed. However, useful evidence in any
particular case May include:
j ,
• Negotiations as to price.
• Calculations based on the net cost of labour and materials used, plus
overheads and mpij,f.
a~for
I
i
• Measurement of work
iL
9PQf aqd matepi?l§ §uppIjIjl
Quantum meruit claims Claims for a reasonable sum may arise for the following
reasons:
• \FailedNegOtiations J
wor 0the terms of the contract are
proceed in e
c or IS entitled to be paid a reasonable sum for the work carried out.
l\'" •
I
Prevention of completion y employer
jJLP •
,L
~
~ (;(.I.N~:"-
If wrongful acts by the employer prevent completion, the. contractor can claim
k \fI15'C fj"(J,o. ~ a quantum meruit payment. For example, there is an implied duty upon the.
ctit\\ ~
t
..:->
""'"
~ ~s·
.\ ~
employer to give the contractor an opportUnity to remedy defects, breach of
.which amounts to prevention.
?
~~~~~~--------------
:JA \or"., Acceptance of part performance
32
,, - FOUR REMEDIES FOR BREACH OF CONTRACT
Such a contract may be inferred from acceptance by the employer of the work
done, with the full knowledge of the failure to complete. However, it is
,1 - difficult to prove willing acceptance, and th~onus of proof will be on the
i _ contractor. ?\-"-
Where there is a contract for specified work, but the contractor does work
. the contract at the em 10 ers est the contractor is entitled to be
paid a reasona e sum or e a rtional work. In the case of Parkinson v.
Commissioners of Works (1950), the contractor agreed under a varied contract
to carry out certain work to be ordered by the Co=issioners on a cost plus
-profit basis, subject to a limitation as to the total amount of profit. The
Commissioners ordered work to a total value of £6,600,000, but it was held
by the court that, based on the limttation of profit, the varied contract only
gave the Commissioners authority to order work to the value of £5,000,000.
The additional work had to be paid for on a quantum meruit basis, so that the
contractor could recover more than the total fixed profit.
It is a policy of the law that there should be an end to the right to litigation. The
reasons for this policy are as follows:
III Defendants should be protected against claims being made on them after a
long period during which they may have lost the evidence available to them
to rebut those clairps.
III Plaintiffs should be encouraged not to delay in asserting their legal rights, and
to institute proceedings as soon as possible.
33
-,---:----------------~-- -~--- .
Limitation Ordinance
Hong Kong's Limitation Ordinance provides that for Simple contracts (except in cases
of fraud), and tort (except in actions for personal injuries), no action can be bought
after the expiration of six years from the date on which the cause of qction accrued.
The Ordinance also provides that no action upon specialty contracts (a contract made
under seal) can be brought after the expiration of twelve years from the date on which
the cause of action accrued.
Building contracts
For building contracts (except in cases of fraud or concealment), the limitation period
in respect of defective work begins to run from the time when the contractor is in
breach of his express or implied obligation under the contract (normally on practical
completion), and not from the time when damage occurs or the defect is discovered.
However, there may be a cause of action in negligence, independent of the contract,
against the contractor in tort; and such cause of action will not accrue until loss or
damage is sustained.
Tort
Tort is a civil wrong independent of contract, it arises. from breach of legal duty owed
to persons generally. Most of the law of tort is to be found in co=on law (case
precedents), although the,e are some important statutes. The case which fIrmly
established the precedent of when a duty of care might arise in tort, is the caSe of
Donoghue v. Stevenson (1932). In this case a manufacture of ginger beer was held
to owe a duty of care to the ultimate consumer who suffered damage as a result of
froding a snail in the bottle from which he had been drinking.
34
1· .'
A building contract may be formed by oral or written agreement and the terms make up the
contract itself. While simple works of limited extent and cost may be undertaken with simple
documents, the possible areas of misunderstanding and dispute between the parties to a
building contract expand with every increase in extent, complexity, and cost. Therefore, for
the majority of building contracts, it is essential to set out all the details of the work in a
proper form of contract, and state each party's duties, obligations, and rights. Failure to do
this may cause difficulties and possibly lead to arbitration or court proceedings. For these
reasons, it is now common practice to use standard forms of contract in the building
industry.
11 The parties to the contract become familiar with, and therefore gain a greater
understanding of the document, through the practice of using it for each
successive contract.
11 The parties to the contract are clearly made aware of their duties, obligations
and rights, as they are all written in one well referenced document. The
terms have been carefully worded so as to avoid any vaguen~s or ambiguity,
and are referred to by clause name and number.
11 Using a standard document avoids the waste of time that would result from
having to individually draft the many terms necessary for each new contract.
35
-'
FIVE STANDARD FORMS OF CONTRACT
There are, on the other hand, some arguments against the use of a standard form of
building contract:
• Because the terms are written using legal jargon (meaning legal terminology
and phrasing) the parties to the contract might not understand the full
consequences of the various clauses, and their inter~relationship to each other.
• Standard forms do not cover every event which might lead to a dispute, for
the reason that they do not take into account all the peculiarities of each
individual contract.
36
FIVE STANDARD PORM:S OF CONTRACT
Differences Between Private Sector and Public Sector Standard Forms of Main
Contract
The public sector and private sector standard forms used in Hong Kong's
building industry are very similar in nature and content. However, there are
a number of essential differences which should be appreciated, these are:
III Under the terms of the public sector standard forms payment
certificates are to be issued to the employer with a duplicate copy to
the main contractor. Payment required within fourteen days of issue.
37
FIVE STANDARD FORMS OF CONTRACT
Most standard forms of main contract used in Hong Kong's building industry,
whether it be public or private sector, will produce a with quantities edition
and a without quantities edition, . Where bills of quantities have not been
produced and it is the intention of the parties to use a specification and a
.schedule of rates in its place, the without quantities edition of the standard
form will be used.
The without quantities edition differs· from the with quantities edition in the
following respects:
38
,
FIVE STANDARD PORM:S OF CONTRACT
Most standard forms of main contract (private sector and public sector) will
have a sister document to be used when the main contractor is directed by the
employer to enter into a nominated sub-contractor agreement with a
sub-contractor chosen by the architect. When using the HK Standard Form,
this document is: Sub-Contract For use where the Sub-Contractor is nominated
under the Standard Form of Building Contract for Hong Kong 1968 Edition
(1986 Edition if issued by the RICS). Due to its colour it is popularly known
as the Green Form. Standard forms for domestic sub-contractors are also .
available, although their use is not mandatory.
Standard forms of warranty contract are also available, where the employer
chooses to enter into a subsidiary agreement with a nominated sub-contractor.
It is an optional contract and is subsidiary (meaning secondary) to the contract
between the main contractor and nominated sub-contractor.
The tender submitted by a contractor constitutes an offer and if the tender is accepted
without any qualifications or amendments, then a legally binding contract will be
formed.
However, it is usual practice· to qualify the acceptance of a tender with the words
subject to contract, which has the effect of not binding either party legally, until the
standard form of contract document has been signed by both parties. Furthermore,
an employer may withdraw his invitation to tender at ilnytime, and if he does, the
contractors who have submitted tenders are not entitled to any payment for expenses.
A contractor may also withdraw his tender at anytime before it has been accepted.
When using the HK Standard Form, the signatures, together with name and address,
of both parties to the contract, the Employer and the Main Contractor, are recorded
in the Articles of Agreement. The names of both the Architect and the Quantity
Surveyor appointed by the Employer should also be recorded as must the amount that
the Employer has agreed to pay the Main Contractor, which is known as the Contract
Sum. If the contract is to be made under seal, it is desirable for purposes of proof,
but not essential, to have the signature of two witnesses, and a section of the Articles
of Agreement -is reserved for this· PUrpose:- -
Details peculiar to each individual contract are written in schedule format in the
appendix of the Standard Form. Therefore, it is necessary to complete the appendix
before signing, so that each party is fully aware of the terms relating to the individual
contract.
39
----:
-'
FIVE STANDARD FORMS OF CONTRACT
If a standard form is amended in any way, it could lead to problems which may give
rise to disputes for the following reasons:
• The party making the amendment may use wording that is vague and/or
ambiguous.
• The parties may not appreciate the full legal consequences of the amendment,
due to the interrelationship of the clauses.
• There may be disagreements over the amendment which may lead to one of
the parties refusing to sign the contract.
• The various copies of the standard form document used in one contract may
not correspond with each other.
• Contract drawings
Once incorporated into the contract, the bills of quantities are referred to as
the contract bills; they are essentially the same document.
40
........•.••.• --------.. . ..._.. . ...... ............... .
FIVE STANDARD FORMS OF CONTRACT
• Terms of the Contract - this sets out the rights and duties of the
parties in the form of numbered clauses.
The Standard method of measurement used in Hong Kong, both in the private
and public sectors is: Hong Kong Standard Method of Measurement of
Building Works, Third Edition Metric, February 1979.
Tender documents
These will include not only the standard documentation sent to each tenderer,
and subsequently submitted, but also any qualifying letters which may have
accompanied the successful tender.
- -
These bulletins on which fluctuation payments are based, are published by the
Census and Statistics Department of the Government of Hong Kong.
41
·'
FIVE sTANDARD FORMS OF CONTRACT
It can be seen that there are quite a few documents that go to make up a building
contract. Ideally the information in each document should correspond with the other.
Unfortunately, due to the complexity of most contracts and human error, this is rarely
the case. The question is, therefore, if one document conflicts with another document
which one takes precedence over the other. In' cases where a specially written or
amended clause or document conflicts with a standard clause or document, then it is
a general principle of legal interpretation that the specially written or amended clause
or document will take precedence over the standard document.
However, in the HK Standard Form, Clause 12 states that the Conditions in the
Standard Form will take precedence over the Contract Bills. Therefore, special
conditions written in the preliminaries of the Contract Bills will have no effect if the
Standard Form is signed with Clause 12 intact.
42
TI- -'
FIVE STANDARD FORMS OF CONTRACT
j
i=- 5.6 Discrepancies and Errors in Contract Documents
i·
I, III Discrepancies
i
i Discrepancies between contract documents may be discovered both before and
after the contract has been signed. The procedure to be followed is different
in each case.
Pre-contract period
If a contractor fInds any discrepancy between the drawings and the bills of
quantities before entering the contract (that is during the tendering period), he
should immediately inform the architect in writing. The architect should then
make the necessary amendment as soon as possible, and in writing, inform the
contractor concerned, together with the other tenderers, of the amendment.
Post-contract period
If the contractor fmds any discrepancy between the contract drawings and the
contract bills after the contract has been signed, he should immediately give
the architect written notice. The architect should then issue an instruction to
correct the discrepancy which would then be adjusted in the fInal account.
III Errors
Errors in the contract bills.are usually the fault of either the main contractor's
quantity surveyor or the employer's quantity surveyor.
• An arithmetical error.
If the error is discovered before the contract has been signed (where
a=ptance is subject to contract), then it may be corrected without affecting
the contract itself. However, if the correction has the effect of increasing the
contract sum to a level which is no longer a=ptable, the employer may reject
-the offer -and not proceed with the formalisation of the contract. . If the error
is not discovered until after the contract has been signed, then the error cannot
be corrected (unless with the consent of the employer) as to do so would have
the effect of changing the contract sum, which has already been agreed upon.
43
- - - - - - - - - - - _.. - - . -
FIVE STANDARD FORMS OF CONTRACT
• Error in quantity ..
The procedure the main contractor should follow, if an error has been found
before the contract has been signed, is exactly the same as previously
discussed for discrepancies. However, the situation after the contract has been
signed is somewhat different. The main contractor should give written notice
of the error to the employer's quantity surveyor, who would then treat the
correction as a variation.
44
'T.:
,
When the HK Standard Form is used, the main contract is between the Employer and the
Main Contractor. However; various other contractual relationships are established in
addition to the one which exists between the parties to the main contract. Some of these will
be mandatory, as required under the conditions of the main contract, and others will be
optional. For example, mandatory contracts are entered into between the Main Contractor
and Nominated Sub-Contractors, and optional contracts 'may be entered into between the
Main Contractor and domestic sub-contractors.
The various contractual relationships are considered in detail, with specific reference to the
requirements of, and terminology used by, the HK Standard Form.
The parties to the main contract, when using the HK Standard Form, are the
Employer and the Main Contractor. The obligations of both parties are clearly
specified and are su=arised below.
IIiI Progress and complete the Works in accordance with the Contract
(Clause 1)
The Main Contractor is required to carry out and complete the Works, as
shown in the Contract Drawings and described by the Contract Bills, to the
reasonable satisfaction of the Architect.
45
-- ~- -----~--- ----
SIX CONTRACTUALRELA..TIONSHIPS
All the work shown in the Contract Drawings and described by or referred to
in other Contract documents must be completed in every respect. Nothing
may be added or omitted except if issued on an Architect's instruction under
Clause 2(1). The Main Contractor's obligation only comes to an end on the
issue of the Certificate of Practical Completion produced under Clause 15.
• Submit any claims to the Architect within a reasonable time (Clause 23)
46
SIX CONTRAcrDAL RELATIONSHIPS
Employer's obligations
The Employer is under an obligation to pay the Main Contractor for work
carried out. This may come as one lump sum when the work is practically
complete, or as stage payments, or more frequently by monthly instalments.
It is generally the duty of the Quantity Surveyor to value completed work,
which is then certified by the Architect, which in turn lS paid by the
Employer.
The Employer must give the Main Contractor possession of the site in order
that the Main Contractor may carry out the Works. Failure to do so will
make the contract impossibie to perform; it will, in effect, be prevention of
performance and may frustrate the Contract.
The Employer should allow the Main Contractor a reasonable time in which
to complete the Works, specifying the start on site date (possession) and the
finish date (completion).
The Employer ·must give the Main Contractor instructions concerning the
Works. This is usually carried out by the Architect, on the Employer's
behalf, in the form of Contract Drawings and Architect's instructions.
The Employer must not interfere with the Works. If he requires any part of
the Works to be altered or amended, he must see the Architect. The Architect
would in turn follow the correct procedure by issuing an Architect's
instruction. If there is any financial implication, the Contract Sum should be
adjusted accordingly.
47
,
srr COh7RACTUALRELATIONSHWS
If the Main Contractor or the Employer fail to carry out their required duties, they
will be in breach of contract. If the Employer fundamentally breaches the contract
during performance, for example, non-payment, the Main Contractor may abandon
the Works and seek damages. However, if the breach is not fundamental to the
Contract, the Main Contractor must continue with the Works and then sue for
damages over and above the Contract Sum.
Where the Employer or the Main Contractor employ others to carry out a part of the
Works, they are said to be sub-letting the Contract, that is, forming separate sub-
contracts to the main contract by engaging the services of sub-contractors and
suppliers.
Assignment or Sub-Letting
Under Clause 17 sub-clause (2), both the Employer and the Main Contractor
may sub-let part of the Works with the written consent of the other.
However, it should be noted that there is a difference between sub-letting and
assignment. Under sub-clause (1) neither the Employer or the Main
Contractor may assign the Contract - sign. over the entire Contract to the
benefit of another - without the written consent of the other.
These are chosen by the Main Contractor, with the written consent of the
Architect, (not necessary for suppliers under the HK Standard Form), to carry
out a certain part of the Works or to-supply goods. The Architect may object
to the use of a particular domestic sub-contractor only if he has good reasons
for doing so. Apart from his right to object and otherwise to provide written
consent, the Architect has -nothing to do with a-domestic sub-contractor.
• Responsibilities
The Main Contractor is entirely responsible for the work carried out
by a domestic sub-contractor, or goods supplied by a domestic
supplier, as well as for supervision and payment. It should be
remembered that if the Main Contractor is responsible for sub-letting,
the Employer will still be entitled to have the Contract- completed
under the same terms of time and price. If the Main Contractor, when
tendering, bases his prices on those contained in sub-quotations, he
does so at his own risk. Any disputes which arise between the Main
Contractor and a domestic sub-contractor or supplier must be settled
between them. Neither the Employer or the Architect have any right
or obligation to interfere.
48
te:
.,
" ,I "
i SIX CONTRAcruALRELATIONSHIPS
11 Prime cost sums (See 11.9 Provisional and Prime Cost Sums)
11 Nomination procedure
The Quantity Surveyor will estimate the cost of the work to be carried
out, or the goods to be supplied by each nominated sub-contractor or
nominated supplier, and insert this figure in the bills of quantities as
a prime cost sum. The relevant tender documents are then sent out to
the various sub-contractors· or suppliers wishing to tender for
nomination. When the tenders are received, the Architect will choose
a sub-contractor or supplier and, by using· an Architect's instruction
(Clause 2), will instruct the Main Contractor to enter into a standard
form of sub-contract with each nominated sub-contractor (Clause·27(a)
and a contract of sale with each nominated supplier (Clause 28(b).
Consequently, only the Main Contractor has a contractual relationship
with any Nominated Sub-Contractor or any Nominated Supplier, and
therefore all instructions and payments must be made through him.
49
-'
SlX CONTRACTUALRELATIONSH~S
• Responsibilities
Warranty Contract
50
T
SIX CONTRACTUAL RELATIONSHIPS
Re-Nomination
One particular point not made clear in the HK Standard Form is the position
of the Employer and Main Contractor, when a Nominated Sub-Contractor or
a Nominated Supplier fails to complete the work or to supply the goods as
required, and the question of re-nomination arises. Is it the duty of the
Architect or is it the duty of the Main Contractor to re-nominate a new
sub-contractor or supplier.
As none of the aforementioned are parties to the main contract, they cannot alter, in
any way, the terms of the Contract itself. They do, however, have certain obligations.·
as discussed in the following.
Architect
51
SIX CONTRACTUAL RELATIONSHIPS
• Design - the Architect must exercise great care to give the best
possible advice, and to warn the Employer of potential risks.
Consultant Engineer
Note: In some cases a consultant may be employed to carry out the entire
design and supervision of a project on an employer's behalf. In such cases
the consultant engineer would assume the same duties as those of the Architect
under the HK Standard Form. However, this can only be done where there
is no stipulation in the contract that an architect must be employed; there is
such a stipulation in the HK Standard Form.
52
SIX CONTRACTUAL RELATIONSHIPS
Like the Architect and consultant engineer, the Quantity Surveyor (working
for the Employer) is a member of the design team. Often referred to as the
professional quantity surveyor, to distinguish him from his counterpart
working for the Main Contractor, his skill in cost planning techniques has
made his contribution at the pre-contract stage invaluable. During the
execution of the Works, known as the post-contract stage, the Quantity
Surveyor should establish a very close relationship with the Main Contractor's
quantity surveyor, as they will need to agree on such things as monthly
valuations, variation accounts, and fluctuation payments.
III Prepare variation accounts - this will involve measuring, pricing and
agreeing the value with the Main Contractor's quantity surveyor.
Clerk of Works
53
SIX. CONTRAcruALRELATIONSlliPS
The clerk of works will also make regular reports to the Architect, and it is
important that he keep a diary throughout the project. Although on paper the
clerk of works has no authority, the Architect will back him on most
occasions. The Main Contractor will, therefore, usually bend to his wishes
and treat him as a senior member of the project team.
Foreman-in-Charge
The Architect, the Quantity Surveyor and consultant engineers are professional
people, and as such owe a duty to the Employer to carry out their work with
proper care. They are liable for damages for negligence if the Employer
suffers a loss that is due to a lack of care or duty. Legal action may be taken
against them by the Employer based on the terms in their respective contracts
of employment. If the Main Contractor suffers a loss due to their negligence,
he can only take legal action, based on the contract, against the Employer; the
Employer would then in turn have the option of taking legal action against the
professional person concerned.
54
re-
I SIX CONTRACfUALRELATIONSH!PS
i
I
I The Employer subsequently decided to take legal action against
1=
i ~ the Architect in an attempt to recover the amount that had been
I- over certified. The court held that although the Architect was
I- discharging a duty under the contract between the parties, there
was no dispute over the subject matter, it could therefore not
be contended that he was acting as an arbitrator .. The Architect
was thus liable to the Employer for negligence, on the grounds
that he failed to take due care or exercise proper skill; he was
ordered to compensate the Employer for his losses. The court
further ruled that an architect is in no different position
regarding actions for negligence than any other professional
person.
Note: In this case the employer's quantity surveyor had not been informed of
the defective work and could not therefore be held negligently responsible.
However, the case of Tyrer v. District Auditor for Monmothshire (1974) had
a similar outcome to Sutcliffe in respect of professional quantity surveyors.
"
~.
-.
".
j-
-
.:.
~
:..:z.
'"'''''''~
'ML.
2"'~:'
<~I
'JIiE. 55
~4:
~I
.I .
I
I.
I
r .
.'
The frnancial arrangement of a contract together with the selection of a main contractor is
referred to as contract procurement. Several different procurement methods are used in
Hong Kong, including design build and turnkey contracts, both of which are considered at
the end of this chapter. However, the traditional, most widely used method, is where the
employer decides on the contractual arrangement, and then selects a contractor through a
process of tendering (see Chapter Eight - Tendering Procedures). Contractual arrangements
fall into three broad categories depending on the means of arriving at the contract sum, these
are: lump sum contracts, measurement contracts, and cost reimbursement contracts.
In lump sum contracts, the contract Sllm is agreed in advance, subject to possible
"jncreases or decreases as a result of variations ordered by the architect in accordance
with the contract. The sum agreed upon may be frxed, or adjustments may be
allowed for fluctuation in the cost of labour and/or materials due to inflation during
the contract period.
57
SEVEN CONTRACTUAL ARRANGEM'ENTS
Commentary
A(fo~"'''''
• There are substantial risks imposed on the tenderers under this
arrangement. A tenderer is responsible for any errors he makes in the
taking off from the drawings. He is also required to take up all
responsibilities for any costs incurred due to uncertainties or
:unforeseen difficulties when preparing the tender. In order to allow i
for these risks, the tenderers are likely to include high contingency I
factors in their prices.
\ i
• It is always a gamble as to whether the tenderer has overestimated or Ii:
underestimated the risks. In either case, the employer will be unaware
of the extent of the contingency and can exercise no control over its
.expenditure.
The employer will save a lot of work on quantities. However, the cost
to the tenderersof producing their .own qmn1ities will be reflected in
high tender prices. .
• Because there are substantial risks imposed upon the contractor due to
uncertainty over the extent and nature of the work required, this
contractual arrangement is only suitable for minor works where the
likelihood of variations is small and the amount of informJion to be
supplied during the progress of the~a1.
)5.N~TI>':lI'-.)\Y ...--j;? ~\ So •
LmripSmnonB~ofQlliilltiti~ I'
In lump sum contracts based on bills of quantities, the contractor undertakes
to carry out the work in accordance with the plans and as described in the
bills for a lUmp Slim This sum is derived from the total of the items in the.
hills of ~s. The documents required are the QQmplete working
drawings and the bills of QuantitieS. The ;Wecification mayor may not be
. included as one of the contract documents.
Commentary
58
, '
1
; SEVEN CONTRAcrUALARRANGEMENTS
, --
i
i I
III It gives the employer a good indication of the final cost of the work.
However, if a fluctuation clause is built into the contract and the
contract period is measured in years rather than months, the fmal cost
may be well above the original contract sum.,
, -
III The guantities and the unit rates of the measured items will serve as
the basis for assessing the cost of variations. It therefore gives the
.ernpluyer control over the amount the contractor can charge for extra
and varied work.
6F-
""'" \?>tl--l-S
t.-"", AFM::>XlKAf4
~n"ES
~ -.fiV';'':~ ~ \"'I\.€t'.Stk.1M I""""» frrc.e.A .
-) _ (Au~lm. 'To
;~ P.Af~ If..! '[l-t;t; 59
-"" ~Iu...'& t5f
t"-!'f>, &.)
-'
SEVEN CONTRACTUAL ARRANGEM:ENTS
Although the quantities in the bills are approximate, there are certain
requirements :
11 Where the bills are too approximate, for example, where the
uncertainty as to the character of the work passes a particular point,
the usefulness of the bills will diminish.
60
T
I
i·
SEVEN CONTRACI'UALARRANGEMENTS
!
I
1
Commentary
III A schedule of pricr;s may b~eCiallY prepared and only the items
relevant to the jQb. in question ill be written into the schedules; these
schedules are known as ad- QC schedules. They should contain as
many items as practicable so that the fIxing of rates on varied work
will be easier.
~/c-~
III A variant of the ad-hoc schedules of prices is a standard pre-priced
schedule prepared by the Property Services Agency. A schedule of this
type contains items of work which are comprehensive and not relating
to any j;!artjcular ~t. The tenderers are required to quote a
percentage on or off various sections of the schedule as a whole. Due
to the fact that the basis of the prices are not known to tenderers and
may not be completely appropriate in every instance, tenderers may
objeCttO the use of this schedule.
In cost reimbursement contracts, the price to be paid is determined on the basis of the
acma! cost incllrred by the contractor in carrying out the work. plus an agreed amount
tQ cayer Qyerheads and profit. This is used where the requirements are only in A..-
general terms because of the nature of the work, such as repair of damage, and/or of
the acute shortage of time. There are a few variants.
The contractor carries out the~ and is paid all costs plus a fee. calculated
. as. a percentage of whatever the total cost may be, for .overheads and profit.
It is used for building work of an unusual ilature, such as experimental work,
where Iequirernents cannot he ascertajned before the contract is Jet, and where
it is not possjble to make any estimate of the total final cost
61
SEVEN CONTR.~crUAL ARRANG~"TS
Commentary
• Once the basis of the contract is agreed the work can co=ence
immediately, thus avoiding the delay which is necessary if estimates
have. to be prepared.
• It is diffIcult to predict the fInal cost at the early stage of the work.
This may be used where an accurate estimate of the maximum total fInal cost
can be made. Since the fee is fIxed and will not be affected by the costs, the
contractor may try to reduce the time, and thus the cost of the construction;
this will result in a saving to the employer.
Commentary
• If there are any major yarjations, which caD. be diffIcult to avoid in this
type of work, then the fee must be re-negotiated to take account of
. such" variations.
In this arrangement the fee paid to the contractor fluctuates in inverse ratio
~.5?Q111"" '!.'}D acc:ording to whether:the total [mal cost is more or less than the agreed
_~~ ~~e~s~tllll~a7.t;e_o_f_c~O=st=.==~~~~~__________~
1j'4\\'I\~\=-g'naV'~f~'
):;;p. Is%
10 % --:l?- - - - -) - - - A;;f<j;'li-D "Ei5fTHAfo;. O'lf" =T
115;% ,.
62
"t~
I:.'
f-
'"0"
SEVEN CONTRACI1JAL ARRANGEMENTS
I
I However, when it reaches a pre-determined minimum fee, it will remain
1:-:
.-
I :. JlDcbanged desPite further increases in the cost of the work, thus guaranteeing
a minimum profit and providing a financial incentive for the contractor.
Additional incentives may be achieved by Wding a profit-sharing clause or a
bonus clause.
Commentary
11 Cost plus fluctuating Jee gives the contractor more financial incentive
to reduce costs than in other types of cost reimbursement contract.
Target Price
Similar to the cost plus fluctuating fee, the employer's requirements must be
known in some detail, and it must be possible to prepare a reliable estimat"
of the probable cost. Under this arrangement, a target price is agreed for the
work. The contractor is reimbursed in the [lIst place on the basis of cost plus
percentage or fixed fee, and then further paymeyt will be made according W
the comparison of the actual cost and the target price.
Any savings that can be effected, compared with the target price, will accrue
to the contractor either by way of a share of the savings or an.increased fee.
Conversely, should the cost exceed the target, then either the contractor would
be paid no fee on the excess or possibly a substantially reduced fee. This
method provides an effective incentive for the contractor.
Commentary
11 The .ti3rget price must be fixed 'accurately" and the extent of work to be
carried out must be well defmed.
III Extensiye negotiations between the employ~r and the contractor should
take place in order to arrive at a realistic target price.
~
'.
i=",_
III The target prie,e. must be kept constantly under review tlrroughout the
-- progress of the contract and amended for the vaIu" of any variations
-
.~
:to required by the employer.
-
"-
I;:;
:-.:5.:
~
llE'i"
.~
63
::Er-
,
SEVEN CONTRACTUAL ARRANGEMENTS
build. The idea behind this arrangement is that the contractor can offer a better deal
when he is in control of all aspects of the project, and that the client does not have
to employ professional advisers. However, the idea does not seem to work in its
fullest sense, since clients still frod it necessary to employ a representative in order
to ensure that the contractor's work is of an acceptable standard and that he is not
over-charging. Such representatives may take the form of an architect to ensure the
quality of construction work and/or a quantity surveyor to advise on and monitor
costs. Alternatively, a management contracting company may be employed who will
provide a filII representative, supervisory, and advisory service throughout the
'*
duration of the contract.
lumkry contracts require the contractor not only to design and build but also to
furnish and fit out as well - he literally takes care of everything. All the client has
to do when he receives the keys to the completed building, is to turn the key in the
lock (hence turnkey), step in, and start using the building for its intended purpose.
The degree of fmancial risk borne by the contractor and the employer under each of
the contractual arrangements discussed, may be su=arised as follows:
• Maiority or risk borne by the contractor -lump sum on plan and specification;
the contractor's risk is slightly reduced if based on bills of quantities.
• AII the risk borne by the employer - cQS1..pius percentag," fee; the degree of
risk will be slightly reduced if it is on a flXed fee basis. Turnkey and, to a
lesser extent, design build; the risk to the employer of both may be reduced
by employing a management contracting company. .... ..
It is co=on practice in Hong Kong for the employer to transfer as much risk as
possible to the contractor. Therefore, the most widely used contractual arrangement
is the lump sum, fixed pric,", usually based on hills of quantities. Consequently,
tender prices generally tend to he higher than the¥ need be, as contractms allow higb.
contingency factors in their price.
64
When the contractual arrangement has been decided upon, attention turns to the selection of
the main contractor. The process of selecting a contractor is referred'to as the tendering
procedure. A large proportion of work obtained in the building industry is by way of
tendering, either on a competitive or a negotiated basis, or sometimes a combination of both.
The methods of tendering co=only used in Hong Kong are: Q,pen competitive tendertng,
selective competitive tendering, and negotiated tendering, ,
Some of these criteria can be easy to defme and measure, for example, price and time
of construction. Others are more difficult to measure, such as quality of
workmanship and organisation which depend partly on subjective judgment for their
assessment. The procedure for inviting tenders is simnly to advertise the reguirement
for tenders and permit any applicant to submit a tender.
.. Commentary , , ..
65
EIGHT TENDER.ll'lG PROCEDURES
• It is difficult tQ determine which tenderer is giving the best Qffer. The criteria
fQr the a=ptance Qf a tender may be multifQld and the IQwest tender will nQt
always result in the mQst eCQnQmic project.
, 'i.'!;;p
~.,"a IQUS cQntractQrs w ill prob ably
• . .ill the CQmpetItIQn,
In Qr der tQ Will .. unscrupu
keep dQwn CQsts in bQth labQur and materials, at the expense Qf qUality. This
will nQt Qnly be unfair tQ the reputable firms, it will alSQ increase the running,
repair, and maintenance CQsts Qf the bUilding.
• Because Qf the heavy cQmpetitiQn, it is PQssible that the CQntract price may be
so Jaw that the CQntractQr may nQt cQnsider the rewards sufficient to warrant
.dili~.DLQJ efficj~l\LW_Qrkrnaoshi.p.. AI; a cQnsequence of this, late completion
may reslllt.
• As the tender price may fail to reflect the difficulty Qf carrying out the work,
~conomic design :vill be discour~ged. The architect may be ~cIined to*,)
'illcIude uneconomIC over-desIgn, ill order to compensate for PQssIble shbrt
..Q.l.ts that the successful contractor may take.
• If the employer does not know anything about the tenderers, the contract price
becomes the only criterion of competition. The contract may be awarded to
a technically unsuitable and/or fi:llancially unsound firm.
,. The most often voiced criticism is the fast of tenderiog, which, in the long
run, ..must fall on the employer.'
Selective tendering is often dQne in two stages. The first stage limits the number of
competing contractQrs to a number decided in advance to be reasonable. The number
will usually aim at a comprom¥etween the need for rigorous competition and the
avoidance of excessive, aborti~ '~imating work by the unsuccessful tenderers. It
also depends on the size, nature and the resource requirements of the project. AI; a
rough guide, the number- of contractors invited tQ tender WQuld be between five and
eight;.the greater the value of the prQject. the greater the number.
First stage selection may be carried out by either advertising or by selection, in the
following ways:
66
TI EIGHT TENDER.rn"G PROCEDURES
Second stage will usually be. the final selection of one contractor on the criterion of
price. As the fIrms have been selected to tender, -there would appear to be no reason
""tOaCcept any but the lowest tender. Other criteria, however, may also be considered
at this stage, the most common being time and any qualification within the tenders.
Commentary
III In most cases the employer will allow the architect full control over which
firms wjll be invited to tender.
III Standard of work should be high, as the firms chosen will be reputable
contractors.
III .Contractors have more of a chance of being selected than with open tendering
because of less competition
III Some contractors feel obliged to tender if they are chosen, even if they do nut
really want to, for the fear of being black listed. This is why it should be
pointed out in the letter of invitation, that if the contractor does not wish to
tender, it will not prejudice any future chances.
III Prices tend to be higher when compared with open tendering because there is
less competition.
67
,
EIGHr TENDERJNG PROcP..J)URES
The tenderer will usually be aware of the lack of competition and the
improbability of the employer selecting- another fIrm without at least serious
loss of time. Therefore, he will invariably offer an expensive tender.
These procedures would be similar to those for the fIrst stage of selective
tendering, on such matters as: selection of tenderers; preliminary inquiries;
tender documents (including an explanation of two stage procedure); time for,
tendering;-'lualificatiQ~_ errQTj; evaluation of tenders; acceptance: and
notifjgtiQlL9i results.' An essential feature of the selection process is the
establishment of the price basis for subsequent negotiation.' This can be
achieved by the contractor nominating a bill submitted for a past project of a
.similar nature, pricing an approximate bill, or submitting a schedule of prices.
All tenders are fIrst compared on a price basis. It should then be possible to
select the contractor for the second stage negotiations.
The second stage would be mainly concerned with developing the project
design, preparing bills of quantities to be priced on the basis of the fIrst stage
tender, and agreeing a fInal price for the work. As the design evolves, the
data contained in the price basis is used for cost control purposes. The bills
of quantities is prepared, and negotiation on prices proceed until the design is
complete and an acceptable total price is agreed. A tender can then be
submitted by the contractor, which should meet with automatic acceptance.
68
EIGHT TENDERING PROCEDURES
Commentary
III There isc no contract between the employer and the contractor "'--
until a
tender has been accepted following the completion of the design and
t
the agreement on the total price.
III If a project were gnceUed before the second stage was completed, the
contractor could Fecover ilI!Y costs resulting from any contribution be
had made to the design. He would, however,.have to bear tendering.
_costs for stage one.
III Where it is desired to make an early start on site before the design
process is complete, the timing of the procedure must change, so that
a contract is entered into whilst design is still continuing. However,
the earlier the contract is let, the less scope there is for a firm tender
to be negotiated. There soon comes a point when a lump sum contract
ceases to be appropriate and a measurement contract, or even a cost
reimbursement contract, may become more suitable.
69
~.-.----
I
,
T
I
r
I
I
The Date for Completion will either be agreed by both parties or alternatively decided
by the Architect on the Employer's behalf. The Date for Completion will be written
in the appendix of the Standard Form and will be subject to any extension of time
granted by the Architect, for delays which are not the fault of the Main Contractor.
When the Works are practically complete the Architect is obliged to issue a
Certificate of Practical Completion. This signifies that on the date shOwn on the
certificate, Practical Completion of the Works took place.
~l
.. --'l" 71
I
NINE POSSESSION AND COMPLETION I(
In certain cases the Employer may not wish to take early possession. In such cases
the building will be practically completed and the Architect must issue a Certificate
of Practical Completion of the Works to the Main Contractor or the Employer will
be in breach. The issue of this Certificate however, does not mean that the Main
Contractor can hand over the building before the agreed Date for Completion; this
can only happen with the Employer's consent.
Clause 16 of the HK Standard Form provides for the possibility of the Employer
taking possession of some section of the Works before practical completion of the
whole, by an agreement made with the Main Contractor during progress of the
Works, rather than forming part of the original contract. The intention is to ensure
a fair and reasonable position under the Contract when a part, or successive parts, of
the Works are taken possession of by the Employer, in advance of their total
completion. This is achieved by treating each part as it is taken over, for the
purposes of this clause, as if it were the whole Works. The procedures and
consequences of a sectional completion agreement made during progress of the Works
are as follows:
11 The Architect by issuing a certificate fixes ·an approximate total value for the
part !aken over. Clause 16(a)
11 Practical Completion of that part is deemed to have taken place, and the
Defects Liability Period in respect of it is deemed to have begun, on the date
of its taking over by the Employer. Clause 16(b)
11 The rate of damages for non-completion provided for by Clause 22 and the
appendix, is to be reduced proportionally within fourteen days of the taking
over of the part. Clause 16(e)
72
TI NINE POSSESSION AND COMPLETION
1-;-
III One moiety (one half) of such amount retained as is proportionately
I· appropriate to the certified approximate value for that part, is to be paid to the
Main Contractor within fourteen days of the taking over of the part. Clause
16(f) (i)
III The remaining moiety of such amount is to be paid to the Main Contractor
according to the provisions of Clause 30(4) (c) , but without the need for a
certificate. Clause 16(f)(ii)
Clause Amendments
Having regard to the provisions of Clause 12(1), which in essence allows the Standard
Form to take precedence over the Contract Bills, it is probably not sufficient merely
to note the sectional completion dates in the Contract Bills. All clauses affected
should be carefully considered and amended as follows:
Articles of Agreement
III Sections should be clearly defined when describing the Works in the Articles
of Agreement.
III The Contract Drawings and Contract Bills should identify the sections which
comprise the whole Works. These sections should be serially numbered and
details of each section clearly given.
11 Provision should be made to have the effect that practical completion of each
section is deemed to have occurred for all the purposes of the Contract, as it
does for the whole Works under" the unamended clause. Hence, the Defects
Liability Period in respect of each section completed shall commence
accordingly. .
-~ :~.:::--
-- . Clause 16 Sectional Completion
11 The need for the Main Contractor's consent should be deleted from this
clause. The reason for this is to avoid any confusion; the contractor already
having agreed to the principal of sectional completion and the completion
dates of each section.
73
NINE POSSESSION AND COMPLETION
• Provision should be made to indicate that any completed section be at the sole
risk of the Employer as regards any of the perils under Clause 20.
Consequently, the Main Contractor will be allowed to reduce his value
insured, according to the approximate value of the section completed.
• The regular specified issue of Interim Cf<rtificates continues until the last
section has reached practical complf<tion. Only then may certificates of
payment be issued intermittently.
• The Period of Final Measurement and Valuation may also be timed from each
of these practical completions, if a special provision is agreed. In the absence
of such a provision it will start only after the last practical completion.
• Only one Final Certificate is to be issued, related to the timing of the last
practical completion amongst other things, which accords with the principle
that the Contract is still one despite its sections.
Clause 35 Arbitration
• It should be made clear that arbitration matters that are required under the
terms of the Contract to wait until after the issue of the Certificate of Practical '!
!
Completion, may co=ence after the issue of a Certificate of Practical
Completion of any section.
74
NINE POSSESSION AND COMPLETION
Where it has been determined, before awarding the Contract to the Main Contractor,
that the Works are to be completed by phased sections, on practical completion of
which the Employer takes possession, the arrangement may be incorporated into the
Contract, and the tenderers notified at the tender stage. This may be implemented
by amending the relevant clauses in the Standard Form, or by appending the Sectional
Completion Supplement to the Contract.
If the Works has not been divided into sections in the tender documents, the
Supplement cannot be used at a later date. If the Employer wishes to take possession
of a section of the Works after the Contract has commenced, he may only do so with
the consent of the Main Contractor as stated in Clause 16.
Liquidated and Ascertained Damages is the full expression used in the HK Standard
Form, to describe the monetary compensation paid to the Employer by the Main
Contractor in the event of late completion. The word liquidated means that the
principle to pay monetary compensation for a breach has been established; the word
ascertained means that the amount to be paid has been decided. Although the full
expression is used in the Contact, it is common practice to use the abbreviated
. expression liquidated damages, or in many cases simply, L.D., both of which are
accepted as having the same meaning as the full expression.
75
------------------------~-------------------------;:-
The Government of Hong Kong uses a formula in order to arrive at a more accurate
assessment of loss. The Government's daily loss is calculated as: the daily rate at
which Government would have to amortise (payoff a debt by a sinking fund) the cost
of the project over the period of its probable life at a fixed rate of interest; plus daily
I
supervisory staff costs during the delay period; plus an assessment of the daily sum
payable to the Main Contractor in respect of the in,creased cost of labour and
materials used during the delay period.
Architect, if 4e is to deduct damages, must certify in writing that, in his opinion, the
Works ought reasonably to have been completed, stating when completion should
have occurred after taking into account any extension of time awards.
Payment for liquidated damages can be made either progressively in each interim
valuation or by a final adjustment of the amount due under the Final Certificate. If
any liquidated damages due to the Employer are not paid, or otherwise allowed by
the Main Contractor prior to the issue of the Final Certificate, the Employer's right
to recover such amount from the Main Contractor is terminated by the issue of the
Final Certificate. .
In the case of Philips Hong Kong Ltd v. The Attorney General of Hong Kong (1991),
the Privy Council held that provisions for minimum liquidated damages can be valid
where the Employer .is able to show standing expenses, such as the cost of
maintaining resident site staff, which would occur in any event, even if only some
small part of the work is not completed.
76
.'
1=
An insurance contract is an agreement whereby one party, the insurer, in return for a
consideration, the premium, undertakes to pay to the other party, the insured, a sum of
money or its equivalent, upon the occurrence of a specified event which is against the
insured's financial interest. It is a contract of the utmost good faith as the insured is required
to provide details of the interest to be protected. Consequently there is an implied duty upon
the insured to disclose all known facts when applying for an insurance policy; in the event
of non-disclosure, the insurer may avoid liability.
10.1 Insurance
It is essential that the main contractor should take out comprehensive insurance cover
relating to the contract works. Although the contract document may stipulate a
minimum limit of indemnity, it is the main contractor's responsibility to select a limit
adequate for his protection. It is therefore necessary to have an understanding of the
following terminology used by insurance companies.
III Cover
Cover is the extent of protection that insurance provides to the insured. The
term exceptions is used to describe this cover by stating .what is excluded.
77
TEN INSURANCE AND SURETY BOND
-'
"It
• Limit of indemnity I
Indemnity means compensation for loss, so the limit of indemnity is the
I
maximum amount that may be paid in compensation for loss by the insured.
• Premium
Premium is the amount of money paid by the insured to the insurer as the
consideration to the insurer for undertaking the insurance policy. It is
calculated based on the sum insured, the limit of indemnity, cover, exceptions,
and any other conditions of the poilcy. For example, in the Contractors' All
Risks (C.A.R.) policy, the sum insured is the total of the value of the contract
works, plus professional fees, the escalation in costs, and the costs for
removing the debris. The premium shall be retrospectively adjusted on the
actual value of the contract sum when known.
• Excess
• Period of insurance
The Period of insurance is the period of time during which the insurance
policy is effective. Usually, a C.A.R. policy will cover the period from the
co=encement of the contract (date for possession) until two weeks after
practical completion of· the works. The third party and workmen's
compensation insurance should be extended to cover the defects liability
period and until no further work of any kind is being carried out.
First party insuranCe policies ·are those under which one voluntarily insures
one's own life, or property, against loss, injury or damage. Third party
insurance policies ·are those which insure against one's potential liability in
law to pay damages to another, and in some cases are compulsory, such as
third party car insurance.
It is essential to draw the employer's attention to the fact that some insurances
will become his liability on the issue of the certificate of practical completion
(or on any other date as required in the contract) and that he should arrange
his own cover in good time before the main contractor's policy terminates.
78
, ii.
When there is more than one party insured under a policy, a cross liability
__ clause must be included in the policy. Cover then operates as though a
separate policy had been issued to each party making up the insured.
Although there may be more than one insured, the aggregate liability of the
insurer would not be increased beyond the limit of indemnity to which the
insurance policy is subject.
The HK Standard Form requires that .the Main Contractor shall maintain
insurances, as required under the Contract, in the joint names of the Employer
and the Main Contractor. In this way, the insurers (the insurance company)
will be unable to take legal proceedings against either party to recover money
payed out under the policy as a result of a claim for damage or injury caused
by the negligence of either of the parties. Also, as the Main Contractor will
be jointly liable with the Employer in any legal proceedings taken by a third
party, both parties (as joint insured) will be eligible to claim payment from the
insurance company for any damages that may be awarded against them.
Liability Insurance
These polices cover the insured's regal liability to third parties, that is,
liability to any person who is not a party to the insurance contract.
<:- ~:; ••
11 Public liability policy
-', ,,?--
This policy provides an indemnity against personal injury claims by the
public (other than employees), and property damage claims.
79
TEN INSURANCE M'D SURETY BOND
Material damage insurance is taken out in respect of: the works; buildings and
contents of owned and occupiedpremises;_ and main contractor's plant &
equipment. These three are examined in more detail below.
The two main types of policies under this section are the Contractors'
All Risks policy and the Fire and Special Perils policy.
The cover required for the insurance of the works depends upon the
requirements of the particular contract governing the works.
80
TEN INSURANCE A..ND SURETY BOND
For example, the HK Standard Form requires a Fire and Special Perils
policy. However, irrespective of the requirements of the particular
contract concerned, the wider cover provided by the Contractors' All
Risks policy. makes it a better form of cover. Major contractors
usually acquire a blanket C.A.R policy to cover all their contracts.
A Fire and Special Perils policy covering the buildings and contents of
oWJied and occupied premises will provide an indemnity against loss
of capital in the event of damage or destruction by fire or other
insured peril. However, a fire of any magnitude1J1ay bring about a
serious interruption of the business. Although the premium will be
higher it is nevertheless prudent to arrange a policy that will cover
such consequential losses.
;:~ ~.
'FiO
~~
~.
11 Insurance of main contractor's plant and equipment
'":: ;;:.-
'1
A~ This applies to both the main contractor's own plant and that hired.
~:'.
~
,'c'
It may be arranged as an extension of a Contractors' All Risks policy,
F- or a Fire and Special Perils policy, it can also be provided for under
a separate Contractors' Plant policy. It should be noted that the HK
Standard Form, along with most of the common standard forms of
contract used in Hong Kong's building industry, do not require the
81
-'
TEN INSURANCE AND SURETY BOND
main contractor to insure his own plant and equipment, or that hired.
Although it may not be mandatory to do so, it is nevertheless advisable
for the contractor to acquire insurance to cover his plant and
equipment, as if it is lost (stolen) or damaged, he could be faced with
a considerable fInancial loss. Most contractors will consider the
additional premium required to extend the C.A.R. or Fire and Special
Perils policy to cover such risks, or the purchase of a seperate
Contractors' Plant policy, a worthwhile investment.
The HK Standard Form has one indemnity clause and two insurance clauses. The
indemnity .clause - Clause 18, specifIes the limit of the Main Contractor's indemnity,
makillg it clear exactly what h.e is to assume responsibility for. Clause 19 is the
liability insurance clause, and Clause 20 is the materials damage insurance clause.
This states that the Main Contractor shall assume liabilityJor, and indemnify
the Employer' against, any claim in respect of personal injury or death arising
out of the execution of the Works, except where the injury or death has been
due to any act or neglect of the Employer or of any person for whom the
Employer is responsible.
The liability assumed by the Main Contractor and the indemnity given to the
. Employer are very wide. . The words· any person whomsoever used in the
clause, will cover not orily the Maip. Contractor's employees and his sub-
contractors and their workmen, but also, subject to the exception at the end
of the sub-clause, the Employer himself, his servants and agents and any third
party who may, whether in the course of his business, or as a mere passer-by,
or on looker, come into contact with the Works.
The exception at the end of the sub-clause, provides that the Main Contractor
shall not be liable if he is able to prove that the injury or death was due to the
act or neglect of the Employer, orof any person for whom the Employer is
responsible. The onus is on the Main Contractor, to prove in a court of law
the Employer's act or neglect in connection with any injury or death, if he is
to avoid liability.
82
TEN rnSURANCE AND SURETY BOND
Under Clause 18(1) the Main Contractor assumes sole liability, and
indemnifies the Employer against liability for injury to persons, except in
cases where he can prove affIrmatively that the injury is due to the act or
neglect of the Employer or of a person for whom the Employer is responsible.
Under Clause .18(2), however, the Main Contractor assumes liability and
fudemnifies the Employer against liability for injury or damage to property
only where such injury or damage is due to any .negligence, omission or
default on the Main Contractor's part, on the part of his servants or agents,
or on the part of any sub-contractor.
The reason for this difference is not clear. It may have been thought to be in
the public's interest to minimise the possibilities of disputes over liability for
personal injuries as far as possible by placing the wider responsibility on the
Main Contractor. At the same time, it may have been considered that
substantial damage to neighbouring property is likely to be caused at least as
much by faulty planning and design as by the Main Contractor's negligent
execution of the Works, so that it would be unfair to place upon the Main
Contractor the onus of proving the Employer's act or negligence. .
". ~~
,~ 83
~
.'
TEN INSURANCE M'D SURETY BOND
The Main Contractor is free to choose any company through which to effect
these insurances. However, this freedom of choice does not deprive the
Employer of the right to satisfy himself that the Main Contractor has secured
adequate cover. The Main Contractor is obliged to. produce documentary
evidence that the required insurances are properly maintained, but subject to
1.
the right of the Employer to have produced for his inspection the actual
policies and premium receipts. If the main Contractor has not effected the
required irisurances, then under Clause 19(1)(c), the Employer is given the
right to effect cover himself and deduct the premium from any monies due to
the Main Contractor.
There are two important points to note in Clause 19(1). First there is the
obvious intention that the obligations undertaken by the Main Contractor in
respect of Clause 18(1) and 18(2) must be insured. Second is the clear
warning that the Main Contractor shall cause any sub-contractor to maintain
insurances, for failure to do so means that the Main Contractor himself
assumes the liability of an uninsured sub-contractor.
Usually, the Main Contractor would arrange public liability insurance (third
party insurance), and employers' liability insurance (workmens' compensation
insurance) to cover the liability under this clause; both taken out as joint
insured with the Employer.
84
-'
TEN INSURANCE AND SURETY BOND
This provides for the inclusion of a provisional sum in the Contract Bills to
cover the insurance of risks not covered by the Main Contractor's indemnity
given under Clause 18. The Main Contractor is required to insure on behalf
of the Employer, with certain exceptions, against liability for damage to third
party property caused by collapse_subsidence, vibration, weakening or removal
of support or lowering of ground water arising in connection with the
Contract. There are three important points to note:
This clause, which deals with the insurance of the Works against the accidents named,
that is, fire, lightning, explosion, etc., is divided into two parts [A] and [B], which
are alternatives; one of them is to be struck out as circumstances· may require.
Alternative [A] is applicable to the erection of a new building if the Main Contractor
is required to insure against loss or damage by fire, etc. Alternative [B] is applicable
to alterations of, or extensions to, an existing building.
Clause 20[A] places an obligation upon the Main Contractor to insure the
Works, in the joint names of the Employer and the Main Contractor, against:
... loss or damage by fire, lightning, explosion, storm, typhoon, flood, bursting
or oveiflowing of water tanks, apparatus or pipes, earthquakes, aircraft and
other aerial devices or articles dropped therefrom, riot and civil commotion.
The perils set out in Clause 20 follow the wording currently used by insurance
companies. The Main Contractor is to take out policies of insurance in the
joint names of himself and the Employer or where he holds a Contractors' All
Risks policy covering the Works, have the Employer's interest endorsed
therein.
85
-'
TEN lliBURANCE AND SURETY BOND
The cover should be for the full value of the work executed, which will be an
increasing amount, and all materials and goods upon the site.
It is possible to insure these perils under a Fire and Special Perils policy.
However, a main contractor who attempts to save on insurance costs by
arranging only the minimum cover, carries the risk himself for perils such as
theft, and could therefore face substantial fInancial losses in the event of a
mqjor claim caused by an uninsured peril. The C.A.R. policy is designed to
protect the main contractor against such losses, and although the premium will
be ~igher, the extra protection offered is worthwhile.
The insurers are to be approved by the Architect .and the policies and premium
receipts are to be deposited with the Employer. The Main Contractor will be
discharged from his obligation to deposit the policies and premium receipts,
by producing for inspection by the Employer, documentary evidence that the
. policies are properly endorsed and maintained. However, the Employer
retains the right to have the policies and receipts produced for his inspection.
If the Main Contractor does not do so, the Employer is empowered to effect
the insurance himself and deduct the cost from the Main Contractor's account.
Upon the settlement of any claim, the Main Contractor must proceed with the
work of repairing or replacing whatever has been damaged or destroyed. In
respect of this work he is to obtain payment only from the monies received
under the policies of insurance, and is not entitled to anything in excess of
such amount. It is. essential, therefore, for the parties to see to it that the
policy monies will be adequate to meet the cost of reinstatement in a period
of rising prices.
Clause 20[B] requires the Employer to arrange inSurance against the perils
mentioned, when the Main Contractor is carrying out alterations of, or
extensions to, an existing building. The existing structure and contents are
also the Employer's responsibility but only for the perils specifIed in the
clause. All other losses are the responsibility of the Main Contractor and he
carries his own risk unless he or the Employer arranges C.A.R. insurance.
In some cases it may not be possible for the Employer to take out insurance
against certain of the risks mentioned in the clause. This matter should be
arranged between the parties at the tender stage and the clause amended
accordingly.
86
"
A co=on form of protection for the employer is to require the contractor to obtain
a guarantee - in the form of a surety bond - from a third party, such as a bank or an
insurance company, who, for a fee, agrees to accept fInancial responsibility for the
performance of the contractor's obligations. In the event of the contractor's default,
the third party pays an agreed amount of money to the employer as way of
compensation for his loss.
This appears to be a very simple legal obligation. However, as there are different
forms of bond and the terminology involved often confusing, the contractor may not
appreciate the full implications of purchasing such a bond.
111 collateral may be required by the surety ip. the form of a cash deposit
covering the bond amount. Alternatively the surety may accept shares
quoted on the stock market or a mortgage to real estate. In some cases
a promissory note (for example, a personal cheque), may be accepted
although this involves great risk to the surety in the case of
ban.ki1lptcy; therefore, this is onIy regarded as pseudo-collateral.
87
-'
TEN rnSURANCE AND SURETY BOND
The terms conditional and first demand refer to whether or not payment of the
bond amount will be paid with or without proof of the contractors default
(failure to perform the obligation guaranteed). A Conditional bond will only
be paid upon actual proof of default, such as an arbitration or court ruling,
and the payment will only cover the proven loss sustained by the employer up
to the bond amount.
Types of Bond
88
TEN ThlSURANCE AND SURETY BOND
The usual form of a surety bond is a three party guarantee contract between
the employer, the contractor and the surety, guaranteeing performance by
providing the employer with a stated maximum fInancial benefit in the event
of non-performance. Under Common Law, contracts of guarantee must be in
writing and like any other contract, must be supported by consideration. Due
to the absence of consideration between the surety and the employer, the bond
must be issued under seal if it is to be enforceable. Once issued it cannot be
cancelled other than by agreement with the employer.
However, in the case of a first demand bond, the full amount of the bond will
be paid by the surety to the employer in the first instance, regardless of the
actual loss sustained. The contractor will then have to recover the balance
(between actual loss and the bond amount) from the employer through
arbitration or litigation.
Issue of Bond
Once a bond has been entered into it cannot be withdrawn. The surety as a
guarantor is responsible for costs incurred by the employer up to the amount
of the bond limit. The guarantor does not insure the contractor he only
guarantees him. As a condition of issuing the bond, the contractor will be
required to execute an indemnity in favour of the guarantor, thereby ensuring
that, if the bond is called, the guarantor is only likely to suffer financially if
the contractor goes into liquidation. The guarantor will normally require a
thorough knowledge of the contractor's financial situation, resources and
capability to execute the contract.
89
TEN INSURANCE AND SURETY BOND
Cost of Bond
Although the cost of obtaining a bond will eventually be· borne by the
employer through incorporation in the tender sum, it is nevertheless the
contractor's responsibility to purchase the bond in the frrst place. Insurance
companies usually charge 1 % of the value of the bond (bond amount) per
annum, which they refer to as the premium. Banks may sometimes charge
less provided that they hold collateral from the contractor for the full amount
of the bond; they refer to their charge as the commission.
The cost will vary between contractors and contracts, according to the amount
to be guaranteed (bond amount), the form of the guarantee (conditional or frrst
1
demand), and the security provided by the contractor. Generally, a bank bond
is likely to be cheaper than an insurance company bond, although both may
prove expensIve.
90
TEN INSURANCE AND SURETY BOND
Bond Amount
Bond amount is the term given to the sum of money that the surety guarantees
to pay the employ.er wlien demanded.ll the prescribed manner (in the case of
a fIrst demand bond), or the maximum amount up to which the surety will
compensate the employer for proven losses as a result of the contractors
default. In the private sector it is usually 10 % of the contract sum, whilst for
government projects it may vary between 1 % and 5 % of the contract sum;
bonds required for Housing Authority projects, for example, will not exceed
$5 million. The reason for the relatively low bond required by government
is that only contractors who are on the government's approved list of
contractors are eligible to tender for government work. As a sound fInancial
background and reliability are criteria for inclusion on the list, the likelihood
of the contractor failing to complete the contract is remote.
The contractor's only real fInancial liability is if the bond is called by the
employer. By calling the bond (requesting payment from the bondsman -
bank or insurance company) the employer is claiming that the contractor has
defaulted on his obligations and that he wishes to receive the fInancial
compensation guaranteed by the bond. Whatever amount the bondsman pays
the employer, will in turn be recovered from the contractor; hence the
contractor is the one who ultimately loses fInancially.
This sounds quite reasonable, provided that the contractor has indeed failed
to perform his obligations under the contract. It would seem just that the
employer should receive some frnancial compensation and that the contractor
should be the one who ultimately pays. - ..
If a conditional bond is called then the employer will have to prove the
contractor's default and will only receive payment for proven losses as a result
of the default. As the losses iJ;lcurred by the employer can only be ascertained
after completion of the contract, and because of the usual lengthy process of
either litigation or arbitration, it may be up to one or two years, in some
cases, before the contractor is required to reimburse the surety. Even then it
will only be an amount to cover the employer's actual loss as decided by the
due process of law.
However, what happens if a fIrst demand bond is called, but the contractor
does not agree that he is in default, or believes that he has a legitimate reason
for being so.
91
-' TEN INSURANCE AND SURETY BOND
The dispute remains unresolved and yet the employer is paid the bond amount
by the surety who in turn recovers it from the contractors collateral. Some
might consider this unfair as it could, in some cases, lead to the contractor
suffering a fInancial loss through no fault of his own.
If the contractor considers that a fIrst demand bond has been called unfairly
(without justifIcation), his only recourse is to make a claim against the
employer in order to try and recover the bond amount. To be successful in
his claim the contractor must prove, through arbitration or litigation, that the
employer had called the bond without justifIcation.
It should be noted that lio action may be taken by the contractor against the
surety. The position of the surety is clear and was set out by Lord Denning
in his judgment of the Edward Owen Engineering Ltd. v. BarcUrys Bank
International case in 1976:
Contractors' Vulnerability
92
TEN IN"SURANCE Ah'D SURETY BOND
The practice of requiring a surety bond or security, for the due performance
of the contract, is usual in Hong Kong, although the amount differs widely
from one per cent to ten per cent of the contract value. The provision of a
surety bond is a term included in most of the private and public sector
standard form contracts co=only used in Hong Kong's construction industry.
Private sector: Clause 31 - Surety Bond, of the HK Standard Form allows for
the provision of a guarantee of an insurance company or bank to be jointly
and severally bound with the Main Contractor to the Employer for the sum of
money as stated in the appendix of the Standard Form for the due performance
of the Contract. Release from the bond will occur on the issue of the
Certificate of Practical Completion.
93
~... TEN lNSURANCE AND SURETY BOND
Commentary
The Architect is expressly empowered under the Conditions of the HK Standard Form to
issue instructions to the Main Contractor. Clause 2(1) - Architect's Instructions states that:
The Main Contractor shall... comply forthwith with all instructions issued to him by the
Architect in regard to any matter in respect of which the Architect is expressly empowered
by these Conditions to issue instructions. However, if an instruction is not issued according
to the provision of these Conditions, the Main Contractor is not obliged to comply.
T4ere are three ways in which an Architect's instructions may be OffiCiallyt~d to the
Main Contractor: as written instructions direct from the Architect; as oral instructions direct
from the Architect; .or as oral directions given by the clerk of works on behalf of the
Architect.
Clause 2(3) deals with the procedure for confrrmation of an instruction. The primary
effect of this clause is that all Architect's instructions must be confirmed in writing;
until they are, the Main Contractor need not comply.
Clause 2(1) provides that the Main Contractor must comply with Architect's written
instructions. which are issued under express authority.
If the Main Contractor does not comply with properly authorised written instructions
within seven working days. then the Employer can employ and pay other persons to
carry out the work necessary to give effect to the instruction. The cost of such work
shall be;recoverable from the Main Contractor by the Employer as.a debt or may be
.deducted from monies d.:ue to the Main Contractor under the Contract.
95
ELEVEN lNSTRUCI'IONS AND V ARlllTIONS r~
This avoids the Employer having to determine (end the employment of the Main le
Contractor, see Chapter Fourteen - Determination of Employment) under Clause 25
or having to treat the contract as repudiated at co=on law.
oRAl..
11.2 Oral mstruCtions A.]..· P41? ?~y [.IJ- 11-:1, -J
I
L--
\>,6..'f \ -+
M'C -t A~C""
~c
~~\\
-I->c"",
''''t""C-
~
Clause 2(3) allQws the Ar.chitect to give oral instructions if he so wishes. This will
in effect minimise delays in the time taken to write and deliver a written instruction.
The Main Contractor should however, get the instruction in writing, since if the
matter in question is allowed to remain unwritten for too long or is forgotten during
subsequent operations, the Main Contractor runs the risk of ~osing payment if the
Architect has no record or cannot recall items. Where instructions are requested on
s1te and given orally by the Architect these .should be written in a site record book
kept by the Main Contractor and..s.i gned by the Architect.
The normal procedure for confIrmation of an Architect's oral instruction is for the
Main Contractor to write to the Architect within seven days confirming the
<instruction. If the Architect does not dissent (disagree) in writing within seven days
of receiving the Main Contractor's confIrmation, then the instruction will take effect
as from the expiration of the latter seven days - Clause 2(3).
If the Architect confIrms an instruction in writing flfSt within seven days, then.the
Main Contractor does not have to confIrm his instruction - Clause 2(3)(a).
The clerk of works acts only as an inspector on behalf of the Employer under the
direction of the Architect. As such he has no authority to give instructions to the
Main Contractor, however, he may give directions. According to Clause 10: If any
directions are given to the Main Contractor or his foreman upon the Works by the
clerk of works or the Architect's representative the same shall be of110 effect unle"
"given in regard to a matter in respect of which the Architect is exuressly empowered
by thesLConditions and unless ,confirmed in writing by the Architect within two
Jj!Qrking dClJl£ Qf,their being given. If any such directions are so giv.en" a'nd confirmed
then as from the date of confirmation they shall be deemed to be Architect's
instructionS .
In practice, this means" that directions given to the Main Contractor by the clerk of
works will usually be treated as Architect's instructions. The Main Contractor will
therefore comply with such directions, knowing that the Architect's written
confIrmation will invariably follow.
96
.'
ELEVEN INSTRUCTIONS AND V ARIA..TIONS
The Architect is empowered to issue instructions to the Main Contractor under the
following clauses and provisions:
6(4) Removal of materials or goods from the site which are not ill
accordance with the Contract.
20(2) Removal of any of the debris after storm, flood, flIe etc.
27 Nomination of sub-contractors.
28 Nomination of suppliers.
32(2) Doing special work, for example, protecting the Works in the event of
an outbreak of war.
Disputing an instruction
Clause 2(2) sets out that the Main Contractor is not required to comply with any
instruction which is not expressly empowered under the Contract, and may request
the Architect to specify the relevant clause number which empowers his instruction-
at the time of issue.
97
ELEVEN illSTRUCTIONS AND VARIATIONS
The standard form of Architect's instruction provides a space to enter the relevant
clause number. This practice not only provides the Main Contractor with immediate
confirmation, but also ensures that the Architect considers and identifies his authority
before issuing each instruction. This is intended tQ. protect the Main Contractor
against such things as the Architeds interference with the Main Contractor's site
organisation. If the Main Contractor is still not satisfied, his remedy is arbitration
which can proceed at once under clause 35(2) but will involve inevitable delay to the
Works.
11.5 Variations
Most building contracts are entire contracts. The significance of an entire contract
is that there is no obligation to carry out variations or to pay for variations; this is
known as the. doctrine of entirety. However, standard forms of building contract
co=only introduce a variations clause, under which the doctrine of entirety is
modified. This is to give the employer the right to require variations and provide
rules governing the adjustment of the contract sum.
A variation is defmed in Clause 11 (2) of the HK Standard Form as: ., .the alteration
or modification of the design, quality or quantity of the Works as shown upon the
Contract Drawings and described by or referred to in the Contract Bills, and includes
the addition, omission or substitution of any work, the alteration of the kind or
standard of any of the materials or go.ods to be used in the Works, and the removal
from the site of any work, materials or goods executed or brought thereon by the
Main Contractor for the purpose of the Works other than work, materials or goods
which are not in accordance with this Contract.
The Main Contractor may be ordered to carry out variations for the following
reasons:
98
ElEVEN rnSTRUCTIONS A..""lD VARIATIONS
The Architect's general authority to make variations is set out in Clause 2(1) -
Architect's Instructions, while specific authority is given in Clause .11 ~ Variations,
Provisional and Prime Cost Sums, and Clause 33 - War Damage. Variations may
only be ordered within the terms of the Contract and they must be written and signed
by the Architect.
Clause 11 (5) provides that both variations and the adjustment of provisional sums are
to be allowed for in Interim Certificates and are subject to retention. This clause also
authorises the adjustment of the Contract Sum to take into account the value of the
variation work carried out.
Clause 11 (6) deals with the situation where the Main Contractor might suffer some
direct loss and/or expense (for example, idle plant) while carrying out work ordered
by the Architect under Clause 11(1) or 11(3) for which he will not be reimbursed by
payment made in accordance with the valuation rules contained in Clause 11 (4). In
such a case the Main Contractor is required to submit a separate claim under Clause
11(6) which, subject to the Architect's approval, will be added to the Contract Sum
and included as payment in the next Interim Certificate.
It is the duty of the ,Quantity Surveyor to measure and value variations under Clause
11(1), 11(3), and 11(4). Variations will ultimately be presented as part of the final
account, and the Main Contractor is to be presented with a copy of the priced Bills
of Variation before the issue of the Final Certificate, as provided by Clause 30 (5)(a)
- Certificates and Payments. If the Main Contractor is dissatisfied with the Quantity
Surveyor's valuation, he can take the matter to the Architect who must review the
valuation.
(a) Work of similar character in similar conditions, use prices in the Contract
Bills to determine proportionally valued rates (pro-rata rates).
(c) Work that cannot be properly measured or valued, use dayworks, which is
written evidence of time spent and materials used to cariy out the variation
work. The information is recorded on standard dayworks sheets, which are
signed by the clerk of works.
99
ELEVEN rnSTRUCTIONS AND VARIATIONS
Variation work carried out on a daywork basis must be in accordance with the \
following:
(i) Rates for labour must be those offered by the. Main Contractor in the
Contract Bills.
(ii) If the Main Contractor did not include daywork rates in the Contract
Bills then the rates will be those given in the current Standard Day
Labour Schedules, and current Plant Hire Schedules.
I
(iii) Materials provided specifically for the variation work will be valued
at its actual cost plus the cost of packing, carriage and delivery with
an addition of 15 % for overheads and profit.
There are three main methods of assessing pro-rata rates (proportionally valued rates)
which are by derivation, analogy, and reconciliation of analysis.
Derivation
From two or more similar unit rates in the contract bills, for example:
100
ELEVEN INSTRUCTIONS AND VARlATIONS
Analogy
For example, a rate might be required for screwing and pelleting hardwood
and only a rate for the same operation in softwood appears in the bills.
Provided the screws are of the same description (the pellets being
~. --- manufactured out of waste material have no value as such), it may be assumed
that the difference is virtually one of labour.
Reconciliation of Analysis
III When substituting material cost - break up the unit rate by:
101
.'
ELEVEN IN"STRUCTlONS AND VARIATIONS
Rate in contract bills: brick wall in type A fcg. bk. in'stretcher bond
in g.m. 1:1:6 ptg. wi. fl. jt. a. w.p. $65.00/sq.m
Required: Pro-rata rate for bk. wall in type B fcg. brick in substitution.
$56.52/sq.m
Less material cost for type A facing brick
Bks.lsq.m x % waste
=(60 x 1.075) x 650.00 1000 $41.93/sq.m
Bks.lsq.m x % waste
= (60 x 1.075) x 750.00 1000 $48.38/sq.m
$62.97/sq.m
Add profit and overheads 15 % $ 9.45/sq.m
A fair valuqtion is simply an estimate of the cost of carrying out an item of work,
including overheads and profit, and may be used as an alternative to pro-rata rates.
Where a fair valuation is required, it may be valued by:
• Building up a unit rate from basic principles taking into account all factors
such as invoice cost of materials, waste allowance, transportation and handling
cost, standard labour constants, cost of plant, overheads and profits.
\ ;
• Obtaining prices from building price books, such as Spons, Laxtons, Griffiths,
and adjusting them to take into account the peculiarities of the contract
concerned. Such factors may be: location, size, quality and complexity of
work, fluctuations, overheads and profit.
102
ELEVEN lNSTRUC!10NS AND VARIATIONS
III Extracting unit rates from bills of quantities used on jobs of a similar nature,
and adjusting for factors previously mentioned: location, size, quality,
complexity, fluctuations (meaning, that the prices would have to be higher if
the employer has not agreed to pay increases in costs, which may occur
= during progress of the works), overheads and profit.
-
•i, Clause 11 (3) states that: The Architect shall issue instructions in regard to the
expenditure of prime cost and provisional sums included in the Contract Bills and of
prime cost sums which arise as a result of instructions issued in regard to the
expenditure ofprovisional sums. There is a footnote to this sub-clause stating that the
term prime cost may be indicated by the abreviation P. C. in any document relating
to the Contract.
A provisional sum is a sum of money provided in the Contract Bills for costs
which cannot be entirely foreseen, defined or detailed at the time the tendering
-documents are issued. This may include the value of measured work (which
. is the actual quantity of finished work whether valued by measurement or as
daywork), and any preliminary costs such as scaffolding and plant directly
related to the work in question. It may even, in some cases, include the cost
of other preliminary items such as special supervision. Adjustments would be
made by deducting the provisional sums from the Contract Sum and replacing
them with the value of actual expenditure.
A.prime cost sum is a sum of money provided in the Contract Bills for
payment of Nominated Sub-Contractors and Nominated Suppliers and is to be
expended in favour of such persons as the Architect shall instruct. Normally,
prime cost sums are incorporated into the tender as cover for the cost of
nominated work. In so doing the Employer does not have to enter into a
series of special contracts. After the initial nomination these specialists
become sub-contractors and suppliers to the Main Contractor. In the
adjustments, the prime cost sums would be deducted from the Contract Sum
and substituted by the final accounts of the specialist sub-contractors and
suppliers so nominated.
103
-'
Payment certificates are binding statements, issued by the Architect under Clause 30 of the
HK Standard Form, which co=it the Employer to an obligation to pay the Main Contractor
the amount certified; the two types of payment certificate are Interim Certificates and the
Final Certificate. Other certificates issued by the Architect throughout the contract period
include, the Cel1ificate of Practical Completion and the Certificate of Making Good Defects.
Interim valuations and the final account are the responsibility of the" Quantity Surveyor.
Clause 30 - Certificates and Payments, of the HK Standard Form, deals with all
certificates that regulate payments under the Contract. Interim Certificates certify the
value of the work completed to the time of the certificate and are an estimate of value
only. The _Employer is bound to pay the sum" stated on the certificate, but
adjustments can be made on future certificates. The procedure to be followed for the
issue of Interim Certificates is set out by Clause 30(1), while Clause 30(2) sets out
what may be included in the amount stated as due in an Interim Certificate. Both of
these clauses also apply to interim valuations. Interim valuations are for the purpose
of ascertaining the amount due in an Interim Certificate, and must be prepared
whenever the Architect considers them necessary.
105
1
-'
11¥.E7.VE CERTIFICATES AND PAYMENTS
Clause 30(1) provides for the issue of Interim Certificates by the Architect both
before and after practical completion. Interim Certificates are issued periodically
before practical completion at intervals which are defined in the appendix, usually one
I
month. The Architect is under an obligation to issue Interim Certificates; if he does
not, the Employer will be in breach of contract. I
i
When an Interim Certificate has been presented to the Employer by the Main
Contractor, payment must be made within the Period for Honouring Cenificates
named in the appendix, fourteen days from presentation unless otherwise stated. If
the Employer does not pay within the time, then after giving notice the Main
Contractor may determine (end his own employment under the contract) in
accordance with Clause 26(1). If the Main Contractor feels that any Interim
Certificate was not properly prepared, he can give notice of arbitration.
Clause 30(2) sets out what may be included in an Interim Certificate (and therefore
an interim valuation), which is the estimated value of the work properly executed, and
the total value of materials and goods delivered to or adjacent to the Works for use
thereon. Restrictions on the materials or goods to be included are. as follows:
11 Delivery must have taken place up to and including a date seven days before
the date of the Certificate.
11 Materials and goods must be adequately protected against weather and theft.
Under Clause 14(1), once these materials and goods are certified and paid for,
they become the Employers property, though the Main Contractor remains
responsible for loss or damage to them.
Clause 30(2)(A) deals with off site goods and materials. This clause gives the
Architect a discretionary power to include in the amount stated as due in an Interim
Certificate: ... the value of any materials or goods before delivery thereof to or
adjacent to the Works... This is on the proviso that such materials or goods conform
to certain requirements, such as: intended for inclusion in the Contract; in accordance
with the Contract; and insured against the perils set out in Clause 20 [A] or [B].
106
TIY.ELv.E CERTIFICATES AND PAYMENTS
This sub-clause is intended to cover the increasing use of pre-fabricated materials off
site, and to enable the Main Contractor to be paid for them before their delivery to
site. This sub-clause will only be a part of the Contract if specifically stated to be
so in the Contract Bills.
From the total of work, materials and goods, retention due under Clause 30(3) is to
be deducted. All previous instalments (certificates) that have been paid by the
Employer must also be deducted from the total.
12.3 Retention
,
The object of retention is to secure the Main Contractor's obligation to complete the
Works and make good defects. The Employer holds retention money as a trustee for
the Main Contractor but without obligatidn to invest.
Clause 30(3) provides that the Employer may retain a percentage of the total value
of the work, materials and goods valued under Clause 30(2). This is referred to in
the appendix as Percentage of Certified Value Retained and should not normally
exceed 10%.
When the sum of the amount of retention money retained equals that shown in the
appendix as Limit of Retention Fund then no further amounts will be retained. The
limit referred to should not normally exceed 5 % of the Contract Sum.
Clause 30(4) sets out the nature and purpose of the retention fund and how it should
be paid over to the Main Contractor. The Employer is permitted under the Contract
to draw from the fund to reimburse himself for:
III Work executed by another party where the Main Contractor has not complied
with a valid instruction.
III Premiums paid for insurance when the Main Contractor has failed to insure.
After the Certificate of Practical Completion is issued, one moiety of the retention
fund
. is released with the other moiety being released after the issue.,of the Certificate
of Making Good p~fects.
The caSe of Hsin Clwng Construction Co. Ltd. v. Yaton Rea Co. Ltd 1986), raised
a question con e the HK Standar Form.
107
11laVE CERT1F1CATESAND PAYMENTS
The question raised was: whether or not Clause 30 creates in the hands of the
Employer, an effective retention fund in relation to the Nominated Sub-Contractor's
proportion of the fund.
The Main Contractor, as plaintiff, contended that in relation to these monies (the
Nominated Sub-Contractor's proportion of the fund), the retention fund is effective
in his hands only. The Employer must first accumulate the monies in a trust account.
Then when each moiety is released by certificate, the Employer must pay such moiety
to the Main Contractor without any deduction. The only party eD.titlkd IQ exercise
any rights of deduction or §fa Off awdI]~t an)! particular Nomin@ted SUb-Cpntractor,
r; the Mnin GpptraCi:Qr himself. ""'
The Employer, as defendant, contended on the other hand that Clause 30 creates a
single indivisible fund. The initial obligation to set aside and accumulate the trust
was not disputed. However, in the same way that moiety of the whole fund on
release becomes due and payable to the Main Contractor, so the Employer can
recover losses from the whole fund.
The basic facts of the !;lsin Chong v. ratap RealQ> case are as follows:
The plaintiff gave notice of arbitration on 11th June 1984, and also
asked the Employer to place the total retention monies in a trust
account. The defendant only paid $20,048.17 into the account. This
amount was arrived at by deducting the total of the two certificates in
question ($9,064,123.38), from the total of tIie retention fund
($9,084,171.55). The crucial question which therefore arose, and
which the court was asked to rule on, was ~ether the defendant was
entitled to deduct from the portion of etention morues mat was due
-
to the Nowmat . _ u -
upon a to under
- clauses 2(1), 19(1)(c), 22, or 27(c); all are equal! effective. '
\~.~
108
THaVE CERTIFICATES AND PAYMENTS
If there has been early final payment of a Nominated Sub-Contractor, for example,
a contractor engaged to complete piling, then half the retention fund should be
released for the value of the work carried out by that Nominated Sub-Contractor
under Clause 27 (e». Likewise, if there is sectional completion, that is the Employer,
with the Main Contractor's consent, takes over a part of the Works before they are
complete, then under Clause 161f), half the retention fund should be released for that
section of the Works completed. ~* .'
12.4 Certificate of Practical Completion (See Appendix 3)
Contractual proviSions that are dependent on the date of the issue of the Certificate
of Practical Completion are as follows:
11 Ending of the Main Contractor's liability for typhoon damage. Clause 15(5)
III Beginning of the Period of Final Measurement and Valuation. Clause 30(5)
109
1'm!Lv.E
-'
CERTIFICATES AND PA'Y.MENTS
The issue of the Certificate of Practical Completion marks the beginning of the
Defects Liability Period stated in the appendix; six: months unless otherwise stated.
For this period of time after the issue of the Certificate of Practical Completion, the
Main Contractor is required to maintain and repair the building in respect of damage·
occurring through his poor workmanship, such as plaster cracking, doors and
windows. not closing properly.
Clause 15(2) requires that the Architect must deliver a Schedule of Defects within
fourteen days from the expiry of the Defects Liability Period. If the Architect fails
to do this, the Schedule would become invalid and the Employer would have to resort
to a separate claim for damages against the Main Contractor for his failure to
properly complete the contract.
The Main Contractor is to make good defects within a reasonable time of receiving
the Schedule. Much depends on the nature and circumstance of a particular defect
as to what may be considered a reasonable time. All work will normally be at the
Main Contractor's expense.
Clause 15(3) overrides the provisions of Clause 15(2), allowing the Architect to issue
instructions covering urgent individual defects, for example a leaking roof.
When the Defects Liability Period has expired and on completion of the repairs the
Architect is required to issue a Certificate of Making Good Defects (Clause 15(4».
The Main Contractor is then relieved of any further contractual responsibility for the
maintenance and repair of the bUilding. One Certificate is issued covering all making
good defects.
The issue of the· Certificate of Making Good Defects has two effects as far as the
Contract is concerned; these are:
The Certificate of Making Good Defects means that the Main Contractor himself is
no longer obliged to return and remedy defects, but it does not end the Main
Contractor's liability for the cost of remedying them. The Main Contractor remains
liable to the Employer, under the Limitation Ordinance, for any breach in complying
with Contract specifications (See 4.6 Limitation of Action). The period of the Main
Contractor's liability, is six years for ordinary (simple) contracts and twelve years for
contracts under seal.
I
1;
In the case of sectional completion, the same limitation of action rules apply, the only I
difference being that the Defects Liability Period applies only to that section of the
Works which has received a Certificate of Practical Completion. 1
110
THRVE CERTIFICATES AND PAYMENTS
Before the Final Certificate can be issued, the fInal account has to be prepared by the
Quantity Surveyor, who is required to adjust the Contract Sum in the Contract Bills
to include all the monetary additions and omissions of the following items:
Under the HK Standard Form the Period of Final Measurement and Valuation should
begin with the issue of the CertifIcate of Practical Completion and be completed
within the time stated in the appendix; six months unless otherwise stated. All
adjustments made to the Contract Sum should be agreed by the Main Contractor's
quantity surveyor. When the fInal account has been agreed, a summary is prepared
setting out all the adjustments, which should be signed by the Main Contractor. The
agreed fmal account sum is the amount that the Employer should pay the Main
Contractor for executing the Works.
The Final CertifIcate is issued to certify that the Works have been entirely completed
to the Employer's satisfaction in accordance with the terms of the Contract between
the two parties.
Clause 30(6) provides that the Final CertifIcate must be issued as soon as is
practicable but before the expiration of three months from the end of the Defects
Liability Period, or from completion of making good defects under Clause 15, or
when the Main Contractor has completed his obligation to send all the necessary
documentation to the Architect so that the [mal a=unt can be completed; whichever
is the latest.
The Final Certificate will include the sum of all amounts .previously certifIed and the
Contract Sum adjusted as necessary in accordance with the Conditions of the
Contract. The difference (if any) between these two sums will be expressed as a
balance due to the Main Contractor from the Employer or to the Employer from the
~
Main Contractor as the case may be. This balance must be settled as from the
,
i>-
fourteenth day after the Main Contractor has presented the Final Certificate to the
~ Employer.
~,
I
~.
111
-' THELVE CERTIFICATES AND PAYMPJ..,"TS
r
Clause 30(7) deals with the effects that the Final Certificate has on the Contract.
These effects are that all materials and workmanship are to the reasonable satisfaction
of the Architect, and that all adjustments to the Contract Sum have been made.
Once the Final Certificate is issued, all adjustments made are indisputable by any
. accidental inclusion or exclusion. It is therefore extremely important that all
calculations are checked carefully while adjusting the Contract Sum. However, if
arb itration is going to take place, or is taking place when the Final Certificate is
issued, the Certificate will be subject to the arbitrator's main award.
(See 15.1 Awards)
112
,;'
When using the HK Standard Form, most claims submitted by the Main Contractor during
progress of the contract will be in the form of bona fide claims, such as claims for direct loss
and/or expense and claims for extension of time. Such claims if not submitted, will not be
paid or granted, as the case may be. However, in practice, the Main Contractor may also
have to submit claims for payments which should be made automatically by the Employer,
but which may be overlooked. Fluctuations falls into this category.
13.1 Fluctuations
Fluctuations may be defined as adjusting the contract sum for subsequent increases
or decreases in wage rates and/or materials during the contract period; depending on
the contract being used. The HK Standard Form allows for increases or decreases
in wage rates only, by the provisions of Clause 36 - Fluctuation in Wage Rates.
,
" Fluctuation in wage rates is based on the Index of Wage Rates for the Building
Industry (referred to in Clause 36(1) as the Wage Index), an edition of which is
published each month by the Census and Statistics Department of the Government of
Hong Kong. The Index for each of the eight selected trades listed under Clause
36(2), is taken from the Wage Index and averaged to give an Average Wage Index.
The edition of the Wage Index which will form the basis for comparing the Average
Wage Index of each subsequent month, is the edition issued in the same month in
which the Employer receives the tender from the Main Contractor. This month is
referred to as the base month. At monthly intervals the Architect is required to
review the Wage Index and calculate, as a percentage, any increase or decrease in the
Average Wage Index, when compared to the base month.
113
THlRIEEN CONTRACTOR'S CLAlMS
The monetary amount by which the Contract Sum is· adjusted is calculated in the
following way:
• Ascertain from the appendix the Percentage Labour Content for the Contract.
This is expressed as a percentage of the Contract Sum; usually 25 %.
• Determine the gross value of work executed during the particular month
concerned after deducting the following items listed under Clause 36(5)(a)-(t):
(a) Nominated Suppliers and Main Contractor's profit on the work valued:
(e) Preliminarie$.
(t) Any variation valued using wage rates for labour, that were not based
on wages contained in the Wage Index.
These three figures are multiplied together to produce a figure which is the amount
by which the Contract Sum should be adjusted for increases or decreases in the cost
of labour. Fluctuation payments must be made to the Main Contractor (if it is an
increase) or allowed to the Employer (if it is a decrease) in Interim Certificates. -
It should be noted that the Fluctuation in Wage Rates clause.in the HK Standard
Form, will be deemed part of the Contract only if specifically so stated in the
Contract Bills. It is co=on practice in Hong Kong not to include the clause as part
of the contract. However, employers will rarely save costs by not including the
Fluctuation in Wage Rates clause, as contractors when tendering, will include an
allowance in their tender figure for possible increases in the cost of labour. Such an
allowance may well be much greater than the actual cost of eventual increases.
114
THlRIEEN coNTRAcrOR'S CLAlMs
13.2 Delay
Delay in the completion of the Works is one of the most common causes of dispute
between the two parties, and of subsequent claims. Delays may be considered under
three headings:
Delays caused by the Main Contractor are usually due to bad management in
executing the Works, such as insufficient labour on site, late ordering of
materials, insufficient or unsuitable plant.
I,"
11 Issue of drawings, instructions, details or levels which the Architect
has either failed to supply or is late in supplying, which the Main
Contractor has specificallY requ,ested in ~i!ing. "
115
THIRTEEN CONTRACTOR'S CLA.Th{S
-'
Where delays of this nature occur, the Architect has an obligation to issue an
Architect's instruction awarding an extension of time.
There are occasions when delays arise due to circumstances over which
neither party to the Contract have any control. These may be su=arised as:
force majeure (something caused by nature totally unconnected with man, or
war, or epidemics, 'or legislative interference); inclement weather; insurance
matters (such as fire, lightning, explosion); strikes affecting the Works; delay
on the part of Nominated Sub-Contractors or Nominated Suppliers; and
unforeseeable shortages in materials and labour. For any of these matters the
Architect has an obligation to grant an extension of time to the Main
Contractor.
If failure to complete the Works by the original date for completion is caused by a
delay which is outside the control of either party or a delay which is the Architect's
or Employer's fault then the Main Contractor may, under Clause 23 - Extension of
Time, apply for an extension of time. The original date for completion would then
be revised to take into account the delay, so relieving the Main Contractor from
liability for liquidated damages based on the original date for completion.
If the delay is the fault of neither party, the Main Contractor is entitled to an
extension of time, but is not entitled to-receive any payment for direct loss andlor
expense that he may have incurred due to the cause of the delay. However, if the
delay is the fault of the Employer or the Architect, the Main Contractor. is entitled to
submit a claim, under Clause 24, for direct loss and expense in connection with the
cause of the delay. (See 13.4 Claims for Direct Loss andlor Expense)
The causes of delay for which the Main Contractor is entitled. to be granted an
extension of time by the Architect are listed under Clause 23 (a)-(k). The following
is a su=ary of the causes of delay (with sub-clause letter references) categorised as
either the fault of neither party, or the fault of the Employer or the Architect.
116
THIRTEEN CONTRACTOR'S CLAIMS
(c) Insurance - loss or damage for which the Main Contractor is insured
under Clause 20 [A] or [B] which is Insurance of the Works against
Fire, etc.
(d) Strikes, etc. - protects the Main Contractor from unions and protects
the Employer from increased costs.
(k) Antiquities - the Main Contractor can claim if a delay is caused due
to the discovery of antiquities.
Causes of delay which are the fault of the Employer or the Architect:
(f) Lateness of drawings - the Architect must give the Main Contractor
the drawings within a reasonable time.
(h) Delay of artists or tradesmen - the Main Contractor can claim for
o
,- extension of time if they are late with their work.
(i) Inspection and testing of work - protects the Main Contractor against
unreasonable inspection and testing.
:r
! Note: Causes (a), (b), (c), (d), (g), 0), (le), do not entitle the Main Contractor to
submit a claim for direct loss and/or expense; causes (e), (f), (h), (i), do.
117
,
THIRIEEN CONTl<.AcrOR~S CLAJ}..{S
The Main Contractor must take the initial action by giving notice of delay and
stating the cause of delay. He must be prompt, or the Architect may
justifiably refuse to consider the extension where notice is given long after the
delay in question was apparent; however, there is no stipulated time period
stated in the Contract. The Main Contractor may estimate the length of delay
although the Architect will make the [mal decision.
When the Architect'has received notice of delay from the Main Contractor,
he must decide whether the delay is caused by one of the matters for which
the Main Contractor is entitled to an extension of time under Clause 23 -
Extension of Time, and whether the delay, if valid, is going to result in late
completion.
The Main Contractor is obliged to co-operate with the Architect to reduce the
effects of any delay which is not his fault, and for which he is claiming all
extension of time. It is the Main Contractor's responsibility to co-ordinate his
own work and that of sub-contractors, which will involve holding regular
meetings to review progress, and making changes to the master programme,
as necessary, to prevent likely delays.
However, the Main Contractor is not obliged under the Contract, to work
overtime or bring in extra plant or take other expensive steps to regain lost
time. If the Architect requests the Main Contractor to take special measures
to catch up the lost time, and the Main Contractor agrees, then the Employer
is required to pay for the cost of such measures.
118
THIKIEEN COh"TRAC!OR'S CLAIMS
"Where the Architect decides that no extension of time is necessary, and the
Main contractor is dissatisfied with the decision, or where the Main
Contractor is dissatisfied with the period of time granted, the parties may refer
such dispute to the decision of an arbitrator.
Causes of delay for which the Main Contractor may claim direct loss
and/or expense are listed under Clause 24(1) (a)-(e); these are:
Loss may be defined as where the Main Contractor will not recover what he could
have expected to as a direct result of disruption (disturbance of regular progress),
variation, or the discovery of antiquities. Expense may be defl!led as where the Main
Contractor has had to increase his expected expenditure on an item of work to
produce the same result, also as a direct result of disruption, variation, or the
discovery of antiquities.
The Main Contractor may, under the HK Standard Form, make a separate claim for
direct loss and/or expense where the cause is either one of disruption, set out in
Clause 24(1) - Loss and Expense Caused by Disturbance of Regular Progress of the
Works; or variation, set out in Clause 11 (6) - Variations, Provisional and Prime Cost
Sums, or the diScovery of antiquities, set out in ClaUse 34(3)" - Antiquities.
It should be noted that the term direct loss and/or expense, is used in the text of each
of the clauses under which the Main Contractor is entitled to submit such claims.
The word direct is used in order to make it clear that such claims are directly related
to the cause, and are not incidental losses or expenses.
119
I1IlRTEEN CONTRACTOR'S CLAJMS
The process of arriving at a monetary fIgure which will accurately reflect the
true direct loss and/or expense suffered by the Main Contractor is diffIcult,
as there are so many different factors involved. In order to facilitate the
process of evaluation, claims may be considered under the following headings:
• Materials L •
120
THIRTEEN CONTRACTOR'S CLATh{S
When preparing the tender, the Main Contractor will make allowances
for labour market conditions. Once the Contract is awarded and work
starts on site, a much more detailed appraisal of costs is made. These
detailed costs more accurately reflect the Main Contractor's direct
losses and/or expenses that will almost certainly be claimed.
"
;;
III Inflation
Neither Clause 11 (6) - which allows claims for direct loss and/or
expense due to variation, nor Clause 24(1) - which allows claims for' , ..
direct loss and/or expense due to disturbance of regular progress of the
Works, gives the Main Contractor the right to challenge the adequacy
of a fluctuations clause; this is a risk which the Main Contractor
accepts once he has signed the Contract. It is only the increase in the
burden of that risk, due to an extended contract period, that is relevant
in relation to a claim for direct loss and/or expense.
121
TBIKI'EEN CONTRACTOR'S CLAIMS
-'-
)~
Care must be taken to ensure that any reimbursement under the
fluctuation clause is not duplicated when evaluating direct loss and/or L
i, '
expense.
Head office overheads and profit are usually allowed for in a tender by
. means of a percentage on the value (or part value) of the Contract.
The payment of additjqnal money in respect of head office overheads
and profit is the subject of much debate.
• Finance charges
The plaintiff will make the original claim and a cross claim then may be made by the
defendant. A cross claim may take the form of a set-off or the form of a counter
claim.
Counter claim simply means that the defendant is making his own independent claim
against the plaintiff.
122
THIRTEEN CONTRACTOR'S CLAIMS
11 Costs
A set-off may reduce a plaintiffs claim to a sum which does not normally
carry costs; payable by the defendant if the plaintiff succeeds. This is the
main reason for a defendant asking that a cross claim be set-off. In the case
of a successful claim and counter claim, both plaintiff and defendant would be
ordered to pay costs.
123
-'
-'
The action contemplated by Clause 25 of the HK Standard Form, under which the Employer
can determine, and by Clause 26, where it is the Main Contractor who can determine, is
referred to as: ... determine the employment of the Main Contractor under this Contract. This
is to be distinguished from determination of the Contract, when the Contract itself becomes
inoperative, leaving legal proceedings for breach as the only recourse. The two clauses on
determination in the HK Standard Form set out the procedures to be followed after
determination of the Main Contractor's employment, and the rights and duties of the parties,
until fInal. settlement. These two clauses determine only the employment of the Main
Contractor, while leaving the Contract itself in place, therefore, the clauses themselves
remain operative.
Optional Determination
Clause 25(1)(a)-(d) provides the option for the Employer to determine the
employment of the Main Contractor under the Contract for the following reasons:
(a) If the Main Contractor wholly suspends the Works without reasonable
cause. This means a complete cessation of work; partial suspension is not
enough. The stoppage must be without reasonable cause.
125
-'
FOURTEEN DETERMrnATION OF EMPLOYMENT
(b) Failure to proceed regularly and diligently. This is very difficult for the
Employer to establish and does not merely mean failing to comply with the
programme. Also, the Main Contractor could argue, depending on the
circumstances, that he had reasonable cause for the alleged failure. For
example, if the Employer were persistently late in honouring certificates, this
could well be reasonable cause for slowing down so as to reduce cash flow
problems.
The Employer must follow the determination procedure exactly; If he fails to do so,
the determination will be invalid. First the Architect must serve notice on the Main
Contractor by registered post or recorded delivery, specifying the default, so as to
provide on opportunity of remedying it. If the notice is in general terms, for
example, merely alleging that the Main Contractor is not proceeding regularly and
diligently, it will not be sufficiently explicit. On receipt of the notice the Main
Contractor has three courses of action open to him:
• He can accept that he is in default, put matters right immediately and inform
the Architect that the default specified in the notice has ceased. However, if
the Main Contractor repeats tI:ie specified default at anytime thereafter, the
Employer is entitled to determine his employment without further notice of
default from the ArchiteCt.- .
• The Main Contractor may ignore the notice of determination and risk the
consequences of the Employer· exercising - his option to determine his
employment under the Contract.
If the Main Contractor continues his default for fourteen days after receiving the
notice, then the Employer may, within ten days after such continuance or repetition,
determine the employment of the Main Contractor under the Contract by a registered
post or recorded delivery notice.
126
POURIEEN DETERMlliATION OF EMPLOThffiNT
Should the Main Contractor cease his default within the ten day option period, the
Employer's option to determine does not end but will continue for a further ten days
from the date that the default ceases. The reason for this is to allow for the situation
where the Main Contractor makes only a token attempt to cease the default without
seriously intending to.
If the Employer does not notify the Main Contractor of his decision to determine
within the said ten day period, he will lose his option to determine the Main
Contractor's employment for the specified default. No matter what the Employer
chooses. it will be without prejudice to any other rights or remedies, meaning, for
example, that he may still sue for damages .
.
l
,
,
The Employer's notice of determination of the Main Contractor's employment must
not be given unreasonably or vexatiously as stated in Clause 25(1). It is difficult to
defIne exactly what is meant by the phrase unreasonably or vexatiously.
Unreasonably suggests that the Employer must not be taking advantage of the Main
Contractor in circumstances which, from a business point of view, are totally unfair.
Vexatiously suggests a situation where there are insufficient grounds and that the
notice has obviously been issued to cause annoyance.
Automatic Detennination
Clause 25(3)(a)-(d) deals with the respective rights and duties of the parties on
determination by the Employer whether optional or automatic. In summary, the
position is as follows:
(a) The Employer may employ others to complete the Works, who for this
purpose, may enter on them, use all temporary buildings, plants, tools,
equipment, goods and materials intended for them and placed on or adjacent
to them; and purchase all materials and goods required for completion.
(b) " "The Main Contractor shall (except where determination occurs by reason of
the Main Contractor's bankruptcy) if so required, assign to the Employer the
benefit of any agreement for the supply of materials or goods and/or the
execution of any work under the Contract.
127
FOURIEEN DETERM1NATION OF EMPLOYMENT
(c) The Main Contractor shall, when required in writing by the Architect to do
so (but not before), remove from the Works any temporary buildings, plant,
tools, equipment, materials and goods belonging to or hired by him. If within
a reasonable time after such a requirement, the Main Contractor has not
complied, then the Employer may (without being responsible for any loss or
damage) remove and sell any such property. The proceeds, less all costs
incurred, will be held by the Employer to the credit of the Main Contractor.
(d) The Employer is not bound to make any further payment to the Main
Contractor until the completion of the Works. Upon completion he may
deduct from sum due to the Main Contractor the amount of the direct loss
and/or damage caused by the determination. If, as a result, there is a balance
in favour of the Employer, that balance will be payable as a debt to him by
the Main Contractor. Conversely if the amount payable to the Main
Contractor is greater than the amount of the direct loss and/or damage caused
to the Employer, the difference shall be a debt payable by the Employer to the
Main ·Contractor.
The events which may give rise to such a determination by the Main Contractor are
clearly set out in Clause 26(1)(a)-(d) and may be summarised as follows:
(a) Failure to honour certificates of payment. If the Employer does not pay
amounts properly due on certificates within the Period for Honouring
Certificates named in the appendix (fourteen days if none other is stated), the
Main Contractor may then exercise his right to determine his own employment
under the Contract.
128
FOURTEEN DETERMINATION OF EMPLOYMENT
The Main Contractor may do this by sending a letter to the Employer (not the
Architect), by registered post or recorded delivery stating that if payment is
not made within seven days of receipt, notice of determination of employment
will be served. Should the Employer fail to pay within seven days of receipt
of the letter, the Main Contractor may determine his own employment
forthwith by a notice sent by registered post or recorded delivery to the
Employer or the Architect.
(c) Suspension of the Works for a period stated in the appendix. This can be
due to any of the following causes as listed under Clause 26(1)(c):
I
fi.'. .·
,~ There is no need for the Main Contractor to serve a preliminary notice of
default in any of these cases. Once the period of suspension has elapsed the
Main Contractor may determine his own employment forthwith by serving
notice on the Employer or the Architect by registered post or recorded
delivery.
129
---- .. ---.
.'
FOUKlEEN DETERMlNATION OF EMPLOYMENT
(a) The Main Contractor must forthwith remove all his temporary buildings,
plant, tools, equipment, materials and goods in such manner and with such
precautions as will prevent injury, etc.
(b) The Main Contractor is entitled to receivepay~ent from the Employer for the
following:
(ii) The total value of work begun and executed but not completed at the
date of determination, valued as if it were an authorised variation.
(iii) Any sum ascertained as direct loss and/or expense under Clause
11(6), 24, and 34(2), whether ascertained before or after
determination.
(iv) The cost of materials ordered for the Works for which the Main
Contractor has paid or is legally bound to pay.
(vi) Direct loss and/or damage caused to the Main Contractor by the
determination.
I
I
130
The settlement of disputes arising from building contracts by methods other than litigation
is co=on practice. The main reason for this is, that where the substantial questions of the
dispute are matters of fact rather than of law, a fInal and conclusive decision can be obtained
in a manner which is quicker and cheaper than the formal legal process. Arbitration is the
most widely used method of settling building contract disputes. However, alternatives such
as mediation, conciliation and adjudication are rapidly gaining recognition; they are
collectively referred to as alternative dispute resolution, abbreviated to ADR.
15.1 Arbitration
Tenninology: Arbitrator is the person to whom the dispute is referred for settlement.
Sometimes there are two in which case a third person, an umpire, is appointed to
settle the dispute between the parties should the arbitrators fail to concur; Award is
the term used for the decision of either an arbitrator or umpire; the Court means the
High Court.
131
FIFTEEN RESOLUTION OF DISPur:gs-'"
Arbitration Agreement
Appointment of an AIbitrator
When drawing up the arbitration agreement the parties may either name the
arbitrator or arbitrators, leave their appointment.in the ·hands of some named
person, such as the president of one of the professional institutions, or leave
the matter open until a dispute occurs and then make the appointment
thelllSelves. If the arbitration agreement is silent as to whether there are to . I
be one or two arbitrators, then the reference shall be heard by a single I
arbitrator. If the parties cannot agree on the appointment of an arbitrator or 1
if an appointed arbitrator dies, refuses to act, or becomes incapable of acting I
and the parties cannot agree on his successor, the Court will appoint a new I.
arbitrator on application. l
Disqualification of an Arbitrator
132
-'
FIFTEEN RESOLUTION OF DISPUTES
III Interest may indicate that the arbitrator has a direct interest in the subject
matter of the dispute or that he is indirectly interested by reasons of a
relationship to one of the parties. The latter point may arise in connection
with building contracts where the architect, although employed by the
building owner, is frequently nominated as arbitrator for the settlement of all
disputes arising out of the contract (note that this is not the case under the HK
Standard Form). Such a person is not barred from acting as arbitrator ifboth
parties agree and are fully aware of his position at the time of his
appointment. However, the Court may subsequently revoke the authority of
the arbitrator or grant an injunction to restrain the arbitrator from proceeding,
if on the application of one of the parties, it considers that by reason of his
position he is not a suitable person to hear the case. Also, the arbitrator
cannot act as a witness for either party; this would compromise his neutrality
in the reference.
III Bias indicates a state of mind on the part of the arbitrator which creates
a possibility that he will not arbitrate justly an fairly with respect to both
parties. For example, where the arbitrator is heavily indebted to one of the
parties without the knowledge of the other he can be restrained from acting
by the Court. Remarks made during the conduct of a case which clearly
show that the arbitrator is biased against one of the parties will probably lead
to his removal by the Court for misconduct. For example, in an arbitration
reference relating to a collision between two vessels of foreign nationality the
arbitrator remarked: .. .the Italians are all liars in these cases and will say
anything to suit themselves. On the other hand Nonvegians in my experience
are generally truthful people. In this case I accept the evidence of the
,, Captain of the Nonvegian ship. The Court removed the arbitrator for
misconduct.
Provision for arbitration during the progress of the Works is also made under
Clause 35 (2), in the following cases:
133
FlFT£.EN RESOLUTION OF DISPUTES
-' ----, ' r~
...
Arbitration Procedure
In the event of any dispute arising under the HK Standard Form which either
party may desire to refer to arbitration, a written request to concur in the
r}'
appointment of an arbitrator shall be given by one party to the other. The i·'.·
matter will then automatically be referred to the arbitration of the person so Ji. '
r!
appointed, or in default of agreement, appointed by the President or the
Vice-President of the Royal Institute of British Architects co--jointly with the
Chairman or Vice-Chairman of the Royal Institution of Chartered Surveyors.
Once appointed, fuiI power is given to the arbitrator to act as.he may think
fit in order to decide the rights of the parties concerning the questions
submitted to him for his decision.
Preliminary meeting
A preliminary meeting with both parties will be held before the hearing itself
begins; there are several reasoJ.S for this. The arbitrator is able to introduce
himself and meet the parties informally. He will make clear his position as
arbitrator, including the important point that his decision is final and binding,
and is enforceable in the same way as the judgment of a court. Also, the
arbitrator will be able to explain to the parties the procedure at the hearing
and what is required of them. The parties will be told that they will need to.
produce details of their claims, in writing, sending copies both to the
arbitrator and the other party, and that they will be required to explain in
writing to the arbitrator how they intend to conduct their case, naming
witnesses and citing any evidence they wish to use. FinaiIy, a date, time, and
place for the hearing, which is convenient to both parties, can be arranged.
• The party .making the claim (claimant) will open the proceedings by I
stating his claim and producing any witnesses he requires to prove his points
of claim. Witnesses have to take an oath; to give false evidence on oath is
a crime known as perjure.
I
I
• The respondent will open his defense to the claim, present his cross claim
I
and call his witnesses.
• The claimant may cross-examine the witnesses, and if any new points
arise, the respondent may re-examine on those points only.
• After evidence has been completed, both parties in turn may address the
arb itrator summarising their case and the points to which they wish to draw
the arbitrator's attention; these are known as the closing submissions. The
arbitrator may require that all or part of the closing submissions be reduced
to writing.
134
FlFIEEN RESOLUTION OF DISPUTES
11 At the end of the closing submissions the arbitrator will declare the
hearing ended. However, the arbitrator may, if he considers it necessary due
to exceptional circumstances, either upon his own motion or of the parties,
re-open the hearing before making his award.-
11 The arbitrator. may order the parties to make any property or thing
available for his inspection or investigation, and inspect or investigate it in
their presence.
Awards
The arbitrator will make two awards, the fIrst dealing with all matters in
dispute among the parties - the main award, the second dealing solely with
costs - the costs award. All awards must be in writing and signed by the
arbitrator who is also required to give reasons for every award except the
costs award. The main award should be made 'within sixty days of the
conclusion of the hearing. The costs award will not be made until at least
fourteen days after the main award, during which period of time the parties
will send their submissions on costs to the arbitrator. Subject to the
Arbitration Ordinance, all awards are legally binding on the parties, who must
carry out the terms of the awards without delay.
Appeal
Both parties have the right of appeal to the High Court, although such appeals
are very rarely successful. In most cases the Court will uphold the decision
of the arbitrator, unless there are real grounds for doubting the validity of the
award. Such grounds may be that the arbitrator had misconducted himself or
the proceedings, or that the award had been improperly brought about.
Under such circumstances, the Court may either set-aside the award, which
means they will make it unenforceable, or remit the award. If the Court
remits the award, they will ask the arbitrator to revise all or certain aspects
of the award. An appeal to set aside or remit the award must be made within
six weeks of the award being given.
Costs
The costs of the reference and the award will be at the discretion of the
arbitrator who may direct to, and by whom, and in what manner, those costs
or any part of the costs, must be paid. Such an order is known as the costs
--award. The term costs inClude:
135
FIFTEEN RESOLUTION OF DISPUTES
Security for costs If, upon application of a party to the arbitration, after due
notice to the other party, it appears to the arbitrator that a claimant (or
respondent making a counter claim) may be unable to meet any order for
. costs made against them in the arbitration, the arbitrator may require that the
I
.!
party in question provide security for the costs of the other party. Such
security may, for example, be the guarantee of a bank or insurance company.
Advantages of Arbitration
11 Technical procedural rules of a court of law are not rigidly applied, which greatly
simplifies and consequently expedites matters.
11 The time and place of the reference can be chosen to suit the convenience of the
parties. If litigation is used to resolve the dispute, the parties will be instrU(~ted when
and where to appear; they- have no say in the matter.
11 Arbitration is usually less costly, partly because often there are no legal fees
involved. Also, costs may be apportioned between the parties at the discretion of the
arbitrator. ~\.J>"
11 It can be made a condition of the arbitrators appointment that he should view the
property or sample the goods which are the subject of dispute.
I,
11 An arbitration reference is held in private and the decision is not published. This
means that neither party is at risk of suffering as a result of possible adverse
publicity.
Disadvantages of Arbitration
11 The arbitrator may be required to seek the decision of the courts on points of law
which may lead to delay. If there are a number of points of law referred to in a case
which require a court ruling, it may prove cheaper and quicker to refer the whole
matter to the courts in the fIrst instance.
136
FIFTEEN RESOLUTION OF DISPUTES
III Only the parties to the arbitration agreement can be bound by the decision of an
arbitrator. Interests of third parties, such as sub-contractors, cannot be prejudiced
(affected).
III There is no precedent in arbitration as there is in court cases. This means that
no previous case decisions are taken as the rule; the award will be entirely at the
arbitrator's discretion. This is often classified as a disadvantage because there is no
basis on which to judge the likely outcome of a dispute. However, some may argue
that it is an advantage not to be bound by precedent; allowing each case to be judged
on the individual facts presented.
Facing similar problems to those encountered in the USA - significant direct costs in
the form of legal fees, wasted management time .and indirect costs imposed by the
adversarial nature of the contract - construction contract policy makers in the United
Kingdom started to re-examine the contract administration process. As a result,
ADR provisions, in the form of adjudication and conciliation clauses, were
introduced into a number of standard form main and sub-contracts in the private
sector. However, the notable exception was the JCT 80 standard form 'of main
contract (the equivalent of the HK Standard Form and the most widely used private
standard form of building contract in the United Kingdom) which to this day does not
contain an ADR provision. The situation in Hong Kong is similar in as much as the
HK Standard Form, Hong Kong's most widely used private standard form of building
contract, has yet to introduce an ADR provision, despite having been given the lead
by government. The Government of Hong Kong introduced a provision for
mediatioll in the Settlemellt of Disputes. clause of the 1990 edition of their
Conditions of Contract; and the 1992 edition of the General Conditions of
Contract used for the Airport Core Programme includes provision for both
mediation and adjudicatioll, in addition to arbitration.
137
:.:. ;':--:':"':';;';':';':'~-;'-':-;."'-"'-"'-"'-'-"'-'-'-'"
.-.- -.-,-~ ..-.-.-.'...-.. ;._.,. ," -".' '.-, ...•.........•.•............•,.,...---:.... -.
~ ~OLUTIONOFDmp~ . t'.
--,1
I:
15.4 Strengths and Weaknesses of ADR I
11
Strengths of ADR
1
Cost savings Approximately 90 % of cases which are started through the i
courts or arbitration, settle just before the hearing. In view of this, a major
strength of ADR may be seen as the bringing forward of the traditionaI date
of settlement, from just before the court proceedings or arbitration hearing
I
(the phrase co=only used is, 'a settlement on-the-steps of the court), to a
much earlier stage in the procedure, thereby saving legal and executive costs.
Multi-party All too often construction disputes involve the employer, the
main contractor, the sub-contractor and the consultants. All these contractual
I
arrangements are subject to different dispute resolution processes, which often
means that an employer is faced with the unsatisfactory prospect of having to
138
1I FIFTEEN RESOLUTION OF DISPUTES
resolve some of the disputes through the courts and some through arbitration.
i-• ADR allows all disputing parties to come together in a co=on forum
regardless of the requirements of the contract.
J
Weaknesses of.ADR
I
too close to trial for alternatives to be of any value. On the other hand, with
ADR there is a risk of proceeding without proper discovery or disclosure of
evidence provided by expert witnesses. However, it is possible to minimise
11 this risk by the parties agreeing to disclose key documents and by giving an
" undertaking that they know of no other evidence which would affect the
position of either party signifIcantly. It is also possible to allow the parties
to present a statement of the evidence; in addition to the facts upon which
they rely, in order that the other 'party is not taken by surprise. Finally,
expert witness statements can be prepared at a very early stage and exchanged
for the purpose of the ADR process. The only material disadvantage is that
the production of statements at such an early "stage would effectively reveal
to the opponent the nature of the evidence to be relied upon.
139
--,--1f'---'.
FIFTEEN RESOLUTION OF DISPUTES
and that by making such a suggestion the other party is, in effect, displaying
some degree of weakness. In fact, ADR is not a sign of weakness but a
rl i
suggestion of confidence in an ability to put the cards on the table and to
negotiate a positive outcome. Also, business clients often underestimate the
constructive impact that a third party will have on dispute negotiations. The
syndrome of 'suggesting ADR conveys a weakness' can easily be overcome
by incorporating an ADR clause in the original contract between the parties.
I
I
Most ADR organisations actively encourage the use of ADR clauses in
co=ercial contracts by providing sample clauses which may be adapted to
particular contracts.
Appropriateness of ADR
The advantages of ADR mean that it should be considered fIrst in most cases.
However, it is not always appropriate. The following are circumstances
under which ADR might be rejected as a fIrst approach:
140
-'
FIFTEEN RESOLUTION OF DISPUTES
III Contrary to what some may believe, the risks of ADR are minimal
Because ADR is non-binding, settlement is not required at any time unless
there is an 'agreement that both parties can live with. Confidentiality is
assured by requiring the neutral and the parties to sign a confidentiality
agreement. The greatest risks run are (a) that there will be a greater
understanding by each party of the others side's case and (b) a settlement will
be reached; 80 % settlement rates are reported after mediation. If there is a
real worry about revealing information or positions, ADR is flexible enough
to work with separate meetings between the neutral and the parties (' shuttle
diplomacy'). In any case, it should be remembered that the other side will
also disclose their hand; joint disclosure assists settlement.
--
IIIIt is a common belief that managers and lawyers already practice ADR
in settlement discussions It is true that mangers are often practised in the
skills of direct negotiations and that lawyers do sometimes bring about a
settlement through negotiation. However, this is not genuine ADR in which
the powerful influence of a skilled third party neutral plays a very important
part. ADR ensures that settlement is truly managed rather than an endurance
process dependent on court timetables, legal uncertainty and costs based on
the taxi-metre billing system. ADR helps all parties and their advisors to
focus on the- problein with ilie benefit of an impartial overview of the case.
141
FIFTEEN RESOLUTION OF DISPUTES
assessment of the case more rapidly than the adversarial process. Many
disputes settle soon after a failed ADR process.
Litigation and ADR There can be an agreement to stay further legal action
during the ADR phase. However, it is possible to continue with both
litigation and ADR simultaneously. Again, the earlier ADR is used, the
greater the potential benefits. It is sometImes even useful to use ADR after
a trial or award; for example, the parties may have been left with
uncertainties on how to implement a judgement.
• Mediation
• Conciliation
• Adjudication
• Expert Appraisal
142
,
FIFTEEN RESOLUTION OF DISPUTES
Mediation
Mediation describes a voluntary process (which either side may abandon at any time
without prejudice), whereby each side to a dispute is brought together before a
neutral mediator, whose function is to assist the paries to arrive at a co=on position
by joint open session and private caucus. During this process the mediator acts only
as a catalyst, not expressing his or her own opinion and not disclosing confidential
information imparted by one of the parties, to the other. Through this process the
parties move closer together until they reach a coriunon position when settlement is
reached. Because the mediation process itself is non-binding and entirely without
prejudice, it is necessary to record the agreement, in contract form, if it is to have
legal effect.
,~
i;
Although mediation is not a regulated process, some rules do exist and are published
by a few organisations, for example: The Construction Industry Mediation Rules
published by the National Arbitration Co=ittee in the United States, and the Hong
Kong Government Mediation Rules published by the Government of Hong Kong.
Mediation Procedure
143
-'
FIFTEEN RESOLUTION OF DISPUTES
• The whole mediation process, from the time the mediator first introduces
himself to the parties to the reaching of a settlement, takes, on average, no
more than four days.
The mediator The role of the mediator, as a neutral and trained professional
chosen by the parties, is to: provide a framework for negotiation; act as an
impartial third P<ll1Y in the negotiation process; and make recommendations
as to how the dispute may be settled. A mediator is not given the authority
to make legally binding decisions. However, if the parties find the
reco=endations acceptable, they then have the option of making their
agreement legally binding. On the other hand, if they are dissatisfied with the
process, either party or the mediator may terminate the mediation at any time.
The claimants may then proceed to assert their legal rights through arbitration
or .litigation.
144
FIFTEEN RESOLUTION OF DISPUTES
architect fails to' give a decision as required, they may request the initiation
of mediation by delivering a written request for mediation to the other party
with copies to the architect and the HKlAC. Such a request for mediation
must contain a brief self explanatory statement of the nature of the dispute,
the relief or remedy sought, and the name of a nominated mediator thought
suitable. The party who receives a request for mediation must notify the
other party, the architect, and the HKIAC, within twenty-eight days after
receipt of the request, whether or not he is willing to participate in the
mediation, and if so, whether any mediator nominated is acceptable. In the
event that the nominated mediator is unacceptable, the parties must· within
fourteen days of the date of the acceptance of mediation attempt to agree on
a suitable mediator. Where the parties agree on a mediator and the proposed
mediator is willing to serve, they will notify the HKIAC. The mediation will
then proceed in accordance with the Hong Kong Government Mediation
Rules. If the parties fail to agree on the appointment of mediator within the
stipulated time, they will inform the HKIAC who will, on the advice of the
HKIAC Mediation Committee (comprising a balanced representation from
various professional bodies connected with the construction Industry), appoint
within fourteen days a single mediator who is prepared to serve and is not
disqualified under the disqualification rule.
Mediator may not subsequently act as arbitrator The mediator may not
be appointed as arbitrator in any subsequent arbitration between the parties,
whether arising out of the dispute or otherwise arising out of the same
contract, unless the parties agree in writing. Neither party is entitled to call
the mediator as a witness in any subsequent arbitration or litigation arising out
of the same contract.
Time constraints Under the Hong Kong Government Mediation Rules the
mediator is required to enter upon the mediation as soon as possible after his
appointment' and should endeavour to conclude the mediation (including any
report which may be required) within forty-two days of his appointment. His
appointment will not' extend' beyond' it period of three months without the
consent of both parties.
145
FlFTEEJl RESOLUTION OF DISPUTES
-' Il!•
1
separately, for the purpose of informing himself of the nature and facts of the I
dispute. If the mediator considers it appropriate, or if he is requested by the !•
parties, he may express preliminary views orally or in writing on the matters i
in dispute during the mediation. The mediator may, and shall if requested by
the parties, seek legal or other advice from third parties not connected with I
the dispute. During the course of the mediation the mediator may attempt
various compromise solutions with the parties in an informal manner. Also,
the mediator has the option to abandon the mediation whenever in his
judgement further efforts at mediation would not lead to settlement of the
I
dispute. He must notify the parties in writing of such a decision.
Costs Under the Hong Kong Government Mediation Rules the sum of I
$20,000 is to be deposited by each of the parties with the HKIAC before the
mediator enters upon the mediation, as a contribution to the cost and proper I
expenses of the mediation, including the costs of the HKIAC.The mediator
may at any time during the course of the mediation require the parties to
make a further deposit or deposits with .the HKIAC to cover anticipated
I
j
i
additional fees and expenses. Subject to any order the mediator may make,
after deducting the costs and expenses of the mediation, the HKIAC must I
return any surplus funds, in equal shares to the parties, at the'conclusion of I'
the mediation. If the mediator frods that the mediation has been initiated or
conducted frivolously or vexatiously.. then he has the power to order the. party
t•
2
Conciliation I
Conciliation is procedurally similar to mediation, and in practice the difference I
between a mediator and a conciliator is often more perceived than actual. It is often
the case that the terms mediation and-conciliation are used inter-changeable and that
146 ,
"
which raises doubts over the difference between the two. Indeed at a seminar held
by the British Academy of Experts, two leading experts in the' field expressed
diametrically opposite views on the interpretation of both methods. It would
therefore be prudent, if ADR were discussed seriously, to ensure that both parties
agree on the precise meaning of the proposed procedure.
Conciliation Procedure
III A copy of the conciliation request and the names of the parties
representative must be sent to the conciliator.
III Written submissions will be exchanged between the parties and copies
supplied.to the conciliator. Each party states their own version of the dispute
and attaches docUments relied Oll 'aiid any written statement of evidence: - ,
147
-'
,
FIFTEEN RESOLUTION OF DISPUTES
I
• A formal meeting with both parties may be convened by the conciliator,
at seven days notice, for the purpose of taking evidence and hearing
I,
i
submissions . i
the conciliator. . I
• The conciliator is required to prepare his recommendations within 21 days
I
of the formal meeting.
Conciliation in Practice
i
Adjudication I
Adjudication differs from mediation [and conciliation] in that, to a greater or lesser I
extent, the outcome is binding on the parties and therefore its efficacy is not
dependent on the co-operation of both parties. It differs from arbitration in that the .
I,•
process is summary and may to some extent be inquisitorial, and the decision is !
ordinarily only an interim one. It should be made clear that the 'outcome' is the
adjudicator's finding which may stand as a permanent binding decision if the parties
so agree; or be used as the basis for further negotiations between the parties; or
accepted as a temporary binding decision until a certain time has passed (e.g.
contract completion) at which time the parties will be free to seek if legal or irrbitral
award to revoke the earlier decision.
148
FIFTEEN RESOLUTION OF DISPUTES
panel, who are retained for the duration of the project under a separate contract; the
parties share the costs equally. .
Adjudication Procedure
Adjudication in Practice
Adjudication is in use in many contracts in the UK, for example: III ACA
Form of Building Agreement (second edition 1984) allows for the resolution
of disputes using an adjudicator although the clause is optional. The
adjudicator must be named in the docnment if the option is to be exercised.
The adjudicator's powers extend to matters concerned with extension of time
and adjustments to the contract sum.. The adjudicator's decision is fInal and .
binding untiI completion of the works after which either party may then refer
the matter to arbitration. III JCT with Contractor's Design (CD 81)
provides an optional supplement for Resolution of Disputes by Adjudication.
The matters which may be referred to the adjudicator under this clause are
not dissimilar to those under the ACA Form.
149
-'
FJFIEEN RESOLUTION OF DISPUTES
However, unlike the ACA Form the decision of the adjudicator becomes a
provision of the contract and fInal and binding unless either party disputes the
decision within 14 days of receipt. In any event arbitration over the matter
1
i,
•
cannot take place until after practical completion. 11 ICE New Engineering
Contract and Sub-Contract (1991), it's principle features are that the I
;
adjudicator is named from the outset; the right to proceed to adjudication I
arises on either party disagreeing with an action of the Project Manager or
Supervisor, or considering it to be outside their authority; a party dissatisfIed
with the decision of the adjudicator has eight weeks in which to refer the
matter to arbitration, the clause does not otherwise address the status of
binding effect of the decision; the fees of the adjudicator are shared equally. I
,
11 The mini-trial panel is expected to hear the parties and then to propose
I
or to facilitate a settlement. If no settlement is reached or proposed within a
reasonable time, then the panel should submit a reco=endation either
unanimously or by the chairman.
Ii
11 The proced.ure is brief with only a few weeks allowed for the parties to
prepare their- case followed by a 'trial' of a few days' duration.
150
FIFIEEN RESOLUTION OF DISPUTES
III Presentations are informal with rules of evidence not strictly adhered to.
Cross-examination of witnesses is allowed but severely limited in duration.
Mini-Trial in Practice
Mini-trial clauses are not to be found in any of the standard form contracts
used in Hong Kong or the UK. However, it is an alternative form of dispute
resolution offered by many ADR organisations including International Dispute
Resolution Europe (IDR Europe). If the mini-trial is chosen, the parties may
adopt one of the following two frameworks available at present: III Rules of
the Centre for Public Resources (CP.R), New York; or 11 Rules of Zurich
Chamber of Co=erce.
Expert Appraisal
This technique offers the parties in dispute a technical expert's assessment of their
case to assist negotiations. In some cases, parties may wish to seek such appraisal
individually rather than jointly. There is very little in the way of co=entary on this
technique of ADR, although the Centre for Dispute Resolution (CEDR) in the UK
list expert apprclisaZ as an ADR technique available through their organisation.
Expert appraisal may be viewed as a tribunal of a lay nature, where the parties chose
an expert to provide a valuation for them but not to make a decision in a dispute.
As such the tribunal is not governed by or subject to the UK's Arbitration Acts 1950, .
1975 and 1979, or to Hong Kong's Arbitration Ordinance.
Under the FIDIC Conditions of Contract for Civil Engineering Work, 4th edition'
(1987), there is an obligation on both the employer and the contractor to attempt to
resolve disputes through amicable settlement under the provisions of sub-clause 67.2, .
before proceeding to arbitration. The essence of this sub-clause is that when an
intention to co=ence arbitration over a dispute has been given (in accordance with
Sub-Clause 67.1 Engineers Decision), arbitration of the dispute may not co=ence
unless an attempt has first been made by the parties to settle the dispute amicably.
However (unless the parties otherwise agree) arbitration may co=ence on or after
the fifty-sixth day on which notice of intention to co=ence arbitration of the dispute
was given, whether or not any attempt at" amicable settlement has been made. Under
these provisions, it would appear that any ADR technique may be chosen by the
parties as a means of arriving at an amicable settlement.
151
, I
...
II,
!
I
1!
~
,~
r
j
!
j
~i
I;
I
I:I, .
i!
---- - - ------ - - . - - - - - ----
-'
APPENDICES
J
i
I
I
I
i-
I~
i
11
.'
r-i
Appendix 1 i
I
Architect's
INTERIM CERTIFICATE
Serial No.:
I
i
•
I
name and address:
Valuation date:
. Employer's name
and address: Instalment date:
IIWe certify that in accordance with Clause 30 of the Agreement and Schedule of Conditions
of Building Cont:I:act for use in Hong Kong; Second Edition 1976 (May 1979 Revision),
I
Under the Contract
dated: .......................................... .
154
Appendix 2
INTERIM VALUATION
!
4. Unless stated, liquidated
damages have not been deducted. Total Retention as Valuation 2,812,030.00
155
Appendix 3
CERTIFICATE OF PRACTICAL COMPLETION
In accordance with the Agreement and Schedule of Condition of Building Contract for use
in Hong Kong, Second Edition 1976 (May 1979 Revision), IfWe certify that subject to the -
completion of any outstanding items, and/or making good of any defects, shrinkages and
other faults which appear during the defects liability period,
(a) the Works were in my/our opinion practically completed as described in Clause 15(1)
on:
and that the said Defects Liability Period will end on:
the approximate value of which I1we estimate for the purposes of Clause 16 (but for
I
I,
I
no other) to be:
!
i
was taken into possession under Clause 16 on:
I•
-;
and that in relation to the said part of the Works, the said Defects Liability Peiiod
will for the purpose specified in Clause 16(b) end on: i
IfWe declare that a certificate for one moiety of the retention moneys deducted under
-previous certificates in respect of the said Works or part thereof is to be issued in accordance
with the Conditions of Contract.
I-i
Signature: ...................... Architect Date: ............... :: .... .
I
i
Original to: Main Contractor
Copies to: Architect's fIle . Quantity Surveyor. Clerk of works. Consultant -engineers
156
·'
Appendix 4
CERTIFICATE OF MAKING GOOD DEFECTS
Date:
Works:
Situated at:
To Main Contractor:
In accordance with the Contract, we certify that all outstanding items and all defects, and
other· faults which appeared during the Defects Liability Period were in our opinion
completed and made good.
We declare that a certificate for the residue of the retention monies deducted under previous
certificates in respect of the said Works is to be issued in accordance with the Conditions of
Contract.
157
Appendix 5
l !
i
!
FINAL ACCOUNT
i!
i
Contract No.: Architect's name
and address:
Employer's name
and address:
SUMMARY
Omissions Additions
$ $
ADJUSTMENTS:
Provisional sums
421,220.00
5,000.00
410,181.65
4,681.35
I
•
I
Agreed Contractor's claims 2,310.50 iI
Fluctuations 55,000.00
I
500,775.20 2,493,530.50
i
500,775.20
I
TOTAL FINAL ACCOUNT $1,992,775.30
=========
. ·IfWe agree to accept the sum of $1,992,775.30 (in words) ONE MILLION, NINE
HUNDRED AND NINETY TWO THOUSAND, SEVEN HUNDRED AND SEVENTY
FIVE DOLLARS AND THIRTY CENTS ONLY, as full, final and sufficient payment for
work carried out under the above Contract.
158
li
-'
Appendix 6'
FINAL CERTIFICATE
In accordance with Clause 30(6) of the Agreement and Schedule of Conditions of Building
Contract for use in Hong Kong, Second Edition, 1976 (May 1979 Revision), *IfWe certify
under the Contract
dated: .......................................... .
that 1. The Contract Sum adjusted as necessary in accordance with the terms of the
above mentioned Conditions is:
$ ................................................... .
and 2. The sum of the amount paid to the Main Contractor under Interim Certificates
and of any payments not included in that amount made in respect of the
amount named as the Limit of Retention Fund is: I *The sum of the amounts
already paid to the Main Contractor under Interim Certificates and certificates-
...., issued under sub clause (4)(b) and (4)(e) of the above mentioned Conditions
15:
159
Appendix 7 1
!
,f
i ~
THE WAGE INDEX
I,
i
Wages in February 1993 i'
Occupation
!I
HK$ Index
160
.1
I•
I
I
I: Appendix 8
"'
i~
I
r•
~
FLUCTUATION CALCULATIONS
i
; . OCCUPATION INDEXED DAILY WAGES OF WORKERS
CONTRACT INFORMATION
REQUIRED
11 Average wage index for SEP 1991 (base month) given the above information in
accordance with Clause 36(2)
I III Average wage index and average percentage increase for aCT 1992 given the above
information in accordance with Clause 36(2) and 36(4)(a)
Ir
11 Average wage index, average percentage increase, and the amount that the Contract
Sum should be adjusted by for fluctuation in wage rates for FEB 1993 given the
above information in accordance with clause-36(2) and 36(4)(b)
SOLUTION
i 81 18618 = 2327.25
161
-'I
I
I
Appendix 8 I
i
• Average wage index for OCT 1992
Labourer (Male)
Concretor, Bricklayer, Drainlayer
1782
2664
I
!
i,
Steel Bender 3782
Blacksmith 2484
Carpenter and joiner· 2608
Plasterer 2507
Glazier 2244
Painter 2298
8/20369 = 2546.13
AB the percentage increase does not exceed 10% no adjustment to the Contract Sum
will be made for fluctuation in wage rates for OCT 1992
$237,700 x 4.45% = $10,577.65 added to the next interim certificate for wage I'
rate increases in FEB 1993
162
GLOSSARY
J .
i
-'
l ,J
GLOSSARY I
;
Accord and satisfaction an agreement to discharge a right pf action for some consideration
Affidavit a written statement sworn on oath which may be used in cenain cases as evidence
Affirmation of contract election not to terminate a contract which has been breached
Aggravated damages damages awarded when the conduct of the defendant or of the I
I
surrounding circumstances increase the injury to the plaintiff by subjecting him to
humiliation, distress, or embarrassment, panicularly in such tons as assault, false
imprisonment, and defamation
II
Appearance ackrwwledgement, by the defendant in a civil action, of the writ or sunmwns
I!
Apprentice a person who is under an agreement to serve for a number of years, usually for
low wages, in order to learn the skills of panicular trade
164
,- -'
r
i
t
•
t
GLOSSARY
i
A priori from cause to effect.
r
• Arbitration proceedings before a private tribunal to which the parties agree to submit
II
disputes
Auction a public sale at which goods are sold to the highest bidder
Bailment delivery of goods into the possession of a person who is not their owner
Bankrupt a -person who cannot pay his debts and who is adjudicated a bankrupt
Bar the profession of barristers from which practically all judges are recruited
II
Barrister a lawyer whose main function is to act as an advocate in court
Bill of sale a document by which a person transfers the ownership of goods to another
•
I' Body corporate a company
165
I
GLOSSARY I
i
f
•
!
Case stated a statement of facts prepared by a court or arbitrator for the decision ofa !
higher court on a point of law i
Cause of action the. circumstances giving rise to a right to bring a legal action i
Cestui que trust the beneficiary of a trust
Caveat emptor let the buyer beware; a maxim indicating that any risk is upon the buyer
and not the seller
Codification bringing together the existing case law and statute law on the same subject
under one statute
Collaterai contract an independent agreement, additional but not subordinate to the main
agreement on the same matter
Commercial court a special court in the Queen's Bench division for dealing with
commercial actions
Common l!lw law embodied in case precedent as opposed to statute law or equity
Company a legal entity which is brought about by the registration procedure laid down by
company legislation
Consolidation joining of two separate actions so that they may be tried together
Contract under seal a contract which is signed, sealed, and delivered; it is enforceable
I
without consideration
166
1
i
i
I GLOSSARY
Contra proferentum rule the ·doctrine that the least favourable construction should be
i
adopted against the party who prepared and seeks to rely a the document
Conveyance a written instrument which transfers property, especially land, from one person
to another
Corporation a legal entity, endowed with perpetual succession, a common seal, the ability
to own property, and ·the capacity to sue and be sued
Counterclaim a cross action brought by the defendant against the plaintiff, or by the
respondent against the claimant
Court of Appeal the court which hears appeals from, inter alia, the High Court and county
courts in the UK
Crown Court the branch of the Supreme Court which deals with criminal trials and also
some "civil cases
I Decision ofthe court a decision of the court consists offindings offacts, the legal principle
applicable to the legal problems disclosed by the material facts, and the judgment
l..
J
Deed a written instrument, signed, sealed and delivered
De facto in fact
Defamation liability in tort for untrue statements which attack a person's character or
reputation
De nova anew
167
I
I
GLOSSARY I
1,
i
Detinue an action in tort for recovery of a specific chattel j
!
j
Dictum an authoritative pronouncement; judicial assertion; maxim •
Disclaim to give up a claim or right
Discovery disclosure of all the documents relating to a case, before the trial
I
Domicile the country or state with which a person or company is most closely connected
Equity law based upon discretion and conscience, derived from the old Court of Chancery
EstoppeJ the prevention of a party from asserting a fact or a claim inconsistent with a
position he previously took, either by conduct or words, especially where a representation I
has been relied or acted upon by others
Ex parte by one side only, for example, an application ex parte for an injunction
Fi fa abbreviation offieri facias; execution of a judgment by seizing and selling the debtor's I
- goods
I
Firm. persons who have entered into partnership with one another are called collectively a
firm
168
1I GLOSSARY
f•
i
Force majeure irresistible compulsion; especially such as to cause breach of contract, such
t as war or act of God
i Foreclosure the process whereby a nwrtgagee becomes the owner of the nwrtgaged property
Forfeiture a provision, especially in a contract or lease, enabling one party to strip the
other of his whole interest in certain .events; for example, determ~nation of a building
contract
Fraud at comnwn law, fraud refers to the advantage gained by unfair means, such as by
afalse representation offact made with knowledge of its falsity, or without belief in its truth,
or recklessly, not caring whether it is true or false. In equity, it refers to the violation,
intentional or otherwise, of the rules of fair dealing
Fraudulent misrepresentation a false statement offact made with knowledge of its falsity,
or without belief in its truth, or recklessly, not caring whether it is true or false
Freehold a legal estate held in fee simple absolute in possession. For practical purposes,
it is equivalent to absolute ownership
I General damages and special damages general damages are damages given for a loss
which cannot be precisely quantified in nwney terms, such as pain and suffering or loss or
reputation, and the court is free to assess the anwunt and to award substantial damages.
Special damages· are damages given for losses such as expenses for medical treatment and
I
. I
loss of earnings, which are exactly calculable and must be specially set out in the pleadings
General indorsement a brief description of the plaintiff's claim indorsed on the writ; a full
statement of claim must then be served separately
-j
Hearsay testinwny by a witness as to a matter not within his personal knowledge
I
If High Court the principal court in which civil actions are heard at first instance
It Incorporeal rights and interests which are intangible are said to be incorporeal, such as
debts or shares in a company
~ Indorsement something written on the back of a document, such as the claim indorsed on
I
a writ
169
"
GLOSSARY
Injunction an order of the coun which commands a person to do or refrain from doing
some act
In re in the matter of
Instrument a formal legal document creating or recording some legal right or liability
Intention to create legal relations the readiness of each party to accept the legal
consequences if he does not peiform his obligations under the contract
Interlocutory a matter dealt with before the trial of an action; such as an interlocutory
injunction
I
Interrogatories questions formally put in writing by one party to another, before the trial
of a civil action
Joint where two or more persons share some right or obligation such that their interest is
not severed, each having an interest in the whole, for example, a joint tenancy or account
. Joint obligation an obligation by which two or more undenake to be made liable jointly,
with the consequence that proceedings in respect of the obligation mUst be taken against both
I
or all of them together
Joint and several obligation an obligation by which two or more persons undenake to be
made liable jointly or severally, with the consequence that proceedings in respect of the
whole obligation may be taken against all, or more than one, jointly, or against only one of
them
Laches a doctrine providing the defendant with an equitable defence where there is neglect
and unreasonable delay on the pan of the plaintiff in enforcing an equitable right
170
il
I•
I
I GLOSSARY
f!
i• ,
Lapse of an offer the termination of an offer as a result of the passage of time, death, or
the unfulfillment of a condition
i Latent that which exists but is as yet concealed Of unrevealed
Lease a contract for the use and possesssion of lands, buildings, property, etc. for a
specified time and for fixed payments.
Legal aid a system for providing free or assisted legal advice or representation, for persons
of slender means
Legislation the process of making laws; a law or body of laws thus made
I,i Lien a right to retain possession of some article until a claim by the holder is satisfied
,
~ Limitation statutory periods within which actions must be commenced
!
~ Limitation of actions the law which prescribes the period within which legal proceedings
i
to enforce a right must be taken or the right of action will be barred
i
~ LiIDited company a company limited by shares
l
•
,i
.'i Liquidated damages ascertained pr calculated monetary loss claimed in an action. Also
a sum provided by a contract as payable in the event of breach, which is not deemed to be
f, a penalty
il
Liquidation winding up of a company
I; Locus sigilli the place for the seal
I 171
GLOSSARY
r,
I
Marine insurance a fonn of insurance in which the insurer undertakes to indemnify the
insured against loss of the ship, the cargo, or any sums paid in freight occurring during a
I
sea voyage
Master an official of the High Court who decides many interlocutory matters
Merchantable quality goods of any kind are of merchantable quality if they are as fit for
the purpose or purposes for which goods of that kind are commonly bought as it is
reasonable to expect having regard to any description applied to the price and all other
relevant circumstances
Misrepresentation afalse statement offact, past or present, which one party to the contract
makes in the course of negotiations with a view to inducing the other to enter into the
contract
Mitigation something told to a court in mitigation makes a wrong doing easier to understand
and excuse, usually in the hope that the court will be less severe in their punishment of the
person responsible
Mutual mistake a situation where the parties are at cross-purposes in contract formation
-
Negligence conduct falling short of the duty of care owed to persons generally
Neutral by convention, the neutral is the tenn used to describe a neutral, independent
person app'-ointed to act as a'!lE..diator,__ conciliatt!r, or adjudicator
Nominal damages a token amount awarded for the technical infringement of a right where
no actual loss or hann has been suffered.
Non est factum it is not my deed. This is a common law defence which enables a person
who has executed a written document in ignorance of its nature at the time of execution to
plead that, notwithstanding the execution, 'it is not my deed'
172
1I
-'
t GLOSSARY
I
Ii Novus actus interveniens a new intervening cause which breaks the chain of causation
! Nuisance unlav.ful inteljerence with the use or enjoyment of another person's land
Obiter dictum statement of a judge on a point not directly relevan.t to his ci.ecision and
therefore not strictly of authority
Offer a proposal made by one person (the offeror) to another, (the offeree) coupled with an
intimation that the offeror is ready to peTjorm his promise if the offeree accepts it
OfficiaI reference a judge who tries technical cases in the Queen's Bench division of the
High Court
Official solicitor an officer of the Supreme Court who acts for persons under a disability
Ordinance legislation in hong kong made by the governor by and with the advice and
consent of the Legislative Council
I Part performance an equitable doctrine enabling a plaintiff to' enforce a contract in spite
of a lack of necessary formalities where he has done (lcts in peTjorming his obligations under
it, and where it would be a fraud on the part of the defendant to set up the legal invalidity
, of the contract
-.
Past consideration an act which is wholly executed and finished before a- promise by
another person is made
Penalty a sum provided by'a contract as p(lYable in the event of breach, which sum is not
deemed to be liquidated damages
PenaltY clause in a-contract" cm extravagant and extortionate sum fixed 'in advance as
p(lYable in the event of the breach of contract; it will not be enforced by the court
Petition a document used to begin certain civil actions such as winding up a company
Plea. a defence
Power of attorney authority conferred by deed on one person by another enabling the
former to act for the latter
Private company a company which by its articles of association restricts the right to
transfer its shares; lilT-tits "the number of its members to fifty, not including persons who are
in the employment of the company and persons who, having been formerly in the employment
of the company, were while in that employment, and have continued after the determination
of that employment to be, members of the company; and prohibits any invitation to the public
to subscribe for any shares or debentures of the company
Privity of contract the relationship that exists between parties to a contract; at common
law, only the parties to a contract can sue and be sued under it
Privy council the judicial committee of the privy council is the final court of appeal for
some commonwealth countries
I
Promissory note an unconditional promise in writing made by one person. to another signed
by the maker, engaging to pay, on demand or at a fixed or determinable future time, a sum
certain in maney to, or to the order oj, a specified person or to bearer
Quasi as if it were
Quasi contract not a true contract, but is an obligation created by law for reasons ofjustice
andfaimess
I
174
1
i
ri GLOSSARY
I
i Queen's Counsel a senior barrister, appointed by the Lord Chancellor. Q. c. 's are known
I colloquially as 'silks' because they wear silk gowns
Ratio decidendi the relevant part of a judge 's decision in a case, which is authoritative
Re in the matter of
Real property certain interests and rights in land; as opposed to personal property
Remedy the means provided by the law to obtain redress or compensation for a wrong
I Repudiation an express or implied refusal by one party to peiform his obligation under a
I
contract
Res a thing
I
I
RE:Spondent the defendant in certain types of action, including an arbitration
I
I:
Rylands v F1etcher, rule in a principle of strict liability for dangerous things accumulated
on land that escape and cause damage that was first stated in the case of Rylands v Fletcher.
. - - - ." -- .-
I
ri Sequestration order of the High Court to seize goods and lands of a defendant who is in
;
I, contempt of court
IJ
Set aside cancel
175
.'
\
GLOSSARY •
t.
Settlement a disposition of property, made by deed or will, under which trusts are created i
1 .
by the settlor designating the beneficiaries and the terms on which they are to take the
property
Several where two or more persons share an obligation so that it may be enforced in full
against anyone of them, independently
Sign write on a document, etc., indicating that one has authorised it. In the case of a
person unable to write, the affixing or making of a seal, mark, thumbprint, or chop is
acceptable I
I .
Solicitor a lawyer whose main functions include the giving of legal advice, the drafting of
legal documents, the preparation of cases for litigation, and the representation of clients in
court I
Solus agreement an agreement by which a retailer binds himself to buy a product from one
source only - for example, a garage proprietor agreeing to kuy all his petrol from one oil
comparry
Statement of clalin the plaintiff's initial pleading in an ordinary civil action in the high le
court followed by the defence and reply
-. Statntory instrument a form of delegated legislation, which has fuil force of laW
Strict liability in tort liability for a wrong that is imposed without the necessity of proving
intention or negligence on the part of the defendant
Subject to contract an agreement which is subject to contract has no binding force: the
parties do not intend to be bound until aformal contract is prepared and signed by them
176
1
I
1 GLOSSARY
I
i
! Subpoena an order requiring a person to appear in court and give evidence or produce
,
!
documents
I Subrogation the right to bring an action in the name of another person
Sufficient consideration if the promisor gets what he has asked for in return for his
promise, that is sufficient consideration. A promise to do any act, or to forbear from doing
any act, which the promisor might lav.fully do, is generally a sufficient consideration
Summons an order to appear before a judge or magis:rate. Some civil actions are begun
by an originating summons
Supreme Court the High Court, the Court of Appeal and the Crown Court are collectively
known as the Supreme Court of Judicature
Third party a person not originally a party to an action, but who may be brought in by a
defendant
Tortfeasor a person liable on a civil wrong other than a contractual or trust matter
Uberrinia fides the utmost good faith, required in certain transactions, such as insurance
contracts
Ultra vires beyond their powers; espeCially of a limited ·compani or statutory body. The
opposite of intra vires
Il
If
177
i!
r
j[
GLOSSARY
I
If
ji
Ultra vires doctrine in company law a company incorporated under the Companies
Ordinance has power to carry out the objects set out in the memorandum, as well as
everything which is reasonably necessary to enable it to carry out those objects. If an act
r
!
I
is peiformed or a transaction carried out which, though legal in itself, is not authorised by
the objects clause in the memorandum, it is ultra vires and therefore void, 'so that it cannot
be ratified even if all the members wish to ratify
I
Undue influence equity gives relief to a contractual party on the ground of undue influence
II
I
where an agreement has been obtained as a result of improper pressure exercised by the
other
Unilateral mistake a mistake made by one party only, the other not being mistaken at all
Unliquidated damages damages which cann6t be calculated as a monetary loss, arid which
are assessed by the judge; such as damoges for personal injury
Vacation the periods between legal terms, when the superior courts do not sit. There are
four vacations in the year
Vicarious liability the liability of an employer for the careless acts or omissipris of an
employee which injure other persons; even though the employer himself has not been careless
Volenti non fit injuria . a defence in the law of tort that the plaintiff fully and freely
consented to the injury or to the risk of being injured
Writ a document used to begin an ordinary civil action; it must bear a special or a general
endorsement of the plaintiffs claim
I
I
178
11 -'
lt
I
BIBLIOGRAPHY
..•
-' l-
II
•I
i
~(
I,
BIBLIOGRAPHY
Aqua Group, The (1992) Pre-Contract Practice for the Building Team 8th ed Oxford: BSP
Aqua Group, The (1990) Contract Administration for the Building Team 7th ed Oxford:
BSP
Aqua Group, The (1990) Tenders and Contracts for Building 2nd ed Oxford: BSP
- Atiyah, P.S. (1989) An Introduction to the Law of Contract 4th ed Clarendon law series
Oxford: Clarendon Press; New York: Oxford University Press
Barker, D.L.A. & Padfield, C.F. (1992) Law: made simple 8th ed Oxford: Butterworth-
Heinemann
Burns, A. ed (1989) Construction Disputes Liability and the Expert Witness London:
Butterworths
Chui, Carole Pedley (1988) The Law of Contract in Hong Kong One country two systems
law series Hong Kong: China and Hong Kong Law Studies Ltd
Comes, David L.(1989) _Design Liability in the Construction Industry 3rd ed Oxford: BSP
Professional Books
180
11
f BIDLIOGRAPHY
I
i
De Bono, E. (1986) Conflicts: a better way to resolve them Harmondsworth: Penguin
f
i Emden, Alfred E. (1990) Emden's Construction Law 8th ed rev London: Butterworths
Graw, Stephen (1990) An Introduction to the Law of Contract North Ryde, N.S.W.: Law
Book Co
Hong Kong laws, etc The District Court Law Reports Hong Kong: Government Printer
Hong Kong laws, etc The Hong Kong Law Reports Hong Kong: Government Printer
Hong Kong Law Digest Hong Kong: Hong Kong Legal Publications, 1939
Howarth, D. (1984) Common,Law - Tort: from accident to liability London: Sweet &
Maxwell
Hughes, G.A. (1992) Building and Civil Engineering Claims in Perspective 3rd ed
London: Longman Scientific & Technical
Major, W.T. (1988) Law of Contract 7th ed M&E Handbook series London: Pitman
Manson, Keith (1981) Building Law for Students 4th ed rev London: Cassell
Martin, Robyn (1987) The law of tort in Hong Kong One country two systems law series
Hong Kong: China an,d Hong Kong Law Studies
May, Anthony, Sir (1991) Keating on Building Contracts 5th ed London: Sweet & Maxwell
, Rogers, W. V.H. (1989) Winfield and lolowicz on Tort 13th ed London: Sweet & Maxwell
Shum, Clement (1992) General Principles of Hong Kong Law Hong Kong: Longman
Smith, Jim (1989) The Law of Contract: fundamental principles of law London: Sweet &
Maxwell
Stanton, K.M. (1986) Breach of Statutory Duty in Tort Modern legal studies London:
Sweet & Maxwell
181
-'
BIBLIOGRAPHY
Treitel, G.H. (1989) An Outline of the L([}V of Contract 4th ed London: Butterworths
Turner, D.F. (1989) Building Contract Disputes: their avoidance and resolution London:
Longrnan
Turner, D.F. (1984) Building Contracts: a practical guide 4th ed London: George
Goodwin
Uff, John (1991) Construction L([}V: l([}V and practice relating to the construction industry
5th ed London: Sweet & Maxwell
White, John (1988) The English and Hong Kong Legal Systems Hong Kong: Co=ercial
Press
Willis, Christopher J. and Ashworth A. (1987) Practice and Procedure for the Quantity
Surveyor London: Collins
-I
I
1
,
182
---,-
I
I
I'I
I
INDEX
.'
INDEX
A c
Acceptance . . . . . . . . . . . . . . . 2-6, 33, 39 Case law . . . . . , . . . . . . . . , . . . . . . ,. 1
Adjudication ........... , ........ 137, 148 Cause of action . . . . . . . . . , ' , . . . , . . . 34
Adler v. Dickson . . . . . . . . . . . . . . . . 182' Causes of delay . . . . . ' . . . . . , . . . . . 117
Advertisements . . . , . . . . . . . . . ' , , . , . . 4 Certificate of making good defects ... 110, 147
Agreement . . . . . , . . . , . . . ' . . . . , , . . . 1 Certificate of practical completion , . . . ., 109
Alternative dispute resolution (ADR) , 131, 137 Competitive tendering . . . , ' , . . , . . . 65-67
Amendments to a standard form . . " . . , ' 40 Certificates aod payments , . . . . . . ,... 105
Analogy .. , .. , , , ... ' , , , , .. , . .. 101 Claims for direct loss aod/or expense .. ,. 119
Antiquities . . . . . , . . . . . 97, 117, 119, 120 Clauses which empower instructions . , . . . . 97
Appeal . . . . . . . ' ... , . . . . , . . .. 1, 135 Clerk of works. , .. , .. , , , , . , , ., 53, 54
Appellant . . . . . . , . . . . . . . . ., .: . , . . 1 Clerk of works directions ... " , . . . . . " 96
Appendix . . . . . , '. .' .. , , ... , . . . . 39-41 Client . . . . . . . . . . . . . . . . . . . . . . . . . I
Arbitration ... , . . . . . . . . ,., .... 131-137 Collateral '; 7'.-,-,-.-.'7'.""', , . . . . , . , . . . 87
Arbitration Ordinance .... , , , , , . . 132, 135 Collins v, Godefoy . . . . , ' , . . . , . , . . , . 7
Arbitration procedure , , . , , .. , , , ... , 134 Completion . . . . , . ' , , . . . ' , , . . . . , . 71
Arbitrator ... , .. , . . . . . , . . . .. 131-137 Companies Ordinance . . , . . '. . . , . . . . . . . 9
Arbitrator's awards ,., . . . . . . . . . . . , 135 Comparison: arbitration aod litigation , . .. 137
Architect .,." .... , ... " . . . . , 51-54 Comparison of risk , , , , . . . . . . . , . . , . 64
Architect's instructions, . . . . . , ... , 95-103 Condition , , ' , , .. , .. , , . ' .. , ... ' , 16
Articles of agreement ... , . , . . . . , . . 3941 Conditional bond " . , " , ......... ,. 88
Assessor . . . . . , . . . . . . . , . . . . . . .. 132 Consideration . . . . . . . . . . . . . , . , .. 2, 6-8
Assigrunent . . . . . , . . . ' , . . . . , . . . , . 48 Consultant engineer , . . . . , , .. , , ., 52, 54
Auctions. , . . . . ' ... , . , , , , , .. , , ... 4 Contingency ., . . . . . " , . , . . 58, 64, 148
Automatic determination .. , ... , , .. " 127 Contra charge ... " . , . . . . . . , . . . . 122
Average wage index .. , .. ,', .. " . . 113 Contract sum ... , . . . . .. 39, 111, 112, 149
Awards . . . . . . . . . . . . . . . . . . . . . . 135 Contract bills . , , . . . . . . , . . . . . . . , 40-43
Contract drawings . , . , ... ' .. , ... , 40-42
Contractor . . . . . . . . . . . . . . . . . . . . . . 1
B Contractor's claims . . . . , ... , . ,. 113, 148
Contractors' All Risks policy ... " 80-82, 85
Bankruptcy of the employer .. , . . . . . 38, 129 Contracts contrary to a stalnte ' .. , . . . . , 13
Bankruptcy of the main contractor ... , " 127 Contracts for ao illegal purpose . . . , . ' , ,. 13
Banks , ... , ... " , ... , ... ,., ... 90 Contracts of employment ... , .. , . , . , . , 53
Base month , . , , , . , . , ' , . . . , . , . ., 113 Contracts under seal .. ,... 2, 6, 8, 34, 110
Bias ......... :" .. , .. , . . . . . . , 133 Contracts which are against public policy , ,. j j
Bid tender bond . . . . . . . . . . . . . . . . . . 88 Contracts which must be evidenced in writing 12
Bilateral discharge . , , . . . . .... ', . . , , , . 25 Contracts which must be in writing , . . . . . 11
Bills of quantities .... : : . , . , . . . . 38, 40 Contracts which must be under seal , , . . .. 12
Bond amount , . . . . . , . . . . . . . , , . . . . 91 Contractna1 arraogements . . . . . . . . . . . . 57
Breach .. , . . . . . . . , . . . . . . . ' ... , . 27 Contractna1 capacity ... " . . . . . . . . . 2, 8
Breach of condition .. , .. , , ... '. ',' .. , . 27 Contractna1 parties to the main contract .. 45-51
Breach of contract , . , , .. , . . . . , .. , , . 29 Contractna1 relationships . . . . . . . , . . . . . 45
Breach of warranty ., .. ' .. " . ' . . . . . 27 Costs .. , , . . . . . . ' . . . . . . , 123, 135, 146
Builder. ' .. , . . . . . . . . . , ... ' , . , , ' . I Cost reimbursement contracts . . . . , . . . . . 61
Building contract insurances . . , , . , . , . , . 79 Counter claim ... ,." .. " ' , . , 122, 123
Counter guaraotee . . . . . , . , , . , . . . . . . 88
184
.-:--r
I i -'
!
i
I
,I INDEX
~
f Conciliation . . . . . . . . . . . . . . . . . . .. 146
I Cover . . . . . . . . . . . . . . . . . . . . . . . . 77
Cross claims . . . . . . . . . . . . . . . . . " 122
Executive tribunal . . . . . . . . . . . . . . .. ISO
Exceptions . . . . . . . . . . . . . . . . . . . . . 77
Excess . . . . . . . . . . . . . . . . . . . . . . . . 78
Customary implied terms . . . . . . . . . . . . 17 Exclusion and limitation of liability . . .. 18,19
Cutter v. Powell . . . . . . . . . . . . . . . . . . 23 Expense . . . . . . . . . . . . . . . . . . . . .. 119
Expert appraisal .. . . . . . . . . . . . . . .. 151
Express terms . . . . . . . . . . . . . . . . IS, 16
D Extension of time . . . . . . . . . . . .. 116-119
Damages . . . . . . . . . . . . . . . . . . . . . . 29
Date for completion . . . . . . . . . . . . . . . . 71 F
Date for possession'. . . . . . . . . . . . . . . . 71
Davis Contractors v. Fareham UDC . . . . . . 26 Failure .to honour certificates of payment .. 128
Dayworks . . . . . . . . . . . . . . . . . . . . . . 99 Fair valuation . . . . . . . . . . . . . . . . . . 102
Deeds . . . . . . . . . . . . . . . . . . . . . . . . . 8 FlDICcontract . . . . . . . . . . . . . 36,37,151
De Bernardy v. Harding . . . . . . . . . . . . . 24 Final accouut . . . . . . . . . . . . . . .. Ill, 148
DefectS liability period . . . . . . . 109-111,147 Final certificate . . . . . . . . . . . . . . 111, 149
Defendant . . . . . . . . . . . . . . . . . . . . . . . I Final measurement and valuation . . . . . .. I11
Definition of a contract . . . . . . . . . . . . . . . I Fire and Special Perils policy . . . .. 80-82, 86
Delay . . . . . . . . . . . . . . . . . . . . 115-120 First demand bond . . . . . . . . . . . . . . 88-94
Delay of artistS or tradesmen . . . . . . . .. 117 First party insurance . . . . . . . . . . . . . . . 78
Delay of nominated sub-contractors or Fluctuations . . . . . . . . . . . . . . 113, 114, 151
nominated suppliers . . . . . . . . . . . ., 117 Force majeure . . . . . . . . . . . . 116-118, 129
Delays caused by neither party to the contract 116 Foreman-in-charge . . . . . . . . . . . . . 46, 54
Delays caused by the employer . . . . . . .. 115 Form of a contract . . . . . . . . . . . . . . 2, 11
Delays caused by the main contractor . . .. 115 Frustration . . . . . . . . . . . . . . . . . . . . . 26
·Derivation. . . . . . . . . . . . . . . . . . . .. 100 Fundamental breach . . . . . . . . . . . . . . . . 19
Design bnild contract . . . . . . . . . . . . . . . 64
I Determination of employment . . . . .. 125-130
Determination by employer . . . . . . . 125-128
II Determination by main contractor ... 128-130
G
i Determination procedure ... -. . . . . . . .. 126
Genuiness of consent . . . . . . . . . . . . . . 2, 9
Direct loss andfor expense ... _ . . . . . .. 119
Gleeson v. London Borough of Hillingdon. . 42
Discrepancies . . . . . . . . . . . . . . -. . . . . . 43
Government of Hong Kong 37,76,93,113,138
Display of goods . . . . . . . . . . . . . . . . . . . 4
Disqualification of an arbitrator. . . . . . .. 133
Disruption. . . . . . . . . . . . . . . . .. 119-121.
Domestic sub-contractors . . . . . . . . . . . . 48 H
Domestic suppliers . . . . . . . . . . . . -.. . . 48
Donoghue v. Stevenson . . . . . . . . . . . . . 34 Harbutt's Plasticine v. Wyne Tank & Pump . 19
Duress . . . . . . . . . . . . . . . . . . . . . . . . 11 High court . . . . . . . . . . . . . . . . . 131, 13 6
I
i- E
HK Standard Form . . . . . . . : . . . . . . xi, 36
HKIA Standard Form . . . . . . . . . . . . . xi, 36
Hoenig v. Isaacs . . . . . . . . . . . . . . . . . . 25
Hsin Chong Construction Co. Ltd. v. Yaton Realty
Co. Ltd . . . . . . . . . . . . . . . . . 107, 108
Early completion . . . . . . . . . . . . . . . . . 72
Edward Owen Engineering Ltd. v. Barclays Bank
International . . . . . . . : . . . . . . . . . . . 92
Employer . . . . . . . . . . . . . . . . . . . . . . . I I
Employer's obligations . . . . . . . . . . . . . . 47
Employers' liability insurance . . . . . . . . . . 84 Implied terms . . . . . . . . . . . . . . . . . . . 17
Entores Ltd v. Miles Far East-Corporation ... 6 Inclement weather. . . . . . . . . . . .. 116-118
Errors . . . . . . . . . . . . . . . . . . . . . . . . 43 Indemnity agreement . . . . . . . . . . . . 87, 88
Essential requirements of a contract . . . . . . . 2 Indemnity and insurance clauses . . . . . . . . 82
Evaluation of -direct loss and/or expense .-: 120 Index of wage rate . . . . . . . . . . . . . . . 113
Injunction . . . . . . . . . . . . . . . . . . . . . . 31
185
-'
----.,
r,
I"
I'
INDEX F
1
,
!
p
L
Package deal contract . . . . . . . . . . . . . . . 64
Lapse of time . . . , . . . . . . . . . . . . . . . . . 3
Parkinson v. Commissioners of Works ... . 33
Lateness of drawings . . . . . . . . . . . . " 117
Part performance . . . . . . . . . . . . . . . . . 24
Legality of object " . . . . . . . . . . . " 2, 13
Payment certificates . . . . . . . . . . . . . .. 105
Liability insnrance . . . . . . . . . . . . 79,82,84
Penalty . . . . . . . . . . . . . . . . . . . . . . . . 30
Limit of indemnity . . . . . . . . . . . . . . . . 78
Percentage of certified value retained .. " 107
Limit of retention fund . . . . . . . . . . 107,145
Performance . . . . . . 23-25, 30, 87-89, 92, 93
Limitation of action . . . . . . . . . . . . . . . . 33
Performance bond . . . . . . . . . . . . . , 88, 94
Limitation Ordinance . . . . . . . . . , 8, 34, 11 0
Period for honouring certificates . . . . 106, 128
Liquidated and ascertained damages . . . . . . 75
Period of delay. . . . . . . . . . . . . . . . .. 115
Liquidated damages . . . . . . . . . , . .. 29, 30
Period of final measnrement and valuation. 111
Loss . . . . . . . . . . . . . . . . . . . . . . . , 119
Period ofinsnrance .... . . . . . . . . . . . . 78
Loss andlor expense . . . . . . . . . . . . 119-122
PersollaJ injury or death . . . . . . '.' . . . 82-84
Lnrnp snrn contracts . . . . . . . . . . . . 57, 58
Phased completion (see sectional completion)
Philips Hong Kong Ltd v. The Attorney General of
Hong Kong . . . . . . . . . . . . . . . . . . . -76
M Plaintiff . . . . . . . . . . . . . . . . . . . . . . . . 1
Possession . . . . . . . . . . . . . . . . . . . .71, 75
Main contractor .......... 39,45, 115, 128 Possession and completion .. . . . . . . . . 71-76
Main contractor's obligations . . . . . . . . . . 45 Practical completion . . . . . . . . . , 72, 73, 106
Maintenance bond . . . . . . . . . . . . . . . . . 88 Practical Completion of the works 71, 108, 133
Management contracting . . . . . . . . . . . . ... 64 Precedence . . . . . . . . . . . . . . . . . . . . . 42
Material damage insurance . . . . . . . . . . . 80 Precedent . . . . . . . . . . . . . . . . . 1, 54, 137
Measnrement and valuation of variations . .. 99 Preminrn . . . . . . . . . . . . . . . . . . . . . . 78
Measurement contracts . . . . . . . . . .. 59, 60 Prevention of performance . . . '.' . . . . . . . 24
Mediation .. -: . . . . . . . . . . . . . . . 131,143 Prime cost sums . . . . . . . . .' .. 103, 111, 119
Memorandnrn of association . . . . . . . . . . . . 9 Privity of contract . . . . . . . . . . . . . . . . 7, 8
Misrepresentation . . . . . . . . . . . . . . . . 9-11 Pro-rata rates . . . . . . . . ; . . . . . . . . .. 100
Mistake . . . . . . . . . . . . . . . . . . . . . 9, 10 Procednre for claiming an extension of time 118
Monthly statistical bulletins . . . . . . . . . . . 41 Procnrement . . . . . . . . . . . . . . . . . . . . 57
Moore & Co. v. Landauer & Co. . . . . . . . 23 Professional negligence. . . . . . . . . .. 54, 55
Murphy v. Brentwood District Council. . . . . 34
186
i
i~
f i
I
!
,- INDEX
!"
I Proof of contract . . . . . . . . . . . . . . . . " 12 Sub-letting . . . . . . . . . . . . . . . . . . . . . 48
f
; Provisional quantities . . . . . . . . . . . . . , 111 Subsidiary agreement . . . . . . . . . . . . . . . 39
!, Provisional sums . . . . . . . . . . . 103,111,119
, , Public liability insurance . . . . . . . . . . . . . 84
Substantial performance . . . . . . . . . . . . . 25
I Sumpter v. Hedges . . . . . . . . . . . . . . . . 24 '
Public sector standard fonns . . . . . . . . . . 37
iI
Surety bond. . . . . . . . . . . . . . . . . . . 87-94
Sutcliffe v. Thackrab . . . . . . . . . . . . . . . 54
Q
T
-I Quantum meruit . . . . . . . . . . . . . . . . . . 31
Quantity Surveyor . . . . . . . . . . . . . . . . . 53 Tender . . . . . . . . . . . . . . . . . . . . . . . . . 4
Tender documents . . . . . . . 53,61,68,72,75
Tendering, competitive. . . . . . . . . . . . 65-67
R Tendering procedures . . . . . . . . . " .. : . 65
Tenns implied by the courts . . . . . . . . . ., 17
Re-nomination ... ',' . . . . . . . . . . . . . . 51 Tenns of a contract . . . : . . . . . . . . . . . . 15
Reasons for the use of a standard form .. " 35 Third party insurance . . . . . . . . . . .. 78, 84
Reconciliation of analysis . . . . . . . . . . . 101 Tbompson v. L.M.S. Railway . . . . . . . . . 18
Reference ... . . . . . . . . . . . . . . . . .. 131 Time at which arbitration may be opened.. 133
Rejection . . . . . . . . . . . . . . . . . . . . . . . 3 Time of performance . . . . . . . . . . . . . . . 25
Representations . . . . . . . . . . . . . . . . . . 20 Ton . . . . . . . . . . . . . . . . . . . . . . . . . 34
Rescission . . . . . . . . . . . . . . . . . . . . . . 31 Turnkey contract . . . . . . . . . . . . . . . . ., 64
Respondent . . . . . . . . . . . . . . . . .. 1, 135 Types of bond .. . . . . . . . . . . . . . . . . . 88
Restitution . . . . . . . . . . . . . . . . . . . . . 3 I Tyer v. District Auditor for Momnothshire . 55
Retention . . . . . . . . . 107-110, 144, 145, 147
Revocation . . . . . . . . . . . .... . . . . . . . . . 3
Rickards Ltd. v. Oppenheim . . . . . . . . . . 25 u
Right of appeal. . . . . . . . . . . . . . . . .. 136
RICS Stanfud Form . . . . . . . . . . . . . xi, 36 Unconditional bond . . . . . . . . . . . . . . . . 88
Undue influence .. .. .. .. .. .. .. . . . . 11
Unilateral discharge . . . . . . . . . . . . . . . . 25
s Unliquidated damages .............. 30
187