No. Description of Work Unit Quantity Rate Amount
Page 2 of 12
No. Description of Work Unit Quantity Rate Amount
8 Providing and laying cement concrete M20
grade concrete using 20mm and down size
aggregate for RCC works laid in 150mm thick
layers and well compacted including machine
mixing, laying, vibrating, curing and necessary
steel or plywood or plank centering and form
work, scaffolding, etc., including smooth finish in
cement mortar 1:3 etc., complete for Roof
Beam etc., (excluding the cost of steel and
fabrication charges).
Page 3 of 12
No. Description of Work Unit Quantity Rate Amount
11 Providing and laying M20 grade cement
concrete for chejja/cill slab projection and
similar works of 75mm average thickness, using
20mm and down size granite aggregate
including machine mixing, laying, tamping and
finishing with cement mortar 1:3 with front
beading and drip moulding including centering,
form work, scaffolding, curing etc., complete,
including providing 40mm dia PVC spouts,
wherever shown in the drawings and as directed
by engineer-in-charge.
Page 4 of 12
No. Description of Work Unit Quantity Rate Amount
15 Providing 12mm thick cement plaster to
ceiling, beams in cement mortar 1:3, average
thickness 12mm including providing and
removing scaffolding, applying lime rendering,
lead, lift, curing, etc., complete as per
specification.
Ground Floor Sft 3010.00 45.00 135450.00
Page 5 of 12
No. Description of Work Unit Quantity Rate Amount
19 Providing oil bound distemper paint to
internal walls of Asian make or any other
approved equivalent make, colour and shade
two coats over one coat of approved primer and
two coats of putty. The original surface should
be scrapped and rubbed with sandpaper of zero
size. All small holes, nails, open joints and
minor defects of every kind shall be stopped by
putty. Before applying subsequent coats of
paint, the surfaces shall be dried and lightly
rubbed down smooth with sandpaper dusted.
For both the coats of painting rollers shall be
used. Putty made from whitening with zinc oxide
and glue and cement primer shall be used.
Linseed oil mixed putty shall not be used before
priming coat is pur on including all lead, lift
charges etc., complete for all heights including
providing and removing scaffolding etc.,
complete.
Page 6 of 12
No. Description of Work Unit Quantity Rate Amount
22 Providing and fixing Teak Wood doors
consisting of sal wood frame of size 5" x 2.5" or
as specified as per approved drawing and
design including cost of materials, labour etc.,
complete. The rate shall include fixing of frame
to the masonry with 40mm x 6mm size flat iron
hold fasts 450mm long embedded in 150mm
thick cement concrete of mix 1:3:6 or as
specified. The frame shall be fixed with Flush
shutters with both side commercial plywood
finish all as per as per approved drawings,
designs and specifications. The shutters shall be
made out of 30mm thick solid core and resin
bound boiling water proof flush shutters exterior
grade with teak wood lipping on all four side
including cutting of shutters to the required size,
etc., complete. The flush shutters shall confirm
to IS: 2202. The rate should include providing
and fixing necessary hardware fittings. The
basic rate of sal wood, both side commercial
plywood flush shutter shall be as specified in the
tender. No extra shall be given towards
wastages.
Page 7 of 12
No. Description of Work Unit Quantity Rate Amount
24 Providing and fixing Sal wood doors consisting
of sal wood frame of size 5" x 2.5" or as
specified as per approved drawing and design
including cost of materials, labour etc.,
complete. The rate shall include fixing of frame
to the masonry with 40mm x 6mm size flat iron
hold fasts 450mm long embedded in 150mm
thick cement concrete of mix 1:3:6 or as
specified. The frame shall be fixed with Flush
shutters with one side Teak Veener finish and
other side commercial plywood all as per as per
approved drawings, designs and specifications.
The shutters shall be made out of 30mm thick
solid core and resin bound boiling water proof
flush shutters exterior grade with teak wood
lipping on all four side including cutting of
shutters to the required size, etc., complete. The
flush shutters shall confirm to IS: 2202. The rate
should include providing and fixing necessary
hardware fittings. The basic rate of sal wood,
one side veener finished and other side
commercial plywood flush shutter shall be as
specified in the tender. No extra shall be given
towards wastages.
Page 8 of 12
No. Description of Work Unit Quantity Rate Amount
26 Providing and fixing Stainless Steel Hand
Railing as per the design and drawings and
specifications comprising of 32mm dia 10 guage
stainless steel hollow tube vertically fixed to
every fourth step welded to 50mm dia 10 guage
stainless steel pipe on top for handrail and
20mm dia stainless steel pipe vertically in
between welded to 2 Nos of 20 pipe vertically all
as per the drawings, the vertical balusters are
fixed in position with molten lead poured into
40mm dia GI Sleeve with 80 x 80 x 3mm GI
Plate and embedded in RCC including
necessary steel cover and completed as shown
in the drawings or any other method of fixing as
approved by the Engineer in charge like epoxy
grout fixing etc., complete. All the stainless steel
members shall be of grade 304.
Page 9 of 12
No. Description of Work Unit Quantity Rate Amount
28 Providing and fixing vitrified tiles skirting of
approved make and color 100mm high set in
cement mortar 1:3 including pointing with white
cement mortar mixed with color oxide / colour
pigment to match the color of the tiles or with
jointing powder including acid wash, curing etc.,
including chasing the walls wherever necessary.
The pattern of skirting shall be fixed with the
plastering with 4mm wide neatly finished groove
etc., as per drawing and specification complete,
including oxalic acid wash etc., complete. The
skirting shall be covered with plaster of paris
covering. The basic rate of tiles shall be as
specified in the tender. No extra claim towards
wastages shall be allowed.
Page 10 of 12
No. Description of Work Unit Quantity Rate Amount
31 Providing and laying ceramic glazed tiles
dadooing of size 200mm x 300mm or as
specified, of approved make, colour and size for
walls set in cement mortar 1:3 and pointed with
cement mortar 1:3 mixed with colour oxide to
match the colour of the tiles or with jointing
powder and finished nicely all as per the
directions including cost of material, lead, lift,
labour, curing, acid wash, etc., complete as per
specification and as directed by engineer-in-
charge. The tiles shall be laid in the pattern
given in the drawings. The basic rate of tiles
shall be as specified in the tender. No extra
shall be given towards the wastages.
Page 11 of 12
No. Description of Work Unit Quantity Rate Amount
33 Providing and constructing under ground
sump tank including necessary excavation, C.C
(1:4:8) bed 100mm thick RCC base slab 125mm
thick 150 mm thick RCC walls all round, 150mm
thick RCC cover slab with 600x600mm M.S
inspection cover including providing water
proofing plastering inside, curing etc., complete
with all leads and lifts. Ltrs 10000.00 25.00 250000.00
34 Providing and fixing 3 layer Sintex Tank Ltrs 5000.00 25.00 125000.00
TOTAL 6602482.00