Paschimanchal Campus: Tribhuwan University
Paschimanchal Campus: Tribhuwan University
INSTITUTE OF ENGINEERING
PASCHIMANCHAL CAMPUS
LAMACHAUR, POKHARA-16
GROUP -A
1.
Survey Camp 2078 | Group A
ACKNOWLEDGEMENT
This report is the outcome result of survey camp of Paschimanchal Campus,
IOE (lamachaur, Pokhara) carried by Group A, which is held from the date of 2021-
08-10 to 2021-08-19.
The purpose of this fieldwork was to make each student independent to carry
out the work in real problems in the field. We think the purpose is suitable for
further work and which make us produce the report of the fieldwork in time. We are
sincerely indebted to IOE WRC for providing the opportunity to consolidate our
theoretical and practical knowledge in engineering surveying.
i
Survey Camp 2078 | Group A
ABSTRACT
This report is prepared for the fulfillment of the Survey Camp 2078. included in IOE
syllabus conducted by the Department of Civil Engineering, Paschimanchal Campus,
Pokhara. The survey camp was held from the date 10 th mangsir 2078 to 19th Mangsir 2078.
In this report our team has prepared topographical map of the given area of campus, plan,
cross-section, longitudinal section (L-Section) of road near Kali khola, cross- longitudinal
section (L-Section) of Kali khola river (bridge site), cross-section of Kali khola river, counter
plan of river fulfilling all technical requirements. In this regard we have carried out
necessary field work in our group from where we got opportunity to the decision on
planning and execution of field works for the preparation of topographic map, detail road
and bridge site survey Every effort has been taken to ensure the accuracy in the report. We
would be grateful for bringing out errors if any and we are open to any sorts of feedback
and suggestions.
ii
Survey Camp 2078 | Group A
WORKING SCHEDULE
Location : Paschimanchal Campus Premises and Kalikhola
Class : 6 PM to 6:45 AM
3 12th Mangsir Two peg tests, fly leveling and RL transfer to the stations
4 13th Mangsir Traverse calculation, making grid and computation
5 14th Mangsir Selection of an alignment for the road
6 15th Mangsir Level transfer on IP, BC, EC of the road and detail survey
iii
Survey Camp 2078 | Group A
FIGURE INDEX
iv
Survey Camp 2078 | Group A
LIST OF TABLES
S.N Table no. Name of Table Page no.
1. 1 Linear Measurement sheet (Major Traverse)
2. 2 Linear and Angular Measurement sheet (Minor Traverse)
3. 3 Major Traverse computation sheet
4. 4 Minor Traverse computation sheet
5. 5 Two peg Test
6. 6 Ordinary leveling sheet
7. 7 Fly leveling
8. 8 Total station Detailing Sheet
9. 9 Triangulation for Span of Bridge
10. 10 Reciprocal Leveling
11. 11 Tachometric Detailing Sheet
12. 12 Road Alignment Sheet
13. 13 Cross Sectioning of Road
14. 14 Fly Leveling of Road Alignment
15. 15 Earthwork Calculation
v
Survey Camp 2078 | Group A
Contents
ACKNOWLEDGEMENT................................................................................................................i
ABSTRACT.................................................................................................................................ii
WORKING SCHEDULE...............................................................................................................iii
FIGURE INDEX..........................................................................................................................iv
LIST OF TABLES..........................................................................................................................v
Contents..................................................................................................................................vii
1. INTRODUCTION.................................................................................................................1
1.1. Background...............................................................................................................1
1.2 Objective.........................................................................................................................1
1.3 Project Area....................................................................................................................2
1.4 Location and Accessibility...............................................................................................3
1.5 Topography and Geology................................................................................................4
1.6 Rainfall, Climate and Vegetation.....................................................................................4
2.TOPOGRAPHICAL SURVEY......................................................................................................5
2.1 Objectives.......................................................................................................................5
2.2 Brief Description of the Area..........................................................................................5
2.3 Norms (Technical Specifications)....................................................................................6
2.4 Equipment and Accessories............................................................................................6
2.5 Methodology..................................................................................................................7
2.5.1Reconnaissance:.....................................................................................................16
2.5.2 Traversing..............................................................................................................17
2.5.3 Detailing.................................................................................................................17
2.5.4 Total Station...........................................................................................................18
2.6 Resection:.....................................................................................................................20
COMMENTS AND CONCLUSION..........................................................................................20
3.ROAD ALIGNMENT SURVEY.................................................................................................21
3.1 BRIEF DESCRIPTION OF AREA........................................................................................21
3.2 HYDROLOGY AND GEOLOGY.........................................................................................21
3.3 SOIL...............................................................................................................................21
3.4 NORMS (TECHNICAL SPECIFICATIONS)..........................................................................22
3.5 EQUIPMENTS AND ACCESSORIES..................................................................................22
3.6 METHODOLOGY............................................................................................................22
vi
Survey Camp 2078 | Group A
vii
Survey Camp 2078 | Group A
1. INTRODUCTION
1.1. Background
This is a detail report of the works, which was performed by group no.
A,having seven members, during the camp period. It briefly explains the working
procedures and techniques used by this group during that camp period. In addition,
it also contains observations, calculations, methods of adjustment of error, main
problem faced during work and their solution, results of all calculations and their
assessments with some comments is presented in a concise form. Each member has
had equal contribution in performing the given tasks and preparing this detailed
report.
1.2 Objective
● To conduct the topographic survey, road alignment survey and bridge site
survey.
● To familiarize in handling different survey instruments.
1
Survey Camp 2078 | Group A
2
Survey Camp 2078 | Group A
Country: Nepal
Zone: Gandaki
District: Kaski
Municipality: Pokhara
Ward No. : 16
3
Survey Camp 2078 | Group A
Kali Khola lies in the north-eastern part of Pokhara. It is a tributary of the Seti
Gandaki River in Nepal. It runs through Armala Vdc, Valam Vdc and Batulechaur. The
shortest route to Kali Khola from WRC takes about 30 minutes by foot.
4
Survey Camp 2078 | Group A
2.TOPOGRAPHICAL SURVEY
Topographical surveying is the process of determining the positions of
existing features of the locality by means of conventional signs on a topographical
map. They are carried out to depict the topography of the mountainous terrain,
rivers, water bodies, wooded areas and other cultural details as roads, railways,
townships, etc. Topographic surveys are three-dimensional. They provide the
techniques of plane surveying and other special techniques to establish both
horizontal and vertical control
2.1 Objectives
1. To build up a framework of traverse legs and traverse stations with the
visibility of all the features on the ground at least from each station so that it
can be located from the instrument.
2. To provide control points for chain surveying, plane tabling in flat grounds.
3. To fix the alignment of roads, canals, rivers, boundaries etc. when better
accuracy is required.
4. To ascertain the co-ordinates of boundary pillars in numerical terms that can
be preserved for future reference such as forest boundary pillars,
international boundary pillars etc.
5. To prepare a topographic map of the surveyed area for future use during
different engineering project.
6. To make contours of a ground taking suitable intervals to provide an exact
approximation of the nature of terrain and feasibility of a project in that area.
7. To mark the positions of various important details that can induce effects on
the forthcoming project.
Detailing was done from nine stations out of which four were major traverse
stations.
5
Survey Camp 2078 | Group A
● Balance the traverse. The permissible angular error for the sum of interior
angles of the traverse should be less than ±30√n seconds and ±1√n
minutes for major and minor traverse respectively. The sum of
interior/exterior angles in a closed traverse should be equal to
(2N±4)*90o where, N is the total number of stations. For major and
minor traverse, the relative closing error should be less than 1:5000 and
1:3000 respectively.
● Plotting of the major and minor traverse stations is to be done by
coordinate method in appropriate scale (1:1000 and 1:500 respectively).
● Detail survey of the given sub area is to be carried out by total station and
tachometric surveying with reference to the major and minor traverse,
which have been already plotted.
6
Survey Camp 2078 | Group A
o Measuring Tapes
o Leveling Instrument
o Hammer
o Nails and Pegs
o Compass
o Prism
o Prism Pole
2.5 Methodology
Methodology of surveying is carried out based on its own principles, they are:
Traversing
The directions and the lengths of the survey lines are measured with the help
of an angle-measuring instrument such as theodolite and a tape. If the co-ordinates
of the first station and the bearing of the first line are known, the co-ordinates of all
successive points can be computed as follows:
XB=XA+L CosӨ
YB = YA + L SinӨ
where,
7
Survey Camp 2078 | Group A
I. Closed traverse:
If the figure formed by the lines closes at a station i.e. if they form a
polygon or it starts and finishes at the points of known co-ordinates then
the traverse is called closed traverse.
II. Open traverse
If a traverse starts and finishes at points other than the starting point or
point of known co-ordinates, then the traverse is called open traverse.
Link Traverse:
A link traverse is the type of traverse where an open traverse is linked at its
ends to an existing traverse to form a closed traverse.
The closing line may be defined by coordinates at the end points which have
been determined by previous survey. The difficulty is, where there is linear
misclosure, it is not known whether the error is in the new survey or the Departure:
Departure of a survey traverse may be defined as its coordinate length measured
perpendicular to magnetic meridian.
Independent coordinates:
Closing Error
where the sign obtained in ΣL and ΣD denotes the quadrant in which it belongs to.
Relative error of closure= error of closure/perimeter of traverse
8
Survey Camp 2078 | Group A
● Bowditch method
● Transit method
● Graphical method
● Axis method
The basis of these methods is on the assumptions that the errors in linear
measurements are proportional to ‘L’ and that the errors in angular measurements
are inversely proportional to ‘L’ where L is the length of a traverse leg. The
Bowditch’s Rule is commonly used to balance a traverse where linear and angular
measurements are of equal precision. The total error in latitude and in the
departure is distributed in proportion to the lengths of sides. The Bowditch rule
gives the correction as,
Correction to Lat. Or Dept = Total Error in Lat or Dept * (Length Of the
leg)/Perimeter of that Traverse
In order to measure the lengths of the sides of the traverse, two ways taping
(forward and backward) is done. In difficult areas where taping is not possible,
other methods like the subtense bar is used. The difference in values obtained by
forward and backward taping is called discrepancy. The reciprocal of mean of the
two measurements divided by the discrepancy is called precision. Both the
discrepancy and the precision for each traverse leg should be within the given
limits.
9
Survey Camp 2078 | Group A
Mathematically,
Discrepancy = Forward length - Backward length |
&, Linear precision = 1 / (Mean length / Discrepancy)
Tacheometry
Principle of Tacheometry
In isosceles triangles, the ratio of the perpendiculars from the vertex on their
bases is constant.
The formula for the horizontal distance is
𝐻 = 𝑘 ∗ 𝑠 ∗ cos2θ + c cos θ
The formula for vertical distance is
V= 0.5 ∗ 𝑘 ∗ 𝑠 ∗ 𝑠𝑖𝑛2𝜃 + 𝑐 𝑠𝑖𝑛𝜃
Where,
k = multiplying constant (=100)
c = additive constant (= 0)
s = staff intercept
θ = vertical angle
Levelling
Level Surface or line: It is any surface parallel to the mean spherical surface of earth.
The line lying in the level surface is level line.
Horizontal plane or line: It is the plane tangential to the level surface of that
10
Survey Camp 2078 | Group A
The line of Collimation: It is the line joining the intersection of cross hairs of
the optical center of the object glass. It is also called the line of sight.
Turning point: It is a point denoting the shifting of the level. It is the point on
which is the fore sight and back sight are taken. Any stable and well defined
object such as boundary stone, rock etc. is used as change point. A bench
mark itself is a change point.
● Direct Levelling
● Indirect Leveling
Direct Levelling
Differential Levelling
11
Survey Camp 2078 | Group A
Profile Levelling
Cross Sectioning
Reciprocal Levelling
Indirect Levelling
There are two methods of booking and reducing the elevation of points from the
observed staff reading:
Auto Level
12
Survey Camp 2078 | Group A
To check for the collimation error of level two-peg test method should be
performed. Two staffs were placed at A and B of known length (about 50 m).
First the instrument was setup on the line near B and both staff readings (Top,
Middle, and Bottom) were taken. Then, the instrument was setup at the middle C
on the line and again both staff readings on A and B was taken. Then
computation was done in order to check whether the adjustment was within the
13
Survey Camp 2078 | Group A
Contouring:
14
Survey Camp 2078 | Group A
Methods of Contouring
Taking the reading at the change point on the ground does the indirect
method of locating contours. The interpolation method is used to draw
the contour lines. Interpolation of contours is done by estimation, by
arithmetic calculations or by graphical method. The eye estimation
method is extremely rough and is used for small-scale work only.
There are two method of locating contour:
15
Survey Camp 2078 | Group A
2.5.1Reconnaissance:
Reconnaissance (Recce) means the preliminary inspection of the area before
commencing the actual detail survey, for the purpose of fixing the survey stations
and forming a general plan for the network of the chain lines. For this purpose, the
detailed inspection of the given area of Paschimanchal Campus was carried out by
reconnaissance survey.
16
Survey Camp 2078 | Group A
2.5.2 Traversing
The skeleton of lines joining those control points covering the area
to be surveyed is called Major Traverse. To do the survey precisely, two-sets
of reading should be taken for Major Traverse. We take two sets as 0 set and
90 set.
In the Survey Camp, two traverses - major and minor had to be established.
The major traverse had 20 control stations including two given control points. The
control stations were named as AM1, AM2, …… AM9 along with CP1, CP2 (the two
given control points) .The leg ratio of maximum traverse leg to minimum traverse leg
was maintained within 2:1. The discrepancy in length between the forward
measurements and the backward measurements of all the traverse legs was within
1:5000. Two sets of readings were taken for measuring the horizontal traverse
angles. The difference between the mean angles of two sets of readings was within a
minute for all the angles.
It is not sufficient to detail the area by enclosing with the help of major
traverse. So, minor traverse was established to cover small area. Only one set of
reading is taken as less precision is acceptable. We made 5 minor traverse station to
cover all the area. The control stations were named as Am1, Am2,Am3,Am4,Am5
and along with four major stations of major traverse AM3,AM4,AM5 and AM6.. The
leg ratio was maintained within 3:1. The discrepancy in length between the forward
measurements and the backward measurements of all the traverse legs was within
1:3000.
2.5.3 Detailing
Tacheometry was used for the detailing process. Total station was used to
carry out the detailing process. From total station horizontal distances, vertical
distances, and horizontal angles are measured that locates the control points of
different RL at the topographic map.
17
Survey Camp 2078 | Group A
With a total station one may determine angles and distances from the
instrument to points to be surveyed. With the aid of trigonometry and triangulation,
the angles and distances may be used to calculate the coordinates of actual positions
(X, Y, and Z or northing, easting and elevation) of surveyed points, or the position of
the instrument from known points, in absolute terms.
Some total stations also have a GPS interface which combines these two
technologies to make use of the advantages of both (GPS - line of sight not required
between measured points; Traditional Total Station - high precision measurement
especially in the vertical axis compared with GPS) and reduce the consequences of
each technology's disadvantages (GPS - poor accuracy in the vertical axis and lower
accuracy without long occupation periods; Total Station - requires line of sight
observations and must be set up over a known point or within line of sight of 2 or
more known points).
Some modern total stations are 'robotic' allowing the operator to control the
instrument from a distance via remote control. This eliminates the need for an
assistant staff member to hold the reflector prism over the point to be measured.
18
Survey Camp 2078 | Group A
The operator holds the reflector him/herself and controls the total station
instrument from the observed point.
The basic principle of Total Station is that the distance between any two
points can be known once the time light takes to travel the distance and back and
the velocity of light is known. Then the following relation, which is already
programmed in the memory of the instrument along with other correction factors,
calculates the required horizontal distance and is displayed on the LCD screen.
Setup:
Power on the instrument and check the level of battery, if it shows low
replace it with the charged one otherwise it is okay. For the lights on display it can be
made from the buttons provided. Afterwards, the image from the lens was adjusted
so that clear view of the prism center point can be viewed. Then height of the
instruments was noted.
For the angular measurement, the telescope is aligned in the direction of one
of the leg from which angle needs to be measured. Then aligning the telescope, the
instrument is zero set and then the horizontal frame of the total station is rotated
and sighted to the next station. It gives the angle between two adjacent legs in
clockwise direction. In the same way when telescope is focused to the center of the
prism located at any distance give the horizontal distance between them.
For the good operation of Total Station one can refer the catalogue provided
such as for data transfer, layout and other operations.
19
Survey Camp 2078 | Group A
2.6 Resection:
Resection is the process used for determining the position of an unknown
point with the help of already defined known coordinated points. The readings are
taken from the unknown points. Either two-point resection or three-point resection
can be performed. We performed three-point resection in the field
The given topography survey cap was finished satisfactorily within the given
span of time.The campus domain was divided into five numbers of plots . A group
had to complete a single plot following the routine provided. Drawing was plotted in a
full-size sheet i.e. A1 in the same scale i.e., 1:1000 for major traverse and 1:500 for
minor traverse. The topographic maps of several plots such prepared can then be
mosaics to form a single map of the whole area.This has made us clearer about the
principles and field practice of surveying and will ultimately help us to become a
better civil engineer in the future.
20
Survey Camp 2078 | Group A
3.3 SOIL
If along the potential slip surface in the soil the stress produced by gravity
exceeds the shear strength of the soil along the potential failure surface, the slope
21
Survey Camp 2078 | Group A
will become unstable. Obviously, the shear strength of soil is largely depending upon
the type of soil. Cohesive soil has more shear strength than others do. The hard and
dense soil is best for slopes. We found soft clayey soil that was very damp.
i. Theodolite
ii. Leveling Staffs
iii. Ranging rods
iv. Measuring Tapes 30m
v. Leveling instruments
vi. Compass
vii Pegs
viii Marker
3.6 METHODOLOGY
The I.P. was fixed so that the gradient of the road at any place was
less than 7 ‐ 10%. After determining the I.P. for road, theodolite was
22
Survey Camp 2078 | Group A
stationed at each I.P. and the deflection angles measured. The distance
between one I.P. and another was measured by two way taping. The
horizontal curve was set out by angular using theodolite at I.P. Then for that
radius, the tangent length and apex distance of the curve were calculated
using the following formulas.
3.6.3 Leveling
The method of fly leveling was applied in transferring the level from
the given B. M. to all the I.P., beginnings, mid points and end of the curve as
well as to the points along the center line of the road where the cross section
were taken. After completing the work of one way leveling on the entire
length of the road, fly leveling was continued back to the B.M making before
and forming the loops should be less than 25√K mm, where k is tot al loop
distance in km.
23
Survey Camp 2078 | Group A
In order to obtain the data for L‐Section, Staff reading was taken at a point at
20m intervals along the central line of the road with the help of a level by the
method of fly leveling. And thus after performing the necessary calculation
the level was transferred to all those point with respect R.L. of the given B.M.
Then finally the L‐Section of the road was plotted on a graph paper on a
vertical scale of 1:100 and a horizontal scale of 1:1000.
Similarly, Chainage of an I.P. = Chainage of previous I.P. +I.P. to distance The R.L. of
the different points was also computed using this formula.
24
Survey Camp 2078 | Group A
Hence, with the required calculation data regarding the road site in hand, the
plan was plotted on a scale of 1:1000, L‐Section on a graph paper on a scale of
1:1000 horizontal and 1:100 vertical and the cross section at different points also on
a graph paper on a scale of 1:100(both vertical and horizontal). All the data,
calculation (in a tabulated from) and the drawing of the necessary plan, longitudinal
section and the cross section of the road are presented here with this report.
3.6.7 Structures
The main structures provided for road constructions are retaining structures,
cross drain, side-drain, bio-engineering structures etc. retaining structures are
provided where the slope is critical. Gabion structure, dry masonry structures are the
example. The camber of the road is made perfectly by putting 4% of stage for gravel
road so as to avoid any collection of water on it.
The maximum gradient of the road is about 10% and the minimum gradient
of road is about 0% so as to facilitate the flow of drainage to specified direction.
However, the maximum of 12% was taken wherever not possible. Longitudinal drain
is provided on the sides of the road. Retaining walls are provided on required places.
Construction of hill roads involves many special structures. These may include
wide range of structures which are used to retain soil mass, to increase stability of
road embankment slopes as well as natural hill slopes, to accommodate road bed in
steep slope, to penetrate deep through mountain pass and so on. Integration of
bioengineering measures with engineering structures is yet another sector requiring
special attention.
The following types of structures are used normally on the hill road:
1. Retaining structures
2. Drainage structures
3. Slope protection structures
Retaining Structures:
A retaining structure is usually a wall constructed for the purpose of
supporting or retaining a vertical or nearly vertical earth bank, which in turn may
support vertical loads along with the self-weight of it. It provides adequate stability
to the road way and to the slope. Retaining walls are constructed on the valley side
on the roadway and also on the cut hillside to prevent slide towards the roadway.
Types of retaining wall are:
25
Survey Camp 2078 | Group A
Drainage structure
Roadway drainage structure means a device such as a bridge, culvert or ditch,
composed of a virtually non-erodible material such as concrete, steel, plastic or
other such material that conveys water under a roadway by intercepting the flow on
one side of a traveled way consisting of one or more defined lanes, with or without
shoulder areas, and carrying water to a release point on the other side.
We faced difficulty in the starting phase of road alignment but with the help
of our instructors, friends and group discussion we are able to finish the work in
given time. The work was tedious as compared to other surveying work, now with
the experience and knowledge we gained through this survey camp we are confident
enough to carry out in future.We understood factors like economy, convenience and
its use are to be taken in mind while designing such project.
26
Survey Camp 2078 | Group A
The site for the bridge site survey was selected in Kali Khola which was only
few minutes of walk away from Paschimanchal Campus. The site consists of mild
vegetation including cultivated land and scarcely available houses. The duration of
survey was 2 days.
3.1 Objectives
The adequate functioning of a road depends to a large extent on the
effectiveness of the cross drainage like bridges,etc. The main objective of the bridge
site survey it to give the students the preliminary knowledge on selection and
planning of possible bridge site and axis for the construction of the bridge.
The purpose of the bridge site survey was not only to prepare and layout of
the bridge site but also form the engineering point of view, the purpose is to collect
the preliminary data about the site such as normal water flow level, high flood level,
geological features of the ground for planning and designing of the bridge from the
details taken during the surveying.
1. To find the best location for a bridge over the river considering factors like
convenience, economic and geological stability.
2. To use triangulation method for the calculation of the bridge axis length.
3. To take sufficient data of the details including the spot heights, around the
bridge in order to prepare a topographical map of the area, cross section of
the river at certain intervals and longitudinal section of the river.
4. To determine the physical properties of the river like its discharge, velocity of
water, bed slope, etc.
27
Survey Camp 2078 | Group A
The following norms were followed while performing the bridge site survey:
1. Control point fixing as well as determining the length of the bridge axis had to
be done by the method of triangulation. While forming triangles, proper care
had to be taken such that the triangles were well conditioned, i.e., none of
the angles of the triangle were greater than 120° or less than 30°.
2. The triangulation angle had to be measured on two sets of readings by
theodolite and the difference between the mean angles of two sets of
readings had to be within a minute.
3. Transferring the level from one bank to another bank had to be done by the
method of reciprocal leveling.
4. The scale for plotting the topographical map was given to be 1:500.
5. In order to plot the longitudinal section of the river, data had to be taken
along the riverbed 125 m upstream and at least 75 m downstream. The plot
for the longitudinal section along the flow line had to be done in a scale of
1:100 for vertical and 1:500 for horizontal.
6. For the cross-section profile, data had to be taken at 25 m intervals both
upstream and downstream, and one at the bridge axis. Observation had to
cover about 10 m beyond the bank of river on either side. The scale being
1:100 for both vertical and horizontal directions.
28
Survey Camp 2078 | Group A
3.6 Methodology
For the bridge site surveying we use the methods of triangulation, levelling,
tacheometry etc. The methodology of the bridge site survey is given below:
1. The site was chosen such that it should be laid on the very stable rocks at the
bed of river as far as possible and not affect the ecological balance of the
flora and fauna of the site area.
2. The bridge axis should be so located that it should be fairly perpendicular to
the flow direction and at the same time.
3. The river width should be narrow from the economical point of view and the
free board should be at least 5m.
4. The starting point of bridge axis should not in any way lie or touch the curve
of the road.
The site selected for the bridge axis was near the curve of the river with no
community nearby. For the purpose of the shortest span, the stations were set
perpendicular to the river flow direction. The riverbanks were not eroded and were
suitable for bridge construction. The chance of change of direction of river on the
selected axis line was nominal.
29
Survey Camp 2078 | Group A
3.6.2 Triangulation
Figure 4: Triangulation
30
Survey Camp 2078 | Group A
the center line of the river at an interval of about 25 m up to 125 meters upstream
and 75 m downstream. The R. Ls of the traverse stations being known previously, the
levels of the different points on the river were calculated. Then the L-Section of the
riverbed was plotted on a graph paper on scale for vertical and horizontal.
3.6.6 Leveling
Transferring R.L. from B.M. to control points: The benchmark was on the bank of
the river.. The R.L. was transferred to the triangulation station from the B.M. by fly
leveling by taking the back sight-reading to the bench mark which should be within
the given accuracy. The R.L. was transferred to the opposite bank of the river by
reciprocal leveling.
Reciprocal Leveling: This method is applicable when taping is obstructed but not the
vision. For transferring the RL across the bridge reciprocal leveling was performed.
This method eliminates the error due to focusing, collimation, earth’s curvature and
refraction of atmosphere etc.
31
Survey Camp 2078 | Group A
Then, the true difference in elevation between the two stations A and B is given by
H=½ x [(ha - hb) + (ha'- hb')].
3.6.7 Detailing
Detailing of the entire bridge site was done by tachometric method, the
readings being taken with a Total station stationed at the different traverse stations.
The detailing was done with respect to the skeleton formed by triangulation. The
vertices of triangles serve as a control point. With the help of tachometer, the details
were booked, up to 125m upstream and 75m downstream. Trigonometric Leveling
was also done to find out the RL of the inaccessible points. The data and the
calculations have been tabulated in a systematic way.
3.6.8 Computation
The use of total station made the detailing process easy and fast. The total
station gives the direct vales of the horizontal distances and vertical height
difference between the station point and the detailing point. The RLs of the points
can be calculated by using following formula.
RL of detail = RL of station + HI ± V-Target Height
3.6.9 Plotting
The topographic map, the longitudinal section and the cross section were
plotted on the respective scales after the completion of calculations. Control stations
were plotted accurately in the grid paper. Then all hard details as well as contours
were plotted with reference to the control stations by the method of angle and
distances.
32
Survey Camp 2078 | Group A
reciprocal leveling result of the computations of the triangulation gave the axis span
of AB=28.481mm.
During the selection of the site all the considerations like geological,socio-
economical and topographical considerations were made and the best site was
selected.For triangulation, we chose three stations in one bank and one station on
the next bank. The distance between the three stations on same side was measured
by taping. Similarly, the cross-section and longitudinal section were performed. The
X-section was performed at the interval of 25m. The longitudinal section was about
125m upstream and 75m downstream.
33
Survey Camp 2078 | Group A
REFERENCES
1. Surveying vol. 1 by B.C. Punmia, Ashok K jain, Arun K Jain. Laxmi Publication Pvt. Ltd
2. Surveying vol. 2 by B.C. Punmia, Ashok K jain, Arun K Jain. Laxmi Publication Pvt. Ltd
3. A Text Book of Surveying and Levelling, R. Agor, Khanna Publishers
4. Reference link
www.googleearth.com
www.wikipedia.com
www.google.com
5. Past survey report 2075
34