02 Manufacturing Schedule 100442772

This document outlines the project timeline for manufacturing and delivering a GSG B2B 100-300/14 pump. Key steps include designing the pump and packaging over 10 and 80 days respectively in late 2021 and early 2022. Procurement of parts will take place from December 2021 through July 2022. The pump will undergo machining, assembly, testing, and packaging from mid-June through late August 2022 before being packed and shipped, with an expected delivery date of September 15th, 2022.

Uploaded by

gaurav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views1 page

02 Manufacturing Schedule 100442772

This document outlines the project timeline for manufacturing and delivering a GSG B2B 100-300/14 pump. Key steps include designing the pump and packaging over 10 and 80 days respectively in late 2021 and early 2022. Procurement of parts will take place from December 2021 through July 2022. The pump will undergo machining, assembly, testing, and packaging from mid-June through late August 2022 before being packed and shipped, with an expected delivery date of September 15th, 2022.

Uploaded by

gaurav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PFC Customer :HAROUGE OIL OPERATIONS

1 off GSG B2B 100-300/14


Project: WIP for Ghani
Cstomer PO -No.:Frame Agreement No. P1-2021
Sulzer No.: 100442772 -10

ID Task Name Duration Start Finish Half 1, 2022 Half 2, 2022


O N D J F M A M J J A S O N
1 Start of order 1 dy Fri 03.12.21 Fri 03.12.21 03.12
2 Internal prod. Paper / OED Rev.0 3 dys Mon 06.12.21 Wed 08.12.21 100%
3 Design pump 10 dys Thu 09.12.21 Wed 22.12.21 100%
4 Design packaging / GA/PPI/PIL back/approved 80 dys Thu 09.12.21 Tue 19.04.22 59%
5 Part list pump- 3 dys Mon 10.01.22 Wed 12.01.22 100%
6 Part list packaging 30 dys Wed 20.04.22 Wed 01.06.22 0%
7
8 Procurement pump parts 139 dys Fri 03.12.21 Fri 08.07.22
9 Pressure retaining parts / ordered 120 dys Thu 13.01.22 Wed 06.07.22 28%
10 Rotor parts / ordered 105 dys Thu 13.01.22 Tue 14.06.22 32%
11 Mech. Seal EagleBurgmann Germany / ordered 139 dys Fri 03.12.21 Fri 08.07.22 37%
12 Procurement ACC 162 dys Fri 03.12.21 Wed 10.08.22
13 Motor + Softstarter Nidec ASI S.p.A. / ordered 162 dys Fri 03.12.21 Wed 10.08.22 31%
14 Baseplate 80 dys Thu 14.04.22 Wed 10.08.22 0%
15 Coupling 75 dys Mon 25.04.22 Wed 10.08.22 0%
16 Seal System EagleBurgmann Germany / ordered 162 dys Fri 03.12.21 Wed 10.08.22 31%
17 Unit Control Panel (Eldatex) / / ordered 143 dys Mon 17.01.22 Wed 10.08.22 22%
18
19 Machining 15 dys Wed 15.06.22 Wed 06.07.22
20 Rotor parts @ SPDE Bruchsal 15 dys Wed 15.06.22 Wed 06.07.22 0%
21
22 Bareshaft pumps 25 dys Thu 07.07.22 Wed 10.08.22
23 Preparation for Hydrotest / balancing 5 dys Thu 07.07.22 Wed 13.07.22 0%
24 Hydrotest witness 2 dys Thu 14.07.22 Fri 15.07.22 0%
25 Rotor balancing 2 dys Thu 14.07.22 Fri 15.07.22
26 Assembly Pump for Testbed 6 dys Mon 18.07.22 Mon 25.07.22 0%
27 Assembly on Testbed 5 dys Tue 26.07.22 Mon 01.08.22 0%
28 Performance Test / witness 5 dys Tue 02.08.22 Mon 08.08.22 0%
29 Disassembly, Cleaning, Assembly 2 dys Tue 09.08.22 Wed 10.08.22 0%
30 Packaging 13 dys Thu 11.08.22 Mon 29.08.22
31 Assembly 2 dys Thu 11.08.22 Fri 12.08.22 0%
32 Pipework / painting / install wiring 10 dys Mon 15.08.22 Fri 26.08.22 0%
33 Final inspection / witness 1 dy Mon 29.08.22 Mon 29.08.22 29.08
34
35 Packing & Dispach 43 dys Tue 30.08.22 Fri 28.10.22
36 Packing sea worthy / preparation shipping doc 12 dys Tue 30.08.22 Wed 14.09.22 0%
37 FCA packing company ( 41 weeks after 03-12-2021) 1 dy Thu 15.09.22 Thu 15.09.22 15.09
38 Shipment to Ras Lanuf / Libya 30 dys Fri 16.09.22 Fri 28.10.22 0%

Task Project Summary Inactive Task Duration-only Finish-only


Start date : 03-12-2021
Delivery date FCA : 15-09-2022 / CIF Ras Lanuf Split External Tasks Inactive Milestone Manual Summary Rollup Progress
Milestone External Milestone Inactive Summary Manual Summary Deadline
Summary Inactive Task Manual Task Start-only

Project Manager: Kasim Patel 1/1 Date:01-03-2022


Coordinator Order Processing : Hans Gaibler Rev.02