1st Sessional Question Paper Production and Material Management
1st Sessional Question Paper Production and Material Management
Note: Attempt any three questions including Q.no. 1 which is compulsory. All questions carry equal marks.
Q.2. (a) Define Production System and explain in detail the various types of Production Systems.
OR
(b) ABC company has received the following jobs at a Work Centre to be processed. The
processing time (in days), arrival date and due date (in terms of shop calendar days) are
given. Determine the sequence in which these jobs should be processed according to
each of the following priority rules viz., FCFS, SPT, LPT, EDD, TSPT, LS and
COVERT. Assume today is day hundred and the jobs cannot be delay for more than 60
days for TSPT rule. Assume expected cost per day is Rs.10 per day.
P 15 95 185
Q 20 110 200
R 10 112 175
S 30 125 235
T 25 125 180
U 18 130 220
(10)
Q.3. (a) What is Production Management? Discuss the various types of Production Management
Decisions.
OR
(b) A Computer Centre has four expert programmers and needs to develop four application
programmes. The head of the Computer Centre, estimates the computer time (in
minutes) required by the respective experts to develop the application programmes as
follows:
(10)
***************