Lecture 1 - Introduction To Construction Management
Lecture 1 - Introduction To Construction Management
Lecture 1: Introduction to
Construction Management
Overview
1. Scope of Civil Engineer Projects
2. Introduction
3. Steps In Project Management
4. Working With Project Teams
5. Project Initiation, Estimates & Budgeting
6. Project Planning & Scheduling
7. Construction Phase
8. Construction Technology
9. Case Studies
10. Project Management Softwares
MTCC5007: CONSTRUCTION MANAGEMENT 1
Building Projects
Residential Buildings
MTCC5007: CONSTRUCTION MANAGEMENT 1
Transportation Systems
Hydraulic Structures
Nuclear Plant
Offshore Structures
These are huge steel and concrete structure in sea, used usually
for petroleum extraction.
MTCC5007: CONSTRUCTION MANAGEMENT 1
2. Introduction
Project Management is about the ‘overall’ planning and
co-ordination of a project from: conception to
completion
The main aims of Project Management:
Meeting the stated requirements
Completion On Time
Completion within Cost
Meeting required Quality Standards.
3. STEPS IN PROJECT
MANAGEMENT
1. Project Definition and Scope
2. Technical Design
3. Financing
4. Contracting
5. Implementation
6. Performance Monitoring
FUNCTIONS OF MANAGEMENT
1. Planning
2. Organizing
3. Staffing
4. Directing
5. Controlling
MTCC5007: CONSTRUCTION MANAGEMENT 1
4. PROJECT TEAMS
1. Each triangle in Figure
represents a team.
CONFLICT MANAGEMENT
DEVELOPING A CONSENSUS
Sometimes Multiple Solutions To A Problem Exist.
Each Of Which May Yield The Same Result.
The following an Be Helpful In Reaching A
Consensus/Agreement:
Voting
Trading
Averaging.
MTCC5007: CONSTRUCTION MANAGEMENT 1
5. PROJECT INITIATION,
ESTIMATES & BUDGETING
Initiating Is The Basic Processes That Should Be Performed
To Get The Project Started.
This Starting Point Is Critical Because Everyone Involved
needs to be on agreement with the Initiation:
Those Who Will Deliver The Project
Those Who Will Use The Project
Those Who Will Have A Stake
6. PROJECT PLANNING
& SCHEDULING
Project Planning: Process Of Identifying All The Activities
Necessary To Successfully Complete The Project.
7. CONSTRUCTION PHASE
The site management should be carried out through suitable
site organization structure:
Roles and responsibilities should be assigned to the construction
personnel.
Safety management is one of the important components of site
management.
MTCC5007: CONSTRUCTION MANAGEMENT 1
TIME MANAGEMENT
It is desirable that the project is completed in the defined time
schedule to get its full benefits.
Some of the issues that need to be considered in time management:
Total schedule of project
Identification of total resources
Timely availability of all equipment (including critical ones), and
its processing during construction of a project.
QUALITY MANAGEMENT
Quality of a project should be planned for all activities from
conception to completion.
It is desirable that the management gives adequate assurance and
controls that it shall meet project quality objectives.
Quality management should cover review of existing requirements,
subcontracting, materials, processes and controls during process,
auditing, training of personnel, final inspection and acceptance.
MTCC5007: CONSTRUCTION MANAGEMENT 1
8. CONSTRUCTION TECHNOLOGY
Power Shovel
MTCC5007: CONSTRUCTION MANAGEMENT 1
Dragline
MTCC5007: CONSTRUCTION MANAGEMENT 1
Dumper
MTCC5007: CONSTRUCTION MANAGEMENT 1
Tower
Crane
MTCC5007: CONSTRUCTION MANAGEMENT 1
Lining
Machine
MTCC5007: CONSTRUCTION MANAGEMENT 1
Concrete
Mixer
MTCC5007: CONSTRUCTION MANAGEMENT 1
Bulldozer
MTCC5007: CONSTRUCTION MANAGEMENT 1
Scrapper
MTCC5007: CONSTRUCTION MANAGEMENT 1
Belt
Conveyor
MTCC5007: CONSTRUCTION MANAGEMENT 1
9.CASE STUDIES
Al Habtoor Engineering
Fletcher Construction
MTCC5007: CONSTRUCTION MANAGEMENT 1
1. labor supply
2. concrete work
3. structural steel supply
4. Erection
5. high rise management experience
6. Purchasing
7. cost control
8. management staffing
MTCC5007: CONSTRUCTION MANAGEMENT 1
RESPONSIBILITIES OF COMPANIES
AL HABTOOR ENGINEERING
Responsible for the labor required and the quality of the
concrete and block work.
The procurement system put in place by the joint venture was
based on Al Habtoor Engineering's proven system.
FLETCHER
They had the high-rise management and planning expertise.
The project director and project manager came from Fletcher
and were based in Dubai.
MTCC5007: CONSTRUCTION MANAGEMENT 1
PHASE 1
The first phase would address the complexity of the building.
Some of the major challenges were related to the exoskeleton
embodiments:
This was redesigned in order to ease the installation & speed up
the cycle times to adhere to the tight schedule.
In addition, the rear-braced frame was completely redesigned
from lattice girder construction to box girders.
This redesigning phase was not only a saving in money but
also made the building much easier to build (AL HABTOOR).
MTCC5007: CONSTRUCTION MANAGEMENT 1
PHASE 2
Actual construction
The partners used many new technologies to speed up construction
& lower the construction cost:
This way, the companies could earn more profit by saving
money in such places as labor and equipment
One new technology that was used was the Cantilever’s Top
Climbing Jump Form system for the main core area.
Cantilever Pty Ltd, Queensland, Australia designed and
furnished the 300 ton forming system.
The companies’ use of value engineering, constructability, and
preplanning and planning included all members of the group:
All of this helped to keep cost down as well as keep up with the
schedule that was set by the Owner.
MTCC5007: CONSTRUCTION MANAGEMENT 1
1. BURJ KHALIFA
CONSTRUCTION TIME: 48 MONTHS
TECHNOLOGIES USED
The tower consists of more than 160
floors & to be completed within a very
tight schedule.
The following construction technologies
were incorporated to achieve the 3-day
cycle for the concrete works:
Auto Climbing formwork system (ACS).
Rebar pre-fabrication.
High performance concrete suitable for
providing high strength, high durability
requirement, high modulus, and
pumping.
Advanced concrete pumping technology.
Simple drop head formwork system that
can be dismantled and assembled
quickly with minimum labor requirement.
Column/Wall proceeding method, part of
ACS formwork system.
MTCC5007: CONSTRUCTION MANAGEMENT 1
MAJOR EQUIPMENTS
The process of selecting the right equipment to ensure delivery of
materials and workers effectively and efficiently is an art in its own right.
Selecting the optimal equipment and vertical transportation system for
construction requires ongoing analysis and constant modifications due
to the dynamic nature of the project during its construction life.
1. TOWER CRANES
2. TOWER MAIN HOISTS
3. CONCRETE PUMPING EQUIPMENTS
MTCC5007: CONSTRUCTION MANAGEMENT 1
End of Lecture