Substation Training Module
Substation Training Module
&
MAINTENANCE
OF
SUBSTATION
1
INDEX PAGE NO.
1. INTRODUCTION 3
3. MAIN EQUIPMENTS 6
4. COMMON TERMINOLOGY 7
6. INSTRUMENT TRANSFORMER 10 - 17
7. ISOLATORS 18 - 19
8. CIRCUIT BREAKER 20 - 23
9. CAPACITORS 24 - 25
3
SINGLE LINE DIAGRAM
132 / 33 KV SUBSTATION
132 KV I/C
LINE 1
LINE PT LA
LINE CT (CT1)
LINE CB
BUS ISOLATOR
132 KV BUS
BUS ISOLATOR
BUS PT
HV CT OF TRAFO. (CT2)
HV SIDE CB
POWER TRANSFORMER
132 / 33 KV
LV CT OF TRAFO. (CT3)
LV SIDE CB
BUS ISOLATOR
33 KV BUS
BUS ISOLATOR
4
Above-mentioned Single Line Diagram is General layout of Switchyard
Equipments. Only Single Incoming 132 KV Line and Single 33 KV Outgoing
Feeder are shown. There may be ‘n’ number of Feeders as per design. It depends
upon the rating of installed Switchyard Equipments.
The CTs in circuit are used for different purpose as mentioned below:
CT1 – 132 KV Line Metering and Distance, Directional O/C & E/F Protection
CT2 – Transformer HV Metering & Differential, REF & Non-Directional O/C & E/F
Protection
CT3 – Transformer LV Metering & Differential, REF & Non-Directional O/C & E/F
Protection
5
Substation Main Equipments and Its Functions
1) Power Transformer: To step up or step down voltage and transfer power from
one A.C. Voltage to another at the same frequency
9) Capacitor Bank: To Improve the power factor of the system & provide
compensation to reactive power absorbed by inductive loads, reduce the over
loading of the cables, transmission lines & transformers for the same load to be
handled
10) Protective Relay: To sound an alarm or to close the trip circuit of breaker so
as to disconnect a component during abnormal conditions (over load, under
voltage, unbalanced load, short circuits)
11) Battery Banks: To maintain the D.C. supply continuity during A.C. supply
failure for keeping equipment in operation for normal & abnormal conditions
12) Station Transformer: To supply of A.C. power for charging the batteries and
provide D.C. control supply for station equipments operations, for Illumination, for
spring charging motors of breakers, for cooling system of transformer
6
Some Common Terms used with meanings
20) AVR – Automatic Voltage Control (For Tap Changing on RTCC Panel)
7
Detail description of Each Equipments, Its Testing & Maintenance
1) LIGHTNING ARRESTER
8
Surge Counter
Testing: -
1) IR Testing between Stack to stack & between each Stack to earth by suitable
megger.
2) Surge Counter Test - Apply 230V AC supply across the counter & check pointer
movement in clockwise direction.
Maintenance: -
1) Insulator cleaning
2) Connections tightness
3) Checking of Earthing connections
4) Reading of leakage current on daily basis to be taken. If current shoots in red
zone, then that particular LA is to be replaced as early as possible.
9
2) INSTRUMENT TRANSFORMERS
These transformers are minimum oil type & hermetically sealed. They are
expected to be maintenance free during their service life. They transform the high
current or high voltage connected to their primary windings to the standard low
values in the secondary that feed the metering and protection apparatus. It also
isolates the secondary circuits from very high voltages of power system.
From the application point of view, these are divided into mainly two
categories 1) Metering 2) Protection type.
PT CT
CT is connected in series with the supply line & PT is connected across the
supply line. The CT secondary should never be open circuited and no fuse should
be inserted. In a PT the secondary should never be short-circuited and a fuse is
used in PT secondary circuit.
11
Current Transformer: Types
d) Wound CT: - This CT has a primary & secondary winding like a normal
transformer. This CT is rare and is used at very low ratios and currents, typically in
CT secondary circuits to compensate for low currents, to match different CT ratios
in summing applications, or to isolate different CT circuits.
The type of primary winding depends upon the type of CT insulation i.e. whether
Dead tank or Live tank (Inverted Type) Design.
Dead Tank: - In this design, the secondary core windings are housed in metallic
tank, which is lower part of the CT and solidly earthed. The leads of the primary
winding are brought at top chamber for termination. The primary winding in the
shape of ‘hair pin’ or ‘bolt’ is passed through the secondary cores and full
insulation is provided on primary windings.
Live Tank (Inverted): - In such design, the secondary cores and the primary
windings are assembled in the metal tank located at the top of the Current
Transformer. Here the secondary cores assembly is insulated fully for high system
voltage & primary winding is looped through the core assembly. The primary
winding can be single bar primary or multi-turn primary.
12
Hermetically Sealing: - The Instrument Transformer is supposed to be
maintenance free and hence there is no scope of filtering or change of oil during
its life. This makes it essential to hermetically seal the transformer to avoid
breathing of atmospheric air.
13
CT Testing: -
1) IR Testing –
2) Polarity Test - For carrying out this test, we require one 1.5 V cell, DC
analogue ammeter.
P1 P2
S1 + − S2
Analogue Ammeter
+ −
CELL
3) Ratio Test - Inject current in primary winding & measure induced secondary
current for different current readings and verify with CT Ratio.
4) Knee point check for PS class core - Inject 230 V variable AC voltage in
secondary core with ammeter in series. At certain stage, with 10% increase in
voltage, current shoots up almost 50%. This is the Knee point voltage. After
performing this test, Voltage is gradually reduced to Zero to demagnetise the CT.
14
6) Tan Delta Measurement – For getting concept of Tan Delta (Tan δ), we
consider the insulation of equipment as Capacitor.
Ideal Ic = V/Xc
Actual Ic
Loss δ Xc ∼ V
Angle φ Phase Angle
V
If the capacitor is good or perfect, it will pass only capacitive or charging current
on application of voltage. Ideal capacitive current Ic leads voltage by 90°. But in
practice, insulation has impurities & actual charging current vector departs from
the ideal Ic vector by a small angle (δ) called the loss angle.
The loss angle (δ) = 90 – Power factor angle (φ)
Higher tan δ produces high dielectric loss that causes increase in temperature of
paper insulation. Increased value of Tan δ can be due to any of the following: -
a) Moisture in the insulation.
b) Contamination of oil.
c) Internal partial discharge.
CT Maintenance: -
15
Potential Transformer: - There are two types of PTs as mentioned below:
PT Testing: -
1) IR Testing –
a) Primary to earth by 5 KV megger
b) Secondary each core to earth by 500 V megger
c) Primary to secondary by 5 KV megger
d) Secondary core to core by 500 V megger.
2) Ratio Test - Inject A.C. variable voltage in primary winding & measure induced
secondary voltage at different voltages & verify the same with PTR.
16
PT Maintenance: -
17
3) ISOLATOR AND EARTH SWITCH
Isolator is the device, which makes & breaks circuits in no load condition.
Types of Isolators:
a) Centre Break Rotating Type Isolator.
b) Double Break Rotating Type Isolator.
c) Pantograph Type Isolator.
d) Tandem Isolator.
Earthing Switch is provided for safety purpose to work on Dead Lines and is
electrically & mechanically interlocked with Isolator.
Isolator Testing: -
18
Isolator Maintenance: -
1) Checking of the male / female contacts for good condition and proper
connections.
2) Checking proper alignment of male & female contacts & rectify if required.
3) Cleaning of Insulators.
6) In case of Isolator with Earth switch, check electrical and mechanical interlock
i.e. Isolator can be closed only when E/switch is in open condition & vice versa.
7) As Isolators are operated on No load, hence check the interlock with Circuit
Breaker, if provided i.e. Isolators can be operated when Breaker is in OFF
condition.
9) Check the Panel indications i.e. semaphore & bulbs if provided (Isolator and
Earth switch - close and open condition) and rectify if required.
19
4) CIRCUIT BREAKER
Circuit Breaker is used to close or isolate the circuit in normal and abnormal
condition and to protect the electrical equipment against the fault. The parts of a
circuit breaker include –
1) Poles with interrupter, support porcelain, arc quenching medium, etc.
2) Operating mechanism
3) Support structure
4) Control circuit
SF6 Circuit Breaker
The part of the breakers assembled in one phase is called a pole. A circuit
breaker suitable for three-phase system is called a triple pole circuit breaker. All
the three poles operate simultaneously. Each pole comprises one or more
interrupters or arc quenching chambers. The interrupter is mounted on support
insulators. The interrupter encloses a pair of fixed and moving contact. The
moving contact can be drawn apart by means of the operating mechanism. The
operating mechanism gives the necessary energy for opening and closing of
contacts of the breakers. The arc produced by the separation of current carrying
contacts is extinguished by a suitable medium.
20
When a fault occurs in the protected circuit, the relay connected to the CT
actuates and closes its contacts. D.C. current flows from the source in the trip
circuit. As the trip coil of the breaker is energized, the circuit breaker operating
mechanism is actuated & it operates for the opening operation automatically. The
spring in the operating mechanism is charged by electrically or manually. Breaker
auxiliary switches are mechanically attached with the operating mechanism of
breaker. The contact changeover takes place as per breaker operation. Auxiliary
contacts are used for breaker operation circuit, indication circuit, and trip circuit
supervision circuit.
The Circuit breakers are classified on the basis of arc extinction medium:
1) Bulk Oil Circuit Breaker – Contacts are separated inside a steel tank filled
with transformer oil used for arc quenching.
3) Air Blast Circuit Breaker – It utilizes high-pressure compressed air for arc
extinction.
21
4) SF6 Gas Circuit Breaker – Sulphur-Hexa-fluoride gas is used for arc extinction
in this breaker. It is must to monitor the SF6 gas pressure inside the breaker pole
and check periodically the contact resistance of each pole or the travel of each
pole. This is helpful to prevent the problem of bursting of poles. The SF6 breaker
has an advantage that the rate of restricting voltage is zero & hence the burning of
male / female contacts is less. Operating mechanism is of two types: -
1) Movement of contacts is controlled by spring mechanism. (Spring Operated)
2) Movement of contacts is controlled by air pressure. (Pneumatic operated)
5) Vacuum Circuit Breaker – In this breaker, the contacts are housed inside a
permanently sealed vacuum interrupter. The arc is quenched as the contacts are
separated in high vacuum. For VCBs, the vacuum bottle is hermetically sealed
and as such no maintenance is required. However to ascertain the failure of
vacuum bottle, it is necessary to check the contact resistance of each pole or the
travel of each pole as specified by the manufacture. VCBs are generally used up
to 33 KV voltage systems.
a) Fault clearing time – It is the time elapsed between the instant of the
occurrence of a fault and the instant of final arc extinction in the circuit breaker. It
is the sum of relay time and breaker time.
b) Relay time – It is the time elapsed between the instant of occurrence of fault &
the instant of closure of relay contacts, i.e. closure of trip circuit.
c) Breaker time – It is the time elapsed between the instant of closure of trip
circuit and the instant of final current zero.
d) Anti Pumping of a circuit breaker – It blocks the repeat closing pulse when
breaker is already in closed condition.
22
e) Auto- reclosing of a circuit breaker – Auto-reclosing is provided to restore the
supply after interrupting a transient fault on overhead lines.
f) Rated short circuit breaking current – It is the highest value of short circuit
current, which a circuit breaker is capable of breaking under specified conditions
of recovery voltage and power frequency recovery voltage.
g) Rated short circuit making current – It may so happen that circuit breaker
may close on existing fault. The circuit breaker should be able to close without
hesitation as contact touch. The rated short circuit making current should be at
least 2.5 times the R.M.S. value of a.c. component of rated breaking current.
In any power utility, maintaining stable power supply at proper voltage is always a
problem. Due to lot of inductive load, the reactive power flow takes place in the
system which results into lowering of system voltage and increase in
Transmission & Distribution losses. The HT capacitor provides an interim solution
in improving the power system stability, the voltage and power factor. HT
capacitor bank also compensate the losses occurring in the transmission lines.
Capacitor unit has one steel container, two bushings and several capacitor
elements enclosed in the unit. A single HV Capacitor may have a capacitance of 5
KVAr to 200 KVAr. Several identical units are mounted on Insulator racks and
connected in series parallel combination to obtain a High Voltage Capacitor Bank.
Before commissioning, megger the capacitor bank between phases and earth.
The megger reading for individual capacitor should not be less than 50 MΩ. For
more than one unit in parallel, minimum acceptable megger value can be derived
by dividing 50 MΩ by the number of units connected in parallel. Before switching
on capacitor, bus voltage, system incoming load current and power factor can be
noted. After energising, check that capacitor draws almost balance current in all
the 3 phases and is near to its rated value. Note the change in bus voltage, load
current and system power factor. Normally after capacitors are energised, there
will be little rise in bus voltage and some reduction in system load current and
improvement in power factor. In case load current increases instead of reducing, it
shows that capacitors connected are more than required for the load and in this
case the power factor shall be leading.
When Residual voltage factor (RVT) is used for unbalance protection, measure
open delta voltage, which should be negligible. In case, capacitors are connected
in double star with neutral CT, the current on the secondary side of neutral CT can
be measured, which should also be negligible.
24
Protection of Capacitor bank:
1) Fuse is provided for each capacitor in the bank. The fuses shall be external
type for 11 KV capacitor bank. The capacitor unit together with external fuse shall
be arranged in such a way to avoid bird faults by providing adequate clearance
between the body and the line terminal. Capacitor bank of voltage level more than
11 KV is provided with internal fuse type. In case of fault, the faulty element will
automatically go out of circuit.
2) Discharge resistors are provided within the capacitor unit to ensure safety after
de-energisation of capacitor (To reduce the residual voltage from crest value of
rated voltage to 50 volts or less within 5 minutes). The power loss in these
resistors is negligible.
3) Each capacitor bank is protected against lightning by gapless zinc oxide
arrester.
4) The capacitor protection equipment include over current, earth leakage and
protection to detect unbalance loading due to abnormal conditions.
Maintenance of Capacitors: -
25
6) POWER TRANSFORMER
26
General view of Power Transformer :-
Main fixtures of Power Transformer and their functions are listed below: -
In case of a serious fault, gas generation is more, which causes operation of lower
float & trips the circuit breaker. The gas can be collected from a small valve at the
top of relay for Dissolved Gas Analysis (DGA).
27
Checking the floats operation manually: -
a) Close the both valves. (From Transformer and main conservator side)
b) Drain oil from the buchholz relay.
c) Top float makes contact as the oil gets lowered and gives Alarm.
d) If oil is further drained, bottom float makes contact and gives trip signal.
After testing, both valves must be opened without fail and released the air from
relay. Alarm & Trip circuit can also checked by shorting contacts externally by link.
b) Oil Surge Relay - It is similar to Buchholz relay with some changes. It has only
one float & operates when oil surges reach and strike the float of OSR. It is used
with OLTC for detection of any damage or fault inside the tap changer and
prevents tap changer from damages in case of low oil level in OLTC tank.
28
d) Pressure Relief Valve - When the pressure in the tank rises above pre-
determined safe limit, this valve operates & performs the following functions: -
1) Allows the pressure to drop by instantaneously opening the port.
2) Gives visual indication of valve operation by raising a flag.
3) Operates a micro switch, which gives trip command to breaker.
31
The assembly is enclosed in hollow porcelain and is provided with support flange
and top hood. The porcelain is filled with oil.
A) Off Load Tap Changer - In this type, before moving the selector, transformer
is made OFF from both ends. Such tap changers have fixed brass contacts,
where taps are terminated. The moving contacts are made of brass in the shape
of either roller or segment.
RTCC (Remote tap change control cubicle) is used for tap changing by manually
or automatically through Automatic Voltage Relay (AVR) which is set +/- 5% of
110 Volt (Reference taken from secondary side PT voltage). During Auto tap
changing, Bell / Hooter will ring up thus gives information to substation operator
for tap changing.
Transition resistances are used in OLTC for avoiding momentarily interruption of
power supply during tap changing. At the time of tap changing, load current
passes through the transition resistances & no power interruption occurs during
tap changing.
33
If two transformers of same output operating in parallel, the % impedance must be
identical, if Transformers are to share equally. If % impedance is not identical,
suppose T/F 'A' is having 4% impedance and T/F 'B' is having 2% impedance,
then load sharing will be,
Load A = L x ( Z2 / Z1+Z2 ) Where L is total combined output
Load B = L x ( Z1 / Z1+Z2 ) and Z is percentage impedance
So that A transformer will share only 1/3rd load & B transformer will share 2/3rd
load. Hence operating transformers in parallel, the output of the smallest
transformer should not be less than 1/3rd of the output of largest one.
When operating two transformers in parallel, one of the RTCC panels is kept on
Master mode and another one is kept on Follower mode so that simultaneously
tap changing is possible on both transformers. If transformers are not running
parallel, the control switch is kept on Independent Mode i.e. both transformers
taps can be separately changed.
2) Voltage Ratio Test - This test is essential to check the output or the secondary
voltage on each tap position. By virtue of this test the problems in the OLTC can
be easily detected. 3 Phase, 440 V LT supply is applied to the primary side of the
transformer and the output volts at the secondary side for each tap position is
measured. If any break in voltage reading is observed during change of tap
position, then there is some problem in that particular tap.
34
3) Magnetic Balance Test - This test is carried out to check the balancing of the
induced voltages in the windings & flux distribution. Transformer is kept on normal
tap position and 3 Phase, 440 V LT supply is applied to the primary windings as
given below:
1) YNyn0 Transformer: - First the voltage is applied between R & N. Voltage will
be induced in between YN and BN. Voltages are noted & will be observed that:
35
4) Vector Group Test - This test is carried out to check correctness of windings
connections. The Phase angle difference arises out of the internal connections of
the windings. A star / star transformer having the similar vector diagram for
primary and secondary side can be connected in two different ways internally.
In the first case there is 0° displacement between primary and secondary whereas
in the second case there is 180° displacement. In addition to this, a +30 or −30°
displacement is possible in a 3 phase transformer when the vector diagram is
different i.e. delta/star OR star/delta type.
For parallel operation, secondaries must have same phase angle displacement
with respect to their primaries so that there may be no phase difference between
the terminals of the secondaries themselves.
36
Vector Group Testing at the time of Commissioning or on repaired Job:
1) YNyn0 Transformer: - Keep the transformer on normal tap position. Short R &
r of windings. Apply 3 Phase L.T. voltage to primary windings. Measure voltages
on the secondary side.
R, r
R r
n n
b y
b y N
B Y B Y
Primary Secondary Vector Representation
2) Dyn11 Transformer: - Keep the transformer on normal tap position. Short R &
r of windings. R,r
R r y
n
n b
b y B Y
B Y
Primary Secondary Vector Representation
37
5) Magnetizing Current Test - When a Power Transformer is charged, it is
generally presumed that it is to be charged on NO LOAD condition because it
draws magnetizing current containing high harmonics. Transformer may trip on
differential protection if it is not provided harmonic restraint protection. This current
inrush is due to the iron losses of the transformer. This current should be equal in
all three phases so that there would not be any spill current in the relay to trip the
primary circuit breaker of the transformer. The test is carried out at normal tap
position.
6) Short Circuit Current Test – Short circuit test is carried out to check the
healthiness of windings. Apply 3 Phase L.T. voltages to primary windings &
secondary windings are shorted through ammeters of suitable range. If the
readings are equal in all three phases, transformer is supposed to be healthy.
38
7) Oil Test - The oil is used as insulation between windings & core and between
windings & tank. Without oil, the paper insulation of the windings could be
punctured early which in turn will result in failure of transformer. The oil facilitates
cooling of the windings and magnetic circuits. The oil protects windings and core
of transformer from the absorption of moisture. The test on oil is divided into two
different categories.
c) Flash Point – Flash point is a minimum temperature at which oil will support
instantaneous combustion (flash) but before it burns continuously. Flash point of
new oil should be fairly high.
d) Pour Point - It is the indicator of the ability of oil to flow at cold operating
conditions. It is the lowest temperature at which the fluid will flow when cooled
under prescribed conditions.
39
f) Water Contents - It is expressed in parts per million (ppm). Dielectric strength
of oil is very high when water content is low.
2) Electrical Testing: -
a) Dielectric Strength - The BDV of oil is its ability to withstand electric stresses
without failure.
40
Standard Values of New Oil as per IS : 335-1983
41
Dissolved Gas Analysis (DGA): - Transformer, in operation, is subjected to
various thermal and electrical stresses, resulting in liberation of gases from the oil
which is used as insulation media and coolant. The solid insulating materials like
paper, wooden support, pressboard, etc. cause degradation and form different
gases, which get dissolved in the oil. The most significant gases generated are
Hydrogen (H2), Methane (CH4), Ethylene (C2H4), Acetylene (C2H2), Propane
(C3H8), Propylene (C3H6), Carbon Monoxide (CO), Carbon Dioxide (CO2), and
Ethane (C2H6). The gas connected in the relay will help to identify the nature of
the fault. The greater the rate of gas collection, the more severe is the nature of
the developing fault.
Ratio Method used for Analysis of DGA results:-In this method three ratios of
gases are used. They are methane / hydrogen, ethylene / ethane, acetylene /
ethylene. If the ratio comes out more than one, it indicates abnormal deterioration
and less than one indicates normal aging.
42
Interpretation of the faults according to the observed ratios of Gases
43
Actions during failure / tripping of Transformer –
The action to be taken depends upon the size of the transformer, operation of
protective relay, whether tripping is accompanied by loud noise, smoke or
expulsion of oil from the transformer, etc. Observe the transformer external
condition; look for any damage to the bushings, leads or cable box. Note the
temperature of oil & check if the oil level in the conservator is right. Take megger
readings between primary and secondary and also of each to earth. If everything
is right, proceed as noted below:
- The failure may possibly be due to a sudden and heavy overload, or short-circuit.
If a DO fuse has dropped out, check if its ampere rating is right. If incorrect,
replace by the correct size and energise the transformer, after switching off the
load. If everything is all right, close the secondary circuit; if fuse blows again, the
fault is obviously in the outgoing lines, which should be traced and rectified; if on
the other hand, the primary circuit fuse blows out, even when the load is
disconnected, an internal fault is indicated. This also apply, if an over current relay
alone has operated and tripped the breaker.
Any tripping of buchholz relay requires to be carefully looked into. If the lower
assembly has tripped due to sudden evolution of large quantities of gas, a major
internal fault is to be inferred especially if either over current or differential or earth
fault relay has operated. If, on the other hand, the upper assembly has operated
due to slow release of gas it is necessary to find out its composition before any
conclusions can be drawn. If it is air only, there is no cause for worry, as air can
enter into the transformer in many ways.
44
When transformer is commissioned, it sometimes happens that the buchholz
relay upper assembly operates, after a few hours of run, due to the release of air
bubbles entrapped within the windings, such as when hand filling is employed for
filling of oil into the tank. If the accumulated gas is not air, an incipient fault is
indicated.
DGA would help in identifying the nature of the fault, and this should be done as a
routine measure. If the buchholz relay has tripped, without any gas being given
out, it may be due to electrical fault in the wiring.
- Thorough checking is required if the earth fault relay has tripped, or there is an
evolution of smoke or oil, and also PRV has operated in case of large transformer.
In such cases reclosing of breaker should not be permitted as it may cause further
extensive damage. Detailed testing of transformer is to be carried out and
compare the results with test certificate figures and consult the manufacturer.
In most of the cases, the cause of the fault can be found out if you carefully
observe the condition of windings by lifting the core and coil assembly. The
following notes may be of help in identifying the cause:
Sustained overloads: The windings in one or all the phases would show signs of
overheating and charring; the insulation would be very brittle and have lost all its
elasticity.
Inter-turn short: The same signs as for sustained overloads would be noticed,
but only on one coil, the rest of the coils being intact.
45
Dead short-circuit: This can be identified by the unmistakable, lateral or axial
displacement of the coils. The coils may be loose on the core; some turns on the
outermost layer may have burst outwards and broken as if under tension. If, in
addition to these signs, the windings are also completely charred, it is conclusive
evidence that the short-circuit has continued for an appreciable period, not having
been cleared quickly by the protective relays.
46
7) CONTROL & RELAY PANELS
Control or relay boards are built up by using requisite number of self-contained
sheet steel cubicles, comprising a front panel to carry the control apparatus & the
hinged or removable back cover to give access to interior wiring, cable
termination. This type is called as Simplex type panel. When panels are arranged
back to back in corridor formation, and door is then fitted at each end, are called
as Duplex panels. Depending upon the size of the substation the control and relay
board may incorporate the followings:
1) Indicating and metering instruments mounted on front.
2) Relays mounted on the backside in Duplex panel, flush mounting on front in
Simplex panel.
3) A mimic diagram representing main circuit connections is incorporated on the
front panel. It is a single line diagram incorporated on the front side of the control
panel. This diagram represents the actual physical position of various HT
electrical equipments in the sub-station yard along with status of equipments, ON
and OFF positions of various breakers and isolators through semaphore indication
or lamp indication.
47
4) The automatic semaphore indicators are used to denote position of switches.
5) Circuit Breaker control switch (TNC switch) is fitted on front. Normally switch is
on Normal (Centre) position. Handle is moved to the right or left to initiate close or
trip operations.
6) Indication lamps mounted for various purposes follow a standard colour code.
Red - C.B. or switch CLOSED
Green - C.B. or switch OPEN
White - Trip circuit healthy
Amber - Alarm indication i.e. CBs tripped on fault
7) Annunciation System – It gives alarm in case of any abnormality in the system.
Alarm bell rings and appropriate facia lamp flashes ON & OFF. Substation
operator has to ACCEPT the signal by pressing a button, which silences the bell
and causes the lamp to show a steady light. After taking remedial action, the
operator RESETS the alarm circuit by pressing another push button, the lamp
being simultaneously extinguished.
48
Colours for Internal Wiring
Each wire should have a letter to denote its function. D.C. supply from +ve source
should bear odd number & from -ve source should bear even number.
a) Wiring Drawing: The routing of wires from various equipments in a control and
relay panel is shown in this drawing. The route of the particular wire as per its
purpose of application can be traced easily while attending any faults in the
particular circuit.
For reading of drawing it should be kept in mind that drawing is prepared
when isolator & breaker positions are OFF & spring of the breaker mechanism is
in deenergised condition.
49
b) Schematic Drawing: This drawing is a representation of various circuits such
as metering, protection, control, indication, annunciation, etc. in a control and
relay panels.
c) Layout Drawing: This drawing shows arrangement of various indoor and
outdoor equipments in a particular installation in a sequential order.
50
8) STATION TRANSFORMER
1) A.C. supply is used for battery charger, which converts A.C. to D.C. supply for
charging the batteries and parallel provides D.C. source for various controls of
substation equipments. In case of A.C. supply failure, batteries will take care of
D.C. supply continuity for equipment’s controls.
2) A.C. supply is used for OLTC for tap changing operation of transformer and
also cooling arrangement of transformer.
5) A.C. supply is used for Oil filtration, some miscellaneous welding work, and
Test supply for carrying out testing of various equipments in switchyard.
51
9) BATTERIES & BATTERY CHARGER
Precautions / Maintenance: -
- Batteries should be cleaned regularly.
- Cell voltages & Specific gravity is to be recorded as per schedule.
- Batteries should be charged in a well-ventilated place, so that the gases and the
acid fumes are blown away.
- Do not disturb any connection with charger on, as there is risk of sparking.
- If acid or electrolyte gets spattered into the eyes, wash them immediately with
large quantity of clean, cold water.
- Tighten connections periodically. Apply petroleum jelly to terminals to prevent
corrosion.
- Maintain level of the electrolyte – Add only the distilled water. Add electrolyte
only if some of the electrolyte spills out.
52
10) MEASURING INSTRUMENTS
53
POWER TRIANGLE
Active Power
KW (P)
Active Power: The actual amount of power that produces the effective work is
called active or real power. It is measured in Watts.
Reactive Power: The power drawn by reactive load such as Capacitors and
Inductors in a system is called reactive power. It is measured in VAr (Volt amp
reactive).
Apparent Power: The total power demanded by the load is the product of current
and voltage. This power is referred as apparent power. It is measured in VA (Volt
amp).
54
Case 2: - a) Feeder CTR = 100/1 A, Feeder PTR = 33000/110 V
b) Meter CTR = 400/1 A, Meter PTR = 33000/110 V
[(100/1) x (33000/110)]
M.F. of Energy Meter = ----------------------------- = 0.25
[(400/1) x (33000/110)]
SECURE MAKE
1 2 3 4 5 6 7 8 9 10
M1 R L1 M2 Y L2 M3 B L3 N
R R R Y Y Y B B B N
E
P P P P P P P P P U
H H H H H H H H H T
A A A A A A A A A R
S S S S S S S S S A
E E E E E E E E E L
C P C C P C C P C
T T T T T T T T T
s s s s s s
1 2 1 2 1 2
55
d) Earth Tester: - Resistance of the earth pit ‘E’ in following figure can be
measured directly with the help of an ‘earth tester’
Earth Tester
P1 P2
C1 C2
E P C
Electrode Potential Current
(Earth Pit) Electrode Electrode
E is the earth pit electrode under measurement; P & C are two auxiliary electrodes
of 15-20 mm diameter and 40 cm long bars. The electrode C1 is planted at a
distance of approx. 25 metres from E and P1 is fixed centrally between E and C1.
One reading of Pit resistance is taken by rotating handle of earth tester. Two more
readings are taken by shifting P1 a distance of 3 metres on either side of its
central position. The value is the resistance of Electrode E to the earth.
56
f) Oil Tester (BDV Tester): - Dielectric breakdown strength of transformer oil is
one of the most reliable tests for proving the condition of oil. Oil sampling is done
by taking due care. The glass bottle into which oil is drawn should be perfectly
clean, clear, transparent and dry. It should then be thoroughly rinsed with oil
known to be good. The sample of oil should drawn preferably be drawn from the
bottom of the transformer tank. As water is heavier than oil, it settles down at the
bottom. The first sample or two may be thrown away if it contains sludge or
droplets of water.
The gap between two electrodes is to be maintained / checked at 2.5 mm by
gauge and the test cup is cleaned properly. The cup is then filled with the sample
oil to be tested up to 1 cm above the electrodes. The cup top should then be
covered with a clean glass plate and allowed to rest for at least 5 minutes so that
all air bubbles may disappear. Any bubbles still standing on the surface may be
removed with a clean glass rod. Use thin rubber gloves if you can, so that the
sweat on your fingers may not cause any contamination of the oil. Carry out test
as per procedure until there is positive and final breakdown of the oil. The test is
carried out for six times on the same sample after a gap of at least 5 minutes. The
average of all six readings is the dielectric strength of oil under test.
57
Some Important Numbers used with their meanings
58
Trouble Shooting Works: -
PT Circuits
1 Voltmeter not showing correct - Check fuses
reading
- If above is OK, voltmeter may be
faulty
- Loose connections in PT circuit
2 Energy meters recording on - CT secondary circuit may be in
lesser side shorting position for one or two
phases
- PT circuit fuse may be blown
- Loose connections
- Energy meter may be faulty
59
S/No. Probable Trouble Cause / Works to be attended
D.C. Protection Circuits
2 Non tripping of breaker - D.C. fuse may be loose or blown off
- Loose connections
- Trip coil is open or burnt
- Misalignment of auxiliary contacts
of breaker
- No free movement of plunger of trip
coil
- Mechanical trouble in breaker
- Trip switch or Push button may be
faulty
- Air pressure may be low in case of
pneumatic operated breaker. If low,
correct it
- Check the circuit as per circuit
diagram
60
S/No. Probable Trouble Cause / Works to be attended
D.C. Protection Circuits
5 Mal-operation of Relay - Defect in relay or setting, If relay is
defective, relay needs to be replaced
- Wiring connection problem
7 Spring charging motor does not - Either loose fitting of fuse and link
start or blowing of fuse
- Loose connections
- Failure of A.C. or D.C. supply
- Misalignment or defective limit
switch of Spring charging mechanism
- Defective motor
Annunciation Circuits
1 Non working of Bell - Either loose fitting of fuse and link
or blowing of fuse
- Loose connections
- Burning of Bell coil
- Disturbance in bell adjustment
- Aux. relay provided may not
working
- Sealing (hold on) supply getting to
the aux. relay through ‘accept’ push
button might have disconnected due
to faulty ‘accept’ push button
61
S/No. Probable Trouble Cause / Works to be attended
Indication Circuits
1 Lamp not indicating for breaker - Either loose fitting of fuse and link
ON-OFF position or blowing of fuse
- Lamp may be loose fitted or fusing
of lamps
- Loose connections
- Defective aux. switch contacts of
breaker
62
Safety Electrical Clearances: -
Most of the equipments in a substation are provided with sufficient insulation from
breaking down. There is a need for assurance that the breakdown or flashover will
not occur to the operating personnel and some safe distance is to be maintained.
Clearances are broadly categorized as below.
64
Technical Data of some common used Line Conductors (ACSR)
65
Earthing for EHV Substation: -
Types of Earthing: - It can be divided into Neutral earthing & Equipment earthing.
a) Neutral Earthing deals with the earthing of system neutral to ensure that
neutral points are held at earth potential and return path is available to neutral
current.
Points to be earthed: Transformer neutral is to be earthed to two separate and
distinct earth electrodes interconnected with substation earth mat.
66
With a low resistance earth bus and the neutrals connected to a common earth
system, there will be no danger to the low voltage system and advantages in
keeping everything in the station at a common potential above earth will outweigh
the disadvantages.
a) LA Earthing – The earthing lead for any LA shall not pass through any iron or
steel pipe, but shall be taken as directly as possible from the LA to a separate
earth electrode interconnected with substation earth mat. Individual earth
electrodes should be provided for each station type lightning arrester, while for
distribution type lightning arrester, one electrode may be provided for a set of
lightning arresters.
a) Earth Electrode: Any plate, pipe or rod embedded in the earth to obtain
effective electrical connection with general mass of the earth is known as Earth
Electrode.
67
b) Touch Potential: If a person standing on substation floor touches a faulted
structures by raised fingers, potential between his raised fingers and the feet is
called touch potential.
c) Step Potential: If fault current flowing through the ground of the sub-station, a
potential between two steps of a person standing on the ground is called step
potential. A person moving in the switchyard and touching an earthed metallic
structure should not get a shock. Hence touch potential should be below 45 Volt.
Also step potential should be below 45 Volt so that a person walking on substation
floor does not get shock due to high step potential.
1) Soil resistivity: -
Before designing earth mat, it is necessary to determine the soil resistivity of the
area in which substation is to be located. Resistivity of the earth varies
considerably from 10 to 10,000 Ω-m depending on the types of the soil. Also
resistivity varies at different depth depending upon the type of soil, moisture
content and temperature etc., at various depths, which affects the flow of current
due to the fact that the earth fault current is likely to take its path through various
layers.
As the earthing system has to carry the earth currents, the maximum earth fault
current likely to flow in the system is considered for designing of earthing. A good
earthing system for substation can be designed using an earth mat which is
formed by a grid of horizontally buried conductors which serves to dissipate the
earth fault currents to earth, also as an equipotential bonding conductor system,
along with required number of vertical earth electrodes which are connected to the
points of earthing of various equipments, structures and also interconnected with
the horizontal earth mat. M.S. rods are generally used for the earthing of
substation.
Total Earth resistance of the station system must be below 3 ohms for low voltage
domestic system, below 0.5 ohms for low voltage and medium voltage sub-
station, and below 0.1 ohm for 220 KV and 400 KV sub-station and power plants.
If value of Earth Pit resistance is found high, then it is to be treated to bring back
the value within the normal range.
Electric Shock:-
69
Cure of Shocks:-
When anyone gets a shock, the first and foremost duty of the observer is to break
the contact of the live mains and body either by switching off the main supply or
the body should be rolled away with a dry wooden stick. If a stick etc. is not at
hand, a dry piece of cloth should be used to detach the body from the live mains
or if that is not available the loose cloth such as coat or shirt of the victim should
be pulled with care without touching his body.
In most of the electric shocks, it is momentary and the contact with live wire is
imperfect, in such cases breath stops momentarily. But due to the shock the victim
becomes unconscious, stops breathing and his heart still beats, the most urgent
and immediate cure for this victim is that he should be given immediate artificial
respiration and it should be continued until the victim starts breathing normally. It
should be borne in mind that if the artificial respiration is stopped just after the
victim recovers, he is liable to become unconscious again. In such cases the
artificial respiration is to be continued for 6 to 8 hours. Method of artificial
respiration is displayed at every electric control room and substation.
70
PROTECTIVE RELAYS:
1) Reliability: - Protection scheme must operate, when the system condition calls
upon to do so. Failure in the trip and control circuit of the breaker can be
determined by continuous supervision arrangement (Trip circuit healthy lamps in
the panel)
2) Selectivity: - Protective system must be such that it should correctly select the
faulty section and cut off the same from the system without disturbing other
healthy sections.
4) Stability: - The protection system should be stable and it must actuate from the
concerned signal only and not from any other similar signal.
Back Up Relaying: If due to some reason the primary relaying system fails to
operate, the back up relays must operate and isolate the faulty equipments.
Auto Reclosing Relays: These relays are used to reconnect the circuit so that if
the fault is of transient nature, the system is returned to normal operation. This
system is used mostly on overhead lines where 80 to 90% faults are of transient
nature. (lightning, birds passing near or through lines, tree branches, etc.)
71
Three types of Relays:
1) Relay back up - To trip same breaker by other relay if main relay fails.
2) Local Breaker back up (LBB) – To trip next breaker on the same bus.
1) Distance Relay: - This Relay is directional type & works on the principal of
Impedance rather than current. Generally there are 3 Zones in forward direction
and 1 Zone in reverse direction.
Protected Zone - X KM
Station C
72
2) Over current & Earth Fault Relay: -
This Relay is made directional type & is a backup for Distance Relay.
Transformer Protection: -
1) Differential Relay: - This Relay compares the currents in the windings of the
transformer through CTs whose ratios are such as to make their currents normally
equal. The polarities of the CTs are such as to make the current circulate without
going through the relay during load conditions and external faults. During internal
faults, the balance condition is disturbed and relay operates
P1 P2 P2 P1
s1 s2 s2 s1
PROTECTED ZONE
RELAY
73
2) Restricted Earth Fault Relay: -This protection helps easy and quick detection
of fault in the star connected winding of power transformer. The relay operates
whenever there is a fault in the tap changer or the star connected winding.
Normally the balance three-phase loads are feed through the transformer. There
is no current flow through the star point neutral to the earth in this normal
situation. One CT of similar ratio and the protection class is provided in neutral
side of the transformer which is used for matching / balancing the circulating
current through the main CTs in case of external faults.
P1 P2
R
R
s1 s2
Y
N
s1 s2 B Y
B
s1 s2
s2 P2
Relay
s1 P1
74
Feeder Protection: -
R Ph Y Ph B Ph
P1 s1 C11
P1 s1 C31
P2 s2
C51 C73
P2 s2 P1 s1
P2 s2
C71
R Ph Y Ph B Ph
P1 s1 C11
P1 s1 C31
P2 s2
C51 C31
P2 s2 P1 s1
P2 s2
C71
75
Relay Settings Calculations: -
250/1 A
R1
132 / 33 KV, 25 MVA, 10% Imp. Load - 190 A
R5 R4 R3
132 KV Bus 33 KV Bus
Fault Level - 580 MVA 250/1 A
R2
Load - 170 A
% Source Imp. = [(Base MVA)/ (Fault MVA)] x 100 = (100/580) x 100 = 17.24%
76
Total % Imp. at 33 KV Bus = [Source Imp. + Trafo. Imp.] = 17.24 + 40 = 57.24%
Fault MVA (33 KV Bus) = [(Base MVA)/ (Total Imp.)] x 100 = (100/57.24) x 100
= 175 MVA
Fault Current (I) = [(Fault MVA x 1000) / (√3 X 33)] = 3061 Amp
Time in Sec. @ TMS 1.0 for Normal Inverse = {(0.14) / [(PSM*0.02) – 1]} and
Above 20 PSM, curve becomes flat, Time in second is 2.2
For 14.4 PSM, Operating time = 2.55 Sec @ TMS 1.0 (Normal Inverse graph)
Say, Fault clearing time = 110 ms i.e. operation time = 0.11 = (TMS x 2.55)
Therefore TMS = (0.11) / (2.55) = 0.04313
Select TMS = 0.05, Operation of Relay = 0.05 x 2.55 = 127 ms for O/C Relay.
B) Secondary current in Relay for Earth Fault = [(Fault Current)/ (CTR x PS)]
77
Part B: - 33 KV Feeder Relay Setting (R2)
Secondary current in Relay for over current = [(Fault Current)/ (CTR x PS)]
B) Secondary current in Relay for Earth Fault = [(Fault Current)/ (CTR x PS)]
78
Part C: - 33 KV Incomer Feeder Relay Setting (R3)
Secondary current in Relay for over current = [(Fault Current) / (CTR X PS)]
B) Secondary current in Relay for Earth Fault = [(Fault Current)/ (CTR x PS)]
79
Part D: - 132 KV HT Transformer Feeder Relay Setting ( R4 )
B) Secondary current in Relay for Earth Fault = [(Fault Current) / (CTR x PS)]
80
Part E: - 132 KV Line Feeder Relay Setting (R5)
B) Secondary current in Relay for Earth Fault = [(Fault Current) / (CTR X PS)]
2 E/F Relay
a) PS - 0.20 PS - 0.20 PS - 0.20 PS - 0.20
b) TMS – 0.05 TMS – 0.16 TMS – 0.23 TMS – 0.20
c) O/T – 110 ms O/T – 352 ms O/T – 506 ms O/T – 606 ms
81
Daily Operational Duties at SUBSTATION: -
1) Watch the hourly transformer temperature, load, etc. and they do not exceed
the permissible limit or the rating of all the equipment involved or connected in the
circuit.
3) When a feeder trips, its indication should be noted and entered in the relevant
register. VCB or SF6 CB controlling overhead lines can be charged after a 2-3
minutes of tripping as most of the problems are of transient nature. If the breaker
trips again, the feeder should be declared as faulty and message sent to
concerned person and patrolling arranged. In case of tripping of Transformer,
cause of the same is to be cleared before charging.
4) Always check and ensure that proper D.C. supply is available on the trip circuit.
For checking Trip circuit healthiness, Push button is provided on the CRP. Also on
Trip circuit supervision relay, Green LED shows the healthiness, and Red LED
shows unhealthiness. Take corrective actions accordingly if required.
6) Ensure that batteries are in proper state of charge and have correct voltage and
charge rates and the same are to be checked every day.
Operating Instructions:
These shall be displayed in the substation at a suitable place. The operator will
perform the sequence of operation in accordance with these instructions. These
instructions should be either in English or Local language.
82
Consider that in sub-station there is one Main Bus & one Transfer Bus as
mentioned in following drawing:
Auxiliary Bus
89 A 89 C
89 A 89 C
52 B 52 T
BUS COUPLER 89 L
CT
TRANSFORMER
LOAD
84
Safety Rules:
2) See that sufficient sets of earthing sets, hand gloves, ladders, etc. are always
kept at the substation in proper working order & can be safely used for such work.
3) Only authorised men take permits to work as per formats. While issuing permits
to others, proper earthing should be ensured. Danger notice ‘Do not operate, men
at work’ should be affixed on the concerned dead feeder.
4) Fire fighting equipment, first aid box, etc. is maintained in proper condition. First
aid chart should be displayed in control room in English or Local language.
General:
1) All tripping at the substation should be reported. Also wrong tripping and non-
tripping should be reported to concerned superior.
3) Single line diagram should show the incoming lines, isolators, breakers,
transformers, LAs, CTs and PTs with their make, current rating, and rupturing
capacity.
85
Maintenance of Substation Equipments: -
86
Recommended Maintenance Schedule of Power Transformer
S/No. Items to be inspected Inspection notes Action required
Hourly
1 Load Amps Check against rated If high, reduce the
figures load
2 Voltage Check against rated An improper tap
figures position can cause
excessive core loss
3 Winding and Oil Check that temperature Shutdown the
Temperature rise is reasonable transformer and
investigate if either
is persistently
higher than normal
Daily
1 Oil level in Main & Check oil level from oil Top up, if found low
OLTC Conservator gauge
2 Oil level in bushings Check oil level from glass Top up, if found low
3 Dehydrating Breather Check colour of silica gel, Reactive/replace
check that air passages with new charge, if
are free, check oil level in it is pink, make up
oil cup oil in oil cup
4 Oil leakage Check for any leakages Arrest leakages, if
any
Monthly
1 OLTC driving Lubricate bearings, check Clean, adjust, or
mechanism gearbox oil level & replace as required
inspect all moving parts,
motor, etc.
2 OLTC automatic Check all circuits If faulty, take
control independently, check suitable actions to
step by step operation set it right
including limit switches
Quarterly
1 Insulation Resistance Compare with earlier Take suitable
values actions if required
2 Bushings Examine for cracks and Clean or replace if
dirt deposits required
87
S/No. Items to be inspected Inspection notes Action required
Quarterly
3 Oil in transformer & Check for BDV Take suitable
tap changer action to restore
quality of oil
4 Cooler fan bearings, Lubricate, check gear Replace burnt or
motors & mechanism box, examine contacts, worn contacts or
check manual control and other parts
interlocks
Half Yearly
1 Oil cooler Test for pressure
Yearly
1 Oil in transformer Check for BDV, acidity Filter or replace oil
and sludge
2 Gasket joints Tighten the bolts
evenly to avoid
uneven pressure
3 Cable boxes Check for sealing Replace gasket if
arrangements leaking
4 Surge diverter & gaps Examine for cracks and Clean or replace
dirt deposits
5 Relays, protection Check for protection Take suitable
circuits circuits actions if required
6 Earth resistance Compare with earlier Take suitable
values actions if required
7 Temperature Pockets holding Oil to be
Indication thermometers should be replenished, if
checked required
8 Dial type oil gauge Check pointer for Adjust if required
freedom
9 Paint work Should be inspected Touching up if
required
10 Diverter switches of Check for worn out Replace worn out
OLTC after 10,000 contacts parts, filter oil
operations
88
S/No. Items to be inspected Inspection notes Action required
2 Yearly
1 Oil conservator Internal inspection Should be
thoroughly cleaned
2 Buchholz relay Mechanical inspection Adjust floats,
switches, etc., as
required
Note:
1) All maintenance test results and observations should be specifically recorded.
2) In case of anything abnormal occurring during service, the matter should be
reported to the manufacturer.
89
Recommended Maintenance Schedule of Circuit Breakers
S/No. Points to be Inspected Periodicity
1 Check gas pressure in case of SF6 CB Daily
2 Check air pressure in case of ABCB or Daily
pneumatic operated breaker and check the
operation of compressor by realising air
pressure just below minimum value. Drain
condensation from reservoir
3 Check oil level, its condition, any oil leakage in Daily
case of OCB and correct if required
4 Check & tightness of all power connections and Yearly
control wiring connections
5 Check contact resistance Yearly
6 Clean breaker insulator & check for any cracks Yearly
7 Clean & lubricate of moving parts of operating Yearly
mechanism
8 Check condition of trip & close coil & its Yearly
assembly for free movement. Replace if required
9 Check breaker close-open timing Yearly
10 Check insulation resistance Yearly
11 Check all Controls, Interlocks & Protections like Yearly
checking of pole discrepancy system i.e.
whether all three poles are getting ON – OFF at
the same time
12 Clean auxiliary switches by CTC or CRC spray Yearly
and check its operation
13 Check structure supporting hardware & its Yearly
tightness. Also check paint condition
14 Carry out compressor maintenance in case of Yearly
ABCB or pneumatic operated CB, replace oil in
compressor if required
90
Recommended Maintenance Schedule of Current Transformer
S/No. Points to be Inspected Periodicity
1 Check oil level & leakage, rectify the same Daily
2 Check & tightness of all power connections and Yearly
CT secondary connections
3 Clean bushings / insulators & check for any Yearly
cracks
4 Check earthing connections and tightness Yearly
5 Check the working of stainless steel bellows Yearly
6 Check the nitrogen pressure as per specification Yearly
of manufacturer in case of Nitrogen filled CT
7 Check insulation resistance Yearly
8 Check and adjust the gap of arcing horn if CT is Yearly
provided with arcing horn
9 Check tan δ (Tan Delta) Yearly
10 Check structure supporting hardware & its Yearly
tightness. Also check paint condition of CT unit
& structures, touch up if required
91
Recommended Maintenance Schedule of Isolator
S/No. Points to be Inspected Periodicity
1 Check & tightness of all power connections Yearly
2 Check proper alignment of contacts & rectify if Yearly
required
3 Clean insulators & check for any cracks Yearly
4 Check earthing connections and tightness, clean Yearly
earth blade contact
5 Lubrication of all moving parts Yearly
6 In case of Isolator with Earth switch, check Yearly
electrical and mechanical interlock i.e. Isolator
can be closed only when E/switch is in open
condition & vice versa
7 Check insulation resistance Yearly
8 As Isolators are operated on No load, hence Yearly
check the interlock with Circuit Breaker, if
provided i.e. Isolators can be operated when
Breaker is in OFF condition
9 The motor operating mechanism box, in case of Yearly
motor operated isolators, should be checked for
inside wiring, terminal connectors, etc
10 Check the Panel indications i.e. Semaphore & Yearly
bulbs if provided (Isolator Close and Open
condition) and rectify if required
12 Check structure supporting hardware & its Yearly
tightness. Also check paint condition, touch up if
required
92
FIRE & FIRE EXTINGUISHERS:
Class “A” Fires: These are fires involving solid materials (such as wood, cloth,
paper, rubber, etc.), normally of an organic nature (compounds of carbon), in
which combustion generally occurs with the formation of glowing ambers, where
the cooling effect of water is essential for extinguishment of fire.
Class “B” Fires: These are fires involving flammable liquids e.g. kerosene,
naphtha, LDO, mix oil, gasoline, where blanketing effect (A layer of foam over the
surface of burning liquid) is essential for extinguishing fire.
Class “C” Fires: These are fires involving gases e.g. LPG, Methane, Ethylene,
Propylene, Hydrogen etc. Fire can be put out either by dry chemical powder or
carbon dioxide gas. Here isolation of leaking source is essential.
Class “D” Fires: These are fires involving combustible metals, such as
magnesium, titanium, sodium. These fires can be put out with the help of special
dry powders. Ordinary DCP or Foam or Water is of no use on such fires.
Caution:-
1) Do not use Foam Fire Extinguisher on fires involving live electrical equipment
and metal.
2) Do not use CO2 Fire Extinguisher on big size fire. It is also not to be used on
metal fire. While extinguishing oil fire, precaution against flash back or re-ignition
is to be taken.
94