100% found this document useful (1 vote)
361 views

Rate Analysis Notes 3

The document provides rate analyses for various construction items including: 1) Earthwork excavation estimated at Rs. 163 per cubic meter 2) Earthwork filling estimated at Rs. 125 per cubic meter 3) Cement concrete bed foundation estimated at Rs. 5173.71 per cubic meter 4) Size stone masonry estimated at Rs. 3974.97 per cubic meter 5) Brick masonry estimated at Rs. 7090.68 per cubic meter 6) Hollow block masonry estimated at Rs. 8570 per 10 square meters The rates are estimated based on material quantities and costs, labor costs, and overhead expenses.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
361 views

Rate Analysis Notes 3

The document provides rate analyses for various construction items including: 1) Earthwork excavation estimated at Rs. 163 per cubic meter 2) Earthwork filling estimated at Rs. 125 per cubic meter 3) Cement concrete bed foundation estimated at Rs. 5173.71 per cubic meter 4) Size stone masonry estimated at Rs. 3974.97 per cubic meter 5) Brick masonry estimated at Rs. 7090.68 per cubic meter 6) Hollow block masonry estimated at Rs. 8570 per 10 square meters The rates are estimated based on material quantities and costs, labor costs, and overhead expenses.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

3.

RATE ANALYSIS OF DIFFERENT ITEMS OF WORK

1.EARTHWORK EXCAVATION

EARTWORK in excavation in trenches for foundation not exceeding 1.5m width including
dressing of sides and ramming of bottoms, lift upto 1.5m and lead upto 30 m

Take 10 cum

RATE ANALYSIS- EARTHWORK EXCAVTION


Amount
Sl.no particulars Quantity unit Rate Rs unit
Rs
LABOURS
1
Mazdoor 3.25 no 450 Rs/day 1462.5
Total 1462.5
water charges @1% of the Total 14.625
Profit and overhead @10% of the total 146.25
Grand Total 1623.375
Rate per cum= Grand Total/10 (in Rs) 162.34

Rounded off Rs 163

2.EARTHWORK IN FILLING

Filling available excavated earth in trenches,plinth sides of foundation in layers not exceeding 20 cm in
depth, consolidating layer by layer ramming and watering, lead upto 50m and lift upto 1.50m

Take 10 cum

RATE ANALYSIS- EARTHWORK FILLING


Amount
Sl.no particulars Quantity Unit Rate Rs Unit
Rs
LABOURS
1
Mazdoor 2.5 no 450 Rs/day 1125
Total 1125
water charges @1% of the Total 11.25
Profit and overhead @10% of the total 112.5
Grand Total in Rs 1248.75
Rate per cum=(Grand Total /10) in Rs 124.88

Rounded off Rs 125


3.CEMENT CONCRETE BED IN FOUNDATION 1:4:8

Take 10 cum,

For dry quantity add 54 % extra

=10+(54/100)x10 =15.4 cum

COARSE AGGREGATE
CEMENT CALCULATION SAND CALCULATION CALCULATION
(1/13)X15.4=1.2 Cum (4/13)X15.4=4.8Cum (8/13)X15.4=9.6Cum
1.2/0.0347=34.60
BAGS

RATE ANALYSIS- CEMENT CONCRETE BED IN FOUNDATION 1:4:8


Sl.no particulars Quantity unit Rate unit Amount
MATERIALS
Coarse aggregate 40mm
9.6 cum 1250 Rs/cum 12000
1 down size in Cum
Sand (Coarse) in cum 4.8 cum 1800 Rs/cum 8640
Cement in bags 34.6 bags 450 Rs/bag 15570
LABOURS
Head mason( numbers) 0.25 no 600 Rs/day 150
2
Mason (numbers) 2 no 500 Rs/day 1000
Mazdoor (numbers) 20 no 450 Rs/day 9000

3 Contingencies ,T and P etc lumpsum Rs 250

Total 46610
water charges @1% of the Total 466.1
Profit and overhead @10% of the total 4661
GrandTotal 51737.1
Rate per cum=Grand Total/10 5173.71
4.SIZE STONE MASONRY IN CM 1:6

Volume of mortar(dry ) per 10 cum=4.20 cum


stone calculation
CEMENT CALCULATION SAND CALCULATION including wastage
(1/7)X4.2=0.60 Cum (6/7)X15.4=3.6Cum 12.5 cum
0.60/0.0347=17.29 BAGS

RATE ANALYSIS- SIZE STONE MASONRY IN CM 1:6

Take 10 cum
Sl.no Particulars Quantity unit Rate unit Amount
MATERIALS
Stone including bond stone
12.5 cum 600 Rs/cum 7500
1 and wastage in cum
Sand (Coarse) in cum 3.6 Cum 1800 Rs/cum 6480
Cement in bags 17.29 Bags 450 Rs/bags 7780.5
LABOURS
Head mason( numbers) 0.50 No 600 Rs/day 300
2
Mason (numbers) 10 No 500 Rs/day 5000
Mazdoor (numbers) 19 no 450 Rs/day 8550

3 Contingencies ,T and P etc lumpsum 200

Total 35810.5
water charges @1% of the Total 358.105
Profit and overhead @10% of the total 3581.05
Grand Total 39749.655
Rate per cum=Grand Total/10 3974.97

5.BRICK MASONRY IN CM 1:6 FOR SUPERSTRUCTURE

Take 10 cum
10/(0.1x0.1x0.2)=5000
Number of bricks with mortar= no
quantity of mortar=Quantity with mortar- Quantity without mortar
10 -(5000x0.09x0.09x0.19)=2.30 cum

ADD 15% extra for wastage and frog filling=2.3+(15/100)x2.3 =2.64 cum
for dry mix add 1/3 rd extra=2.64+(1/3)x2.64=3.50 cum
Volume of mortar(dry ) per 10 cum=3.50 cum
CEMENT SAND
CALCULATION CALCULATION
(1/7)X3.50=0.50 Cum (6/7)X3.50=3.0Cum
0.50/0.0347=14.40
BAGS

RATE ANALYSIS- FIRST CLASS BRICKWORK MASONRY IN CM 1:6


Take 10 cum
Sl.no particulars Quantity unit Rate unit
Amount
MATERIALS
Bricks 20cmx10cmx10cm
5000 No 8 Rs/number 40000
(numbers)
1
Sand (Coarse) in cum 3 Cum 1800 Rs/cum 5400
Cement in bags 14.4 Bags 450 Rs/bags 6480
scaffolding,ropes etc Lumpsum 250
LABOURS
Head mason( numbers) 0.50 No 600 Rs/day 300
2
Mason (numbers) 8 No 500 Rs/day 4000
Mazdoor (numbers) 16 no 450 Rs/day 7200

3 Contingencies ,T and P etc lumpsum Rs 250

Total 63880
water charges @1% of the Total 638.8
Profit and overhead @10% of the total 6388
GrandTotal Rs 70906.8
Rate per cum=Grand Total/10 (Rs) 7090.68
6.RATE ANALYSIS- Hallow block masonry in cement mortar 1:4

RATE ANALYSIS- HOLLOW BLOCK MASONRY IN CM 1:4


Take 10 Sq m
Sl.no Particulars Quantity unit Rate unit Amount
MATERIALS
Hollow blocks
40cmx10cmx20cm 122 no 45 Rs/numbers 5490
(numbers)
1
Sand (Medium) in cum 0.12 cum 1800 Rs/cum 216
Cement in bags 0.82 bags 450 Rs/bag 369

scaffolding, ropes etc lumpsum 250

LABOURS
Head mason( numbers) 0.20 no 600 Rs/day 120
2
Mason (numbers) 1.5 no 500 Rs/day 750
Mazdoor (numbers) 2.5 no 450 Rs/day 1125

3 Contingencies ,T and P etc Lumpsum Rs 250

Total in Rs 8570
water charges @1% of the Total in Rs 85.7
Profit and overhead @10% of the total in Rs 857
Grand Total in Rs 9512.7
Rate per sqm=Grand Total/10 951.27
7.RATE ANALYSIS- Solid block masonry in cement mortar 1:4

RATE ANALYSIS- SOLID BLOCK MASONRY IN CM 1:4


Take 10 Sqm
Sl.no particulars Quantity unit Rate unit Amount
MATERIALS
Solid blocks
40cmx10cmx20cm 122 no 55 Rs/number 6710
(numbers)
1
Sand (Medium) in cum 0.2 cum 1800 Rs/cum 360
Cement in bags 1.5 bags 450 Rs/bag 675

scaffolding, ropes etc lumpsum 250

LABOURS
Head mason( numbers) 0.20 no 600 Rs/day 120
2
Mason (numbers) 2 no 500 Rs/day 1000
Mazdoor (numbers) 3 no 450 Rs/day 1350

3 Contingencies ,T and P etc lumpsum Rs 250

Total in Rs 10715
water charges @1% of the Total in Rs 107.15
Profit and overhead @10% of the total in Rs 1071.5
GrandTotal in Rs 11893.65
Rate per sqm=Grand Total/10 1189.37

8. RATE ANALYSIS- POINTING IN CM 1:3 ON BRICK WALLS

TAKE 100 Sq m
Volume of dry mortar=0.63 cum
Cement=(1/4)x0.63=0.157 cubic meters
cement in bags=(0.157/0.0347)=4.52 bags
sand=(3/4)x0.63=0.47 cum
RATE ANALYSIS- POINTING IN CM 1:3 ON BRICK WALLS
Take 100 Sqm
Sl.no particulars Quantity unit Rate unit
Amount
MATERIALS
Cement in bags 4.52 bags 450 Rs/bag 2034
Sand (Medium) in cum 0.47 cum 1800 Rs/cum 846
1

scaffolding, ropes etc lumpsum Rs 100

LABOURS
Head mason( numbers) 0.50 no 600 Rs/day 300
2
Mason (numbers) 10 no 500 Rs/day 5000
Mazdoor (numbers) 10 no 450 Rs/day 4500

3 Contingencies ,T and P etc lumpsum Rs 100

Total in Rs 12880
water charges @1% of the Total in Rs 128.8
Profit and overhead @10% of the total in Rs 1288
GrandTotal in Rs 14296.8
Rate per sqm =Grand total /10 142.97
ROUNDED OFF 143.00

9. RATE ANALYSIS FOR CEMENT CONCRETE FLOORING 75MM THICK 1:4:8

Take 100 Sqm


VOLUME OF CONCRETE= 0.075X100=7.5 CUM

ADD 10% EXTRA FOR UNEVENNESS OF BASE CONCRETE=7.5+(10/100)X7.5=8.25 CUM


for dry mix add 50% extra=8.25+(50/100)X8.25=12.375 cum

CEMENT CALCULATION SAND CALCULATION COARSE AGGREGATE


(1/13)X12.375=0.95 Cum (4/13)X12.375=3.8Cum (8/13)X12.375=7.6Cum

0.95/0.0347=27.40 BAGS
RATE ANALYSIS FOR CEMENT CONCRETE FLOORING 75MM THICK 1:4:8
Sl.no particulars Quantity Unit Rate Unit Amount
1 MATERIALS
Cement in bags 27.4 bags 450 Rs/bag 12330
Sand (Coarse) in cum 3.8 cum 1800 Rs/cum 6840
coarse aggregate 20mm
7.6 cum 1350 Rs/cum 10260
down
2 LABOURS
Head mason ( numbers) 0.50 no 600 Rs/day 300
Mason ( numbers) 10 no 500 Rs/day 5000
Mazdoor ( numbers) 20 no 400 Rs/day 8000

3 Contingencies ,T and P etc lumpsum Rs 200

Total 42930
water charges @1% of the Total
429.30
Profit and overhead @10% of the total
4293
GRAND TOTAL
47652.30
Rate per sqm=grand total/100
476.52

10. RATE ANALYSIS FOR GRANITE STONE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4

Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum

CEMENT SAND
CALCULATION CALCULATION Granite slab Calculation

(1/5)X0.32= 0.064 Cum (4/5)X12.375=0.256Cum Granite slab required=10 sqm


0.064/0.0347=1.84 BAGS add dor wastage and breakage=10%
10+(10/100)*10=11.50 sqm
RATE ANALYSIS FOR GRANITE STONE FLOORING WITH 20mm THICK LAID ON BASE
OF 20mm CEMENT MORTAR 1:4
Sl.no particulars Quantity unit Rate unit Amount
1 MATERIALS
20mm thick Granite slab 11.5 Sqm 2000 Rs/sqm 23000
carriage of slabs lumpsum lumpsum Rs 200
Sand (medium) in cum 0.256 cum 1800 Rs/cum 460.8
Cement in bags 1.84 bags 450 Rs/bag 828
Cement for slurry
1 bags 450 Rs/bag 450
@4.4kg/sqm
2 LABOURS
Head mason ( numbers) 0.25 no 600 Rs/day 150
Mason ( numbers) 2 no 500 Rs/day 1000
Mazdoor ( numbers) 3 no 400 Rs/day 1200

3 Contingencies ,T and P etc lumpsum Rs 400

Total 27688.8
water charges @1% of the Total
276.89

Profit and overhead @10% of the total


2768.88

GRAND TOTAL
30734.57
Rate per sqm=grand total/10
3073.46

11. RATE ANALYSIS FOR VITRIFIED TILE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4

Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum

CEMENT SAND
CALCULATION CALCULATION Vitrified tiles Calculation
(1/5)X0.32= 0.064 Cum (4/5)X12.375=0.256Cum Vitrified tiles required=10 sqm
0.064/0.0347=1.84 BAGS add for wastage and breakage=2.5%
10+(2.5/100)*10=10.25 sqm

RATE ANALYSIS FOR VITRIFIED TILE FLOORING WITH 20mm THICK LAID ON BASE OF
20mm CEMENT MORTAR 1:4
Sl.no particulars Quantity unit Rate unit Amount
1 MATERIALS
Vitrified tiles 60x60 cm 10.25 Sqm 800 Rs/Sqm 8200
carriage of slabs lumpsum 100
Sand (medium) in cum 0.256 Cum 1800 Rs/cum 460.8
Cement in bags 1.84 bags 450 Rs/bag 828
Cement for slurry
0.66 bags 450 Rs/bag 297
@3.3kg/sqm
2 LABOURS
Head mason ( numbers) 0.25 no 600 Rs/day 150
Mason ( numbers) 2 no 500 Rs/day 1000
Mazdoor ( numbers) 2 no 400 Rs/day 800

3 Contingencies ,T and P etc lumpsum Rs 300

Total in Rs
12135.8

water charges @1% of the Total in Rs


121.36

Profit and overhead @10% of the total in Rs


1213.58

GRAND TOTAL in Rs
13470.74

Rate per sqm=grand total/10 in Rs 1347.07

12. RATE ANALYSIS FOR MARBLE STONE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4

Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum

CEMENT SAND
CALCULATION CALCULATION Marble slab Calculation

(1/5)X0.32= 0.064 Cum (4/5)X12.375=0.256Cum Marble stonesrequired=10 sqm


0.064/0.0347=1.84 BAGS add for wastage and breakage=15%
10+(15/100)*10=11.5 sqm

RATE ANALYSIS FOR MARBLE STONE FLOORING WITH 20mm


THICK LAID ON BASE OF 20mm CEMENT MORTAR 1:4
Sl.no particulars Quantity unit Rate unit Amount
1 MATERIALS
Marble slabs 18mm thick 11.5 Sqm 1500 Rs/Sqm 17250
carriage of slabs lumpsum lumpsum 150
Sand (medium) in cum 0.256 cum 1800 Rs/Cum 460.8
Cement in bags 1.84 bags 450 Rs/bag 828
Cement for slurry
1 bags 450 Rs/bag 450
@4.4kg/sqm
white cement in kg 20 kg 20 Rs/Kg 400
2 LABOURS
Head mason ( numbers) 0.25 no 600 Rs/day 150
Mason ( numbers) 1.2 no 500 Rs/day 600
Mazdoor ( numbers) 2 no 400 Rs/day 800
Mazdoor for polishing and
5 no 400 Rs/day 2000
rubbing
polishing machine 4 days 400 Rs/day 1600

3 Contingencies ,T and P etc lumpsum 300

Total in Rs
24988.8

water charges @1% of the Total in Rs


249.89

Profit and overhead @10% of the total in Rs


2498.88
GRAND TOTAL in Rs
27737.57

Rate per sqm=grand total/10 in Rs


2773.76

13. Corrugated Galvanized iron 0.63m thick sheet roofing

RATE ANALYSIS FOR CORRUGATED IRON 0.6M THICK SHEET ROOFING


Sl.no particulars Quantity unit Rate unit Amount
1 MATERIALS
Corrugated G I
Sheets=12.8 sqm OR 0.7 0.7 Quintal 5500 Rs/qunital 3850
quintal
G.I. bolts and nuts 0.7 Kg 70 Rs/kg 49
G.I.Screws 1 Kg 50 Rs/kg 50
G.I. hooks and nuts 1.4 Kg 40 Rs/kg 56
washers 5 dozens 5 Rs/dozen 25
2 LABOURS
carpenter ( numbers) 1.00 no 600 Rs/day 600
blacksmith( numbers) 0.5 no 500 Rs/day 250
Mazdoor ( numbers) 2 no 400 Rs/day 800
Contingencies ,T and P
3 lumpsum Rs 100
etc
Total in Rs
5780

water charges @1% of the Total in Rs


57.80

Profit and overhead @10% of the total in Rs


578
GRAND TOTAL in Rs
6415.80

Rate per sqm=grand total/10 in Rs


641.58

14. WALL PAINTING with plastic emulsion paint of approved brand

Take 100 Sqm


RATE ANALYSIS FOR WALL PAINTING WITH PLASTIC EMULSION PAINT OF APPROVED
BRAND
TAKE 100 Sqm
Sl.no particulars Quantity Unit Rate Unit Amount
1 MATERIALS
Plastic emulsion Paint 12 litres 350 Rs/litre 4200
Materials for filling
holes,Brushes,putty,sand lumpsum 250
paper
2 LABOURS
Painter 5.50 no 600 Rs/day 3300
Helper 5.5 no 500 Rs/day 2750

3 Contingencies ,T and P etc Lumpsum 100

Total 10600
water charges @1% of the Total
Rs 106.00

Profit and overhead @10% of the total


Rs 1060

GRAND TOTAL
Rs 11766.00

Rate per sqm=grand total/100


Rs 117.66
15.Painting two coats for new wood work or iron work

Take 100 sqm

RATE ANALYSIS FOR PAINTING TWO COATS FOR NEW WOOD WORK OR IRON WORK
TAKE 100 Sqm
Sl.no particulars Quantity unit Rate unit Amount
PRIMER COAT
1 MATERIALS
a Primer coat
Primer 5.5 litres 150 Rs/litre 825
Brushes,putty,sand paper lumpsum 100
2 LABOURS
Painter 2.50 no 600 Rs/day 1500
Helper 2.5 no 500 Rs/day 1250

TOP COAT
1 MATERIALS
Enamel paint 12 litres 350 Rs/day 4200
Brushes,putty,sand paper lumpsum lumpsum 100
2 LABOURS
Painter 5.50 600 Rs/day 3300
Helper 5.5 500 2750
Contingencies ,T and P
3 lumpsum lumpsum 100
etc
Total 14125
water charges @1% of the Total
141.25

Profit and overhead @10% of the total


1412.5

GRAND TOTAL
Rs 15678.75

Rate per sqm=grand total/100


Rs 156.79
16.PAINTING ONE COAT FOR PAINTED OLD WOOD WORK OR IRON WORK

TAKE 100 SqM.

RATE ANALYSIS FOR PAINTED OLD WOOD WORK OR IRON WORK


TAKE 100 Sqm
Sl.no particulars Quantity Unit Rate Unit Amount
1 MATERIALS
Paint 7.5 litres 200 Rs/litre 1500
Materials for filling
holes,Brushes,putty,sand lumpsum 200
paper
2 LABOURS
Painter 3.50 no 600 Rs/day 2100
Helper 3.5 no 500 Rs/day 1750

3 Contingencies ,T and P etc lumpsum 100

Total Rs 5650
water charges @1% of the Total
Rs 56.50

Profit and overhead @10% of the total


Rs 565

GRAND TOTAL
Rs 6271.50

Rate per sqm=grand total/100


Rs 62.72

You might also like