Rate Analysis Notes 3
Rate Analysis Notes 3
1.EARTHWORK EXCAVATION
EARTWORK in excavation in trenches for foundation not exceeding 1.5m width including
dressing of sides and ramming of bottoms, lift upto 1.5m and lead upto 30 m
Take 10 cum
2.EARTHWORK IN FILLING
Filling available excavated earth in trenches,plinth sides of foundation in layers not exceeding 20 cm in
depth, consolidating layer by layer ramming and watering, lead upto 50m and lift upto 1.50m
Take 10 cum
Take 10 cum,
COARSE AGGREGATE
CEMENT CALCULATION SAND CALCULATION CALCULATION
(1/13)X15.4=1.2 Cum (4/13)X15.4=4.8Cum (8/13)X15.4=9.6Cum
1.2/0.0347=34.60
BAGS
Total 46610
water charges @1% of the Total 466.1
Profit and overhead @10% of the total 4661
GrandTotal 51737.1
Rate per cum=Grand Total/10 5173.71
4.SIZE STONE MASONRY IN CM 1:6
Take 10 cum
Sl.no Particulars Quantity unit Rate unit Amount
MATERIALS
Stone including bond stone
12.5 cum 600 Rs/cum 7500
1 and wastage in cum
Sand (Coarse) in cum 3.6 Cum 1800 Rs/cum 6480
Cement in bags 17.29 Bags 450 Rs/bags 7780.5
LABOURS
Head mason( numbers) 0.50 No 600 Rs/day 300
2
Mason (numbers) 10 No 500 Rs/day 5000
Mazdoor (numbers) 19 no 450 Rs/day 8550
Total 35810.5
water charges @1% of the Total 358.105
Profit and overhead @10% of the total 3581.05
Grand Total 39749.655
Rate per cum=Grand Total/10 3974.97
Take 10 cum
10/(0.1x0.1x0.2)=5000
Number of bricks with mortar= no
quantity of mortar=Quantity with mortar- Quantity without mortar
10 -(5000x0.09x0.09x0.19)=2.30 cum
ADD 15% extra for wastage and frog filling=2.3+(15/100)x2.3 =2.64 cum
for dry mix add 1/3 rd extra=2.64+(1/3)x2.64=3.50 cum
Volume of mortar(dry ) per 10 cum=3.50 cum
CEMENT SAND
CALCULATION CALCULATION
(1/7)X3.50=0.50 Cum (6/7)X3.50=3.0Cum
0.50/0.0347=14.40
BAGS
Total 63880
water charges @1% of the Total 638.8
Profit and overhead @10% of the total 6388
GrandTotal Rs 70906.8
Rate per cum=Grand Total/10 (Rs) 7090.68
6.RATE ANALYSIS- Hallow block masonry in cement mortar 1:4
LABOURS
Head mason( numbers) 0.20 no 600 Rs/day 120
2
Mason (numbers) 1.5 no 500 Rs/day 750
Mazdoor (numbers) 2.5 no 450 Rs/day 1125
Total in Rs 8570
water charges @1% of the Total in Rs 85.7
Profit and overhead @10% of the total in Rs 857
Grand Total in Rs 9512.7
Rate per sqm=Grand Total/10 951.27
7.RATE ANALYSIS- Solid block masonry in cement mortar 1:4
LABOURS
Head mason( numbers) 0.20 no 600 Rs/day 120
2
Mason (numbers) 2 no 500 Rs/day 1000
Mazdoor (numbers) 3 no 450 Rs/day 1350
Total in Rs 10715
water charges @1% of the Total in Rs 107.15
Profit and overhead @10% of the total in Rs 1071.5
GrandTotal in Rs 11893.65
Rate per sqm=Grand Total/10 1189.37
TAKE 100 Sq m
Volume of dry mortar=0.63 cum
Cement=(1/4)x0.63=0.157 cubic meters
cement in bags=(0.157/0.0347)=4.52 bags
sand=(3/4)x0.63=0.47 cum
RATE ANALYSIS- POINTING IN CM 1:3 ON BRICK WALLS
Take 100 Sqm
Sl.no particulars Quantity unit Rate unit
Amount
MATERIALS
Cement in bags 4.52 bags 450 Rs/bag 2034
Sand (Medium) in cum 0.47 cum 1800 Rs/cum 846
1
LABOURS
Head mason( numbers) 0.50 no 600 Rs/day 300
2
Mason (numbers) 10 no 500 Rs/day 5000
Mazdoor (numbers) 10 no 450 Rs/day 4500
Total in Rs 12880
water charges @1% of the Total in Rs 128.8
Profit and overhead @10% of the total in Rs 1288
GrandTotal in Rs 14296.8
Rate per sqm =Grand total /10 142.97
ROUNDED OFF 143.00
0.95/0.0347=27.40 BAGS
RATE ANALYSIS FOR CEMENT CONCRETE FLOORING 75MM THICK 1:4:8
Sl.no particulars Quantity Unit Rate Unit Amount
1 MATERIALS
Cement in bags 27.4 bags 450 Rs/bag 12330
Sand (Coarse) in cum 3.8 cum 1800 Rs/cum 6840
coarse aggregate 20mm
7.6 cum 1350 Rs/cum 10260
down
2 LABOURS
Head mason ( numbers) 0.50 no 600 Rs/day 300
Mason ( numbers) 10 no 500 Rs/day 5000
Mazdoor ( numbers) 20 no 400 Rs/day 8000
Total 42930
water charges @1% of the Total
429.30
Profit and overhead @10% of the total
4293
GRAND TOTAL
47652.30
Rate per sqm=grand total/100
476.52
10. RATE ANALYSIS FOR GRANITE STONE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4
Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum
CEMENT SAND
CALCULATION CALCULATION Granite slab Calculation
Total 27688.8
water charges @1% of the Total
276.89
GRAND TOTAL
30734.57
Rate per sqm=grand total/10
3073.46
11. RATE ANALYSIS FOR VITRIFIED TILE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4
Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum
CEMENT SAND
CALCULATION CALCULATION Vitrified tiles Calculation
(1/5)X0.32= 0.064 Cum (4/5)X12.375=0.256Cum Vitrified tiles required=10 sqm
0.064/0.0347=1.84 BAGS add for wastage and breakage=2.5%
10+(2.5/100)*10=10.25 sqm
RATE ANALYSIS FOR VITRIFIED TILE FLOORING WITH 20mm THICK LAID ON BASE OF
20mm CEMENT MORTAR 1:4
Sl.no particulars Quantity unit Rate unit Amount
1 MATERIALS
Vitrified tiles 60x60 cm 10.25 Sqm 800 Rs/Sqm 8200
carriage of slabs lumpsum 100
Sand (medium) in cum 0.256 Cum 1800 Rs/cum 460.8
Cement in bags 1.84 bags 450 Rs/bag 828
Cement for slurry
0.66 bags 450 Rs/bag 297
@3.3kg/sqm
2 LABOURS
Head mason ( numbers) 0.25 no 600 Rs/day 150
Mason ( numbers) 2 no 500 Rs/day 1000
Mazdoor ( numbers) 2 no 400 Rs/day 800
Total in Rs
12135.8
GRAND TOTAL in Rs
13470.74
12. RATE ANALYSIS FOR MARBLE STONE FLOORING WITH 20mm THICK LAID ON
BASE OF 20mm CEMENT MORTAR 1:4
Take 10 Sqm
VOLUME OF MORTAR= 0.020X10=0.2 CUM
ADD 20% EXTRA FOR FILLING DEPRESSION,WASTAGE
ETC=0.2+(20/100)X0.2=0.24CUM
for dry mix add 1/3 rd extra=0.24+(1/3)X0.24=0.32cum
CEMENT SAND
CALCULATION CALCULATION Marble slab Calculation
Total in Rs
24988.8
Total 10600
water charges @1% of the Total
Rs 106.00
GRAND TOTAL
Rs 11766.00
RATE ANALYSIS FOR PAINTING TWO COATS FOR NEW WOOD WORK OR IRON WORK
TAKE 100 Sqm
Sl.no particulars Quantity unit Rate unit Amount
PRIMER COAT
1 MATERIALS
a Primer coat
Primer 5.5 litres 150 Rs/litre 825
Brushes,putty,sand paper lumpsum 100
2 LABOURS
Painter 2.50 no 600 Rs/day 1500
Helper 2.5 no 500 Rs/day 1250
TOP COAT
1 MATERIALS
Enamel paint 12 litres 350 Rs/day 4200
Brushes,putty,sand paper lumpsum lumpsum 100
2 LABOURS
Painter 5.50 600 Rs/day 3300
Helper 5.5 500 2750
Contingencies ,T and P
3 lumpsum lumpsum 100
etc
Total 14125
water charges @1% of the Total
141.25
GRAND TOTAL
Rs 15678.75
Total Rs 5650
water charges @1% of the Total
Rs 56.50
GRAND TOTAL
Rs 6271.50