AIQS Questions 06032022-1
AIQS Questions 06032022-1
2. According to many conditions of contract, variation clause gives a amount limitation to vary the
contract. What you know about that? Assume a variation you evaluate increases the contract price
more than 20%, What would be the repercussion would you face due to this?
3. What is VE?
5. What would you recommend as a experienced practitioner, in the event a detailed Design
estimate deviate significantly from the preliminary estimate?
6. As you are familiar with Construction change management, can you explain your procedure of
evaluation of a variation? What is the relationship with a site instruction and a variation?
8. Can you explain the instance you need to derive rates from the first principle, in an evaluation of
a variation?
9. Can you nominate the Nominated subcontractor in the middle of the project?
Siva
15. How do you pay preliminaries in interim certificates? Would it be based on time or work done?
Pratha
21. What can be done in case tender price is higher than the Engineer’s estimate?
23. Can you explain different kind of procumbent methods you are familiar with? And in your
opinion what would be your advised to client, if he need a straight foreword warehouse complex
to be done in fast track basis?
24. Can you explain the general structure of a payment certificate? How do you deduct advance
payment?
25. Tender Qualification – Tender’s alternative proposal
27. What are the cost planning methods you are familiar with? If you are given a scope to give a
rough order estimate for a hospital project, assume still no drawings developed and no idea of
area etc. What would be the best practice used by consultants?
Panojan
33. What is Provisional Sum? For undefined design/scope, to allocate preliminary and time
36. According to your experience in Cost Planning, what would be the accuracy level of Concept
Design Cost Estimate? And how it would be reduced until DD Cost estimate? At DD estimate
what is the form generally used?
37. As a consultant QS senior Level, if you are given a task as a cost controller, how do you propose
to discharge your duties? What methods you adopt?
38. What are the conditions of Contract you are familiar with? According to that is it mandatory for
the contractor to give notice for claims?
Sarujan
42. Why it is very important to have the procurement strategy in place to a success of a project?
43. Why the employer paying AP, MOS etc. to the Contractor?
Siva
45. You are familiar with Lump Sum Contracts? Why there is a very detailed BOQ in all Lump Sum
Contracts in Qatar? In your opinion?
Pratha
46. You are visiting to site, another Engineer without PPE, what will u do?
47. Your client has very basic information? What is estimation technique?