Exercise 1:: 1,1 100 1,1 220 1,1 +46× 1,1 1 0,1×1,1 161,614 Milusd
Exercise 1:: 1,1 100 1,1 220 1,1 +46× 1,1 1 0,1×1,1 161,614 Milusd
FA (mil USD) 0 1 2 3 4 … 20
Revenue 80 80 80
Investment cost 100 100 100
Equipment cost 220
Operation cost 34 34 34
Net benefit -100 -100 -100 -220 46 46 46
17
100 100 220 1,1 −1
NPV =−100− − − + 46 × =−161,614 milUSD
1,1 1,12 1,13 0,1 ×1,1
20
2. Make the economic cash flow of the project, calculate the value of NPV, BCR and IRR. Surpose
all costs of the project are funded by the government budget. The project's social discount rate is
5%.
Exercise 2:
The provincial Department of Transport is considering a new road with the following initial capital
costs that including:
- 10 tons of construction materials. The price per ton is VND 15 billion, including a tax of 1 billion
VND. The local government subsidizes 0.5 billion VND/1 ton (surpose inputs have the replacement
effect)
- 2 million working hours with the hourly wage is 15,000 VND. Employees with 60% are
unemployed with the value of rest is 8000 VND/hour.
- Imported construction machine (that is not produced domestically) at a cost of 22 billion VND, of
which 10% tariff is included.
During the operation phase, the annual operating cost is 150 million VND/year.
If this 20 km long road is built, traffic accident is estimated to be reduced by 10 billion VND/year.
Saving costs for vehicles for one trip is 37,000 VND/km and the traffic capaccity is 8500
vehicles/year.
The project also reduces the annual environmental treatment cost from 300 million VND to 100
million VND/year.
Assume that the long-run inflation is 3%/year.
The yield on government bonds is 8%, the risk is 2%, and the income tax is 20%.
On the view of cost benefit analysis, should the project be invested if the life of the project is 10
years?
1. Initial capital cost
- Materials cost = 10x15 = 150 bil VND
- Labor cost = 2x(0,4x15+0,6x8) = 21,6 bil VND
- Machine cost = 22/1,1 = 20 bil VND
Total capital cost = 191,6 bil VND
2. Annual perating cost = 0,15 bil VND
3. Benefit
- Accident lowering = 10 bil VND
- Saving costs = 37000x20x8500 = 6,29 bil VND
- Reduce environmental treatment cost = (300 – 100) mil = 0,2 bil VND
Total benefit = 16,49 bil VND
Net benefit = 16,49 – 0,15 = 16,34 bil VND
Exercise 3:
Consider the set of NPV values of a mining company with 2 variables:
100 (low) 90
120 (the best) 115 110 96
- At the best land restoration cost: Calculate the elasticity of NPV to output from the best to low,
from the best to high
- At the best mining output: Calculate the elasticity of NPV to cost from the best to low, from the
best to high
Make your recommendation
a. At the best land restoration cost:
( 110−90 ) :110
The elasticity of NPV ¿ output ¿ the best ¿ low= =1,091
( 120−100 ) :120
( 110−130 ) :110
The elasticity of NPV ¿ output ¿ the best ¿ high= =0,727
( 120−150 ) :120
b. At the best mining output
( 110−115 ) :110
The elasticity of NPV ¿ cost ¿ the best ¿ low= =−0,159
( 7−5 ) :7
( 110−96 ) : 110
The elasticity of NPV ¿ cost ¿ the best ¿ high= =−0,445
( 7−9 ) :7