SC-12 Safety Code For Demolition of Building and Structure
SC-12 Safety Code For Demolition of Building and Structure
1.0 Objective:
To provide a safe Procedure for demolition of building and structures.
Associated Hazards are Collapse of structure, falling material, flying material,
impact/hit by material, collapse of equipment/machinery, noise, entrapment, fall
from height, electrocution, Fire, explosion etc.
2.0 Scope:
This standard is applicable to all large, medium and small-scale steel
manufacturing units.
3.0 Procedure:
Page 1 of 40
Doc. No: SC/12, Rev no: 00
ii) Adequate lateral support for adjoining structures should be provided. Before the
existing lateral support is disturbed, provision should be made for the erection of
temporary supports, which will need to be checked for effectiveness as the
demolition proceeds.
iii) It is also important that other buildings in and around the demolition site are not
adversely affected by vibration or concussion during the demolition process.
iv) No part of the demolition process should cause flooding or water penetration to
any adjoining building.
Essential Services
i) One of the most important elements of pre-demolition planning is the location
and disconnection of all essential services.
iii) In each case, any utility agency involved should be notified in advance and its
approval or services, if necessary, obtained. Any service retained for the
demolition work should be adequately protected as required by the relevant
authority.
Page 2 of 40
Doc. No: SC/12, Rev no: 00
viii) The equipment to be used for the work, including the size, type, position and
coverage of proposed demolition crane(s) should be indicated on a site plan,
locations such as unloading points and storage areas (if any) should be shown.
ix) The need to ensure that the ground is compacted to any design specifications to
enable plant to be moved and used safely at the workplace.
x) The proposed methods for handling heavy, bulky or awkward components.
xi) The need for specific lifting arrangements to be detailed to facilitate safe lifting.
xii) The handling, lifting, storing, stacking and transportation of components,
depending on their size, shape and weight
xiii) The provision of safe access and safe working areas.
i) Use of Scaffolding
ii) Use of Portable scaffoldings.
iii) Use of construction staircases & platforms during demolition as specified in safety
standard for working at height.
iv) Use of existing staircases & plat-forms of existing buildings after inspection &
ascertaining their suitability and their strengthening or replacement as required.
v) Use of appropriate & adequate man lifters (Genie or other equivalent man lifters)
vi) Use of appropriate & adequate Mobile Elevating Work Platform (MEWP)like
scissors type MEWP etc.
vii) Use of appropriate and adequate Electrical Winches with dog lock or safe break
system.
viii) Use of hanging scaffolds / cradles / cages.
ix) Use of rope access system with specialized workforce.
x) Use of appropriate & adequate Rope ladders with fall arrestor.
xi) Use of mechanized climber system supplied by authentic manufactures & its
Installation & operation as per OEM (Operational equipment manual).
xii) Other methods based on study, preparation of schemes for the adopted method
& their approval from competent Engineer of the executing department.
It must include the process to be used and persons who should be involved in
developing the new plan.
Page 3 of 40
Doc. No: SC/12, Rev no: 00
i) Equipment – All Tools and Tackles should have valid Test Certificate as per
statuary norm for all the equipment engaged for demolition job.
ii) Personal Protective equipment (PPE’S) to be used.
iii) Risk to health and adequate control measures to be taken in case of use of
Hazardous substances e.g. Hydraulic Oil, Diesel, Gases (oxygen/LPG etc.).
iv) Clear Responsibility to be given: Executing Authority to be designated.
v) Technical content of the job should be taken care.
vi) Follow the approved dismantling sequence.
vii) Disposal of demolished debris and scrap as per instruction of the Executing
Authority.
viii)Safety risk assessment of the work to be done.
Risk Assessment:
Hazards Risk to People Control Measures
Employ good housekeeping, remove
Company Employee materials from the workplace progressively.
Slips, Trips Contractor’s
At the end of the shift remove all tools etc.
&Falls employee,
Site Visitors and inspect all areas to ensure they are left
in a safe condition.
Company Employee Ensure a safe system of work is in place
Cuts, grazes Contractor’s and is explained to all operatives and carry
&Abrasions employee, out toolbox talks on any hazardous areas
Site Visitors etc.
Company Employee Flagmen and workers of the executing
Falling Contractor’s contractor are to be positioned a safe
material employee, distance away during demolition
Site Visitors
All known live services are to be identified
Company Employee and protected during the demolition. Access
Services Contractor’s to be maintained to the gas valve at the
employee, Site
Visitors front of the main building in the event of an
emergency.
Should manual handling be required
Company Employee minimum of two persons needed for heavier
Manual Contractor’s items, adopt correct handling techniques.
Handling employee, Site Only lift what can easily be managed.
Visitors Access each item prior to lift and clear
transit route to ensure safe passage.
Company Employee As soon as is Reasonably practicable,
Fire
Contractor’s remove waste from site to prevent a build-
Page 4 of 40
Doc. No: SC/12, Rev no: 00
ix) Any device or equipment such as scaffolds, ladders, derricks, hoists, etc., used
about demolition work shall be constructed, installed, inspected, maintained and
operated in accordance with the regulations governing the construction,
installation, inspection, maintenance and operation of such device or equipment.
The cage, hoists, tackles shall not be overloaded. Safety appliances (Helmet,
Shoes, Goggles, Gloves, Safety Belts and others as may be required) shall be
used.
xi) When employees are required to work within a structure to be demolished which
has been damaged by fire, flood, explosion, or other cause, the walls or floor shall
be shored or braced.
xii) Ensure POSITIVE ISOLATION of the building / structure from electrical or any
other energy source. All electric, gas, water, steam, sewer, and other service lines
shall be shut off,
Capped, or otherwise controlled, outside the building line before demolition work is
started. In each case, any utility service which is involved shall be notified in
advance.
xiii) All the mains and meters of the building shall be removed or protected from
danger. If it is necessary to maintain any power, water or other utilities during
demolition, such lines shall be temporarily relocated, as necessary, and protected.
xiv) All the roads and open areas adjacent to the work site shall be protected and
Caution Boards/Danger Sign in local language, Hindi and English shall be
displayed at prominent places. Unauthorized entry to the building under demolition
shall be efficiently controlled.
Page 6 of 40
Doc. No: SC/12, Rev no: 00
xv) Provisions shall be made for at least two independent exits for escape of workmen
during any emergency.
xvi) During nights, red lights or luminescent danger sign shall be placed on or around
all the barricades.
xvii) Following work permits shall be obtained before commencement of job from the
working department.
a) Power cutting clearance.
b) Work permit for Gas cutting and welding and working at height as may be
applicable.
c) Work permit for working in gaseous areas. (If applicable).
d) Any other clearance as found appropriate by executing department in
consultation with the concerned department of Organisation.
xiii)Walkways and passageways shall be provided for the use of the workmen and
they will be strictly instructed to use these only. All such walkways and
passageways shall be kept adequately lighted, free from debris and other
materials.
xv) Before demolition buildings with over hangs, chajjas, etc. they should be properly
supported and demolished first before demolishing superstructure of the building.
xvi)While breaking roof slabs, workmen shall not be allowed to sit on the same floor,
but on a separate platform, supported independently. In case they have to work
from the same floor, independent life line to fasten their lanyard shall be provided.
Lifeline should not be connected with the portion to be dismantled.
xviii) Protruding nails in boards, planks and timber shall be withdrawn, driven in or bent
over as soon as the same is removed from the structure being demolished.
To manage the risk of unplanned collapses, the condition of roofs, walls and floors of
the building should be assessed by a competent person before commencing
demolition work. Where concrete members are being demolished manually, the
reinforcement shall not be cut while breaking of the concrete is in progress. Where
pre-and post-tension demolition work is undertaken competent person, advice should
besought as to demolition sequence. Areas where debris will fall should be
barricaded off and signs erected to prevent persons from entering before demolition
starts.
All powered mobile plant used for demolition work must be fitted with a suitable
combination of operator protective devices. Operator protective structures should be
designed to the appropriate standard that eliminates or minimizes the risk, so far as
is reasonably practicable, of operator injury due to:
i) roll over and consequent cabin impact damage
ii) objects falling on or over the cabin
iii) objects penetrating the cabin
iv) Hazardous noise.
Page 8 of 40
Doc. No: SC/12, Rev no: 00
ROOF TOP
De
si
gn
De
GROUND FLOOR m
oli
sh
FOUNDATION / SUBSTRUCTURE
3.4.2. Before demolition work is started, glazed sash, glazed doors and windows, all
fragile and loose fixtures shall be removed. All loose plaster shall be stripped off
throughout the entire building.
3.4.3. All exterior wall openings, which extend down to floor level shall be barricaded
to height of not less than one meter above the floor level. This provision shall not
Page 9 of 40
Doc. No: SC/12, Rev no: 00
apply to a storey after structural demolition has been started for the ground level
floor.
3.4.4. All floor openings and shafts not used for material chutes shall be closed and
be enclosed with guard rails and toe boards.
Page 10 of 40
Doc. No: SC/12, Rev no: 00
i) Stairs and stair railings, passageways and ladders shall be left in place as long as
possible.
ii) All stairs, passageways and ladders to be used by workmen during the process of
demolition
iii) Shall be maintained in a safe condition.
iv) Ladders or their side rails shall extend not less than 1.0 m above the floor or
platform to which such ladder gives access.
v) All ladders shall be secured / fastened against slipping / turning out at the bottom
as well as top end.
Page 11 of 40
Doc. No: SC/12, Rev no: 00
The joints in this type of structure do not normally provide continuity. The stability of
this type of structure relies on other elements such as stairs, lift shafts, shear walls or
other framed structures.
Page 12 of 40
Doc. No: SC/12, Rev no: 00
Page 13 of 40
Doc. No: SC/12, Rev no: 00
parapet along its outer edge of at least 1 m height. The parapet shall be
constructed of the same specifications as the platform.
iv) Catch platforms can be constructed of material other than wood also provided
such material is of equal strength.
v) Catch platform shall be capable of sustaining a live load of not less than 610 kg
per square meter.
vi) The outriggers shall be of ample strength and shall not be spaced more than 3 m
apart.
vii) Materials shall not be dumped on catch platform nor shall such catch platform be
used for the storage of materials.
i) Before attempting the actual removal, a careful study should be made to find out
the strength of the asbestos sheet. In any case, workmen should not be allowed
to walk and stand on AC sheets.
ii) A firm ladder should be provided for workmen to climb to the roof.
iii) A cat ladder which can be kept on the sloping roof (supported from the ridge)
should be used for the workmen to stand and remove the sheets.
iv) Only experienced workmen should be engaged. They will never step on the
unsupported portion of the sheets.
v) Caution boards should be fixed at the ladders leading to the roof top, DANGER:
DONOT GO ON THE ROOF TOP WITHOUT PERMISSION.
i) Before commencing demolition, the nature and condition of the concrete, the
condition and position of reinforcement and the possibility of lack of continuity of
reinforcement should be ascertained.
ii) Attention should be paid to the principles of the structural design to determine
which parts of the structure depend on each other to maintain overall stability.
iii) Demolition should be commenced by removing partitions and external non-load
bearing cladding. It should be noted that in some buildings the frame may rely on
the panel walls for stability.
iv) Where hand demolition methods are to be used, the following procedures should
be used.
i) For beams, a supporting rope should be attached to the beam. Then the concrete
should be removed from both ends by pneumatic drill and the reinforcement
Page 16 of 40
Doc. No: SC/12, Rev no: 00
exposed. The reinforcement should then be cut in such a way as to allow the
beam to be lowered under control to the floor.
Page 17 of 40
Doc. No: SC/12, Rev no: 00
During the demolition of tanks and pipelines, the following precautions should be
taken:
Page 18 of 40
Doc. No: SC/12, Rev no: 00
iii) Any container which has held flammable or combustible substances should be
considered unsafe until confirmed otherwise by a competent person
Page 19 of 40
Doc. No: SC/12, Rev no: 00
3.17.1 Attachment-1
Practice for Sequential Dismantling of Steel Structure:
TABLEOFCONTENTS
SECTION – 1 : PRECAUTIONS TO BE TAKEN BEFORE DISMANTLING OF
STEELSTRUCTURES.
SECTION – 2 : GENERAL SEQUENCE OF DISMANTLING STRUCTURAL
BUILDING.
SECTION – 3 : GENERAL SEQUENCE OF DISMANTLING OPEN GANTRY
SECTION – 4 : GENERAL SEQUENCE OF DISMANTLING CONVEYOR GALLERY.
SECTION – 5 : GENERAL SEQUENCE OF DISMANTLING CRANE
SECTION - 6 : GENERAL SEQUENCE OF DISMANTLING OF TRESTLES &
TOWERS.
SKETCH – 1 : DETAIL OF SHED TYPE BUILDING (SHEET 1 OF 2)
SKETCH – 2 : DETAIL OF SHED TYPE BUILDING (SHEET 2 OF 2)
SKETCH – 3 : DETAIL OF OPEN GANTRY.
SKETCH – 4 : DETAIL OF CONVEYOR GALLERY (SHEET 1 OF 2)
SKETCH – 5 : DETAIL OF CONVEYOR GALLERY (SHEET 2 OF 2)
SKETCH –6 : DETAILS OF TRESTLES /TOWERS ( SHEET 1 OF 2)
SKETCH -7 : DETAILS OF TRESTLES / TOWERS ( SHEET 2 OF 2)
Page 20 of 40
Doc. No: SC/12, Rev no: 00
3.17.2 SECTION – 1
PRECAUTIONS TO BE TAKEN BEFORE DISMANTLING OF STEEL
STRUCTURALS.
Before any dismantling job is taken up, the Contractor shall officially identify a
“Dismantling Leader “by a letter to Organisation authorities. The Dismantling Leader
must have adequate knowledge and experience of structural dismantling and shall
be responsible for safe dismantling work. Apart from other safety precautions, he will
take care of the points, mentioned below:
i) Ensure that the structural to be dismantled are not supporting any other
structures. In case, it is supporting, the other structures should be suitably
supported before dismantling work is taken up.
ii) All service lines like Oxygen, Nitrogen, Compressed air, CO gas, BF gas, LD gas
carrying lines supported on the structural intended to be dismantled, should be re-
routed. In case, it is decided that structural will be partially dismantled to retain
support of the service lines, adequate safety precautions should be taken while
dismantling, to avoid fire hazards and puncturing of service lines.
iii) All electrical lines supported on structural intended to be dismantled, should be
disconnected from source of power, and dismantling should start only after
necessary clearance to that effect is obtained, in writing from concerned Electrical
Power/Operation Department. Ensure Positive Isolation for the entire building.
iv) The condition of structural intended to be dismantled shall be inspected for
corrosion, to ensure that it does not collapse while dismantling.
v) All tools and tackles used for dismantling should be in sound condition and
adequately strong. Lifting tools and tackles used should have test certificate,
issued by competent authority.
vi) Cranes, used for dismantling, should have necessary fitness certificate. The driver
shall also have necessary health and eye test certificate.
vii) If derrick is used in place of crane, it should be properly guyed for stability and
should have specified lifting capacity. In no case, the specified lifting capacity
should be exceeded.
viii)All persons engaged in dismantling work should be given safety training and they
should ensure use of safety appliances. If the dismantling is near any gas line,
then the workmen engaged should be given gas safety training.
ix) While working at height, safety belt should be used. While climbing up or down,
snatch ropes or fall arrestor should be used. A wire rope may be tied at two rigid
points to fasten the life line of safety belt, where other tying members are not
available.
x) All dismantled material should be lowered down on ground in controlled way.
xi) Job safety analysis should be done before dismantling.
xii) Dismantling sequence should be prepared before dismantling.
Page 21 of 40
Doc. No: SC/12, Rev no: 00
3.17.3 SECTION – 2
GENERAL SEQUENCE OF DISMANTLING STRUCTURAL BUILDING:
The sequence of dismantling should be such that the structure does not lose its
stability at any time.
i) Ensure that all precautions, as indicated in Section – 1, are taken.
ii) Remove all roof and side sheeting’s. Purlins should not be dismantled at this
stage, but side girts can be dismantled.
iii) If necessary, all purlins between monitor trusses can be removed and monitor
truss dismantled without damaging the roof truss.
iv) Start dismantling from gable end, and work towards any intermediate braced bay.
This braced bay is to be dismantled last.
v) Remove gable steel work except roof truss.
vi) Remove alternate purlins between end roof truss and adjacent truss.
vii) Hold the roof truss to be dismantled with crane or derrick and remove balance
purlins, rafter bracings, bottom chord bracings and struts, if any, between this
truss and adjacent truss.
viii)Gas cut the truss members along the face of column on both sides, and lower the
roof truss.
ix) Sequence vii to viii to be repeated for dismantling subsequent roof trusses.
x) While removing the last two trusses, both the trusses should be held with crane
before repeating sequence vii and viii.
xi) Dismantle gantry girder, surge platform, surge girder and outrigger girder
between end column intended to be dismantled and adjacent column.
xii) Remove longitudinal bracings and struts if any, between end column and
adjacent column. Also remove any other structural or platform. Dismantle end
column.
xiii) Repeat sequence xi and xii for subsequent columns on both lines.
xiv)For multi storeyed building dismantle all floor beams and floor plates except the
beams connecting the building column. These framing beams and parts of
columns shall be dismantled floor wise, starting from top, maintaining the stability
of structures at all time.
xv) For bin house, dismantle all bin plates except the girder or bin plates connecting
the building columns.
xvi)Dismantle longitudinal bracings, struts, floor beams, bin plates etc., between end
columns and adjacent columns on both rows. Also dismantle beam, bin plates etc.
across the building for end column.
xvii) Dismantle end columns. For long columns, columns can be dismantled in pieces
starting from top.
xviii) Repeat sequence xvi and xvii for subsequent columns on both sides.
xix) Refer to sketch sheet no. 1 for identification of shed type building components.
xx) If during dismantling, a situation is faced, where the remaining component to be
removed is likely to lose its stability due to removal of other connecting members,
the component must be stabilized with guy ropes.
Page 22 of 40
Doc. No: SC/12, Rev no: 00
Based on the above sequence of dismantling, for hazardous jobs, the components
like columns, bracings, girders etc. may be given identifying marking at site to avoid
wrong member cutting.
3.17.4 SECTION – 3
GENERAL SEQUENCE OF DISMANTLING OPEN GANTRY.
i) Ensure that all precautions, as indicated in Section – 1 are taken.
ii) Start dismantling from the end, where column bracing is not provided.
iii) Hold the top of end column/A-frame using a crane/derrick.
iv) Remove gantry girder, surge girder/platform, outrigger girder and any other
structural between end column/frame and adjoining column/frame.
v) Dismantle end frame/column.
vi) Repeat sequence 3 to 5 for all other frames/columns except for last two braced
columns/frames.
vii) For last two braced columns/frames, cut and remove all structural except bracing
between the columns/frames.
viii)Cut and remove top portion of bracing strut and diagonals along with top portion
of columns/frames.
ix) Repeat sequence 8 for next lower portion of bracings and columns/frames, till
complete column/frame is removed.
x) Refer to Sketch Sheet No. 3 for identification of structural parts of open gantry.
3.17.5 SECTION – 4:
GENERAL SEQUENCE OF DISMANTLING CONVEYOR GALLERY:
i) Ensure that all precautions as indicated in Section – 1 are taken.
ii) Remove all mechanical parts like conveyor belt, idlers, deck plates, stringers etc.
before removing the gallery structurals. Remove all cables, pipes and cable trays.
iii) Remove all roof and side sheeting including purlins and side runners.
iv) Provide guy steel ropes on both sides of the trestles in the longitudinal direction
tied with firm structure / foundation at base.
v) Hold the portion of conveyor gallery between two supports with crane/derrick.
Depending on situation, slinging positions, crane position etc. must be planned
and documented. Slings should be tied only at node points.
vi) Gas cut the end connections without damaging the supports and conveyor
gallery. Top end connections to be gas cut.
vii) Lower the conveyor gallery to ground.
viii)After lowering on ground, the structures can be removed in small pieces by gas
cutting.
ix) Refer Sketch Sheet No. 4 and 5 for identification of structural components of
conveyor gallery.
Page 23 of 40
Doc. No: SC/12, Rev no: 00
3.17.6 SECTION – 5
GENERAL SEQUENCE OF DISMANTLING EOT CRANE:
i) Ensure that all precautions as given in Section – 1 are taken.
ii) Dismantle all gear boxes, motors, electrical panels etc. and bring them down to
ground.
iii) Dismantle Trolley structural and hook block using crane/derrick/Repair trolley.
Trolley assembly may be dismantled as a unit if crane or repair trolley capacity is
available.
iv) Dismantle driver’s cabin using crane/derrick.
v) Tie end carriage with existing gantry girder and building structural.
vi) Dismantle bridge girders one by one using crane/derrick.
3.18 SECTION -6
GENERAL SEQUENCE OF DISMANTLIN OF TRESTLES / TOWERS:
i) Ensure that all precautions as given in section -1 are taken.
ii) Provide the steel guy ropes / steel structural stays on both sides longitudinally &
across the trestle/tower based on height, ground condition and type of trestles &
tower.
iii) The steel structural inclined stays shall start from minimum one third heights of
the trestle / tower from the ground. The adequate sized steel stays to be at a
slope between Min 1:4 and Mac. 45degree. the base of the stay to be anchored
on a levelled firm ground with adequate size base plate and H D Bolts. The stays
shall be on both sides of the tower/ trestle. Size of the stay to be ascertained
based on size of the trestle & Tower. Guy rope on both sides in across direction
to be provided as per site requirements and trestle/ tower condition.
iv) Adequate sized steel rope can also be used both side longitudinally as well as
across as per requirements and site layout and conditions. The base of the steel
rope to be anchored to firm structure / object.
v) The trestle/ tower to be preferably hold with adequate capacity crane and can be
dismantled in single length or multiple short lengths depending upon the height &
size of the trestle & towers. If dismantling by crane is not feasible, then manual
dismantling in pieces starting from top is to be taken up.
vi) Before lifting with crane, it is to be ensured that the cut portion detached
completely.
vii) The stays top must be at minimum height of H/3 of the tower at each stage of
dismantling.
NOTE: All above sections are the recommended practice. Site & structure
specific dismantling sequences of steel structures are to be prepared at site
based on above.
Page 24 of 40
Doc. No: SC/12, Rev no: 00
Page 25 of 40
Doc. No: SC/12, Rev no: 00
Page 26 of 40
Doc. No: SC/12, Rev no: 00
Page 27 of 40
Doc. No: SC/12, Rev no: 00
Page 28 of 40
Doc. No: SC/12, Rev no: 00
Page 29 of 40
Doc. No: SC/12, Rev no: 00
Page 30 of 40
Doc. No: SC/12, Rev no: 00
Page 31 of 40
Doc. No: SC/12, Rev no: 00
3.19 Attachment -2
Recommended Practice for Dismantling and Rearranging (D&R) facilities:
The following practices are strongly recommended for all “large” D&R projects. Sites
electing not to adopt any of these practices must have an alternative better practice that
is at least equal to those not adopted.
1. Equipment Identification
i) Use different colour paints or stickers on equipment, piping, or electrical to be
removed to distinguish it from equipment, piping, or electrical to remain.
ii) Identify both what is to be removed and what is to remain.
iii) Use different colours to identify the presence of asbestos, lead, etc. and non-
hazardous coatings.
iv) Use unique colour paint, stickers, or tags to identify the exact location of subsequent
breaks being performed by the contractor personnel.
v) Signs or posters describing the identification method including examples of the actual
colours or tags must be posted in strategic locations throughout the work area
vi) The integrity of the markings should be reviewed throughout the life of the project.
4. Electrical
i) All person’s employees performing demolition & rearranging of electrical conduit,
cables or conductors must be trained
Page 32 of 40
Doc. No: SC/12, Rev no: 00
ii) Provide general “electrical safety awareness training” to D&R contractor personnel
not engaged in electrical demolition & rearranging.
iii) Identification and marking of circuits must be performed by personnel with long-term
site experience.
iv) Remove all fuses from motor control centres.
v) If lighting panels must remain active, determine how energized electrical panels and
circuits will be clearly identified and the location communicated to the D&R contractor.
6. Building Isolation
i) Define and identify any process and/or service piping systems that must be relocated
to isolate the building.
ii) Define and identify any electrical services that must be relocated to isolate the
building.
iii) Use a service of person with long-term site-specific experience to physically break all
electrical, utility, and process piping. Ensure POSITIVE ISOLATION of the equipment
/ system from electrical source or any other energy source.
Page 33 of 40
Doc. No: SC/12, Rev no: 00
Allowances may have to be added to the weights due to residual product, catalyst,
and/or caking if the equipment could not be adequately cleaned.
xix) Weights of platforms, piping, etc., that will remain on the equipment when it is
being dismantled must also be determined.
xx) Verify contractor employees involved in any form of rigging have been adequately
trained or perform on-site rigging training.
xxi) Designate specific operators of freight elevators and provide training.
xxii) All load-conveying equipment must be labelled with its capacity. Skilled and
qualified operators on all demolition equipment.
xxiii) Equipment operator training verified through review of training documentation.
Utilize mechanical equipment for lifting.
xxiv) Overhead hoisting equipment and supports left in the area must be inspected by
the job supervisor of the contractor.
xxv) Only steel chains and slings shall be used for securing / supporting heavy loads
and use of Manila ropes, Fibres ropes in rigging activities shall be strictly prohibited
for heavy loads greater than 70 Kg.
xxvi) Limit manual material handling and lifting to a maximum of two persons; no
manual material handling or lifting with more than two individuals is allowed.
8. Staffing:
i) Contractor with safety knowledge, safety resources dedicated to the D&R project to
be utilized.
ii) Contractor is to utilize experienced operators, mechanics, and resident contractor
employees for decommissioning and decontamination.
iii) Contractor is to utilize experienced operators and mechanics.
iv) Contractor is to engage qualified electrical resource dedicated to follow electrical D&R
fieldwork.
v) Contractor-provided safety supervisor to be assigned to continuously monitor
contractors with inexperienced workers regardless of size of workforce.
vi) Require contractor to submit proposed workforce makeup, i.e., experienced workers
vs. inexperienced workers, and worker to supervisor ratio.
9. Communications
Communicate safety expectations and requirements clearly and early in the bidding
process. Hold weekly / daily safety/schedule meeting between concerned department
and operating area personnel and D&R contractor project management and field
supervisors and safety supervisors.
Page 34 of 40
Doc. No: SC/12, Rev no: 00
13. Miscellaneous
i) The written Job Plan must detail that the work must be stopped, re-evaluated, and a
new plan developed if any condition changes. It must include the process to be used
and persons who must be involved in developing the new plan.
ii) Develop a project-specific disciplinary process that is focused on the contractor
supervision’s accountability for the actions of their workers rather than one that
focuses solely on the workers.
iii) Use task-specific work and hot work permits.
iv) D&R is truly “reverse construction.” The planning of the work must take this into
account. As an example, small piping, lighting, instruments, steam and trap
Page 35 of 40
Doc. No: SC/12, Rev no: 00
manifolds, etc. should be removed first around major pieces of equipment prior to
their dismantling.
3.20 Attachment -3
RECOMMENDED PLANNING CHECKLIST FOR D&R FACILITIES
1. Intent: This checklist is to be used during the planning of D&R. It list items that should
be evaluated before D&R on facilities, buildings, or equipment takes place.
2. Regulations
All regulations which govern D&R activity must be complied with.
3. Pre-Assessment
Prior to conducting a field assessment of the area, equipment, or facilities to be D &R’d,
a knowledgeable/competent person should conduct a pre-assessment to establish
background information and scope of D&R.
i) Identify the products produced at the facility or in the equipment being D &R’d and
their respective health and physical hazards.
ii) What chemicals were used in the process?
iii) How and when the facility or equipment was idled, mothballed, or decontaminated?
iv) Is the area or equipment considered “clean,” i.e., are there any concerns with re-use
of scrapped material?
v) Where will scrap be processed?
vi) What methods/tests will be needed to determine the state of decontamination?
vii) What materials can be recycled?
viii)Where and on what equipment will torch cutting be allowed or will cold cutting be
required throughout?
ix) Will the entire facility or area be D&R’d or are only certain pieces of equipment within
the area being removed?
x) Is equipment (vessels, etc.) to be removed whole or cut up in pieces?
xi) Know weights of equipment, vessels, etc.
xii) What method will be used to distinguish between equipment to be removed and
equipment to remain?
xiii)Will any safety or control feature be temporarily or permanently disabled? How will
this affect operating equipment?
xiv) What is the current operating/energized state of the area?
xv) How will the equipment be, or is it, isolated from pressurized or energized sources
(electrical, service, process, etc.)?
xvi) Have equipment changes or modifications occurred that are not reflected in the
system documentation?
Page 36 of 40
Doc. No: SC/12, Rev no: 00
xvii) What is the proximity of area, equipment, or facilities being D&R’d to occupied
area / operational areas?
xviii) Will access into the area by those not involved in the D&R be required? If so, what
routes will they use and what protections will be required for them?
xix) Will confined space entry be necessary?
xx) Is there a possibility of ground or soil contamination?
xxi) What is the degree of unknown underground services? Will extensive hand
excavation be required?
xxii) Do pits that have been opened by removal of equipment contain residual
lubricants, finish paints or other flammable liquids?
xxiii) Do pits need to be cleaned prior to burning and welding around or above them?
xxiv) Are there any biological hazards associated with residual materials contained in
pits? (Consult the site industrial hygienist.)
4. Assessment
Conduct a field assessment of the area, equipment, or facility to be D&R’d. (photograph
areas adjacent to the area, equipment, or facilities (if any) being D&R’d to be used to
identify damage done to them in the event it occurs during D&R.)
6. Structural Related
i) Condition of the structure; has it been idled for an extended period of time and
deteriorated?
Page 37 of 40
Doc. No: SC/12, Rev no: 00
ii) What temporary or permanent bracing will be required for equipment or structures
being removed or remaining?
iii) Overhead electrical conductors in close proximity?
iv) Proximity to other structures not being dismantled or rearranged.
v) Type of structure (steel, masonry, combination)?
vi) Composition and condition of roof (built-up, precast concrete, transit, brittle)?
vii) Allowable roof and floor loads?
viii)Existing elevator capacities?
ix) Location and conditions of any confined spaces?
x) Basement and sumps involved?
xi) Presence and location of under piping and electrical feeders?
xii) Coatings, insulation, mastics (flammability, lead, asbestos)?
xiii)Do combustible metals such as titanium with an oxide coating glass / glass – wools
exist?
xiv) Vessels empty or do they contain material which adds weight?
7. Planning
Once the pre-assessment and field assessment have been conducted, a preliminary plan
must be developed. The plan should be laid out step-by-step and encompass every
activity of the project with attention to the safety of D&R crew and other employees.
8. Employee Safety
i) PPE requirements.
ii) Fall prevention and fall protection.
iii) Hygiene and decontamination needs.
iv) Special training needs
v) Special medical surveillance required.
vi) Special clothing.
vii) First-aid plan and clinic location and injury treatment/management process.
9. Miscellaneous Planning
i) What governmental permits (federal, state, and local) will be required and who will
obtain them?
ii) Spill-handling procedure, emergency response, and clean up.
iii) Does the area have adequate ventilation should a spill occur?
iv) Will temporary containment enclosures create a negative impact on natural ventilation
and cause a build-up of flammable vapours?
v) Fire and explosion response.
vi) How will fire watch personnel be identified (orange vest, red hardhat, etc.)?
vii) Traffic control and routing of equipment and personnel.
viii)Perimeter barricading.
Page 38 of 40
Doc. No: SC/12, Rev no: 00
ix) What analytical test will be required and who will perform them (lead, cadmium,
asbestos, organic residue)?
x) Heavy equipment inspection and operating requirements. Auditing of work (method,
by whom, frequency).
xi) Incident (safety, health, and environmental) reporting needs, by whom to whom).
xii) Lay down area location.
12.0 Training:
Employees involved in the dismantling shall receive training from a competent person &
qualified person. The purpose of the training is to recognize any hazards associated with
the work in question. Training shall consist of:
i) the nature of height work hazards
ii) the correct procedures for dismantling
iii) the design criteria, maximum intended load carrying capacity, and intended
use of the work platform, lifting tackles, access system, climbing system, winch
system, lifting system, man lifter system, various anchorages, lifelines,
procedures for height work etc.
Page 39 of 40
Doc. No: SC/12, Rev no: 00
Employees who perform work while at height shall be trained by a qualified person so
they can recognize hazards associated with the type of scaffolding, access, lift system
etc. being used and understand the procedures to control those hazards. Training will
cover the following topics as necessary:
i) The nature of any electrical hazards, fall hazards, and falling object hazards in
the work area.
ii) The correct procedures for dealing with electrical hazards and for erecting,
maintaining, and disassembling the fall protection systems and falling object
protection systems used
iii) The proper use of the height facilities and the proper handling of materials on
the system being used.
The maximum intended load and the load carrying capacities of the supports system,
work platform, cages, cradles, access system, ropes, man-lifters, winches, life lines ,
anchorages etc.
13.0 Records:
i) Record of work permit for demolition work shall be kept for at least one year.
ii) Records for incident/accident are to be maintained at the department. At least for
five years.
iii) Records of tests for the equipment, slings, cage, rope ladders etc being used for
demolition shall be kept for the period of work.
Reference:
1. IPSS: 1-11-031-17
2. TSL Safety Standard, SS/ENGG-04
Page 40 of 40