0% found this document useful (0 votes)
20 views2 pages

Para 3 4

1) After losing power from the earthquake, operators at Fukushima Daiichi Nuclear Power Plant were unsure if safety systems were still functioning to cool the reactor cores. They declared a nuclear emergency for Units 1 and 2 due to the inability to inject water into the emergency core cooling system. 2) Over 10 hours later, the safety relief valve for Unit 5 automatically opened multiple times to release pressure buildup in the reactor vessel as the core continued to heat up without cooling. Water injection eventually began for Unit 1 around 0400 on March 12. 3) Radiation levels near the plant increased, indicating a possible radioactive leak from Unit 1's primary containment system. The evacuation zone was expanded to 10km due to high pressure

Uploaded by

Onee chan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views2 pages

Para 3 4

1) After losing power from the earthquake, operators at Fukushima Daiichi Nuclear Power Plant were unsure if safety systems were still functioning to cool the reactor cores. They declared a nuclear emergency for Units 1 and 2 due to the inability to inject water into the emergency core cooling system. 2) Over 10 hours later, the safety relief valve for Unit 5 automatically opened multiple times to release pressure buildup in the reactor vessel as the core continued to heat up without cooling. Water injection eventually began for Unit 1 around 0400 on March 12. 3) Radiation levels near the plant increased, indicating a possible radioactive leak from Unit 1's primary containment system. The evacuation zone was expanded to 10km due to high pressure

Uploaded by

Onee chan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

As these electrical powers were lost in Units 1 and 2, the drivers had no way of knowing whether the

safety systems were running duly or indeed if they were operating at each, to maintain the core safety
functions. Since factory drivers were unfit to identify the water position in the reactor or the working
state of the cooling systems, they claimed that the core cooling introductory safety function had been
lost. Accordingly, the on- point exigency response centre notified off- point organisations, TEPCO
Headquarters, and applicable government authorities that nuclear exigency circumstances was for Units
1 and 2 due to the incapability of water injection into the exigency core cooling system as described in
regulations. At 1818 on 11 March, about 2 and a half hours after the loss of suggestions, some of the
status lights for those faucets were discovered to be functional, attesting that the control faucets were
closed. The drivers tried to start the insulation condenser by opening the faucets. Still, the insulation
condenser didn't operate, suggesting that the AC powered insulation faucets inside the primary
constraint vessel were closed. Therefore, the introductory safety function of core cooling at Unit 1 was
lost when the insulation condenser was turned off by the drivers right before the riffle, and the Unit 1
core hotted up in response. The Government of Japan declared a nuclear exigency at 1903 on 11 March,
following multitudinous reports from the on- point exigency response centre on the condition of Unit 1
and the other units, and with the Prime Minister's authorization. In Unit 2, which likewise demanded
any signals of core cooling system performance, along with core pressure and temperature, the drivers
assumed the worst-case script that the reactor core insulation cooling system wasn't functional and the
Unit 2 core was hotting up. At 2101, the on- point exigency response centre notified government officers
that the Unit 2 core, which had no cooling, was anticipated to be exposed at about 2140. Following this
prognostic, the Prime Minister, as Director-General of the Nuclear Emergency Response Headquarters,
issued an order at 2123 on 11 March for the evacuation of the citizens within 3 km of the installation
and harbors within 3 to 10 km.

10 hours after the station knockout, the Unit 5 safety relief stopcock automatically opened for the first
time roughly because the reactor pressure reached its opening set value, at 0140 on 12 March. Because
the Unit 5 reactor had continued to toast up in the absence of heat junking styles, the stopcock
automatically opened and closed numerous times to keep the pressure within the design range. Latterly,
on March 12, at 0606, roughly 14 and a half hours after the station's knockout, the head articulation
snoot was ever opened and remained open to depressurize the water- filled reactor vessel. Likewise,
about 16 and a half hours after the station knockout, the power connection between Unit 5 and the
functional exigency diesel creator in Unit 6 was completed, allowing some AC power to be handed to
Unit 5 outfit, similar as the pumps and faucets needed for reactor heat evacuation. Meanwhile, the
pressure in the Unit 1 reactor fell downward enough to allow for alternate water input. The infusion of
fresh water from the fire machines into the Unit 1 reactor to restore core cooling began around 0400 on
March 12. Water injection from a single one-tonne truck continued periodically for nearly 5 and a half
hours, with the vehicle returning to the brackish tank to be replenished regularly. Unit 1's constraint
pressure was measured at 0419 on March 12 and revealed that pressure had reduced since the former
test without any homemade hindrance and an established articulation channel. Also, radiation situations
observed at the main entrance shortly after increased. These might be signs of an unbridled radioactive
leak from the primary constraint system. The deteriorating radioactive conditions at the point, along
with the high constraint pressure in Unit 1, forced the government to increase the evacuation zone to 10
kilometres at 0544 on March 12. After roughly 11 hours of water injection into the Unit 1 core, the fresh
water in the fire protection water tank was nearly exhausted and the operation was terminated at 1453
on March 12. The Point Supervisor also decided to fit seawater into Unit 1 from the Unit 3 outcome
stopcock hole, which had accumulated seawater following the riffle. In lower than a half-hour, the
arrangements for seawater injection were finished.

You might also like