0% found this document useful (0 votes)
53 views

Estimation Lalitha Residence

This document provides an estimation for construction work for Mrs. Lalitha's residence. It includes 14 items with quantities, rates, and amounts for earth work, concrete work, masonry, plastering, painting, electrical, plumbing, tiles, doors and other construction materials. The total estimation for the building is Rs. 29,87,440 which includes a 10% contractor profit and 10% GST amounting to Rs. 4,97,906.

Uploaded by

shankar sks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views

Estimation Lalitha Residence

This document provides an estimation for construction work for Mrs. Lalitha's residence. It includes 14 items with quantities, rates, and amounts for earth work, concrete work, masonry, plastering, painting, electrical, plumbing, tiles, doors and other construction materials. The total estimation for the building is Rs. 29,87,440 which includes a 10% contractor profit and 10% GST amounting to Rs. 4,97,906.

Uploaded by

shankar sks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

ESTIMATION FOR MRS.

LALITHA RESIDENCE

S.NO ITEMS QUANTITY RATE AMOUNT

1. Earth Work 1720 cft 7.00 12,040

2. Grade beam I 220.5 cft 250.00 55,125

3. Plinth beam 132.75 cft 250.00 33,187

4. Gravel filling 5060 cft 6.00 30,360

5. Flooring R.C.C 422.52 cft 150.00 63,378


(1:3:5)

6. Foundation P.C.C 212.62 cft 120.00 25,515


(1:5:10)

7. Foundation R.C.C 257.25 cft 150.00 38,588


(1:1.5:3)

8. Column R.C.C 216 cft 250.00 54,000


(1:1.5:3)

9. Grade beam II 205.5 cft 250.00 51,375

10. Roof R.C.C 640.18 cft 250.00 cft 1,60,045


(1:1.5:3)

11. Lintel beam 32.375 cft 300.00 cft 11,812.5


S.NO ITEMS QUANTITY RATE AMOUNT

1. Brick work 2,004.12 cft 170.00 3,40,700

2. Plastering

i Inner plastering 3530 sqft 35.00 1,23,550

ii Outer plastering 2511.61 sqft 50.00 1,25,585

iii Ceiling plastering 1064.3 sqft 40.00 42,572


(Roof inner)

3. Painting

Patti two coat

i Inner coat 4595 sqft 11.00 50,545

ii Primer one coat

Inner coat 4595 sqft 11.00 50,545

Outer coat 2511.61 sqft 18.00 45,208.98

iii Emulsion two coat 7106.6 sqft 28.00 1,98,990


S.NO ITEMS QUANTITY RATE AMOUNT

1. Plumbing 1064.37 sqft 155.00 1,64,980

2. Electrical work 1064.37 sqft 155.00 1,64,980

3. Tile 1277.24 sqft 120.00 1,53,268.8

4. Sunshade 20 sqft 110.00 2,200

5. Surkhi with tiles 1064.37 sqft 110.00 1,17,085

6. Doors (Delivery at site)

D 54 sqft 50.00 2,700

D1 84 sqft 50.00 4,200

D2 52.5 sqft 50.00 2,625

W 72 sqft 70.00 5,040

W1 36 sqft 70.00 2,520

V 12 sqft 70.00 840


S.NO ITEMS QUANTITY RATE AMOUNT

1. Steel 5706 kg 57.50 3,28,095

2. Steel labour 5706 kg 16.00 91,296

TOTAL 24,89,534

CONTRACTOR PROFIT 10% + GST 10% 4,97,906


(Total 20%)

TOTAL ESTIMATION OF THE BUILDING 29,87,440