Appendix - A: Suggested Toolbox Talk
Appendix - A: Suggested Toolbox Talk
Tool Box Talks are comprised of various talks of which the titles are listed on the following Tool Box
96
APPENDIX - C
Training Matrix
Form No: HFC/HSE/TM/27
HILLS AND FORT CONSTRUCTION LLC Rev: 01
Date 15/02/2019
Yearly Training Matrix
Year: 2021
General Mgr.
Procurement
Construction
Office based
HSE Officers
Project Engr
Project Mgr.
Operatives
office staff
Contractor
Operators
workers
Riggers
Normal
visitors
QA/QC
Sub-
Mgr.
staff
PRO
Foreman
Sl Course Title Trainer
No
1.
Project HSE Induction HSE Team YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES
2.PPE & PFPE HSE Team NO NO NO NO YES NO N0 NO NO NO YES NO YES YES YES YES NO
3.Permit To Work HSE Team NO NO NO YES YES YES NO NO NO NO YES YES YES YES YES YES NO
4.
Incident Investigation HSE team NO NO NO YES YES YES YES NO YES NO NO YES YES NO NO NO NO
5.Scaffolding Third Party NO NO NO YES YES YES NO NO NO NO NO NO NO NO NO YES NO
6.Lifting Operation Third Party NO NO NO NO YES YES NO NO NO NO NO NO NO NO NO NO NO
7.
Emergency Procedure HSE Team YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES
8. HSE Team/
Heat Stress NO YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES YES
Third party
9.
Method Statements CM/PM/QA/QC NO NO NO YES YES YES NO NO YES NO NO NO YES NO NO NO NO
10.
Legal & Other
HSE Team YES YES YES YES YES YES YES YES YES YES NO NO YES NO NO NO NO
Requirements
11.
Banksman,
Third party NO NO NO NO YES NO NO NO NO NO NO NO NO YES NO YES NO
Slingers/Signalers
12.
MEWP Third party NO NO NO NO NO NO NO NO NO NO YES NO YES NO YES NO NO
13.
Power tools safety
Third party NO NO NO NO YES NO NO NO NO NO YES NO YES NO NO YES NO
Note: As per the project requirement; if any additional training requires will conduct as per the project training Matrix.
Title 2
HFC HR& Admin Complied implemented as per requirements.
Employment of workers and youth and women labor
HFC HR &Admin, GM,
Title 3
Director construction Complied implemented as per requirements.
Employment contracts, records & wages
Management
Title 4
HFC HR& Admin Complied implemented as per requirements.
Working hours & leaves
Title 5 HFC HR& Admin/HOD/ Complied implemented as per requirements.
Safety, protection health and social care of workers Project Manager HSEMS implemented by all sites and facilities.
Title 6
Disciplinary rules HFC HR& Admin Complied implemented as per requirements
Title 7
Termination of Employment Contract and End HFC HR& Admin Complied. Implemented as per requirements
of Service Gratuity
Title 8
Compensations for Occupational Injuries and HFC HR& Admin Complied implemented as per requirements
Diseases
UAE MINISTERIAL ORDER NO. 32 OF YEAR 1982 ON DETERMINING PREVENTION MEANS AND MEASURES TO PROTECT
2.0
WORKERS FROM WORK HAZARDS
Article 1
• Preventive measures for Protection of workers Director construction HSE team& Fire warden appointed, HIRA (incl.
during work hours and against fire risks (shall Management / Project Yes, being complied. Fire risk assessment) carried out, inspections,
also adopt preventive measures specified by Manager/ HOD trainings and mock drills conducted.
the Ministry of Labor and Social Affairs).
Page -3
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Page -4
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article 16
Project Manager /HOD Not applicable
• Safe usage of steam boilers
Article 17 followed as per site HSE rules and regulations.
Project Manager /HOD/
• Shall not allow worker to enter in to work site Yes, being done. Part of HSE induction for sites.
HSE Team
without proper PPE
Page -5
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article 23
• Competent labour inspector shall take
samples of the materials used in the
manufacturing process during the official
Labour Inspector Not applicable
working hours when conducted inside the
establishment as specified by provision of
article (175) of law no (8)1980 concerning
the regulation of labour relations.
Article 24 Authorities informed along with clients/ consultant
• Notify the competent labour department on Project Manager /HOD Yes, being complained as per requirement.
accidents that occur during work hours
Page -6
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
3.0 UAE MINISTERIAL DECREE NO. 401 OF 2015 CONCERNING THE DETERMINATION OF MIDDAY WORKING HOURS
The ministerial order gives a clear and minimum General Manager/ HR & as per requirements.
requirement to be followed in the summer working Admin/ Director project Yes, being complied Evidenced in Summer work schedule and Circular.
hours. The mid-day break timings of 12:30pm to management/HSE
3:00pm must be followed by all employers. Manager/ Project
manager /HOD
3.0 Occupational Health & Environmental Control HR & Admin / as per requirements. Records maintained by
• Ministerial Resolution No. (37/2) for 1982 Project Manager / administration department.
Yes, being complied
regarding the level of medical attention the Male Nurse /
employer is obliged to provide to his workers. First Aider / HSE Team
Project Manager/Center as per requirements and as identified from risk
4.0 Personal Protective Equipment storekeeper/procurement Yes, being complied assessment. Records of issue available with
dept/ HSE dept. stores department.
5.0 Fire Protection and Prevention as per requirements and cross checked by HSE
Team.
• As per Civil Defense Guidelines HODs / Project Manager Yes, being complied
• UAE Fire and Life Safety code of practice
as per requirements, implemented by Project
6.0 Signs, Signals and Barricades Project Manager/ HODs Yes, being complied Manager as per the control measures mentioned
in risk assessment.
as per requirements. Regular awareness trainings
Store Head / Project are given by HSE Team.
7.0 Material Handling and Storage Yes, being complied
Manager / HOD
Page -7
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
as per requirements.
Project Manager / Yes, being complied Regular electrical inspection is carried out by a
16.0 Electrical Hazards
Electrical PRM / HODs competent electrician
as per requirements and implemented by Project
17.0 Control of Hazardous Energy (Lockout/ Tag Yes, being complied Manager and HOD.
Project Manager / HODs
out) Taken care by plant engineer in all plants.
Page -8
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
DUBAI ADMINISTRATIVE DECISION NO. (30) OF 2007 ENACTING THE EXECUTIVE REGULATIONS IMPLEMENTING LOCAL
5.0
ORDER NO. (11) OF 2003 CONCERNING PUBLIC HEALTH AND COMMUNITY SAFETY IN THE EMIRATE OF DUBAI
ENACTING THE EXECUTIVE REGULATIONS IMPLEMENTING LOCAL
Dubai Municipality For Information.
ORDER NO. (11) OF 2003
6.0 LOCAL ORDER NO. (11) OF 2003 CONCERNING PUBLIC HEALTH AND COMMUNITY SAFETY IN THE EMIRATE OF DUBAI
Article 1
• This order shall be called “Local Order No. (11) Of 2003 Concerning
Public Health and Community Safety in the Emirate of Dubai”, and Dubai Municipality For Information.
shall come into effect as of the date of publication in the Official
Gazette.
Article 2
• In applying the provisions of this Order, the following terms and words
Dubai Municipality For Information.
shall, unless otherwise required by the context, have the meanings set
forth against each of them respectively
Page -9
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
ensure clearance of the Building and its attachments from such Pests on control
the completion of the construction works.
• Without prejudice to the responsibility of the Owner for the rest of the parts
of the building which continues even after the completion of construction
works, the Occupant shall be responsible for controlling Public Health Pests
in the part of the building occupied by the Occupant.
Article 53
• The term “Health and Safety of Buildings” shall mean fulfillment (by the
building) of the health and environmental conditions and safety
Yes, being complied as per requirements and
requirements which ensures protection of health and safety of its residents
Project Manager/ implemented by Project Manager and section
and maintains its interior and surrounding environments (all in good
Section Head heads.
conditions), including the building materials, potable water systems,
sewerage systems, air-conditioning systems, elevators, emergency exists,
firefighting systems, indoor air quality and common service facilities.
Article 54
• With respect to the health and safety of Buildings in the Emirate, the
relevant requirements on health and environmental conditions issued and
Dubai Municipality For Information.
adopted by the Municipality shall apply.
The Executive Regulation of this Order shall specify the relevant conditions
and requirements thereof.
Article 56
• The Occupant shall maintain healthy indoor air quality of the building
through: (a) provision of proper exhaust system for gaseous emissions
and fumes contaminating the indoor air, and for the heat resulting from Project Manager/ Yes, being complied as per requirements and
various activities and facilities in the building; (b) ventilation of indoor HODs implemented by Project Manager/ HODs.
air in conformance to the approved Indoor Air Quality standards; (c)
keeping the quality of indoor air within the acceptable levels and to
implement measures to control the indoor air quality in such levels.
Article 58
• The Occupant shall undertake regular maintenance of the building in such
a manner that would ensure the building’s continuous compliance to the Project Manager/ Yes, being complied as per requirements and
conditions and requirements of public health and community safety. HODs implemented by Project Manager/ HODs
• The Executive Regulation shall specify the rules and standards necessary
for conducting the required regular maintenance works.
Article 59
• It is prohibited to throw, deposit, drain, release, or discharge any waste Project Manager/
material in public places or dispose of it in places other than those HODs
designated for such purpose or in any manner other than those approved Yes, being complied and implemented by Project
by the Competent Department. In particular, the following are prohibited: Manager. Regular awareness is given to all
Page -11
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
(1) Throwing out of any waste from vehicles on public roads. employees. The same is cross checked by
(2) Dropping of any solid or liquid materials from vehicles on public roads, inspections and audits.
and to carry or transport dispersible materials in open vehicle without
cover.
(3) Urinating or to defecate in places other than those designated for such
purpose, and to spit in public places
(4) Spitting residues of “Paan” or throwing of its wastes in public places.
(5) Disposal of building and demolition waste, trade waste or any refuse
material arising from industrial activities, factories or commercial
establishments into places other than approved disposal sites.
(6) Disposal of wastewater in places other than those designated for such
purpose by the Concerned Regulatory Unit.
(7) Disposal of used oil in sewerage networks, soak away pits, or by spilling it
on pavements or roads.
(8) Discharging of oil or any wastes from marine vessels or ships into the
seawater, on beaches, into Creek water or any seaports.
(9) Dumping of trees and parks residues in places other than those sites
designated by the Competent Department for such purpose.
(10) Spill or spraying of wastewater resulting from washing of cars or vehicles
at places other than those sites designated by the Competent Department
for such purpose.
(11) Condensate water dripping from air-conditioning units or leaking of
any water on public places, pavement or roads.
(12) Disposal of wastes by open burning.
Article 60
• Goods, materials, or any other objects shall not be placed, stored, or
left hanging at public places, house roofs or balconies in a manner that Yes, being complied as per requirements and
Project Manager/
can obstruct traffic or pedestrians, or disfigure the public view or the implemented by Project Manager and section
HODs
aesthetic appeal of the Emirate, or the beauty of building façade and head as per applicability.
balconies or that would violate regulations on the protection of public
health, safety and environment.
Article 61
• The Occupant of the building shall:
(1) Provide a room or dedicated place in or within the building and the
Yes, being complied as per requirements and
same shall be equipped with containers for holding and safe storage Project Manager/
implemented by Project Manager and section
of wastes in accordance with the conditions and specifications HODs
head.
specified by the Competent Department. The provision shall include a
contrivance to facilitate transport of wastes from the building into the
waste room, moving of the containers outside for emptying (of its
Page -12
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
waste load) and to replace it back into position. The Occupant shall
also carry out regular maintenance thereof.
(2) Manage and keep the building interior clean in accordance with the
rules on public health and environment protection.
Article 62
• Private establishments, companies, commercial premises, residential
complex, and hotel establishments shall comply with the following :
(1) Provision of containers for the safe storage of wastes generated from
their activities in accordance to the terms, conditions and standards
Yes, being complied as per requirements and
prescribed by the Competent Department.
Project Manager/ implemented by Project Manager. Annual waste
(2) Changing of waste containers whenever the volume of wastes generated
HODs management contract with approved party
at their premises or activities exceeds the capacity of the available
available.
containers, or when the generated wastes pose a threat on public health
and environment.
(3) Implementation of a program for ensuring cleanliness and safety of the
public and private parking areas directly serving their buildings or
premises.
Article 63
• A person can be allowed to carry on the activity of collecting, storing,
Yes, being complied as per requirements and
transporting, reuse, recycling, or treatment of wastes produced by
Project Manager/ implemented by Project Manager and section
others or to provide cleaning services at public places only upon
HODs head where applicable. In some cases, we
obtaining a valid permit issued by the Competent Department and (he)
engage approved third party.
complies with all the standards and conditions specified by the
Competent Department for such activities.
Article 64
• No person is allowed to:
(1) Place any material that may cause damage to the waste container or
waste transporting vehicle, or that which constitutes hazard on the
Project Manager/ Yes, being complied as per requirements and
health and safety of persons working in the collection, transportation
HODs implemented by Project Manager
and disposal of wastes.
(2) Move or change the location of any waste container provided by Dubai
Municipality or rummaging with the contents of such container without
prior approval from the Competent Department.
Article 65
• As determined by the Competent Department, any person whose Yes, being complied as per requirements and
Project Manager/
activity is found producing significant quantity of wastes shall be implemented by Project Manager and HODs.
HODs
required to implement a program to reduce the quantity of or to recycle Waste management plan in place.
such wastes.
Page -13
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article 86
• Without prejudice to any more severe penalty provided by any other
legislation, any person who violates any provision of this Order, its
Executive Regulation, and subsequent resolutions or directive issued
under this Order, shall be charged a fine of not less than Dirhams one
Dubai Municipality For Information.
hundred (AED 100) and not more than Dirhams five hundred thousand
(AED 500,000). This penalty may be doubled on repeating the violation
within one year from the date of committing the same violation,
provided that the amount of penalty does not exceed the maximum
amount stipulated in this Order.
Page -15
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
8.0 UAE FEDERAL LAW NO 24 OF 1999 CONCERNING PROTECTION AND DEVELOPMENT OF THE ENVIRONMENT
Responsible Person Compliance Status and Remarks
SECTION 1 – ENVIRONMENTAL IMPACT OF Project Manager/
1 Yes, aspect impact assessment done for the activities in all sites.
ESTABLISHMENTS HODs
SECTION 2 – THE ENVIRONMENT AND Project Manager/ Yes, included in the corporate and site HSE objectives and targets
2
SUSTAINABLE DEVELOPMENT HODs and is being practiced.
Project Manager/
SECTION 3 – ENVIRONMENTAL MONITORING
3 HODs & HSE Yes, being carried out wherever required as per client requirements.
Engineer/ Officer
Project Manager/
SECTION 4 – EMERGENCY PLANS FOR
4 HODs & HSE Yes, plans are in place.
COMBATING ENVIRONMENTAL DISASTERS
Engineer/ Officer
CHAPTER 2 – PROTECTION OF WATER
ENVIRONMENT Project Manager/
5 Yes, complied as per aspect/impacts identified.
SECTION 1 THE SCOPE OF ENVIRONMENTAL HODs
PROTECTION
SECTION 2 – PROTECTION OF THE MARINE
ENVIRONMENT Project Manager/
6 Not applicable
PART (I) POLLUTION FROM MARINE MEANS OF HODs
TRANSPORTATION
Yes, controlled and measures taken (e.g. Concrete wash done only
PART (II) POLLUTION FROM LAND SOURCES Project Manager/
7 in designated area). Spillage contained in primary and secondary
HODs
bunds and correct waste disposal procedure followed).
SECTION 3 – PROTECTION OF DRINKING AND Project Manager/ Yes, ensured by controlling spillage and ensuring correct waste
8
UNDERGROUND WATER HODs disposal procedures
Yes, controlled and measures taken (e.g. Concrete wash done only
Project Manager/
9 CHAPTER 3 – SOIL PROTECTION in designated area). Spillage Contained in primary and secondary
HODs
bunds and correct waste disposal procedure followed)
CHAPTER IV – PROTECTION OF AIR FROM Project Manager/ Yes, emissions controlled by regular maintenance as per
10
POLLUTION HODs operation manual and manufacturer’s instructions.
CHAPTER V – HANDLING OF HAZARDOUS Yes, done as per MSDS and COSHH assessment results.
Project Manager/
11 SUBSTANCES AND WASTES AND MEDICAL Hazardous waste disposal as per authorized agency approved by
HODs
WASTES DM/SM/AM. Medical waste not applicable.
Page -16
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
8.0 UAE FEDERAL LAW NO 24 OF 1999 CONCERNING PROTECTION AND DEVELOPMENT OF THE ENVIRONMENT
Responsible Person Compliance Status and Remarks
Project Manager/ Protected, cordoned and the entry is restricted. Regularly inspected.
12 CHAPTER VI - NATURAL RESERVES
HODs Vegetation is relocated and replaced once the activities are
completed.
UAE CABINET DECREE NO 12 OF 2006 REGARDING THE REGULATION CONCERNING THE PROTECTION OF AIR FROM
9.0
POLLUTION
Responsible
Compliance Status and Remarks
Person
Yes, noise emissions controlled by regular maintenance as per
Annex (6) – Allowable Limits for Noise Level in Project Manager/ operation manual and manufacturer’s instructions
1
Different Areas HODs
Document/Record – Noise Monitoring Record
10.0 Local Order No 61 of 1991 on the Environment Protection Regulations in the Emirates of Dubai
Responsible
Compliance Status and Remarks
Person
Yes, controlled and measures taken (e.g., Concrete wash done only
in designated area). Spillage contained in primary and secondary
Chapter 1 – Regulations on the reuse and land disposal of Project Manager/ bunds and correct waste disposal procedure followed). No sludge is
1.
wastewater and sludge HODs disposed on land.
Document/Record – Env Inspection Report
Yes, control measures are taken at project/facilities and no
Chapter 2 – Regulations concerning the disposal of Project Manager/ discharges are allowed into marine waters.
2.
wastewater into marine waters HODs
Document/Record – Env Inspection Report
Page -17
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
11.0 Local Order No 7 of 2002 – Management of Waste Disposal Sites in The Emirate of Dubai
Responsible
Compliance Status and Remarks
Person
Yes, the waste generated will only be disposed at DM approved sites.
Project Manager/
Section 3 – Key Policies – Waste Disposal only at DM Document/Record – Waste Hauler approved by DM, Waste
1. HODs/ Plant In-
approved sites Management Certificate, Waste Management Contract and Env.
Charge
Report
Yes, all the waste generated in the Emirate of Dubai project/facilities
will be disposed in Dubai. No waste will be transported outside
Project Manager/
Emirate of Dubai unless approved by DM
2.` Section 4.2 – Import, Export and Disposal of Waste - HODs/ plant In-
Document/Record – Waste Hauler approved by DM, Waste
charges
Management Certificate, Waste Management Contract and Env.
Report
Page -18
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Yes, only waste hauler trucks that are approved by DM will enter DM
Section 4.3 – Prohibitions – Unauthorized entry into DM Project Manager/ disposal sites.
3.
disposal site HODs Record/Document – RASID online system and DM approved list of
trucks
Page -19
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
13.0 DUBAI MUNICIPALITY – PUBLIC HEALTH & SAFETY DEPARTMENT TECHNICAL GUIDELINES, CIRCULARS & BULLETINS
1 TG & Circular No. Title (Technical Guideline) Responsible Person Compliance Status and Remarks
Yes, being complied, implemented by
Industrial Compressed Gas Project Manager/ HODs/
2 DM-PH&SD-P4-TG01 Workshop & Project Managers. Details
Cylinders Plant In-charge
available with workshop.
Audit Manager / HSE
3 DM-PH&SD-P4-TG02 Safety Audit Reports Yes, being complied as per requirements
manager
Yes, being complied and implemented by
Project Manager and section head. Heat stress
4 DM-PH&SD-GU38-MHSW2 Management of Heat Stress at Work Project Manager/ HODs
management plan implanted and followed up by
HSE dept.
Guidelines for Confined Spaces Yes, being complied and implemented by
5 DM-PH&SD-GU39-CSE2
Entry
Project Manager/ HODs
Project Manager. PTW system implemented.
Yes, being complied and implemented by
Guidelines for Electrical Safety at Project Manager / HODs and Project Manager. Regular inspections done by
6 DM-PH&SD-P4-TG05
Work Project manager electrical electrical department. The same is checked
during inspections and audits.
Yes, being complied, implemented by
Project Manager/ HODs/
7 DM-PH&SD-P7-TG06 Emergency Preparedness
Plant In-charge
Department Heads. Emergency response plan
available with all projects.
Project Manager/ HODs/ Yes, being complied as per requirements.
8 DM-PH&SD-GU41-GDM2 Guarding of Dangerous Machinery
Plant In-charge Central workshop ensures the same.
Yes, being complied and implemented by
Project Manager/ HODs/ Project Manager and workshop manager. The
9 DM-PH&SD-GU42-PSB2 Paint Spray Booths
Plant In-charge booths are regularly inspected, and
requirements implemented.
Page -22
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Page -23
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Guidelines for Obtaining Health and Yes, being complied as per requirements when
29 DM-PH&SD-P4-TG29 Project Manager/HODs
Safety Clearance required.
Yes, being complied as per requirements by the
Health Requirements for Labor
30 DM-PH&SD-GU12-HCLA2
Accommodation
HR& Admin administration department. Camp administrator
maintains all relevant documents.
Health Requirements for Project Manager/HODs/HR Yes, being complied as per requirements of
31 DM-PH&SD-P7-WI12
Construction Sites &Admin clients and consultants.
Project Manager/HODs/
Yes, being complied as per requirements.
32 DM-PH&SD-P7-A-TG-xx Accident Investigation and Reporting HSE/HR & Admin/ Transport
Reported to clients, consultant and to MOHRE.
In-charge
Health Requirements for the
Yes, being complied as per requirements.
33 DM-PH&SD-GU22-HCLSA2 Services Provided inside the Labors HR& Admin
Records maintained by camp administrator.
Accommodations
Page -24
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
39 DM-PH&SD-GU73-SUL2 Safe Use of Ladders Project Manager/HODs Yes, being complied as per requirements
40 DM-PH&SD-GU74-MAT2 Mobile Access Towers Project Manager/HODs Yes, being complied as per requirements
41 DM-PH&SD-GU85-LAC2 Labor Accommodation Compliance HR & Admin Yes, being complied as per requirements
Page -25
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
List of Cleaning and Disinfection HR & Admin / Project Yes, being complied as per requirements.
51 DM-PH&SD-L3-CDC
Companies Manager Purchase department ensures the same.
Circular – Safe Use of Cutting & Workshop In-Charge / Project Yes, being complied as per requirements.
54 812/02/02/1/1814034
Grinding Machines Manager/ HODs Regular inspections are carried out.
Page -26
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
UAE OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM (OHSMS) NATIONAL STANDARD
14.0
AE/SCNS/NCEMA 6000:2016
Section OHSMS Standard Responsible Person Compliance Status & Remarks
Section 5.1 OHS Policy GM / HSE Manager In Compliance (and same as MS requirements)
GM / All Departmental head/ Project In Compliance (and same as MS requirements). Project
Section 5.2 Objectives
Manager. and departmental objectives also maintained.
GM/ HR & Admin/ HODs / HSE In Compliance as per legal and contractual requirements
Section 5.3 Resourcing
manager/ PM as a minimum.
Section 5.4 Regulatory Compliance HODs / PM / HSEM In Compliance and ROR with status maintained.
Acknowledgement &
Section 6.5 HODs / PM / HSEM In Compliance
Responsiveness
In Compliance as per the legal requirements and best
Section 7.1 Health and Fitness HR & Admin / HSEM practices.
15.0 Regulation No. (4) of 2009 Concerning the Organization of Work in the Right of Way in the Emirate of Dubai
Responsible
Article Compliance Status & Remarks
Person
Article (3)
• It is prohibited for any Person to carry out any work on the Public Way or Yes, being complied as per requirements and
upon the Right of Way or to impose any Traffic Diversion in the Emirate HODs / PM implemented by Project Manager. NOC obtained
unless a No Objection Certificate has been obtained from the Agency for and consultants informed.
this purpose.
Article (4)
• Notwithstanding the statements in Article (3) of this Regulation, the
Competent Entities may in cases of emergency, carry out work upon the Yes, being complied as per requirements and
Right of Way or impose Traffic Diversions before obtaining a NOC, provided HODs / PM implemented by Project Manager. NOC obtained
that the Agency is notified immediately upon the start of such work, and the and consultant informed of all such works.
NOC is applied for within a maximum period of twenty-four (24) hours from
the start of such work.
Page -28
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article (5)
• It is forbidden to assign any consultant or contractor to construct or carry out Yes, in case of sub-contractor, there is clear
any work to the public road or upon a Right of Way or to impose a Traffic Client agreement on HSE requirements. Kick- off meeting
Diversion unless he is qualified and has been granted a Prequalification is done at site level to brief all HSE requirements.
Certificate by the Agency.
Article (6)
• In carrying out any work or construction upon the Public Way or Right Way,
the Authorised Entity shall be committed to ensuring compliance with the
following:
1. The provisions and technical restrictions, and fixed duration as set out in the
NOC;
2. The temporary and permanent reinstatement of the road cuttings according
to the classifications, provisions and the durations approved by the Agency;
3. Compliance with the approved guidelines of the Agency within the
construction area and the Right of Way, such as the investigation manual
on safety of the roads in the Emirate, the traffic diversions manual, and the
roadsides design manual, or as per any other guidelines as issued by the HODs / PM Yes, being complied as per requirements and
Authority;
implemented by Project Manager.
4. The manhole levels must comply with the conditions approved by the
Agency;
5. The excavations, laying, testing experiments, investigations, backfilling, Site method statements & risk assessments
reinstatement and other works upon the Right of Way are to be carried out approved by consultant are also available and
in sequential manner without interruptions, and the intervals approved by communicated to all concerned.
the Agency;
6. On completion of the work, the construction site must be reinstated as it was
previously, and as per the provisions and technical classifications of the
Agency;
7. The necessary precautions must be observed to avoid any damage to the
existing Service Lines on the construction site;
8. Safety requirements must be followed during the execution of work as per
the approved guidelines manual;
9. Any other obligations stipulated by the By-laws of this Regulation or any
related Resolution.
Page -29
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article (7)
• The Agency may require a refundable security deposit of not more than one
million (1,000,000) dirhams from the Authorised Entity as a guarantee to The Traffic and
ensure that the authorized work is carried out according to the approved Roads Agency of For Information.
classifications of the Agency, and the Competent Entities for the protection the Authority
of public property.
Article (8)
• The Authorised Entity shall be responsible to compensate for any damage
caused to the Public Way of Service Lines, or to any existing or operational
structures upon the Right of Way, including the lighting network, traffic
information signage, traffic systems, roadblocks, fences, artificial humps, HODs / PM For Information.
landscaping, and any other public and private property which requires the
intervention of the Authority.
Article (9)
• A person is banned from occupying a Right of Way by any kind of Yes, being complied as per requirements.
HODs / PM
occupation whether fixed or unfixed temporary or permanent without Implemented by Project Manager.
permission from the Agency.
Article (10)
• Parking of vehicles is not allowed on the Right of Way as it may endanger All employees Yes, being complied as per requirements.
traffic safety.
Article (11)
• On completion of the work, the Authorized Entity may apply for a Clearance HODs / PM For Information
Certificate from the Agency.
Article (12) The Traffic and
• A regulatory record is established by the Agency and cited as “Golden & Roads Agency of For Information.
Black Points Record”. the Authority
Article (13) The Traffic and
• For implementing the Golden & Black Points Record mentioned in Article Roads Agency of For Information.
(12) of this Regulation the Authority
Article (14)
• Schedule of Fines Nos. (1) & (2), issuance of warning letter to the violating The Roads and
Person and in case of repeated violations in addition to a fine, the Agency For Information.
Transport Authority
may impose one more sanction against the violating Person.
Page -30
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Article (15)
• In the case of a violating Person failing to remedy the violations within the The Traffic and
prescribed period, the Agency shall have the power to remedy the violation Roads Agency of For Information.
and shall demand the violating Person to reimburse the cost of remedying the Authority
the same.
Article (16)
• Any interested Person may submit his grievances regarding the application
of the rules & regulations and procedures of this Regulation and its
implementing By-law during a period not longer than thirty (30) days All employees For Information.
following the application through submitting a complaint to the Agency.
Article (17)
• The employees and inspectors of the Authority who are designated by the
Chairman of the Board of Directors shall have the power of judicial police The Roads and
For Information.
officers in recording the facts of the violation and shall take and minute the Transport Authority
relevant action.
Article (19)
• Local Order No. (1) of 2005 Concerning Laying of Service Lines on Public
Roads in the Emirate of Dubai; and any provision in any other legislation, to Dubai Municipality For Information
the extent of its inconsistency with the provisions of this Regulation, are
hereby repealed.
16.0 The Roads and Transport Authority QHSE Guidelines, Procedures and Circulars
Responsible
Compliance Status & Remarks
Person
Yes, being complied as per requirements.
Project Manager/ Implemented by Project Manager.
1 QHSE Management Plan Practical Guideline for TRA Projects (2013)
HODs HSE plans are prepared in line with this document in
RTA projects.
Yes, being complied as per requirements.
Project Manager/ Implemented by Project Manager.
2 RTA Work Zone Traffic Management Manual (2018)
HODs Site specific MSRA takes into consideration the
requirements mentioned.
Page -31
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
17.0 The Roads and Transport Authority - Schedule of Fines for Information (Regulation No. (4) of 2009)
Schedule No. (1) – Fixed fines implemented on simple violations by the contractor.
S. No. Violation Details Fine in Dhs.
1 Non-availability of warning signs on the road or in the construction site (totally or partially) 5000
2 Non-availability of flashers and revolving lights on the road or in the construction site (totally or partially) 5000
3 Non-availability of flag man on the road or in the construction site (totally or partially) 5000
4 Non-existence of fixed cones or plastic barriers filled with water on the road or in the construction site (partially) 5000
Non-availability of public safety requirements such as plastic mesh & tiger tapes on the road or in the construction site (totally or
5 5000
partially)
6 Occupation of a Right of Way without the Agency’s permission. 5000
Occupation of a Right of Way pursuant to a No Objection Certificate (NOC) which has expired during a period not exceeding five (5)
7 5000
working days from the date of its expiry.
8 Reinstatement in a method contrary to the approved classifications of the Authority. 5000
9 Non-removal of debris from the Right of Way during construction or thereafter. 5000
10 Non-availability of footpaths during excavations. 5000
11 Lateness in backfilling or in reinstatement. 5000
12 Non-compliance with the conditions of the NOC and its validity period. 5000
13 Non-fixation of identification signs for projects in the Right of Way, or using logos related to other entities. 5000
14 The language used in information signs on the board is incorrectly written whether Arabic or English. 5000
15 Dripping, dropping or leakage of materials such as sand, paints, concrete, or like, on the road. 5000
Page -32
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
Schedule No. (2) – Fixed fines implemented on major violations by the contractor.
S. No. Violation Details Fine in Dhs.
1 Carrying out deep excavations in the Right of Way without concrete humps and other public safety requirements (partially or totally). 50000
2 Carrying out excavation work on the Right of Way without obtaining a NOC from the Agency. 30000
3 Closure of main roads or any part of it or imposing a Traffic Diversion prior to obtaining NOC from the Agency. 20000
4 Closure of arterial roads or any part of them or imposing a Traffic Diversion prior to obtaining a NOC from the Agency. 10000
5 Closure of local roads or any part of, or the imposition of a Traffic Diversion prior to obtaining a NOC from the Agency 5000
6 Imposing a Traffic Diversion in a way contrary to approved classifications of the Agency. 25000
Causing damage to the public roads, such as sinking resulting from (NDRC) or (SHORING), etc., or damage to bridges or tunnels as
7 50000
a result of collision with project vehicles.
8 Causing traffic jams resulting from closure of road due to damage to public Service Lines. 50000
9 Damage to public and private property. 5000
10 Obstructing the tasks of the Agency’s employees and inspectors through non-cooperation. 1000
11 Parking heavy vehicles and buses upon the Right of Way or adjacent areas in such a way that endangers the safety of traffic. 5000
18.0 Federal Order No. (11) of 2007 on UAE joining the convention of wetlands of international importance (RAMSAR)
Article Responsible Person Compliance Status & Remarks
Three Ramsar Sites of International Importance: the Ras Al Khor
Wildlife Sanctuary, the Jebel Ali Sanctuary and Hatta Mountain
Reserve
The Ras Al Khor Wildlife Sanctuary was declared as the first
Ramsar Site in the country in 2007. The second is the Jebel Ali
The requirements of articles mentioned in the order
Wetland Sanctuary, which was announced as a Ramsar Site at the
HODs/Project Manager will be considered during the preparation of any
13th Ramsar Conference of the Parties (COP13) held in Dubai in
environmental study.
October 2018 and the third is Hatta Mountain Sanctuary
announced in 2019.
Page -33
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
19.0 UAE Federal Law No. 12 of 2018 On the Integrated Waste Management System
Article Responsible Person Compliance Status & Remarks
Article 5 – Liability of the Waste Generator, Supplier and HODs/ Project Manager,
For information & guidance.
Establishment Purchase Manager
Complied, implemented the reuse of certain types of
HODs/ Project Manager,
Article 7 – Waste Reuse or Recycling wastes and recycles the waste stipulated in the
Purchase Manager
guidelines as per the requirements.
HODs/ Project Manager, Complied, the waste as generated are disposed as
Article 8 – Disposal of Waste
Purchase Manager per DM Waste Management guidelines.
HODs/ Project Manager, Complied & implemented whenever secondary raw
Article 10 – Reuse of Secondary Products
Purchase Manager materials are usable as secondary products.
Complied, implemented the reuse, recycling and safe
HODs/ Project Manager,
Article 15 – Industrial Waste disposal of industrial wastes as per DM Waste
Purchase Manager
Management Guidelines.
HODs/ Project Manager,
Article 25 – Civil Liability for Environmental Damage For information & Guidance.
Purchase Manager
HODs/ Project Manager,
Article 26 – Administrative Sanctions For Information & Guidance.
Purchase Manager
Article 27 – Penalties
Article 28 - Every private Establishment that throws, buries, burns
or disposes of Waste in open areas, roads, waterways, public parks
and any other areas not designated for this purpose, shall be
punished by a fine not exceeding AED (1,000,000) one million.
Article 29 - Every physical Person that throws, buries, burns or
HODs/ Project Manager,
disposes of Waste in open areas, roads, waterways, public parks For Information & Guidance.
Purchase Manager
and any other areas not designated for this purpose, shall be
punished by a fine not exceeding AED (30,000) thirty thousand.
Article 30 - Whoever violates the other provisions prescribed under
the provisions of this Law, regulations and the decisions issued in
implementation thereof shall be punished by a fine not exceeding
AED (20,000) twenty thousand.
Page -34
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
21.0 UAE Federal Law No. (14) of 2014 Concerning the Prevention of Communicable Diseases.
Article Responsible Person Compliance Status & Remarks
Article: 1
The protective and Health measures shall be taken in the HR & Admin /
country in the expectance or on the appearance of cases of a HODs/Project
Complied & implemented as per requirements
communicable disease. Such measures shall be taken in manager/HSE team
accordance with the provisions of this law.
Page -35
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
24.0 Executive Council Resolution No. (15) Of 2021 Regarding Sharjah Occupational Safety and Health System
Reference Responsible Person Compliance Status & Remarks
Executive Council Resolution No. (15) Of 2021 Regarding Sharjah HR & Admin/HSE Manager/ HODs /
Occupational Safety and Health System For Information & Guidance
Project Manager
Code of practices.
1.OSHJ-GL-01 Mobile Plant
2.OSHJ-GL-02 Mobile Elevated Work Platform
3.OSHJ-GL-03 Scaffolding
4.OSHJ-GL-04 Mobile Access Towers
5.OSHJ-GL-05 Employer Supplier Accommodation
6.OSHJ-GL-06. Employer Supplied Transport
7.OSHJ-GL-07 Personal Protective Equipment Yes, Complied & implemented as per
8.OSHJ-GL-08 Portable Power Tools HSE Manager/ HODs / Project requirements
9.OSHJ-GL-09 Lone Working Manager
10.OSHJ-GL-10 Safe Driving
11.OSHJ-GL-11Safety in Warehousing
12.OSHJ-GL-12Local Exhaust Ventilation
13.OSHJ-GL-13 Compressed Gases and Air
14.OSHJ-GL-14Spray Finishing
15.OSHJ-GL-15Safety in Heat
Page -36
HSE MANAGEMENT SYSTEM LEGAL REQUIREMENT REGISTER OF REGULATIONS
16.OSHJ-GL-16Permit to Work
17.OSHJ-GL-17Safety Signs and Signals
18.OSHJ-GL-18Working On Over Or Adjacent to Roads
19.OSHJ-GL-19Leadership Commitment and Involvement
20.OSHJ-GL-20Measuring OSH Performance
21.OSHJ-GL-21Managing Buildings Safety
22.OSHJ-GL-22Safety in Education Facilities
23.OSHJ-GL-23Employee Consultation Communication and Involvement
24.OSHJ-GL-24Barricading
Guideline:
1.OSHJ-GL-01Mobile Plant
2.OSHJ-GL-02. Mobile Elevated Work Platform
3.OSHJ-GL-03. Scaffolding
4.OSHJ-GL-04 Mobile Access Towers HSE Manager/ HODs / Project Yes, Complied & implemented as per
5.OSHJ-GL-05 Employer Supplier Accommodation Manager requirements
6.OSHJ-GL-06 Employer Supplied Transport
7.OSHJ-GL-07 Personal Protective Equipment
8.OSHJ-GL-08 Portable Power Tools
9.OSHJ-GL-09 Lone Working
10.OSHJ-GL-10 Safe Driving
11.OSHJ-GL-11 Safety in Warehousing
12.OSHJ-GL-12 Local Exhaust Ventilation
13.OSHJ-GL-13 Compressed Gases and Air
14.OSHJ-GL-14 Spray Finishing
15.OSHJ-GL-15 Safety in Heat
16.OSHJ-GL-16 Permit to Work
17.OSHJ-GL-17 Safety Signs and Signals
18.OSHJ-GL-1 Working On Over Or Adjacent to Roads
19.OSHJ-GL-19 Leadership Commitment and Involvement
20.OSHJ-GL-20 Measuring OSH Performance
21.OSHJ-GL-2 Managing Buildings Safety
22.OSHJ-GL-22 Safety in Education Facilities
23.OSHJ-GL-23 Employee Consultation Communication and Involvement
24.OSHJ-GL-24 Barricading
25.OSHJ-GL-25 Working On, Over or Adjacent to Water
26.OSHJ-GL-26 Training and Competence
27.OSHJ-GL-27 New and Expectant Mothers
28.OSHJ-GL-28 Safety on Farms
Page -37
APPENDIX - E
HSE Forms
Form No: HFC/HSE/IND/01
HILLS AND FORT CONSTRUCTION LLC Rev: 02
Date:05/06/2021
HSE Induction-General
UNDERTAKING
I/we, the undersigned, have attended the HSE Induction training and understood the requirements of
following Health & Safety rules in workplace and agreed to follow them. My signature is appended below.
1. Project Details:
2. Scope of Work:
HSE Representative to explain the basic scope for the project and HSE rules, HSE committee details on this project.
3. HSE Policy & Objectives:
The GM of HFC signs the HSE Policy that is aimed at promoting the company's 'Zero Accident' goal.
The HSE Policy is displayed in several locations on site for you to read, understand, and follow.
4. COVID 19 prevention, First Aid and Medical:
Strictly follow the COVID-19 protocols (wear Mask, hand sanitation, social distancing, vaccination)
There are a First Aid Boxes strategically placed around site offices and work areas.
All first aid cases MUST be reported in the First Aid Log or with the Company nurse/first aid provider.
5. Accident Prevention and Reporting:
HFC believes that strictly following the site HSE rules and using 'common sense' can prevent all incidents.
All incidents/near miss MUST be reported to Project Manager or HSE Representative immediately.
6. Housekeeping and welfare facilities:
Housekeeping must be kept at a very high standard. As well as reducing the fire hazard, it also increases the hygiene
levels around the site and working areas.
Ensure the drinking water, rest area and toilet facilitate at work site.
7. Fire Prevention and Control:
Fire extinguishers are provided at required locations around site; use them in an emergency if you are trained.
All portable welding machines, generators, compressors, etc. must be issued with a fire extinguisher.
8. Excavation Safety:
Underground facilities must be identified before the surface is broken. Any doubts CHECK with HFC HSE Rep.
Operators and Engineers must follow the company excavation procedure.
Signs and barricades are provided; if you move them, for any reason, make sure you put them back.
If you cause or make a new hole, ensure that your demarcation and/or barricades are placed.
9. Scaffolding will be used during this project. All scaffolding must be covered by the SCAFFTAG system
Report any defects to your immediate superior. Ensure before entering the scaffolding structure “it is safe to use”
10. Traffic Safety:
Strictly follow the UAE traffic rules at site also. Speed limits for roads and track ways will be set by HFC Project
Management and signposts will be erected. Authorized persons only operate the vehicles/equipment. Offenders will
be punished. Follow designated routes, signs and directions from HFC signalers.
11. Confined Space:
A confined space is anywhere with limited or difficult access, egress, and the possibility of hazardous atmosphere.
Strictly follow the company confined space procedure. Authorized personals only enter the confined space areas.
12. Smoking Policy:
Smoking is NOT permitted inside temporary buildings and restricted locations except in designated areas.
13. HSE incentives and Disciplinary Notice Procedure: Monthly HSE incentive award will arrange in each site and
any safety violations Disciplinary action will take from the management.
14. Chemical Safety:
Make sure that MSDS is available, and the hazards associated with the chemicals and necessary precautions to be
taken are informed to the personnel handling the same. Use the necessary PPE for handling the same.
15. Emergency Evacuation:
The Emergency 'Assembly Point' is situated at various locations-HSE REPRESENTATIVE must give precise
locations and complete updates.
Whenever required (an emergency) all employees must make their way to the emergency Assembly Point.
16. Personal Protective Equipment:
PPE is designed as a last resort to reduce the effects of an accident. It is not an excuse to forget safe working
practices. Hard hat, steel-toed shoe/ boots, coverall and fluorescent vest are the minimum requirements on site.
All tradesmen or workers must use the correct PPE for his work and/or situation and environment.
*Feedback:
Signature: Signature:
Severity
Probability Minor Injury/Illness Minor Incident 2 2 4 6 8 10
1-8 Low - L Moderate Injury/Illness Moderate Incident 3 3 6 9 12 15
9- 16 Medium - M Serious Injury/Illness Serious Incident 4 4 8 12 16 20
17-25 High - H Fatal/Permanent disability Major Incident 5 5 10 15 20 25
Likelihood: Health & Safety Severity: Environmental Severity: L: Likelihood
Hazardous Chemical required?
1. Unlikely 1. Slight Injury (No lost time) 1. Slight Incident L*: Likelihood with mitigating controls in place
2. May happen 2. Minor Injury/Illness 2. Minor Incident S: Severity
Yes No
3. Likely 3. Moderate Injury/Illness 3. Moderate Incident S*: Severity with mitigating controls in place
4. Very Likely 4. Serious Injury/Illness 4. Serious Incident R: Level of uncontrolled risk
(Tick as applicable)
5. Certain or Imminent 5. Fatal/ Permanent Disability 5. Major Incident R*: Assessed level of Residual Risk
Hierarchy of Control (Controls identified may be the hierarchy to provide minimum operator exposure)
Elimination Eliminate the Hazard General Safety Requirements:
Substitution Provide an alternative, that can perform the same task and is safer to use • The daily Tool box talk shall be done by the
Engineering control Provide or construct a physical barrier or guard workforce.
Administrative Controls Develop procedures and guidelines, in consultation with employees, to mitigate • Risk Assessment and Method Statement shall be
the risk. Provide training, instruction and supervision about the hazard. communicated to all.
Personal Protective equipment Personal Equipment designed to protect the individual from the hazard. • Provide proper PPE to all operatives.
Covid 19 prevention: wear Mask and hand gloves all the time • Ensure to follow the COVID-19 protocol.
J
Project: SITE SUMMARY
Month: Description Issue In %
Open Issue 1 1%
Start date:
Closed Issue 117 99%
End date:
Total observation 118
Weekly Observation Trend:
1st week 2nd week 3rd week 4th week 5th week
Open Issue 0
Open Issue 1 1% 0% Open Issue 0 0% Open Issue 0 0% Open Issue 0 0%
Closed Issue 23
Closed Issue 21 99% 100% Closed Issue 24 100% Closed Issue 23 100% Closed Issue 26 100%
J J J J J
Open Issue
Open Issue Open Issue
Closed Issue Open Issue Closed Issue Open
Closed Issue Issue
Closed Issue
0 0 0 0 0 0 0
Page 1 of 1
1st Week 2nd week 3rd week 4th week 5th week
SITE SUMMARY SITE SUMMARY SITE SUMMARY SITE SUMMARY SITE SUMMARY SITE SUMMARY
Description Issue In % Description Issue In % Description Issue In % Description Issue In % Description Issue In % Description Issue In %
Open Issue 1 1% Open issue 1 5% Open Issue 0 0% Open Issue 0 0% Open Issue 0 0% Open Issue 0 0%
Closed Issue 117 99% closed issue 21 95% Closed Issue 23 100% Closed Issue 24 100% Closed Issue 23 100% Closed Issue 26 100%
Total observation 118 22 Total observation 23 Total observation 24 Total observation 23 Total observation 26
J J J J J J
IF(D6>=0.6,"J",IF(D6>=0.4,"K","L"))
1st 2nd 3rd 4th 5th
2 2 2
week Week week week week 1st Weekly HSE Observation trend 2nd Weekly HSE Observation trend
1 Excavations 1 1 1 1 1
2 Site access/ Site Traffic 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Work at height 0 0 0 0 0
4 Scaffolding/ladders 1 1 1 1 1
Personal Protective Equipment 0 0
5 1 2 1 1 1
Temporary Electricals/
6 certification 1 1 1 1 1
7 Hand tools 1 1 1 1 1
8 Housekeeping 2 2 2 0 2
9 Lifting Operations 1 1 1 1 1
10 Portable Electrical Tools 1 1 1 1 1
11 Mechanical Plant 1 1 1 2 1
12 Confined spaces 1 1 1 1 1
13 Hot works 1 1 1 1 1 3 3
14 Permit to work Procedures 1 1 1 1 1 3rd Weekly HSE Observation trend 4th Weekly HSE Observation trend
15 Certification- lifting/plant 1 1 1 1 1 2 2
2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0
Form No: HFC/HSE/SHI/27
Rev: 02
HILLS AND FORT CONSTRUCTION LLC Date: 05/06/2021
2. Inside the rest areas enough tables and seats facilities are available?
3. Is there cool fresh drinking water and rehydration powder available?
4. If cooler is used to supply water, is the lid sealed with tape and the date of filled
written on the container.
5. Is there a communication system for informing employees the current
environmental condition
6. Are there poster reminding employees to drink water?
7. Are there poster reminding employees of the sign and symptoms of heat injuries
and illness.
8. Are First aider available at site?
9. Are contact number available for medical emergency?
Training / Education
1. Do the employees know the signs and symptoms of heat illnesses/injuries?
2. Did you conduct the summer safety Precautions awareness training to all
employees?
Additional Comments:
Note: Original with Permit Receiver and copy should be at worksite. If any work changes / work stoppage, then permit
should be cancelled and issue new permit.
Form No: HFC/HSE/GWP/24 Rev-02
HILLS AND FORT CONSTRUCTION LLC Ref No: HFC/HSE/SLP/23
Rev: 02
Safe Lifting Permit Date: 05/06/2021
Project Details
Project: Permit No:
Specific location or area where
Date:
lifting will be conducted
Company Details
Company Company managing the lifting
conducting the lift operation
Crane owner Other companies involved
Crane Involved
Tones:
Maximum lift capable in
Make / Model
supplied configuration
(consult Load Chart)
Registration / Plant number Boom length to be used Meters:
Yes Yes No
Is the Load chart available in Is SWL indicator
the crane calibrated Date:
No
3rd party Certification- last
Certification due date
inspection date
Certificate Number Last major service
__
Monthly crane inspection Known defects with
sighted: crane if any:
Complete a separate form if more than one hook or configuration is used.
Lifting Gear
Item ID Number SWLL Date thoroughly examined
Site Conditions
What is the ground angle ___degrees
Obstructions in lifting location
at the lifting location (0 degrees if level ground)
Is the area concealing
Check ground conditions
underground hazards i.e., Pipes,
for outriggers
recently back-filled etc.
Could weather condition effect Yes / No Wind _______m/s
this operation If yes, give details of the
point where the Rain: Light/Heavy
Area barricaded off to prevent Yes / No
operation will cease Other __________
unauthorised access
Information
Pre-start toolbox talk
Name supervisor
conducted
who gave the
Underground services
Toolbox talk
documentation held Yes / No
Approvals
I have checked the above information as indicated and confirm that to the best of my knowledge, the
information is accurate and therefore this form is valid until the prescribed date, providing that conditions
and provided information has not changed.
Draw location of; 1) Crane, 2) Load pick-up location, 3) load placement location, 4) other items as
appropriate. Include radius distances.
Inspected By:
Name:
Signature……………………………………… Date:
Designation:
Please Note:
1. Permit is not transferable
2. Permit is valid until the end time as indicated above.
3. Permit cannot be issued for more than 24 hours.
4. If the work is to be continued beyond the validity time, a new permit shall be obtained.
5. Permit is valid only for the job it is issued.
Complete one form for each product and one form for each change in the process/task/activity
Product classified as Hazardous: ❑ Yes ❑ No
Is product Hazardous to the
environment: ❑ Yes ❑ No (If used correctly)
Name of product:
UN Number:
Supplier or Manufacturer:
Storage requirements:
This Product has a specific WMS for its safe use (if applicable)
WMS No. or name WMS relating to: Approval date on WMS
Full Face Shield Welding Shield Dust Mask Vapour Mask Breathing Apparatus
Duration of Work (One Day Only) Start Date: Start Time End Time:
Check Points
Sl.No. Description Yes No
1 The Person deputed for work is qualified and competent to perform the work
2 Method statement and Risk assessment has taken place and communicated to all workforce
3 Level of Oxygen determined, and ventilation facilities is provided
4 Fire extinguishers are available in the vicinity
5 Second person is available to assist or monitor
6 Adequate personal protective equipment and rescue arrangements is provided
7 Communication and First aid facility is available in the vicinity
8 Emergency evacuation plan in place.
9 Well maintained equipment and tools are provided for work
10 All safety equipment calibrated, and valid certificate is available.
After checking all the above precautions, the confined work can be carried out in the above area
Name of the Permit Name of the Permit
Issuing Engineer: Receiver:
Date & Signature: Date & Signature:
rd
Gas Test reports: (3 party certified person) take the Gas test Prior to start any activities inside the confined space.
Gas Test Details Date: Time: Retest Date: Time:
O2: .................% CO: .................. …...ppm O2: ....................% CO: ......................ppm
H2S: ............ppm LEL: ........................ppm H2S: ............... ppm LEL: ................... ppm
Test Carried out by: Test Carried out by:
O2- Oxygen CO- Carbon Monoxide H2S- Hydrogen Sulphide LEL- Lower Explosive Limit
Emergency Contact Number:
Precautions Yes No
Ventilator provided and ventilated for One hour
Gas Monitor tests is OK (keep the Gas test details)
Proper access and egress provided
Barriers and sign boards provided
Protective equipment worn (like, full body harness, helmet, googles, safety shoes,)
Top man aware of duties and effective communication provided
BA Equipment (if necessary), lighting, Tripod, lifelines are available
Toolbox Talks conducted (emergency procedure and each person’s duties and responsibilities)
I confirm that the above-mentioned precautions have been met.
Name of the Permit Receiver: Signature: --------------------------
Designation: Date:
Verified and signed by Project HSE Team:
Permit Closeout:
I hereby declare the work undertaken under this Permit has been completed and work area has been made safe.
Details of work: (The person taking permit (permittee) to fill up) Duration
From: To:
(Hot work would mainly comprise - Welding, Gas-cutting, use of Open Flames or other sources of fire in a fire-prone
place containing inflammable substances, explosives & / or other such highly combustible materials susceptible to
spontaneous ignition & / or explosion.)
A. The person taking permit (permit Receiver) to fill up:
Points to be checked.
Sl.No Details Yes No Not Remarks
required
1 Risk Assessment and Safe Work Procedure has been carried out and
briefed to the workers.
2 Has the area immediately below the work spot, been cleared / removed
of oil, grease, waste cotton & combustibles etc.?
Check the following in Gas cylinders:
I. Gas Cylinder Trolley available
3 II. Two Flash Back Arrestors fitted at Cylinders end
III. Gas cutting hoses found without any visible damages
IV. All Pressure gauges are in working condition
Check the following Welding Machine:
I. Welding machine connections routed through RCCB
4
II. Return path provided through well insulated cable
III. Cable connections are without damage and well insulated
IV. Electrode holders are insulated and in good condition
V. Proper lugs are used for connecting welding cables
5 Have fire extinguishers been kept handy at site?
6 Has tin sheet/ wet gunny bag/ fire retardant cloth / sheet been placed
(in fire prone area) to prevent sparks from causing fire?
7 Is required personal Protective equipment available to welders and Gas
cutters?
8 Other precautions to be taken (specify):
B. The person giving permit (issuing authority- Engineer) to fill up:
After checking all the above precautions, the hot work can be carried out in the above area.
Name of the Permit Name of the Permit
Issuing Authority: Receiver:
Signature: Signature:
Date: Date:
Verified and signed by Project HSE Team:
C. Permit closeout:( To be completed by the Permit Receiver)
The task has been completed and area is safe and clean. (If work continuing ensures to prepare new permit)
Poor: Absence of major control measures (High risk), work to be stopped and risk assessment to be reviewed immediately.
Fair: Some minor controls are missing (medium risk), additional control measures to be implemented.
Good: All required controls are in place (low risk), only monitoring is required.
Description
Evaluation Remarks
Item (insert your observation,
Good Fair Poor N/A and proposed corrective
action plan)
Waste is segregated & collected at
designated appropriate areas (hazardous
from non-hazardous) &adequate waste
containers/skips provided.
Waste is removed /disposed regularly &
according to the authorities Waste Center
guidelines.
Proper oil/chemicals leakage & spill
control in places (tanks bunding, dripping
trays, oil spill response materials).
Allocation of designated area for washing
concrete mixers & pumps.
Proper collection & disposal of wastewater
& sewage water.
Proper management of noise generated from
the project, by installing noise enclosure
measures (e.g., silencers, & work scheduling).
Dust and/or fumes control measures
have been implemented.
Regular maintenance for mobile equipment,
vehicles &machines.
If any Other Observations:
Name:
Date: Signature……………………….
1. General Information
Date: Project: NCR Ref.Number: Procedure Reference No:
1. HSE Arrangements:
* Any organization with 5 or more employees must have Comments / Response
documented policies and procedures.
performance from
3. Personnel: Comments / Response
reputable sources?
3.1. Are all operatives directly Employed by the
subcontractor?
• All employees should have Workmen Compensation
Insurance, Emirates ID & Medical cards.
3.2. All employees are done the Covid-19 Vaccination?
3.3. Have details been provided of the arrangements to
ensure all personnel are competent to carry out their
work?
3.4. Will all operatives have 3rd Party Certification?
5. HSE Performance:
(*A “Yes” answer must be investigated and discussed with Comments / Response
the HSE Head)
6. Subcontractor Representatives:
Name:
7.1 Assessment Reviewed by: Designation
Signature:
Date:
Name:
7.2. Assessment Approved by: Designation
Signature:
Date:
Name: Signature
Date:
Original: Project HSE Office
CC: PM. CM Engineer Others …………………….
Ref. No: HFC/HSE/SCL/14 Rev-02
Form No: HFC/HSE/PEC/13
HILLS AND FORT CONSTRUCTION LLC
Rev:02
PLANT & EQUIPMENT CHECK LIST Date: 05/06/2021
Head Lights Sound Horn Reverse Horn Reg. No. Plate All Mirrors.
Beacon light Windshield Seat belt Safe Load Indicator. Body & window Glass
Fire Extinguisher Parking Brake / brake. Jib Radius Indicator Lifting points/ Gears/ Accessories.
Remarks:
Name:
Inspected by:
Designation: Signature: --------------------------------
Signature: --------------------------------
Area:
Worker Name:
Supervisor/Engineer Name:
Score:
Description 0 1 2
1. Toolbox talk (TBT)
Attending the Tool box talks regularly
2. Personal Protective Equipment (PPE)
Hard Hat worn (Helmet)
Eye protection worn
Full body harnesses in good condition and worn
Gloves in good condition and worn
Safety boots in good condition and worn
Respirators/dust mask in good condition and worn
Overall or two piece in good condition and worn
3 Safety Culture
Unsafe act/condition reporting
Safe working culture (using of ladders, working on the platform, equipment etc..)
Near miss / incidents reporting
Attending the TBT and training
Using of proper tools
4 General
site duty attendances
Behavior with other colleagues
Using of the welfare facilities
Follow the COVID-19 Protocols (wearing Mask, social distancing, sanitation etc..)
Remarks: Points Schedule
0 Infringement
1 Fair
2 Good
Designation: Designation:
Date: Date:
Note: Weekend submits to Project In-charge and HSE dept.
Contributing Factors:
Improper Equipment Use. Equipment Malfunction/Failure Insufficient Training
Hazardous Waste Disposal Oil Leakage Other……...
Primary Couse:
Preventive Actions:
(What action is need to prevent the near miss happening again?) By Whom When
Designation: Date:
Verified by:
Name: Signature:
Designation: Date:
1
Form No : HFC/HSE/IR/06-A
HILLS AND FORT CONSTRUCTION LLC Rev-01
Date : 05/06/2021
DETAILED INVESTIGATION REPORT
INCIDENT TITLE:
Project Name:
Detailed Investigation Initial Incident
Report Ref. No: Report Ref. No:
EXECUTIVE SUMMARY
INCIDENT DESCRIPTION:
DETAILED DESCRIPTION OF SCENE, LOCATION, PEOPLE INVOLVED, ETC…
SEQUENCE OF EVENTS
EMERGENCY PROCEDURES
WITNESS ACCOUNTS
Environment:
IMMEDIATE CAUSES
ROOT CAUSES
ACTION PLAN
S. NO. ACTION DESCRIPTION RESPONSIBILITY TARGET DATE
1.
2.
3.
4.
MANAGEMENT REVIEWS
DATE & TIME:
Reviewed by
Approved By
Incident Type: Fatality Injury Property Damage Heat related illness Near Miss
ANALYSIS- Track the factors which are thought to have contributed to the cause of the incident
Task Environment Organizational
Lifting Housekeeping Poor communication
Carrying Slippery conditions No Policies/ procedures in place
Repetitive Movement Excessive noise Poor job design
Twisting Weather conditions Failure to identify Hazards
Driving Heat / Cold Lack of staff / budget
Other (works) Lighting / Visibility Lack of training / supervision
Surface conditions Pressure to complete task
Humacn factors Equipment
Lack of experience / training Faulty equipment
Stress/ fatigue Lack of equipment
Safety procedures not followed Poorly maintained
Improper work technique Wrong for the task
Physical limitations Lack of signage
Skylarking / horesplay
Root cause:
Preventive Actions:
(What action is need to prevent the incident happening again?) By whom? When?
Severity
Probability Minor Injury/Illness Minor Incident 2 2 4 6 8 10
1-8 Low - L Moderate Injury/Illness Moderate Incident 3 3 6 9 12 15
9- 16 Medium - M Serious Injury/Illness Serious Incident 4 4 8 12 16 20
17-25 High - H Fatal/Permanent disability Major Incident 5 5 10 15 20 25
Likelihood: Health & Safety Severity: Environmental Severity: L: Likelihood
Hazardous Chemical required?
1. Unlikely 1. Slight Injury (No lost time) 1. Slight Incident L*: Likelihood with mitigating controls in place
2. May happen 2. Minor Injury/Illness 2. Minor Incident S: Severity
3. Likely 3. Moderate Injury/Illness 3. Moderate Incident
Yes No S*: Severity with mitigating controls in place
4. Very Likely 4. Serious Injury/Illness 4. Serious Incident R: Level of uncontrolled risk
(Tick as applicable)
5. Certain or Imminent 5. Fatal/ Permanent Disability 5. Major Incident R*: Assessed level of Residual Risk
Hierarchy of Control (Controls identified may be the hierarchy to provide minimum operator exposure)
Elimination Eliminate the Hazard General Safety Requirements:
Substitution Provide an alternative, that can perform the same task and is safer to use • The daily Tool box talk shall be done by the
Engineering control Provide or construct a physical barrier or guard workforce.
Administrative Controls Develop procedures and guidelines, in consultation with employees, to mitigate • Risk Assessment and Method Statement shall be
the risk. Provide training, instruction and supervision about the hazard. communicated to all.
Personal Protective equipment Personal Equipment designed to protect the individual from the hazard • Provide proper PPE to all operatives
RA-04 Task: REMOVAL OF CONCRETE WASTE, CONCRETE STRUCTURES/ CONCRETE ELEMENTS Date: 07.12.2021
OHS & E
Persons OHS & E Initial
OHS & E Residual Risk Responsible
SN Activity Hazard /Aspect Risk / Impact /Property Risk Rating
Existing Controls Measures Rating Person
Involved
S P SxP S* P* SxP*
Check the integrity of lifting eyes it lifted compile lifting
plan.
Use designed spreader beam. Only use competent trained Foreman,
Crush injury to Operatives
Dropped loads crane operatives and rigger Site Engineer,
Removal of personnel or Consultant/
1 caused by lifting 5 4 20 Lifting Equipment and lifting gears must be certified as per 5 1 5 Construction
concrete waste damage to Client officials
equipment failure policy/standards. Visual inspection of all lifting equipment Manager,
property and visitors
prior to use. Test certificates shall be checked to ensure HSE Officer
validity. All lifting gears to be color coded
Ref: DMCOP CHAPTER 10 Concrete and Masonry
Removal and HFC will appoint an approved third party to carry out the Project Manager,
disposal of Environmental disposal of concrete waste. Maintain the waste consignment Construction
All Operatives 3 3 9 3 1 3
Concrete waste impact note Manager and HSE
from site Ref: DMCOP CHAPTER 10 Concrete and Masonry Department
Serious Cut
Eye injury and/or injury, Blindness Suitable eye protection (goggles or face shields) must be
respiratory Operatives
or respiratory worn at all times when carrying out grinding operations. Foreman, Site
Use of portable problems-caused Consultant/
1 illness 4 5 20 House keeping 4 1 4 Engineer,
grinders by flying metal Client officials
Particular Proper disposal of metal waste HSE Officer
particles from and visitors
problems can Ref: DMCOP CHAPTER Hand and Power-Operated Tools
grinding operations occur with coated
RA-14 Task: EXCAVATION FOR UTILITY SERVICES (FIRE, STREET LIGHT. Etc) Date: 07.12.2021
OHS & E
Persons OHS & E Initial
OHS & E Residual Risk Responsible
SN Activity Hazard /Aspect Risk / Impact /Property Risk Rating
Existing Controls Measures Rating Person
Involved
S P SxP S* P* SxP*
Obtain necessary NOC
Electrocution, As built documentation.
Striking of Serious injury to PTW.
Underground Foreman,
personnel, Operatives Supervision of PTW requirement
services (electric Site Engineer,
Disruption of Consultant/ All the services will be detected, exposed and clearly
1 Excavation cable, water/ 5 4 20 5 1 5 Construction
services. Client officials marked prior to start the excavation
gas/hazardous Manager,
Serious and visitors Detect and expose the underground services prior to
liquid pipelines HSE Officer
environmental machine excavation. PTW, Craft Training,
etc.) pollution System in place for disposal of contaminated earth.
Ref: DMCOP CHAPTER 9 – Excavation
Excavation permits that identify shoring or sloping
Crush injuries to Operatives Site Engineer,
requirements.
personnel and Consultant/ Construction
Collapsing wall 5 4 20 Equipment kept away from edge. 5 1 5
damage to Client officials Manager,
Provide warning signs
property and visitors HSE Officer
Ref: DMCOP CHAPTER 9 – Excavation
Death or serious
Ladders access Foreman,
injury to Operatives
Personnel or Suitable crossing point Site Engineer,
personnel and/or Consultant/
machine falling 5 4 20 Rigid barriers. 5 1 5 Construction
damage to Client officials
into excavation Warning sign Manager,
property. and visitors
Adequate lighting/PTW HSE Officer
Falls of Material, Care must be taken when passing equipment from one
Death or serious
equipment/tools- Operatives location to another. Scaffold
injury to
caused by careless Consultant/ Planning should take place to ensure that only required Supervisor,
personnel, 5 5 25 5 5 25
handling or Client officials amount of equipment in site at any one time. Scaffold inspector,
damage to
inadequate during and visitors Use of tool bags Site engineer
property
the erection process Exclusion zones required
Ref: DMCOP CHAPTER 8Scaffolding Safety
Trapping the
hands/fingers Operatives Scaffold
Care must be taken when removing or replacing equipment
between tubes or Fractures or cut to Consultant/ Supervisor,
4 5 20 in racks 4 5 20
boards when finger Client officials Scaffold inspector,
Ref: DMCOP CHAPTER 8Scaffolding Safety
stacking or de- and visitors Site engineer
stacking
Death or serious Operatives Scaffold
Scaffolds only to be on solid ground with adequate support
injury to Consultant/ Supervisor,
Partial collapse 5 5 25 for standards. Regular inspection 5 1 5
Personnel. damage Client officials Scaffold inspector,
to property
Ref: DMCOP CHAPTER 8Scaffolding Safety
and visitors Site engineer
Foreman,
Crush injury to Operatives Hiring of mobile cranes to meet company policy/standards.
Dropped loads Site Engineer,
personnel or Consultant/ Visual inspection of all lifting equipment prior to use. Test
caused by lifting 5 4 20 5 1 5 Construction
damage to Client officials certificates shall be checked to ensure validity.
equipment failure Manager,
property and visitors Exclusion zones to be created
HSE Officer
Ref: DMCOP CHAPTER 21 Sling and Rigging Equipment
CHAPTER 22 Cranes
Fall from heights, Personnel working close to unguarded openings etc. Are to Foreman,
Operatives
dropped objects wear safety harness. Where there is a potential for personnel Site Engineer,
Serious injury to Consultant/
etc. Caused by 5 4 20 to fall into, guard rails must be provided with toe boards 5 1 5 Construction
personnel Client officials
unguarded Ref: DMCOP CHAPTER 21 Sling and Rigging Equipment Manager,
and visitors
openings CHAPTER 22 Cranes HSE Officer
Color coding and test certificates shall be checked to ensure
Failure of validity. All equipment’s shall be inspected for damage
Foreman,
equipment during Operatives prior to use. On completion of task, check and return all
Site Engineer,
Faulty lifting service –causing Consultant/ equipment’s to storage. Any damaged equipment shall be
5 4 20 5 1 5 Construction
equipment damage to plant Client officials quarantined and reported to supervision immediately.
Manager,
and/or serious and visitors Records maintained weekly
HSE Officer
personal injury Ref: DMCOP CHAPTER 21 Sling and Rigging Equipment
CHAPTER 22 Cranes
Crane operator should possess competency certificate from
third party. Where applicable, method statements shall be
Movement of
read to establish specific precaution is necessary. If direct Foreman,
equipment or load Operatives
lifting is not possible, use of tag lines shall be utilized to Site Engineer,
causing damage to Consultant/
Uncontrolled lifts 5 4 20 avoid the load swinging. Lifting plan to be developed for 5 1 5 Construction
plant and/or Client officials
special lifts. Lifting assessments from 1&2 to be filled and Manager,
serious personal and visitors
signed by supervisor and crane operator prior to lift. HSE Officer
injury
Ref: DMCOP CHAPTER 21 Sling and Rigging Equipment
CHAPTER 22 Cranes
Foreman,
Unauthorized Operatives
Work can be carried out with a cold work permit. Site Engineer,
Working with o out operation can Consultant/
5 4 20 Stop activity, disciplinary action against supervisor. 5 1 5 Construction
permit. cause failure of Client officials
Ref: DMCOP CHAPTER 21 Sling and Rigging Equipment Manager, HSE
supervision. and visitors
CHAPTER 22 Cranes Officer
Foreman,
Routine Slip, fall, Operatives No major maintenance will be at site Site Engineer,
Maintenance and personnel injury 5 4 20 Trained personnel only deployed for routine maintenance 5 1 5 Construction
Oil/Fuel Spillage Environment jobs Manager,
refueling
Appropriate PPE to be used HSE Officer
Used oil/ filters to be collected and dispose separately
Make sure the drip trays are in place and drained/ emptied
properly
DMCOP CHAPTER 2 General Health and Safety
Provision
Provide and maintain temporary storage/ lagoon
All pipe joints shall be regularly monitored, and any leakage
parts shall be immediately repaired
Discharge line to be protected from the damage PM
Collapse of
Discharge of water Special zone to be provided over the discharge line for Site Engineer,
storage/ flooding Operatives
to the temporary 5 4 20
crossing the vehicle/equipment 5 1 5 Construction
Personnel injury Environment
storage or lagoon Regular inspection and maintenance to be done for the Manager,
Property damage
storage area to prevent from collapse HSE Officer
Emergency arrangements in place DMCOP CHAPTER 2
General Health and Safety Provision
Can occur when Poor housekeeping is responsible for the greatest proportion
particles do dust. of hook up and commissioning injuries. Do not expect
Debris or grit etc. others to tidy up. Work sites must be left tidy for the Foreman, Site
Operatives
Are blown around following shift. Engineer,
Foreign bodies in Consultant/
the workplace or 5 4 20
Personnel’s must wear appropriate eye protection and 5 1 5 Construction
eyes Client officials
when such minimize the amount of dust created. manager,
and visitors
particle is HSE Officer
DMCOP CHAPTER 2 General Health and Safety
dislodged from
work areas Provision
Serious personnel
injuries like cut
HSE induction, Craft Trainings, Adequate communication
Slips, trips & falls injury, crush
of Method statement & Risk assessment to work force.
while handling & injury, eye injury,
fixing. fracture, internal
Adequate competent supervision, PPE (safety shoes,
injuries while fall,
coverall, hand gloves, safety goggles, helmets, full body
Faulty hand tools, penetration of Work force Site Engineer,
safety harness etc), daily Toolbox talks, housekeeping,
sharp edges of steel bars into Construction
Handling provision of safe working platforms, access/egress, checking
reinforcements human body or manager,
1 reinforcement Consultant & 4 5 20 of hand tools before starting the day work and adequate 4 1 4
steel and fixing death etc. employer provision of first aid, emergency arrangements and other Superintendent,
Falling of steel Representatives welfare facilities in place. Foremen
reinforcements and visitors. Provision of adequate storage facilitates of steel. HSE Officer
from height. Provision of timely waste removal and provision of separate
skips of steel as well as domestic waste. (waste management
Striking/hit by steel
Generating waste system)
while working.
steel & domestic DMCOP CHAPTER 2 General Health and Safety
Waste generation. waste lead Provision
environment
pollution
Sudden releases Obtain TTC Lifting permit and fulfill all PTW requirement
Lifting equipment and lifting gears must be certified and Site Engineer,
of load or failure Work force
Unplanned lifting will lead to crane operator and rigger must be competent Construction
operation of Consultant & 5 4 20 5 1 5 manager,
fatality /serious employer
formwork DMCOP CHAPTER 2 General Health and Safety Provision Superintendent,
injuries. Representatives
&equipment’s & CHAPTER 21 Sling and Rigging Equip
Overturning of and visitors Foremen
liftingequipment’s HSE Officer
Failure of pump
may fall over the
men will lead
Collapse/failure serious
of concrete pump injuries/property Check the third-party certification of concrete pump,
Site Engineer,
/transit mixer. damage. Work force concrete pouring skips, lifting gear certifications&
Construction
Hazard from using Failure of skips Consultant & maintenance records.
manager,
concrete pouring and falling over employer 5 4 20 Use banks man/flag /rigger for guiding the loads/pump. 5 1 5
Superintendent,
skips. the men. Representatives Remove the waste concrete/ spilled concrete as early as
Foremen
Collapse of Collapse of and visitors possible and dispose it properly
HSE Officer
shutters. shutters will lead DMCOP CHAPTER 2 General Health and Safety
to fatality/serious Provision
injury by
crushing, trapping
of men inside the
shutters.
Chemical burns
Site Engineer,
form concrete and Work force
Construction
skin diseases from Consultant & Appropriate PPE especially hand gloves and gumboots must
Skin diseases and manager,
direct contact with employer 5 4 20 be provided. Washing facility must be available nearby. 5 1 5
eye injury may Superintendent,
concrete. DMCOP CHAPTER 18 Chemical Materials Hazard and
occur Foremen
Representatives Labeling HSE Officer
Hazard of concrete and visitors
splash into eyes
Site Engineer,
Construction
Hazards from Hand Arm manager,
5 4 20
Rotate/provide rest time for vibrator operator to reduce the 5 1 5
concrete Vibration Superintendent,
Work force effect of HAV.
vibrator.(hand arm syndrome (White Foremen
DMCOP CHAPTER 14 Hand and Power-Operated Tools
vibration) finger)
HSE Officer
Serious injuries Use safe access/egress in to the trench for machine as well
due to fall from Work force Site Engineer,
as workers.
height and affect Consultant & Construction
Unsafe 5 4 20 DMCOP CHAPTER 2 General Health and Safety 5 1 5 manager,
emergency employer
access/egress
Representatives
Provision Chapter 9 Excavation Superintendent,
evacuation/ rescue
operations and visitors Foremen
HSE Officer
Site Engineer,
Minimize the exposure time Construction
Vibration from Hand Arm manager,
Work force
Jack hammers. Vibration 5 4 20 Rotate/provide rest time for vibrator operator to reduce the 5 1 5 Superintendent,
syndrome (White effect of HAV (Hand Arm Vibrations). Foremen
finger) DMCOP CHAPTER 2 General Health and Safety HSE Officer
Provision
RA-29 Task: WORKING WITH ROAD SAW (ASPHALT CUTTING) Date: 07.12.2021
OHS & E
Persons OHS & E Initial
OHS & E Residual Risk Responsible
SN Activity Hazard /Aspect Risk / Impact /Property Risk Rating
Existing Controls Measures Rating Person
Involved
S P SxP S* P* SxP*
Work force Make sure the reservoir of cutting fluid always full Site Engineer,
Generation dust. Dust inhalation. Consultant & Construction
Oil spills from the Environment employer Provide regular maintenance for the machine. manager,
4 4 16 4 1 4
machine. pollution Representatives Superintendent,
and visitors and Provide and maintain suitable spill kits if any Foremen
DMCOP CHAPTER 2 General Health and Safety
Environment Provision HSE Officer
Site Engineer,
Possibility of site Work force Provide adequate traffic diversions or traffic managements. Construction
Hazards from site traffic accidents, Consultant &
DMCOP CHAPTER 2 General Health and Safety manager,
traffic. fatality/ serious employer 5 5 25 5 1 5
Provision CHAPTER 6 Sign Signals and Barriers Superintendent,
injuries
Foremen
Representatives
and visitor
HSE Officer
RA-30 Task: WORKING WITH MOBILE CRANES-LIFTING OPERATIONS/CONSTRUCTION WORKS Date: 07.12.2021
OHS & E
Persons OHS & E Initial
OHS & E Residual Risk Responsible
SN Activity Hazard /Aspect Risk / Impact /Property Risk Rating
Existing Controls Measures Rating Person
Involved
S P SxP S* P* SxP*
Site Engineer,
Work force Provide/maintain good housekeeping and fire extinguishers Construction
Consultant & around the area to reduce the fire hazard.
Fire hazard to the Loss of life and manager,
employer
crane. property due to 5 4 20 5 1 5 Superintendent,
Representatives
fire. Implement no smoking at site to reduce the fire hazard Foremen
and visitors
DMCOP CHAPTER 21&22 Slinging and rigging & HSE Officer
Cranes
Site Engineer,
Work force
Fire hazards and Loss of life and Provide/maintain good housekeeping and fire extinguishers Construction
Consultant & 5 4 20 5 1 5
mechanical failure property due to around the area to reduce the fire hazard. manager,
employer
to the machine. fire. Implement no smoking at site to reduce the fire hazard Superintendent,
Representatives
and visitors
DMCOP CHAPTER 9 Excavation Foremen
HSE Officer
Site Engineer,
Work force Follow the weather forecast and stop operation in wind /
Equipment Construction
Consultant & poor visibility.
Adverse weather collision, hitting 5 4 20 5 1 5 manager,
employer Provide temperature and other weather monitoring
conditions. personnel due to Superintendent,
Representatives information to work force.
poor visibility Foremen
and visitors DMCOP CHAPTER 9 Excavation HSE Officer
Site Engineer,
Electrocution, Concrete barriers will be placed around pylon prior to Construction
Death/ Serious 5 5 25 commencement of clearing, leveling and compacting works. 5 1 5 manager,
Striking of pylon Operatives/
burn Superintendent,
inspectors DMCOP CHAPTER 9 Excavation
Disruption to Foremen
supplies. HSE Officer
Collision of plant Plant and equipment entry shall only be allowed access to
5 4 20 working zone via goalposts and shall not move outside of 5 1 5
Site Engineer,
and equipment. Serious injury, Plant operators
working zone which will be demarcated by traffic cones Construction
fatality, fire, and site
Oil spillage manager,
01 Scope
04 Inspection/ Monitoring
08 Emergency response
09 Reporting
10 Posters
12 Cleaning Register
13 DM Circular
15 Distribution
16 Attachments
1.0 SCOPE
This plan aims to provide and maintain, so far as is reasonably practicable, a safe and healthy working environment
for all our employees including sub-contractor and be able to meet all duties by ensuring that adequate precautions
are taken to prevent Coronavirus, during and after the construction works. All the areas where HFC and their
subcontractors working will be covered (related to site works only and offices on site and Dubai Chamber building).
Description of Covid-19
The virus has been named “SARS-CoV-2” and the disease it causes has been named “corona virus disease 2019”
(abbreviated “COVID-19”) Corona viruses are a large family of viruses that are common in people and many different
species of animals, including camels, cattle, cats, and bats. Rarely, animal corona viruses can infect people and then
spread between people
Project/ Site Engineer (janin Jacob) shall be responsible for monitoring of the day-to-day activities on site.
• Co-ordinate with site HSE department to prevent Covid-19.
• Ensure the provided necessary resources (sanitizers and cleaning liquids/ Items) are enough for
the project.
• Ensure that contingency plan of covid-19 is implemented at the site.
3.01 Supervisors/ Charge Hands shall be directly responsible for the day-to-day job at site.
• Conduct trainings and awareness regarding the Covid-19 & Hygiene.
• Make sure the Housekeeping is maintained well.
• Ensure that all the employees are using adequate protection equipment’s.
• If anyone found sick at site immediately inform to the safety department.
3.02 Subcontractors: -
• Ensure that all work area, Welfare facilities are hygiene.
• Conduct adequate training for the labors and staff.
• Provide adequate PPE’s such as Hand protection, Eye protection, and Face mask then work related
PP’s.
• Arrange training cleaning employees with adequate protection measure such as Hand protection,
Eye protection, and Face mask.
3.03 Workers: -
• Avoid close contact with people who are sick.
• Avoid touching your eyes, nose, and mouth.
• Stay home when you are sick.
• Cover your cough or sneeze with a tissue, then throw the tissue in the trash.
• Clean and disinfect frequently touched objects and surfaces using a regular household
cleaning spray or wipe.
Follow CDC’s recommendations for using a facemask
3.04 Safety officer (Praveen K. Pillai) shall be responsible for the health & safety aspects on site as per
the Main contractor and safety Manual.
• Ensure all necessary resources are provided to control Covid-19 at the site.
• Provide adequate Trainings and awareness to the employees.
• Ensure the employees are using all the provided necessary items in a respective manner.
• Ensure that the office and welfare area are clean and tidy.
• Provide and maintain adequate signage.
4.0 Inspection and Monitoring
• HFC security personnel will monitor the employees check temperature of all the employees while entering
and even when descending the site.
• While entering the camp camp-boss or security staff will check all employees’ temperature.
• HFC safety officer will monitor all site staff (contractor, subcontractors and consultant) and check their
temperature in daily basis at offices.
5.0 Strategies Implemented for the employees on site to fight against corona virus (COVID-19)
5.1. Temperature monitoring is conducting for all staff and workers including consultant in daily basis.
5.2. Any employees returning from their home country/other countries/leave will be
quarantined/isolated until negative test result.
5.3. Members of staff are advised to avoid travelling abroad. A range of preventive measures are taken upon
return (including medical checks and quarantine) HFC will assess employees’ return to work on case by case
basis
5.4. Offices, office accessories and welfare facilities are disinfecting in daily basis with appropriate cleaning
agents.
5.5. Labor accommodations, transportation vehicles and prayer room are disinfecting in daily basis.
5.6. Business travel is only allowed if authorized by the company top management
5.7. Non-essential meetings and gathering in the office or on site shall be avoided. Employees shall utilize the
online facilities to hold meetings if possible.
5.8. If unavoidable, indoor meetings may proceed with the minimum number of attendees being seated at
least 2 meters apart if possible, in a well-ventilated room.
5.9. Meeting room surfaces will be sanitized/disinfected after each meeting.
5.10. Greeting will be a simple wave or a hand to chest gesture and must not entail hand shaking, hugging or
kissing.
5.11. Vulnerable employees are more at risk of severe COVID-19 effects and hence shall be given the choice
to work from home if possible.
5.12. If work from home is not practical, then vulnerable employees shall keep their direct contact with others
to the absolute minimum.
5.13. Vulnerable employees are to conduct work from home should a COVID-19 case be identified at work
5.14. Hand sanitizers and hand washing products are provided in all the areas, work stations, welfare facilities,
site offices and security point.
5.15. Face masks and hand gloves are made available for necessary staff on site.
5.16. Designating one receiving desk for all submittals (i.e. Admin desk).
5.17. Visitors and members of staff suffering from flu-like symptoms shall be instructed to work from
home/hotel until they are given the all clear
5.18. Alternative days for Working from home is now mandatory for office staffs where ever possible (Planning
Engineers/QS/Timekeepers/Draughtsman etc.)
6.1. The receptionist who receives the items wears latex non-powdered gloves.
6.2. The item particulars are recorded on a log sheet and the receiving date and time are recorded
on each item.
6.3. If the item surface is of a nature that can be sterilized safely (i.e. smooth plastic, metal etc.) then
this will be done using the sterilizing agents and the item is then delivered after tagging ‘
STERILISED’ to the intended recipient.
6.1. Personal hygiene is key in preventing cross contamination and spread of all types of bacteria and viruses.
Members of staff will be reminded to practice good personal hygiene through circulars, posters and in person.
Employees are to sanitize at least daily their own work space including:
a) Keyboards;
b) Desk phones;
c) Mobile phones;
d) Desk working space.
Sanitizers and tissues will be distributed around the office for this purpose. All contaminated items (wipes, tissues,
masks etc.) are to be disposed of in the bins immediately.
6.2. Employees and visitors shall maintain a good standard of personal hygiene at all times by:
a) Washing hands with soap and water for at least 20 seconds or alternatively rubbing their hands with alcohol
sanitizer after scanning their fingers, shaking hands, sneezing, coughing or touching unclean surfaces.
b) Preventing other from exposure to their sneezing and coughing by using tissue or by using their elbow/sleeve.
c) Avoiding touching their mouth, nose or eyes with dirty hands.
d) Avoiding close contact with others.
6.3 Visitors and members of staff suffering from flu-like symptoms shall be instructed to work from home/hotel
until they are given the all clear.
6.4. Sharing of work equipment
a) Headsets and other items including PPE, mouth, eye or ear pieces shall not be shared among staff.
b) Any other shared work items (i.e. IT equipment, stationery etc.) shall be sanitized before use.
• Immediate isolation of the individual and notification with the Authorities DHA call center -800 342, Estijaba
service at the operation center, Department of Health - 8001717 or Ministry of Health & Prevention -
80011111.
• The Area where that person has been working/staying will be deep cleaned and disinfected and those who
have worked closely with the individual will be stood down at home for 3 days (the period for any symptoms
to manifest)
• Work will resume after this period of precautionary stand down
• IF there is another case in the same office, then it means that the infection has spread and forthwith the
office will be closed and all staff will work from home.
Follow the flow chart in the event of medical emergency occurrence
9.0 Reporting
6.3 Test positive or have reasons to believe that they have been in contact with someone whom has
6.5 Witness other employees or visitors with flu-like symptoms in the office.
10.0 Posters
11.0 Contingency Response arrangements.
Government Health Authority Contacts
For any medical support or inquiry, please contact:
“Estijaba" service at the operation centre –Department of Health at 8001717
Ministry of Health & Prevention at 80011111
Dubai Health Authority at 800342
Site Emergency Contact Number
SL Name Position Contact Number
01 Ahmed Abdelkader Project Manager 0564229585
02 Gopikrishnan Con. Manager 056 5071085
03 Sajin Kumar vijayan Safety Officer 0565481542
04 Subhash First Aider 056 5053244
NEAREST HOSPITALS
Hospital Name Contact Number Distance & Time
Rashid Hospital 04 219 2000 31 min (32.7 km) from site
NMC Royal Hospital, DIP 04 810 8808 29 min (35.3 km) from site
+
APPENDIX – H
Environmental Impact Assessment & Control
ENVIRONMENTAL IMPACT
ASSESSMENT AND CONTROLS
Evaluation of Environmental Impact-Criteria
Fuels, oils and chemicals will be stored and used to prevent pollution as follows:
Activity Impacts Control Measures in Place Additional Control measures
Storage.
1. Drums will be kept in a bund or
Pollution of surface and 1. Storage areas for fuels, oils and chemicals will be located away from
drip tray in a designated area,
ground water. heavily trafficked areas. If this is not possible the fuels, oils and
Storage and use of fuels, oils and with a designated area for
chemicals will be protected from damage by vehicle impact.
Chemicals, Unloading of Diesel. Contamination of Land Air empty drums awaiting removal
2. Tanks for fuels, oils and chemicals will be surrounded by a bund with from site
Pollution
all pipe work kept inside the bund. Bunds containing more than 200
liters of oil, fuel or other liquids will hold 110% of the largest tanks 2. Bags and sacks of materials will
capacity. Fuel dispensing hoses should be fitted with automatic cut- be kept off the ground on
off valves. The area around the tanks and bunds will be concreted and pallets in a designated area and
graded so that spills can be contained and easily cleaned up. covered
3. Small containers of liquids will be kept in a location where they will
not cause pollution if incidentally split
4. All containers will be labelled with their contents and capacity
5. Training and information to be given to all operatives
REFUELLING: -
Unloading: -
Storage and use of fuels, oils and Pollution of surface and 1. Determine the fuel level in the tank and calculate the volume it can
Chemicals. ground water. The tank truck unloading will be
accommodate more.
done during day light hours except
Contamination of Land Air 2. The operator to ensure that spill response materials are in adequate
under
supply.
Pollution emergency conditions and will be
3. Tank trailer brakes shall be set, the wheels shall be chocked, and driver scheduled whenever possible.
shall remain with the vehicle during the entire unloading period.
4. Ensure proper methods are used for hose connection, hose
disconnection and precautions are taken to avoid unnecessary
drippings and/or releases from hoses and connection equipment.
5. Ensure that storage tank is vented prior to connecting unloading line
6. Ensure that all hoses are connected tight and that a collection bucket
is placed under the trailer –unloading valve.
7. Once unloading has ceased, the hoses will be disconnected such that
any material in the line will gravity drain in to the tank
1.2 Storage and use of Vehicles, Plant and Equipment
Vehicles, Plant and equipment will be stored, used and maintained to prevent pollution as follows:
Activity Impacts Control Measures in place Additional Control measures
Construction activities will be managed as follows to minimize noise emissions and the risk of nuisance to the local communities:
Activity Impacts Control Measures in place Additional Control measures
1. Traffic routes to be reviewed to identify any sensitive receptors, such as schools, If excessive smoke is emitted from any
Traffic going to and from Site Noise pollution
hospitals where special controls may be needed to minimize the impacts. vehicle, plant or equipment the item
Air Pollution 2. Engines will be turned off when not in use (this also reduces fuel must be serviced immediately. If this
consumption) does not rectify the problem the item
Depletion of
natural 3. Drip trays will be placed under any vehicle, plant or equipment that is leaking will be removed from site
resources oil or fluid and the item will be serviced immediately to repair the leak
4. Vehicle’s will keep to defined roads where practicable
5. Electrically powered plant will be used, instead of diesel or petrol-
powered plant where practicable
6. Doors and covers on plant and vehicles will be kept shut
7 Training and information to be given to all operatives
8 If excess noise is noticed from any vehicles, it has to be investigated and to be
rectified through proper maintenance or other suitable means.
1.5 Maintenance of Vehicles and Plant
Storage, use and maintenance of Nuisance to local MAINTENANCE OF VEHICLES, PLANT AND EQUIPMENT
Vehicles, plant and equipment communities 1. Vehicles and plant will be regularly maintained
Pollution of surface 2. All major Maintenance works of vehicles of vehicles, plant and
and ground water equipment that may be easily removed from site will not take place Vehicles, plant and equipment will
on site but off-site in a proper workshop not be washed down on site, except
Contamination of land Air
3. Where it is not possible to remove maintenance will take place on to remove any mud/soil before
pollution site. Drip trays and containers will be used to contain oil and fluid leaving the site in order to keep the
changes and any leaks and spills. roads clean and tidy. A minimal
4. Training and information to be given to all operatives amount of water is to be used
1.6 Waste
Concreting
Concreting Pollution of surface and 1. Concrete from vehicles, plant and equipment such as the chutes of ready –
ground water mix wagons will be washed with the minimal amount of water into a designated Nil
wash out pit. The water will evaporate leaving concrete which may be used
hardcore or sent to a concrete recycler
2. Concrete from static lines will not be blown back directly onto the land.
Plastic sheeting is to be provided at all static lines
3. Concrete waste from buckets must only be cleaned out in a designated area.
Spills or incidental discharges from buckets are to be cleaned up immediately
1.8 Welfare Facilities
Contamination of Land Do not discharge to storm drain system if sediments present Nil.
Site welfare facilities (e.g. toilets,
showers, canteen) Pollution of surface Toilets, washrooms and any canteen facilities will discharge into a septic tank and
water with silt taken off site at regular intervals to be disposed of at a licensed area.
Pollution of surface or To prevent incidentally overflowing these tanks a float alarm should be fitted.
ground water
Odour problems
Contamination of Land
1.9 Excavation and Sewerage Works
Excavation and Sewerage Works Impact of Flora such as – Do not destruct any tree if it happens to be at the place of excavation. The tree to be Nil
contribute to global removed carefully with its roots and replant it in another place. Do not remove
warming, national trees (Ghaf Tree). Get permission from the authorities before removal and
enhanced greenhouse re-planting
effect, drier climate
Use of recyclable/reusable Generation of general waste, land Use the printer cartridges to the maximum possible level of Issue and distribute information
resources-cartridges, contamination during disposal use, refill the printer cartridges a number of times before bulletin regarding this subject.
stationeries glass...etc. disposal