Tender Document: Karnataka Neeravari Nigam Limited
Tender Document: Karnataka Neeravari Nigam Limited
TENDER DOCUMENT
GAJ/ VEH/2022-23
Page
Sl.
Particulars
No. From
To
1. Face Sheet
2. Brief/ detailed Tender Notifications, Extension Notices etc.
3. Formal Tender Notice(Adapted version of KPWD Form
P.W.G.66)
4. Tender for Works
5. Declaration
6. Definition of terms used in the Contract Document
7. General Conditions of Contract
(adapted version of KPWD Form. P.W.G 65)
8. Schedule A
9. Schedule B
10. Schedule C
11. Additional Conditions of Contract
12. Detailed Technical Specifications
13. Circular
14. List of Drawings
15. List Of Land Owners
16. Drawings
17. Annexures :
A. Form of Bank Guarantee
B. Form of Agreement
C Schedule of Royalty Charges
D. Proceedings of Govt. of Karnataka vide G.O. No.
PWD/11/GMS/64 dated 10.03.1966 pertaining to deductions
towards shrinkage or settlement of embankments.
18 Enclosures
Note: Contractor shall give fill up the tender for works, the declaration and the Schedule
‘B’ and duly affix his signature. He shall also sign Schedule ‘A’ and Schedule ‘C ‘. Further,
7 Date of opening of :
tender through e-portal
3 Name of Bank :
4 Validity Period :
¸ÀÆZÀ£É:
mÉAqÀgï ¥Àæ¥ÀvÀæUÀ¼À£ÉÆß¼ÀUÉÆAqÀ, mÉAqÀgï ¥ÀĸÀÛPÀUÀ¼À
¨É¯ÉAiÀÄÄ ¥Àæw PÉ®¸ÀPÉÌ PɼÀPÀAqÀAvÉ EgÀÄvÀÛzÉ.
PÁAiÀÄð¥Á®PÀ EAf¤AiÀÄgï,
PÀ¤Ã¤¤, UÀÄt ¤0iÀÄ0vÀæt
«¨sÁUÀ,
vÀÄ.ªÉÄÃ.0iÉÆÃ,
²ªÀªÉÆUÀÎ
Form - 1
1. NAME OF WORK :- Supply of Vehicle on Hire basis to No.3 Q.C Sub-Division, Gajanur
for the year 2022-23
2.
Estimated cost of the work put to tender:3,99,000
2.Blank tender Document which includes the complete set of drawings, the complete
specification of the work to be done, the schedule of quantities of various items of
work to be done, and the set of Conditions of Contract to be complied with the by the
3.The contractors can request for e-tendering documents from __________ in the
web site http://eproc.karnataka.gov.in/eportal/index.seam link e–tender document on
payment (non-refundable) of Rs. _______ towards the transaction fee. While
applying the contractors can pay the transaction fee in the e-procurement portal
using payment modes, Credit card/Direct Debit/National electronic fund transfer
(NEFT)/ over the counter (OTC) up to _________ during office hours.
The contractor can have access to e–tender document from _______ to _______
up to _____ pm.
Submission of completed e-tendering document will be from _______ to
__________up to ______ pm.
4. Completed Tender document should be submitted through the e-procurement
portal on the website itself. In the event of tenders made by an individual, he should
sign documents with his full name. In the event of the tender being submitted by a
firm, it must be signed separately by each partner thereof or in the event of the
absence of a partner, it shall be signed on his behalf by a person holding a power of
attorney authorizing him to do so. Such power of attorney should be produced with
the tender and it must disclose that the firm is duly registered under the Indian
Partnership Act, if it is made by a Corporation it should be signed by a duly
authorized officer with satisfactory evidence of its authorization. Such Tendering
Corporations is required to furnish evidence of its corporate existence.
5. Authorized copies of the specifications, designs and drawings and the schedule of
rates and any relevant documents required in connection with the work shall be
open for inspection to the tenderers at the concerned office of the Executive
Engineer, KNNL UTP Division .................................... District during office hours.
The tenderers inspecting the documents should sign in the register kept for this
purpose in the office, in token of having seen those documents. The tenderers
should note that the quantities mentioned in the Schedule-B of contract form are
only approximate.
6. Each tenderer should give clearly in his tender, his residential address and postal
address. The delivery at the above named places of posting in the Post Box
regularly maintained by the Post Office or sending letter by Registered Post with
Acknowledgement due or by other communications by the Executive Engineer shall
be deemed sufficient service thereof.
7. The tender of the work shall not be witnessed by a contractor or contractors who
has/have tendered or who may tender for the same work. Failure to observe this
condition would render the tenders of the contractors tendering as well as witnessing
the tender liable for summary rejection.
8. The schedule of materials to be supplied by the Department and their rates will be
as indicated in Schedule-A of contract form. Tenderers shall quote their rates for
finished works accordingly. Not withstanding subsequent change in the market
9. The percentage quoted by the contractor and the incidental tender amount on the
basis of percentage quoted must be inclusive of Sales Tax and any other duties,
taxes, etc. The contractor is also required to pay quarry Fees, Royalties, Octroi
Dues levied by the State Government or any Local Body or Authority and ground
rent if any, charged by the Executive Engineer for stacking materials. No extra
payment on this account will be made to the contractor.
10. The Person submitting the tender shall fill up the Schedule-B stating at what
percentage of work specified therein he is willing to undertake work.(Percentage
above or below amount mentioned in the Schedule-B shall be indicated both in
figures and words) Only one percentage shall be indicated in the schedule both in
figures and in words. The total cost of the whole work may also be shown therein.
i)In case of discrepancy between percentage quoted in words and figures, lower
of the two shall be considered. The contractor shall quote the percentage both in
words and figures. If he does not, the tender will be treated as incomplete and
shall be rejected.
ii) The amount stated in the Schedule-B of the contract form will be adjusted by the Executive
Engineer in accordance with the above procedure for the correction of errors, and the contractor shall
be bound by that, if the contractor does not accept the amount so corrected, the tender will be
rejected and earnest money will be forfeited.
The Tenderer should have been registered in KPWD class… /enrolled in KNNL
under category ___ and above in the selection list of contractors. (The copy of
certificate shall be scanned and attached to the e-tender document.
12 a-(i) Each tenderer must pay specified full Earnest Money of Rupees _______ in
the e-proc platform only through any of the payment modes such as Credit card/
Debit Card /NEFT/ OTC/ for the works for which the amount put to tender is below
Rs.50.00lakhs.
a-(ii) Each tenderer must pay an Earnest Money of Rupees upto 50,000-00 in the e-
proc platform through any of the payment modes such as Credit card/ Debit Card
/NEFT/ OTC/ ;and the remaining balance EMD of Rs.__________ through Bank
Guarantee issued by Nationalised/ Schedule Banks for the works for which the
amount put to tender is in between Rs.50.00lakhs up to Rs. 1.00Crore.
NOTE: The validity of Bank Guarantee etc., which is furnished as Earnest Money
along with the tender shall be for a period of one hundred eighty days from the date
specified for opening of tenders. In case of currency period of the tender were to be
extended by the tenderer at the instance of the Executive Engineer (vide para 17 (b)
below), the validity period of the Bank Guarantee etc., shall also simultaneously be
extended upto the date till which the tender is kept open. Successful tenderer
should extend the validity period of Bank Guarantee for a further period as indicated
in the bank guarantee formal given in Annexure-A.
15 a) The tenders for works remain open for acceptance for a period of one hundred
eighty days from the date of opening of tenders. If any tenderer withdraws his
tender before the said period or makes any modifications in the terms and conditions
of the tender which are not acceptable to accepting Authority then the whole amount
of Earnest Money Deposit specified in para 14 (a) shall forfeited to KNNL. The
Nigam is also at liberty to take any other penal action as it deems fit against such
contractor.
16. If the percentage quoted by contractor for the work is below Ninety percent of the
estimated amount then the successful contractor shall furnish an additional
performance security in the form of Bank Guarantee for an amount equivalent to the
difference between the cost as per quoted percentage and 90% of the estimated
amount of all items. In case of contractor quoting percentage above 110% of the
estimated amount of all items, then over and above 110% of the estimated amount
will be withheld during the progress of work.
17.The authority competent to accept the tenders shall have the right of rejecting all or any of tenders
without assigning any reasons and will not be bound to accept the lowest tender.
a) From the date of final decisions on the tenders received in the case of rejected
tenders,
b) From the date of expiry of the initial validity period of 180 days in the case of
tenders who do not extend the validity of their offer beyond that period.
19 The successful tenderer must produce the latest Income Tax clearance certificate
before the work is entrusted to him.
20. The contractor whose tender is accepted shall execute the agreement within 15
days from the written intimation of acceptance of tender. Additional 30 days time
may be allowed with a penalty of 0.5% of contract value.
21.The successful tenderer shall pay Security Deposit in value equivalent to 7.5% of
the cost of work (including earnest money) as laid down in clause 1 (a) of Contract
Form.
22. Failure on the part of the successful tenderer to pay the Security Deposit
amount, additional performance security, if any and to execute the contract
Agreement as provided in para 21 above would constitute a breach of the contract
and hence, he shall be liable for all the consequences resulting there from. Such
failure should entail forfeiture of Earnest Money Deposit. Such failure would also
entail removal of contractor’s name from the select list of contractors of KNNL. In
addition, the competent authority is entitled to have the work executed at the risk
and cost of the contractor. The contractor shall be responsible for making good, in
cash, this extra expenditure failing which the same shall also be recovered from his
dues from other works as contemplated in Clause 36 of the conditions of Contract.
23.The successful tenderer shall pay compensation to workmen working under him
for any injury caused during the execution of work as per Workmen’s Compensation
Act in force from time to time, failing which the amount will be deducted from his bills
and paid to the injured workmen.
25. The submission of tender by a contractor implies that, the contractor has read
the contents of the Tender Notice and Contract Form and all other papers included
in the tender document and made himself aware of the scope and the specifications
of the work to be done and the availability of the quantity of materials required.
26.The tender of any contractor who does not accept the conditions contained in the
Tender Documents is liable to be rejected.
27.Total cost of work on hand in KNNL with one contractor should not exceed Rs.
20.00 crores (Rs. twenty crores) excluding cost of any major works like dam
barrage, lift irrigation gates etc., The contractor should also enclose a statement of
works on hand in KNNL with their balance cost.
28. Bidders for the works who have already executed the works and / or executing
the works under Karnataka Neeravari Nigam Limited should enclose performance
certificates from the concerned executive Engineers for having satisfactorily
executed or executing the works under taken by them under Karnataka Neeravari
Nigam Limited. Such tenders received without performance certificates or
unsatisfactory performance are liable for rejection.
Form -II
To
The Executive Engineer,
KNNL. QC Division. U.T.P,
SHIVAMOGGA
Sir,
Tender for Works: Supply of Vehicle on Hire basis to No.3 Q.C Sub-Division, Gajanur for the
year 2022-23
I/we hereby tender for the execution, for the Managing Director KNNL, Ltd. (herein
before and hereinafter referred to as Nigam of the work specified in the under mentioned
Memorandum within the time specified in the Memorandum of the rates quoted for each
item specified in Schedule ‘B’ (Memorandum showing items of works to be carried out) and
in accordance in all respects with specifications, designs, drawings, and instructions in
writing referred to in clause 12 of the annexed conditions of contract and agree that when
materials for the work are provided by the Nigam such material and the rates to be paid for
them shall be as provided in Schedule ‘A’ hereto.
a Name of work : Supply of Vehicle on Hire basis to No.3 Q.C Sub-
Division, Gajanur for the year 2020-21
b Estimated Cost Put to : 3,99,000
tender
c Earnest money @ 2.5% : 10000.00
d Security Deposit @ 5.0% : 20000.00
i Demand Draft/Bankers :
cheque/ Bank Guarantee
(not less than the amount
of earnest money vide (c)
above)
ii To be deducted from the :
current bills at the rate not
less than those mentioned
in column
iii In the table below clause : 10000+20000
1(i) of conditions contract
Total of (i) & (ii)
e Percentage, if any to :
deducted from each running
bill vide (d) (ii)
f Time allowed for the work : Upto March 2023
from the date of issue of
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the
terms and provisions of the Conditions of Contract and the additional Conditions of Contract
annexed hereto and all the terms and provisions contained in Notice inviting Tenders so far
as applicable, and in default thereof to forfeit and pay to Nigam the sum of money
mentioned in the said conditions.
DECLARATION
I/We hereby declare that I/We have made myself/ourselves thoroughly conversant
with local conditions regarding all materials such as stones, murrum and sand etc., and the
labour on which I/We have based rates for this work, and that the specifications, plans,
designs, Conditions of Contract etc. on which rates are based, have been completely
studied by me/us before submitting the tender. I/We undertake to use only the best of
materials approved by the Executive Engineer construction/and by the Quality Control
Authority before starting the work and to abide by his decision.
“SITE” shall mean and include all the land in which the operations in respect of the
work are carried out. It shall also include the material stacking yard and the area where
permanent or temporary structures are put up for facilitating the execution of the work.
“TEST” shall mean such tests as are required to be carried out either by the
Contractor or by the Engineer, from time to time and on completion as detailed in the
specifications before the work is certified as being satisfactory and is taken over by
Engineer-in-Charge.
Words used in singular shall also include the plural and vice-versa where the context
so demands.
CONTENTS
Clause – 1 Security Deposit
Clause – 4 Contractor to remain liable to pay compensation if action is not taken under
Clause-3.
Clause – 19 Contractor liable for damage done, and for imperfections for twelve months
after certificate of completion
Clause – 20 Contractor to supply plant, ladders, scaffolding, etc., and is liable for damages
arising from non provision of lights, fencing etc.
Clause – 21 Issue of plant and Machinery on hire
Clause – 23 Liability of contractor for any damages done in or outside work area
Clause – 34 Contractor not entitled to any claim or compensation for delay in execution of
work, borrow pits
Clause – 36 Set off against any claim of KNNL/Government under other contracts.
Clause – 42 Deleted
Clause – 43 Contractor not to quote price exceeding controlled price fixed by Government.
SECURITY DEPOSIT
Clause 1 (a) - The person/persons whose tender may be accepted(hereinafter called the
Contractor which expression shall unless the context otherwise requires, includes his heirs,
executors, administrators and assigns) shall pay security deposit in Demand Draft/Bank
Guarantee/Banker’s Cheque of any Nationalised Bank equivalent to the Earnest Money
Deposit indicated in Column (ii) of the table given below and shall permit KNNL
(a). To deduct at the percentage mentioned in Column (iii) of the table given below of all
moneys payable for work done under the Contract, at the time of making such payments to
him/them and
(d)When the Further Security Deposit deducted from the bills exceeds Rs. One lakh,
the amount in excess of Rs. One lakh, at the request of the contractor, be released to him
against the production of Bank Guarantee for an equivalent amount in the prescribed form.
The Bank Guarantee should be kept valid till the completion of the period mentioned in
Sub-clause (f) below.
(e) All compensation or other sums of money payable by the Contractor to KNNL
under the terms of this contract may be realised or deducted from any amount payable to
him or Security Deposit payable to him or from the interest arising there from, or from any
sums which may be due or may become due by KNNL to the Contractor on any account
whatsoever and in the event of his security deposit being reduced by reason of any such
realisation or deduction as aforesaid, the Contractor shall, within ten days thereafter, make
good in cash any sum or sums which have been deducted from, or raised by sale of his
security deposit or any part thereof.
(f) The Security Deposit lodged/paid by a Contractor shall be refunded to him after
the final bills are paid or after twelve months, from the date of completion of the work,
during which period the work should be maintained by the Contractor in good order,
whichever is later.
Clause 2 :
(a) After acceptance of the tender, the Executive Engineer shall issue a written order
to the successful tenderer to commence the work. The Contractor shall enter upon or
commence any portion of work only with the written authority and instructions of the
Executive Engineer. Without such instructions the Contractor shall have no claim to
demand for measurements of or payment for, work done by him.
Programme of work
(b) The time allowed for carrying out the work as entered in the tender shall be
strictly observed by the contractor. It shall be reckoned from the date of issue of written
orders to commence work. The work shall throughout the stipulated period of the contract
be proceeded with, with all due diligence (time being deemed to be the essence of the
Note: The quantity of the work to be done within a particular time to be specified above
when the programme chart is not annexed, shall be fixed and inserted in the blank space
kept for the purpose by the officer competent upto the level of Chief Engineer to accept the
contract after taking into consideration the circumstances of each case, and the contractor
shall abide by the programme of detailed progress laid down by that officer.
The following proportions usually be found suitable in 1/4, 1/2, 3/4 of the time:
(i) Reasonable progress of earthwork that could be achieved will be 1/6, 1/2, 3/4
the respectively of total value of the work to be done.
(ii) ii) Reasonable progress of masonry work and concerting that could be achieved
will be 1/10th, 4/10th, 8/10ths of the total value of the work to be done.
(a) Without prejudice to KNNL’s right to recover any loss from the Contractor under
sub-clauses (b) and (c) of Clause 3 of the Contract, to rescind the Contract (of which
rescission notice in writing to the Contractor, under the hand of the Executive Engineer
shall be conclusive evidence) and in that case, the security deposit of the contractor
including whole or part of the lumpsum deposited by him and also the amount deducted
from his bills as Further Security Deposit shall stand forfeited and be absolutely at the
disposal of the KNNL.
(b) To employ labour paid by the KNNL and to supply materials to carry out the
work or any part of the work debiting the contractor with the cost of the labour and the
price of the materials (as to the correctness of which cost and price the certificate of the
Executive Engineer shall be final and conclusive against the contractor) and crediting him
with the value of the work done, in all respects in the same manner and at the same rates
as if it had been carried out by the contractor under terms of his contract, and in that case
the certificate of the Executive Engineer as to the value of the work done shall be final and
conclusive against the contractor.
(d) If the contractor does not maintain the rate of progress as required under Clause
2 and if the progress of any particular portion of work is unsatisfactory even after taking
action under Clause 2(c) and 2(d) the Executive Engineer shall be entitled to take action
under Clause 3 (b) or 3(c) at his discretion in order to maintain the rate of progress after
giving the contractor 10 days notice in writing whereupon the contractor will have no claim
for any compensation for any loss sustained by him owing to such actions.
(e) In the event of any of the above courses being adopted by the Executive
Engineer, the contractor shall have no claim to compensation for any loss sustained by him
by reason of his having purchased or procured any materials or entered into any
engagements or made any advances on account of or with a view to the execution of the
work or the performance of the contract. And in case the contract shall be rescinded under
the provision aforesaid the contractor shall not be entitled to recover or be paid any sum
for any work therefor actually performed by him under his contract unless and until the
Executive Engineer shall have certified in writing the performance of such work and the
amount payable in respect thereof and he shall only be entitled to be paid the amount so
certified.
Clause 4:In any case in which any of the powers conferred upon the Executive
Engineer by Clause 3 thereof shall have become exercisable and the same shall not have
been exercised, the non-exercise thereof shall not constitute a waiver of any of the
conditions hereof and such powers shall not withstanding be exercisable in the event of any
future case of default by the contractor for which under any Clause thereof he is declared
liable to pay compensation or penalty amounting to the whole of his security deposit and
In the event of the Executive Engineer taking action under sub-clause (a) or
(c) of Clause-3, he may, if he so desires, take possession of all or any tools, plant,
materials and stores in or upon works or the site thereof or belonging to the contractor, or
procured by him and intended to be used for the execution of the work or any part thereof,
paying or allowing for the same in account at the contract rates, or in the case of contract
rates not being applicable, at current market rates, to be certified by the Executive
Engineer whose certificate thereof shall be final. In the alternative, the Executive Engineer
may, after giving notice in writing to the contractor or his clerk of the works, foreman or
other authorised agent, require him to remove such tools, plant, materials or stores from
the premises within a time to be specified in such notice; and in the event of the contractor
failing to comply with any such requisitions, the Executive Engineer may remove them at
the contractor's expense or sell them by auction or private sale on account of the
contractor and at his risk in all respects, and the certificate of the Executive Engineer as to
the expense of any such removal, and the amount of the proceeds and expense of any
such sale shall be final and conclusive against the contractor.
Clause 5: (a) If the contractor shall desire an extension of the time for completion
of the work on the ground of his having been unavoidably hindered in its execution or on
any other ground, he shall apply in writing to the Executive Engineer before the expiration
of the period stipulated in the tender or before the expiration of 30 days from the date or
which he was hindered as aforesaid or on which the cause for asking extension occurred,
whichever is earlier and the Executive Engineer or other competent authority may, if in his
opinion there are reasonable grounds for granting an extension, grant such extension as he
thinks necessary or proper. The decision of such competent authority in this matter shall
be final.
(b) The time limit for completion of the work shall be extended commensurate with
its increase in cost occasioned by alterations or additions and the certificate of the
Executive Engineer or other competent authority as to such proportion shall be conclusive.
Clause 6: On completion of the work the contractor shall report in writing to the
Executive Engineer the completion of the work. Then he shall be furnished with a certificate
by the Executive Engineer of such completion, but no such certificate shall be given nor
shall the work be considered to be complete until the contractor shall have removed from
the premises on which the work shall have been executed, all scaffolding, surplus materials
and rubbish and shall have cleaned thoroughly all wood work, doors, windows, walls, floor,
or other parts of any building, in or upon which the work has been executed, or of which
he may have had possession for the purpose of executing the work, nor until the works
shall have been measured by the Executive Engineer or other competent authority or
where the measurements have been taken by his subordinates until they have received the
approval of the Executive Engineer or other competent authority, the said measurements
being binding and conclusive against the contractor. If the contractor shall fail to comply
with the requirements of this clause as to the removal of scaffolding, surplus materials and
rubbish, and cleaning on or before the date fixed for the completion of the work, the
Executive Engineer or other competent authority may, at the expense of the contractor,
remove such scaffolding, surplus materials and rubbish, and dispose of the same as he
thinks fit and clean off such dirt etc., as aforesaid and contractor shall be liable to pay the
amount of all expenses so incurred, but shall have no claim in respect of any such
scaffolding or surplus materials as aforesaid except for any sum actually realised by the
sale thereof.
(b) Not withstanding the fact that the machinery is operated by the department
crew, the Contractor shall be responsible to return the plant and machinery in such working
condition in which it was issued to him subject to reasonable wear and tear. He shall also
be responsible for all damages caused to the said plant and machinery at site of work or
elsewhere when in operation or otherwise or during transit, including damage to or loss of
part/parts, as also for losses due to failure to return them soon after completion of the
work for which they were issued. The Executive Engineer shall determine the liability of the
Contractor on account of damage and/or losses, if any, and shall be entitled to assess such
damage and/or loss and recover the same from the bills of the contractor or from any other
sums due to him. In the event of any dispute as to the nature and extent of damage/loss,
the decision of the Executive Engineer shall be final and binding on the Contractor.
KNNL to bear repair charges for normal wear and tear as decided by
Superintending Engineer
(c) During the period of hire, KNNL shall bear the charges for repairs
necessitated by normal wear and tear of tools, plant and machinery hired. The cost of the
repairs necessitated by negligent use of tools, plant and machinery shall be borne by the
Contractor. As to what repairs shall under the category of repairs due to normal wear and
tear, the decision of the Superintending Engineer shall be final.
Clause 23: Compensation for all damages done by contractor or his men whether in
or beyond the limits of KNNL property including any damage caused by spreading of fire
mentioned in Clause 22 shall be estimated by the Executive Engineer, and the estimate of
the Executive Engineer, subject to the decision of the Superintending Engineer on appeal,
shall be final and the contractor shall be bound to pay the amount of the assessed
compensation on demand failing which the same will be recovered from the contractor as
damages in the manner prescribed in Clause 1 or deducted by the Executive Engineer or
other competent authority from any sums that may be due or become due from KNNL to
the contractor under this contract or otherwise.
The contractor shall bear the expenses of defending and action or other legal
proceedings that may be brought by any person for injury sustained by him owing to
neglect of precautions to prevent the spread of fire and shall pay any damages and cost
that may be awarded by the court in consequence.
EMPLOYMENT OF FEMALE LABOUR
Clause 24: The employment of female labourers on works in the neighbourhood of
soldier's barracks should be avoided as far as possible.
WORK ON NOTIFIED HOLIDAY
Clause 25: No work shall be done on any notified holiday without the sanction in
writing of the Executive Engineer or other competent authority.
CONSEQUENCES OF SUBLETTING WORK WITHOUT APPROVAL, THE
CONTRACTOR BECOMING INSOLVENT, BRIBING ETC, BY CONTRACTOR
AND ACTION AGAINST THE CONTRACTOR
Work not to be sublet
Clause 26: (a) The contract shall not be assigned or sublet by the Contractor.
However, any specific portion of the work which is of a specialised nature and normally not
executable by a general Contractor could be got done by the specialised agencies which are
executing such works, after obtaining the specific approval of the Executive Engineer in
If the contractor shall assign or sublet his contract or any portion thereof
without the specific approval of the Executive Engineer or attempts to do so or become
insolvent or commence any proceedings to get himself adjudicated as insolvent or make
any composition with his creditors or attempts so to do or if any bribe, gratuity, gift, loan,
perquisite reward or advantage, pecuniary or otherwise, shall either directly or indirectly be
given, promised or offered by the Contractor or any of his servants or agents to any officer
or person in the employ of KNNL in any way relating to his office or employment or if any
such officer or person shall become in any way directly or indirectly interested in the
contract, the Executive Engineer or other competent authority may thereupon by notice in
writing rescind the contract and the security deposit of the contractor shall thereupon stand
forfeited and be absolutely at the disposal of KNNL, and the same consequences shall
ensure as if the contract had been rescinded under Clause 3 hereof and in addition, the
contractor shall not be entitled to recover or be paid for any work actually performed under
contract.
Clause 27: All sums payable by contractor by way of compensation under any of
these conditions shall be considered as reasonable compensation to be applied for the use
of KNNL without reference to the actual loss or damage sustained and whether any
damage has or has not been sustained.
(g) The Contractor should keep his employees covered under the provision of the EPF
Act and the employers state insurance Act. The contractor shall keep the KNNL its
Employees/ Officers indemnified from any loss or damages suffered by KNNL/staff. Officers
for any violation of the provision of the said Act by the contractor Notwithstanding the
above the KNNL shall have the right/remedy available to it under section 8(a) of the
Employees PF and Miscellaneous Act and the relevant provisions of the Employees State
Insurance Act.
Clause 39: All money due from the contractor under this contract may be
recovered by Government without prejudice to the other remedies, as if they were arrears
of Land Revenue.
CONTRACTOR TO COMPLY WITH THE PROVISIONS OF APPRENTICE
ACT
Clause 40: The contractor shall comply with the provisions of the Apprentice Act
1961 and Rules and Orders issued there under from time to time. If he fails to do so, his
failure will be a breach of contract and the Superintending Engineer may at his discretion
cancel the contract. The contractor shall also be liable for any pecuniary liability arising on
account of any violation by him of the provisions of the Act.
CONTRACTOR TO SUBSCRIBE TO WORKER’S AND CONTRACTORS'
BENEVOLENT FUND
Clause 41: The contractor shall subscribe to the Workers' and Contractor's
Benevolent fund at the rate of 0.10% of the gross amount of each bill payable to him in
respect of the contract. The amount of subscription should be recovered out of the amount
payable to him in each bill.
LUMPSUMS IN ESTIMATE – PAYMENT TO CONTRACTOR
Clause 42: Deleted.
CONTRACTOR NOT TO QUOTE PRICE EXCEEDING CONTROLLED PRICE
FIXED BY GOVERNMENT
Clause 43: The price quoted by the contractors shall not in any case exceed the
controlled price if any, fixed by KNNL or reasonable price which it is permissible for him to
charge a private purchaser for the same class and description of goods under the
provisions of Hoarding or Profiteering Prevention Act 1943 as amended from time to time.
Compliance with the provision of Hoarding and Profiteering Prevention Act
If the price quoted exceeds controlled price or price permissible under
Hoarding and Profiteering Prevention Act, the contractor will specifically mention this fact in
(i) The stipulated period of completion of the work is more than two years
AND
(ii) The tendered cost of the work exceeds :
(a) Rs. 50 Lakhs (Rupees fifty lakhs) in case of a Communication and Buildings
works AND
(b) Rs. 100 Lakhs (Rupees 0ne hundred lakhs) in the case of an irrigation work.
(a)The amount payable to the contractor and valued at the rates specified in
Schedule “B” attached to the contract shall be increased or decreased in accordance with
the rise or fall in the indexed costs of labor; materials, fuel, lubricants, electricity and other
inputs to the works by an amount as determined by the formula as prescribed in this
clause. The price adjustment is, however, subject to the following conditions; -
(i) Price adjustment shall not be applicable on the value of work carried out during the
initial 12 months of the contract period.
ii) Price adjustment shall not be applicable to additional / altered or substituted items
of work/or extra quantities executed by the contractor in respect of which rates computed
on the basis of the schedule of rates or market rates etc. prevailing at the time of execution
of such items/quantities are payable in terms of clause-13 of conditions of contract.
iii) Price adjustment shall apply only for work carried out within the stipulated time
including time extension granted by the Executive Engineer and shall not apply to the work
carried out beyond the stipulated time for reasons attributable to the contractor.
iv) Price adjustment shall be applicable on the value of work done during each quarter
period of the year.
v) Cost of materials supplied by the KNNL at fixed rates as specified in schedule ‘A’ to
the contract shall be excluded from the scope of the price adjustment.
vi) To the extent that full compensation for any rise or fall in costs of the contractor is
not covered by the provisions of this or other clauses in the contract the unit rates and
prices included in the contract shall be deemed to include amounts to cover the
contingency of such other rise or fall in costs.
b) (i) in the formula prescribed in (ii) and (iv) below the letter ‘R’ represents the
following .
R = Total value of work done during the quarter MINUR value of items indicated in
sub-clause (a)(ii) of this clause MINUR cost of materials supplied by Karnataka Neeravari
KNNL Limited under Schedule-‘A” to the contract and consumed during the quarter.
Note :- In the case of materials brought to site for which any secured advance is
included in the bill the full value of such materials as assessed by the Executive Engineer
(and not the reduced amount for which secured advance has been paid) shall be included
in the cost of work done for operation of this Clause. Similarly when such materials are
incorporated in the work and the secured advance is deducted from the bill, the full
assessed value of the materials originally considered for operation of this clause should be
deducted from the cost of the work shown in the bill, running or final.
Cost of Marterials :-
(iii) Price adjustment for increase or decrease in cost of material shall be paid
in accordance with the following formula :-
VM = 0.75 x PM / 100 x R(Mi-Mo)/Mo
VM = Variation in materials cost i.e. increase or decrease.
PM = Material component as specified in Sub-clause (c) of this clause.
Mo = Average wholesale price index number for all commodities in the twelfth
month reckoned from the commencement of contract period.
Mi = The corresponding index number for the quarter under consideration.
(‘) = The city nearest to the site of work to be specified here.
1 2 3 4
Schedule showing (Approximately) the materials to be supplied from the KNNL Stores for
work contracted to be executed and the rates at which they are to be charged for.
Rate at which the
Sl. Place of
Particulars Quantity Unit materials will be charged
No delivery
to the contractor
1 Materials including cement, steel for reinforcement, blasting materials will not
supplied by the Nigam contractor has to procure at his own cost.
2 Useful rubble from excavation as per the rate entered in the SR prevailing at the
time of accepting the tender. This contractor has to make his own arrangement
for procuring the rubble from the excavated spoil at his own cot including sorting.
1 The person or firms submitting the tender should see that the rates in the above
Schedule are filled up by the Executive Engineer-in-charge on the issue of the
form prior to the submission of the tender.
2 (i) “The rates shown above will not be applicable for additional altered items of
works for which payment at rates other than tendered rates is to be made
according to clause-13 of the conditions of contract if the materials indicated
above are supplied by the KNNL for such additional substituted or altered items
of work the rates to be charges for the materials supplied by the KNNL shall be
reckoned for arriving at the rates payable for such items of work.
(ii) Stores to be supplied to contractor for a work free of cost should be
mentioned in Schedule – A in addition to Schedule – B and specifications
attached to the contract agreement form.
3 The apparent increase or decrease of weight of steel as issued on weight basis
and as billed for based on liner measurements, as per the standard method in
vogue shall be deemed to have taken into consideration by the contractor at the
time of quoting rates for such of the items as are involving use of steel and as
such, no claims whatsoever shall be entertained in this respect.
4 Certificate of quality as per relevant code of Bureau of Indian Standard (ISI) for
the materials viz. cement, steel etc. brought should be produced by the
contractor before such materials re-permitted for use.
E-tendering.
SCHEDULE-B
Name of work: Supply of Vehicle on Hire basis to No.3 Q.C Sub-Division, Gajanur for the year
2021-22
1. The percentage shall be entered in figures and words clearly and visibly. Any correction shall
be attested by the contractor.
2. The offer shall be for finished items of work, complete in all respects, inclusive of all
materials all tools and plants, all labour required for the work, all leads and lifts, all incidental
charges, dewatering and desilting if any, diversion of water, diversion of road for traffic, initial
and final clearance of site, providing labour amenities, all taxes and levies such as sales tax,
income tax royalty charges etc.,
3. For items of cement concrete and reinforced cement concrete of controlled grades, the
cement content mentioned in the detailed technical specification is for guidance only. The
unit rate quoted should take care of the variation of cement content if any during execution
to achieve the required specification and no extra payment will be made towards any
variation in cement content.
4. If any lands required for the work and for quarries and borrow areas are not acquired by the
KNNL, the contractor should get the lands by negotiations with the land owners without
causing any extra cost to the KNNL on that account.
5. The submission of the tender by a contractor implies that he had read the contents of the
tender notice and contract form, the contents of the conditions of the contract, additional
conditions of the contract, detailed technical specifications and all other contents of the
tender document and made himself thoroughly aware of the scope and specification of the
work to be done and the availability of the quantity of the materials required.
7. The completed tender document should be submitted in to electronic tender box on the
Website itself.
2. The percentage quoted in the Schedule-B should be through rates for the finished items
inclusive of all royalties, sales tax, quarry fees wherever applicable and appropriate (as per the
statement of royalties enclosed)
3. There is no separate item as dewatering or desilting or river diversion work. All items are
inclusive of dewatering or desilting or pumping out water at all stages of work. The percentage
quoted should inclusive of dewatering and desilting charges. No extra payment on any account
shall be made for dewatering or desilting charges.
5. It is the incumbent on the part of the contractor to make the full use of the useful
6. The levels and dimensions shown in the drawings are approximate and may vary during the
course of execution of the above items of work and the contractor will not be entitled for any
extra rate or compensation due to such variation including time extension.
7. Any damage caused during construction to any part of the work due to any reasons including
calamities and flood damages whatsoever shall be made good at the contractor’s expenses until
the work is handed over in the complete manner as per agreement. No claims will be entitled in
this regard including extension of time.
7. a) Percentage quoted include clearance of site prior to commencement of work and at its
completion in all respects and hold good for work under all weather conditions.
b) It shall be the responsibility of the contractor to establish their own quarries for the
materials required for the construction purpose.
9. All items shall be executed as per the approved design, drawing and pattern and shall comply
with the specifications and general conditions relating to the work enclosed with the tender
and orders conveyed by the competent authority in writing from time to time during the
course of execution.
10. Contractors will have to make their own arrangements to obtain electric power at their own cost
from Karnataka Power Transmission Corporation Limited or by their own power generator. In
case of failure of power supply the contractor will not entitled to any compensation or
extension of time.
11. All works shall be carried out as per the detailed specifications and for the items not covered in
the Schedule-B shall be carried out as directed by the Engineer in charge.
12. The offer shall include lighting wherever necessary and provided and maintaining
communication facilities. No extra payments for these will be made on any account.
13. Description of items given below shall be read along with the general conditions of the contract
tender,notifications,general specifications, test and acceptance criteria relating to the works
scheduled specifications and all other component parts of the tender document.
14. It is incumbent on the part of the contractor to use all the useful rubble available from canal
excavated spoil for breaking metal rubble required for UCR masonry rocktoe, pitching and
concrete items after sorting out the same from the stacks. The available rubble will be issued to
the contractor at the issue rates mentioned in the Schedule-A. The contractor shall bring rubble
15. During execution of work the diversion work if any necessary for diverting and rediverting the
natural stream or drainage channels encountered on the alignment shall be done by the
contractor at his own cost till final completion of the work and the rates quoted shall be deemed
to include costs of all such diversion work. The contractor shall be held responsible for any
accidents occurring during execution.
16. The tenderer shall remove the silt wherever it is accumulated at his own cost.
17. The contractor will have to co-operate with the other agency working in the same or adjoining
area and shall not be entitled to any claims due to any inconvenience or delay handing over
any portion of working area. In case of any dispute with the adjacent contractor decision of the
Engineer in charge will be final.
18. Quantities indicated are approximate and may vary during execution due to alterations or
modifications in design. For any increase or reduction in quantities contractor shall are
governed by the provisions of clause 13 of general conditions of contract.
19. The rates for embankment with materials obtained from available spoil bank should not be
more than the rates for the embankment with materials obtained from borrow pits.
20. The useful dumped materials like rubble and soil coming within the toe line of the bank work
should be used for the embankment works after getting necessary quality control test, the
balance and the dumped materials should be disposed off from the site as per the instructions
of the Engineer in charge for which no extra payment will be made.
21. The contractor shall inspect the site and various quarries materials and ascertain the leads
involved in procuring the materials for the various items. The offer shall be inclusive of all leads
and lifts irrespective of what has been considered in the estimate. No extra claims over the
quoted rates on the aspect of lead and lift will be entertained.
The quality of materials used on the work should be got approved from the Engineer in charge
before it is used on the work. All quarry fees royalties octroi dues levied by the Government or
local body or authorities or private body and ground rent if any for stacking materials charged
by the concerned department or bodies shall be paid to the concerned department or bodies by
the contractor.
22. Quoted rates include all leads and lifts for completion of items in all respects and the cost of
removing the overburden in all quarries and no claims for compensation therefor be
entertained.
23. The Karnataka Neeravri Nigam Limited is not responsible for the source of materials.
24. The delay in payment of bills by the Karnataka Neeravri Nigam Limited due to shortage of
funds or any other reasons beyond the control of the Karnataka Neeravri Nigam Limited the
extension of time may be considered depending upon the merit of the case and no revised
rates will be admitted and entertained on any grounds.
25. The tenderer shall make the payment of royalty charges as per Government notification
No.CL-302 MRC 91 Dated 16.8.1995 Govt. order circular (copy under Annexure-C) with a
subsequent modifications / revisions if any as issued by the Government from time to time to
the concerned KNNL at his own cost. The tenderer should produce the necessary certificate to
the Engineer in charge of work for having paid the royalty charges to the concerned authorities
in respect of materials so quarried for the said work failing which no payment will be made to
the tenderer for the measured quantity executed by him through R.A. bills or any other bills.
If the tenderer fails to comply the requirements as stated above then the Engineer in charge of
the work is free to recover the royalty charges as per the Government notification in circulation
with its subsequent modifications/ revisions, if any, as issued by the Government from time to
time from the tenderer’s work bills and thereafter if the tenderer suffers any loss or damages on
26. If the contractor expires during the course of execution of work the decision of the KNNL for
closing / continuing the work shall be final.
27. The contractor is eligible to payment of excavation embankment masonry concrete items etc.,
as per drawings enclosed in the tender. If any extra work is done by him for his convenience no
separate payment will be paid and no claims will be entertained including extension of time.
28. Typing and printing of numerical mistakes and interpretation of rates will not be considered for
any claims of contractor. The decision of the competent authority is final.
29. In case of any obstructions from the land owners during the construction period of the work the
Nigam will not take any responsibility and the contractor has to make his own arrangements to
get the land disputes settled and bear extra cost if any.
30. In case there is any part or whole of land required for work is not yet acquired by the KNNL it
shall be responsibility of the contractor to procure possession of such land by consent of the
land owners before commencement of work at no extra cost to KNNL and no claim whatsoever
relating to non availability of lands would be entertained.
31. The contractor shall furnish a programme of work along with the bar chart to complete the
works within the time stipulated in tender soon after entering in to agreement.
32. The contractor’s attention is specially drawn to Sl.No.3 and 23 of rules under Schedule-B
regarding claims of dewatering etc., and claims for extra lead etc., No claims whatsoever in this
regard are entertained.
The following plant and machinery will be issued to contractor subject to the conditions,
mentioned in clause 21 and also fulfilment of the following rules :-
Contractor should make his own arrangements for construction machineries, vehicles
or tools and plants. No machineries or vehicles of the KNNL will be hired to contractor.
However the KNNL may let out the machineries , vehicles or tools and plants of the
KNNL, if the same are available and idle, on hire charge basis, at charges prescribed by the
KNNL.
Note :- The rates will be calculated and inserted here with respect to the rules framed by
the KNNL from time to time as applicable on the date of finalisation of the tender.
Witness 1.
2.
Note : Tenderers are not required to complete this form at the time of tendering.