The project is ahead of schedule but on budget.
CPI is 1, meaning cost is on target.
SPI is 2, indicating the project is ahead of schedule with 50% work complete against a planned 25%.
However, the original total budget of $800,000 has already been spent on 50% of the work.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
43 views4 pages
Sample sums-EVM
The project is ahead of schedule but on budget.
CPI is 1, meaning cost is on target.
SPI is 2, indicating the project is ahead of schedule with 50% work complete against a planned 25%.
However, the original total budget of $800,000 has already been spent on 50% of the work.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4
Exercise 1: Earned Value Management
Your company specializes in installing PCs. BELL labs
has given you a work contract. The work involves installing PCs in their office. Total work to be performed : 50 pcs to be installed Total Duration of project : 10 Days Rewards : You will be paid at $10,000 for the project. Your plan is to install 5 PCs per day, and at the end of 10 days you would have completed the project. Actual Work: At the end of the 1st week (5 days), your company installed 30 pcs. Actual Cost: You spent $4000 at the end of week 1.. Cost Management Calculations - 1: Given in question: BAC: $10000, AC: $4000 Expectation: 50 PCs installation in 10000. So, per PC installation worth is 10000/50 = $200 50 PCs in 10 days → 5 PCs/ day → 5X200=$1000 worth of work is planned / day. So Planned Value = 1000/ day. After 5 days, Planned Value(PV)= 5*1000 = $5000 But actual work done after 5 days is 30 PCs. Earned Value (EV) = 30*200 = $6000 CPI = EV/ AC = 6000/4000 = 1.5 SPI = EV/ PV = 6000/5000 = 1.2 EAC = BAC/ CPI = 10000/1.5 = $6666.67. ETC = EAC – AC = 2666.67 Cost Management Control Costs
Exercise 2: Earned Value Management
The total budget for a highway construction project is $ 800,000 consisting
of a total 8000 hours of work scheduled. As of today, 25% work was planned, and the actual cost spent is $ 400,000. The percentage of work complete as of today is 50%. Comment on the status of the project in terms of CPI and SPI Cost Management Calculations - 2:
Given in question: BAC: $800000, AC: $400000
25% work was planned to be done. Hence PV = 25% of BAC = 0.25*800000 = $200000 But 50% work is actually completed. Hence EV = 50% of BAC = 0.5* 800000 = $400000 CPI = EV/ AC = 400000/400000 = 1 SPI = EV/ PV = 400000/200000 = 2 EAC = BAC/ CPI = 800000/1 = 800000 ETC = EAC – AC = 800000-400000 = $400000