0% found this document useful (0 votes)
43 views4 pages

Sample sums-EVM

The project is ahead of schedule but on budget. CPI is 1, meaning cost is on target. SPI is 2, indicating the project is ahead of schedule with 50% work complete against a planned 25%. However, the original total budget of $800,000 has already been spent on 50% of the work.

Uploaded by

Shreenidhi M R
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views4 pages

Sample sums-EVM

The project is ahead of schedule but on budget. CPI is 1, meaning cost is on target. SPI is 2, indicating the project is ahead of schedule with 50% work complete against a planned 25%. However, the original total budget of $800,000 has already been spent on 50% of the work.

Uploaded by

Shreenidhi M R
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Exercise 1: Earned Value Management

Your company specializes in installing PCs. BELL labs


has given you a work contract. The work involves
installing PCs in their office.
Total work to be performed : 50 pcs to be installed
Total Duration of project : 10 Days
Rewards : You will be paid at $10,000 for the project.
Your plan is to install 5 PCs per day, and at the end of
10 days you would have completed the project.
Actual Work: At the end of the 1st week (5 days), your
company installed 30 pcs.
Actual Cost: You spent $4000 at the end of week 1..
Cost Management Calculations - 1:
 Given in question: BAC: $10000, AC: $4000
 Expectation: 50 PCs installation in 10000.
 So, per PC installation worth is 10000/50 = $200
 50 PCs in 10 days → 5 PCs/ day → 5X200=$1000 worth of
work is planned / day. So Planned Value = 1000/ day.
 After 5 days, Planned Value(PV)= 5*1000 = $5000
 But actual work done after 5 days is 30 PCs. Earned Value
(EV) = 30*200 = $6000
 CPI = EV/ AC = 6000/4000 = 1.5
 SPI = EV/ PV = 6000/5000 = 1.2
 EAC = BAC/ CPI = 10000/1.5 = $6666.67.
 ETC = EAC – AC = 2666.67
Cost Management Control Costs

Exercise 2: Earned Value Management

The total budget for a highway construction project is $ 800,000 consisting


of a total 8000 hours of work scheduled. As of today, 25% work was
planned, and the actual cost spent is $ 400,000. The percentage of work
complete as of today is 50%. Comment on the status of the project in terms
of CPI and SPI
Cost Management Calculations - 2:

 Given in question: BAC: $800000, AC: $400000


 25% work was planned to be done. Hence PV =
25% of BAC = 0.25*800000 = $200000
 But 50% work is actually completed. Hence EV =
50% of BAC = 0.5* 800000 = $400000
 CPI = EV/ AC = 400000/400000 = 1
 SPI = EV/ PV = 400000/200000 = 2
 EAC = BAC/ CPI = 800000/1 = 800000
 ETC = EAC – AC = 800000-400000 = $400000

You might also like