Cat® Trolley Assist System
Cat® Trolley Assist System
The Cat Trolley Assist System requires incremental truck iron and significant site infrastructure footprint to enable its
operation. There are five key elements of the site infrastructure, they are: AC substation, DC substation(s), support poles,
catenary lines, and the load height check. Site infrastructure for the trolley system must be provided by a third-party.
AC SUBSTATION
Site infrastructure starts with a large AC substation. The AC substation shapes AC power
from the local power grid for use by the smaller DC substations along the trolley assist route.
Typically, only one AC substation is needed for the entire trolley system.
DC SUBSTATION(S)
The DC substations are placed approximately every 1 km along the trolley route. Fed by the AC
substation, these DC substations convert the AC power into 2,600 V DC power for the trolley lines.
The total number of DC substations varies depending on the haul route length and the desired
number of trucks targeted for simultaneous operation.
SUPPORT POLES
CATENARY LINES Support poles consist of a vertical base poles and catenary routing
Supported by the catenary routing poles, and are placed approximately every 40 m along the haul road.
poles, two catenary conductors Poles are placed as far apart as possible to maintain a suitable
are ran immediately overhead catenary arc. Vertical base poles, which typically need 3-4 m of a
the haul road on the trolley assist base to be installed, are placed immediately to the side of the haul
segment. These two catenaries road on the side of the direction of uphill travel. Catenary routing
are DC conductors, and are poles are cantilever mounted to the vertical base poles and extend
directly connected to the DC approximately ¼ of the way over the haul road. Upfront design
substation(s). Carbon brushes on consideration is recommended If mine plan requires relocation of
the pantograph directly contact trolley lines.
the catenary lines for the duration
of the trolley assist segment.
SINGLE TRUCK VALUES (referenced from the point the power is taken off the trolley line)
THE TABLE BELOW CONTAINS VARIOUS REQUIRED DISTANCES AND SPECIFICATIONS FOR TROLLEY OPERATION.
SUPPORT
The Cat trolley assist attachment comes with the full
support of the Cat dealer network. 100% of the trolley
components have a Cat part number and are supported
by the Cat parts network.
Q: When on Trolley, can the A: The operator can modulate speed in trolley assist using the accelerator
operator slow the truck to pedal in a similar fashion to a normal diesel propel mode. If the truck speed
their desired speed and then drops below 8 km/h (5 mph) while on trolley line, the trolley will disengage
accelerate if they need to? and switch back to diesel mode automatically for safety reasons. There are
several additional safety measures built into Cat trolley assist.
Q: What is the line height A: The contact wire to road surface should be set to +/- 100 mm of the
variation amount and frequency? target height. During operation, the system is designed to accept a line
height variation of up to +/- 500 mm at a frequency of 1 Hz. 500 mm reflects
a combination of road surface and machine suspension / tire changes
during operation.
Q: What are typical grade A: Trolley requires dedicated road maintenance, the road must be in
values that must be maintained good shape. Potholes, ruts, and other deficiencies could cause a truck
to reduce the road tolerance on trolley to disengage if it loses contact with the lines. The pantographs
rejection rate, and how much allow for +/- 1 m of lateral movement, and +/- 500 mm of vertical movement
vertical and lateral movement is dynamically. The working range of the pantograph is 1.5 m.
allowed on the truck before the
pantograph disconnects?
Q: Is there a ground fault A: Truck components feature a ground fault protection; however, this is not
protection mechanism on the a personal protection system. The sub station should also contain a ground
truck, or does that lie on the fault protection.
infrastructure side?
Q: What mitigation should be A: To reduce arcing / sparking, the support poles should be placed 40
taken to reduce arcing / sparks m apart, and the road should be regularly graded. The contact wires,
when contact with the line when set with the hangers, should be parallel to the road +/- 100mm. The
is interrupted due to uneven pantograph is designed to respond to vertical changes, but for sudden
road surfaces? How does the vertical changes the pantograph features a quick-drop system. Maintaining
truck behave under these line tension is important, as drooping in the line will cause a sudden
circumstances? snapping of the line at the hangers, resulting in the pantograph arcing.
PEDJ0634-01 (05-2021)
(Global)
© 2021 Caterpillar. All Rights Reserved. CAT, CATERPILLAR, LET’S DO THE WORK, their respective logos,
“Caterpillar Corporate Yellow”, the “Power Edge” and Cat “Modern Hex” trade dress as well as corporate
and product identity used herein, are trademarks of Caterpillar and may not be used without permission.