Risk Analysis and Management
Risk Analysis and Management
RISK MANAGEMENT
Four aspects -
Risk Identification
Risk Assessment
Risk Response Planning
Risk Response Control
RISK IDENTIFICETION
Proceed according to sequence of activities
Engineering risk- product reliability and maintainability
Production risk- producability, raw materials availability
High risk- New technology,
- Developing & testing new equipment, systems or procedures
- Training for new tasks, applying new skills
SOURCES OF RISK
Any factor which can influence the outcome of project is a risk factor or risk hazard.
Risk classified as- internal and external
INTERNAL RISKS
Originates inside the project
Project managers & the organization generally have a measure of control over them.
Market risk and Technical risk
Market risk- Incomplete identification of customer needs
- Failure to identify changing needs
- Failure to identify new products
Market risk can be reduced by defining needs correctly and modifying during execution if
need be.
Technical Risk is not meeting the cost, time and performance requirements due to technical
problems with the end items of project.
It is high in new technologies, new skills, new products
It is low in projects dealing with familiar activities
EXTERNAL RISKS
Market Conditions
Competitor’s action
Government Regulations
Interest Rates
Customer Needs and Behavior
Supplier relations
Weather
Labour availability
Material or Labour resources
RISK ASSESSMENT
Only the notable ones require attention
Risk likelihood- the probability of happening- low/ medium/ high- assign numerical values 0
to 1.0
Risk impact- specified in terms of time, cost and performance measures- assign numerical
values.
Risk consequence expected value is calculated as-
(impact) x (likelihood)
In a complex system with a large number of relationships whose joint failures in several would lead
to system failure, it is common to ignore joint failures in the hope that they will not occur!
Bhopal gas disaster was one such incident which has been attributed to 30 separate causes, with
miniscule joint probability- YET- they did all happen……
CONTIGENCY PLANNING
Identify the risk, anticipate whatever might happen, and prepare a detailed plan of action to
cope with it.
Initial project is followed, and monitored closely throughout execution.
A remedial measure to compensate for impact
An action taken in parallel to original plan
ACCEPT RISK
Do nothing!
Cannot be used as an option when the impact is likely to severe.
PROJECT MANAGEMENT is RISK MANAGEMENT
RISK MANAGEMENT PRINCIPLES
Create a risk management plan that specifies ways to identify all major project risks, and
creates a risk profile for each identified risk
The risk profile should include likelihood, cost and schedule impact, and contingencies to be
invoked.
Create a person responsible for risk management- the ‘risk officer’. ( should not be the
project manager)
The budget and schedule should include risk reserve- a buffer for time, money & other
resources.
Risks must be continuously monitored and the plan updated to include emerging risks.
Establish communication channels- and candor within teams- to ensure that bad news
reaches the manager quickly.
Specify procedures to ensure accurate, comprehensive project documentation – in general
the better the documentation, the more information is available for planning of similar
projects.
EXPECTED VALUE
Expected Value = Σ [ (Outcomes) x (Likelihood)]
NPV PROBABILITY
200 0.3
600 0.5
900 0.2
STANDARD DEVIATION
Standard Deviation = √[Σpi (Ei –Ē)2]
Pi = probability associated with ith value
Ei = ith value
Ē = expected value
Coefficient of Variance = Standard Deviation
Expected Value
Standard deviation is the most commonly used measure of risk in finance.
SENSITIVITY ANALYSIS
Since future is uncertain, managers may like to know what will happen to the viability of the
project if some variable like sales/ investment decision deviates from its expected value.
Also called “what if” analysis.
Consider the following example (Rs in ‘000)
YEAR 0 YEAR1 – 10
Investment (20,000)
Sales 18,000
Variable cost (66 2/3 % of sales) 12,000
Fixed cost 1,000
Depreciation 2,000
Pre-tax profit 3,000
Taxes 1,000
Profit after tax 2,000
Cash Flow from operation 4,000
Net cash flow 4,000(r =12%,t = 10)
Since cash flow is an annuity, the NPV of project is=
= - 20,000,000 + 4,000,000’ PVIFA(r = 12%, n = 10 years)
= -20,000,000 + 4,000,000 (5.650)
= Rs 2,600,000
Since the underlying variables can vary widely, we shall define the optimistic and pessimistic
estimates for the underlying variables. With those values, we shall calculate the NPV for optimistic
and pessimistic values of each of the underlying variables.
Change one variable at a time
Eg. To study the effect of sales (from Rs 18 million to Rs 15 million)- maintain the values of other
underlying variables at their expected levels.(means investment is constant at Rs 20 million, variable
costs at 66⅔ % of sales, fixed cost = Rs 1 million)
pessimistic expected optimistic pessimistic Moderate Optimistic
Investment 24 20 18 -0.65 2.60 4.22
(Rs in million)
Sales 15 18 21 -1.17 2.60 6.40
(in Rs million)
Variable cost as 70 66.66 65 0.34 2.60 3.73
a percent of
sales
Fixed costs 1.3 1.0 0.8 1.47 2.60 3.33
(Rs in million)
It is a very popular method for assessing risk
Shows how robust or vulnerable the project is to changes in values of underlying variables
Indicates where future work may be done
It is intuitively very appealing since it reflects the concerns that project evaluators normally
have.
A survey by Manoj Anand “Corporate Finance Practices in India” has revealed that 90% of
the companies surveyed rated it as the number 1 method of Assessing Project Risk.
SCENARIO ANALYSIS
In sensitivity analysis one variable is varied at a time. But if variables are interrelated, as they are
likely to be, there might be a number of plausible scenarios.
Procedure:
1. Select the factor around which the scenario will be built. The factor must be largest source of
uncertainty for success of a project- the state of economy/ interest rate/ market response/
technological development.
2. Estimate the values of each of the variables in the investment analysis (outlay, revenue, costs,
life) for each scenario
3. Calculate the NPV and IRR under each scenario.
Example:
A company is evaluating a project for introducing a new product. Depending on market response-
the factor of largest uncertainty, the management has identified three scenarios -
Scenario 1: product will have moderate appeal to customers at a moderate price.
Scenario 2: product will have strong appeal to a large segment of the market which is highly price
sensitive.
Scenario 3: product will appeal to a small segment of the market which will be willing to pay a high
price.
The following table shows the NPV calculations for the three scenarios
The objective of scenario analysis is to get a feel of what happens under the most favorable or the
most unfavorable configuration of the key variables.
Sources of Risk
Risk Assessment Form