Pert Analysis Exercises
Pert Analysis Exercises
Question 1
Activity Duration
Label Task Predecessor (Months)
A Market analysis - 1
B Product design A 3
C Manufacturing study A 1
D Select best design B, C 1
E Marketing plans D 1
F Manufacturing process D 3
G Detailed product design D 3
H Test prototype G 1
I Finalise design F, H 2
J Order components I 1
K Order production equipment I 3
L Install production equipment K 2
ID Description Predecessor OT MT PT
1 Initial meeting - 2 5 8
2 Producers association organisation 1 59 70 93
3 Historical features development 1 22 33 56
4 To hire expeditor 1 22 30 50
5 Twenty beneficiaries identification 1 31 40 61
6 Producers association formalisation 2 30 51 90
7 Cultural features development 3 22 33 56
8 Technical norm proposal development 6, 7 25 38 51
9 Technical norm proposal approval 8 36 54 102
10 Ten beneficiaries diagnosis 4, 5 25 40 55
11 Technical assistance to five beneficiaries 10 59 70 93
12 Joining of five entrepreneurs with exporters 11 25 35 45
13 Ten beneficiaries diagnosis 10 25 40 55
14 Technical assistance to five beneficiaries 13 59 70 93
15 Joining of five entrepreneurs with exporters 14 25 35 45
16 Final appraisal meeting 8, 11, 15 3 5 7
Required:
1. Calculate the expected duration and the standard deviation for all activities
2. Draw the network diagram
3. Determine the key. Work out the EST, EFT, LST, LFT and Slack (Float).
4. Show the critical path and the total expected duration
5. State the critical path and the non-critical paths
6. Find the population mean and standard deviation of the critical path
7. Are there any activities on the critical path that need to be watched carefully? Why?
8. Are there any activities on the non-critical path that need to be watched carefully? Why?
9. Will the project finish before 250 days?