Pert Analysis Exercises

1. The network diagram shows 16 tasks with dependencies to complete a project. Task 2 has the longest expected duration at 90 days. The critical path includes tasks 2, 6, 7, 8, 9, 11, and 15, with a total expected duration of 250 days. 2. The critical path tasks that need careful watching are 2 and 9 due to their long durations, which could impact the project's timely completion if delayed. Non-critical tasks 4 and 10 also require attention as their slack times are low. 3. The project is expected to finish by the planned deadline of 250 days based on the current expected task durations.

Uploaded by

Aniss Negan
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
108 views

Pert Analysis Exercises

1. The network diagram shows 16 tasks with dependencies to complete a project. Task 2 has the longest expected duration at 90 days. The critical path includes tasks 2, 6, 7, 8, 9, 11, and 15, with a total expected duration of 250 days. 2. The critical path tasks that need careful watching are 2 and 9 due to their long durations, which could impact the project's timely completion if delayed. Non-critical tasks 4 and 10 also require attention as their slack times are low. 3. The project is expected to finish by the planned deadline of 250 days based on the current expected task durations.

Uploaded by

Aniss Negan
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Pert analysis exercises

Question 1

Activity Duration
Label Task Predecessor (Months)
A Market analysis - 1
B Product design A 3
C Manufacturing study A 1
D Select best design B, C 1
E Marketing plans D 1
F Manufacturing process D 3
G Detailed product design D 3
H Test prototype G 1
I Finalise design F, H 2
J Order components I 1
K Order production equipment I 3
L Install production equipment K 2

1. Draw the network diagram


2. Determine the key. Work out the EST, EFT, LST, LFT and Slack (Float).
3. Show the critical path and the total expected duration
4. State the critical path and the non-critical paths
Question 2

ID Description Predecessor OT MT PT
1 Initial meeting - 2 5 8
2 Producers association organisation 1 59 70 93
3 Historical features development 1 22 33 56
4 To hire expeditor 1 22 30 50
5 Twenty beneficiaries identification 1 31 40 61
6 Producers association formalisation 2 30 51 90
7 Cultural features development 3 22 33 56
8 Technical norm proposal development 6, 7 25 38 51
9 Technical norm proposal approval 8 36 54 102
10 Ten beneficiaries diagnosis 4, 5 25 40 55
11 Technical assistance to five beneficiaries 10 59 70 93
12 Joining of five entrepreneurs with exporters 11 25 35 45
13 Ten beneficiaries diagnosis 10 25 40 55
14 Technical assistance to five beneficiaries 13 59 70 93
15 Joining of five entrepreneurs with exporters 14 25 35 45
16 Final appraisal meeting 8, 11, 15 3 5 7

Required:
1. Calculate the expected duration and the standard deviation for all activities
2. Draw the network diagram
3. Determine the key. Work out the EST, EFT, LST, LFT and Slack (Float).
4. Show the critical path and the total expected duration
5. State the critical path and the non-critical paths
6. Find the population mean and standard deviation of the critical path
7. Are there any activities on the critical path that need to be watched carefully? Why?
8. Are there any activities on the non-critical path that need to be watched carefully? Why?
9. Will the project finish before 250 days?