Data Center Power and Cooling and Virtualization Trends in ASEAN
Data Center Power and Cooling and Virtualization Trends in ASEAN
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Outline: Summary Report
• Methodology Slide 3
• Key Findings Slide 4
DATACENTER TRENDS Slide 8
• Section A: Qualification and Clarification Slide 10
• Section B: Datacenter Overview Slide 16
• Section C: Datacenter Drill Down Slide 24
• Section D: Datacenter Characteristics Slide 34
• Section E: Datacenter Power and Cooling Slide 43
• Section F: Datacenter Operations Slide 51
© 2008 IDC 2
Methodology
45 minute f-2-f survey
Sample of 405 Senior IT Managers/IT Directors and Facilities personnel
that are managing a datacenter/server-storage facility and have a
a server room, localized, mid-tier or enterprise class datacenter
© 2008 IDC 3
Key Findings
The average age of datacenters in ASEAN is 7-9 years with Indonesia,
Philippines having some of the oldest datacenters. Interestingly they all
feel their current datacenters will last a long time but the large
proportion of “Don’t Knows” indicate uncertainty
ASEAN end-users indicate they are generally worried about the future
of their operations, and specifically about cabling space and insufficient
raised floor space.
In terms of their immediate short term goals - most users have
indicated looking at ways they can enhance their datacenter facility to
accommodate additional amount of servers and storage
Slightly more than a third of the sample overall has some power and
cooling issue today, and a higher number feel the issue will become
more critical in future. Enterprise datacenters fared the best among all
datacenters
– Most ASEAN end-users feel the need to revamp/retrofit their datacenters
as well as consolidate and virtualize to address power and cooling issues
© 2008 IDC 4
Key Findings
Despite inefficiencies in the existing datacenters we don’t see end-
users rushing to close them down, although they are building new ones.
IDC saw the maximum build-out in server rooms and localized
datacenters and server rooms led in terms of discontinuation of existing
datacenters. Some reasons for the slow rate of discontinuation seem
to be
– Since the budgets are hard to get and there seems to be some
uncertainty around the type of datacenter that should be built
– End-users fear disruption due to which they are investing in new facilities
that, once running, will help them move workloads from old to new more
seamlessly
The most often noted business impacts from power and cooling issues
is increased operational costs, and most alarmingly, hardware
damaged and datacenter outages. While cooling issues is increased
operational costs, system downtime, and most alarmingly, hardware
damaged and datacenter outages
© 2008 IDC 6
Key Findings
Power/costs spending on electricity followed by available power supply
were among the highly rated challenges overall with some differences
by each datacenter type.
– System/Server level solutions are the most sought after across all
datacenters followed by room level in enterprise and mid-tier, and rack
level in localized and server rooms
Looking at the cost of building and running the datacenter we found the
the biggest proportion of cap-ex spending in ASEAN being the IT
hardware which is averaging to 45-50% for server/storage and
networking & comms hardware, while cost of power seems to be
among the major drivers of op-ex spending in ASEAN followed by
networking and IT maintenance costs.
In terms of datacenter solution provider, except mid-tier datacenters
almost all others prefer using a single vendor who can help them
transform.
– It seems that end-to-end capabilities and single point of contact are key
attributes that the datacenter owners are keen to have in their providers.
© 2008 IDC 7
Datacenter Trends
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Taxonomy
IDC Taxonomy
Server Room: A secondary computer location that usually is under IT control, often less than 500 sq ft and
has some power & cooling as well as security capabilities
Localized Data Center: May be a primary or secondary location that is usually under 1,000 sq ft requiring
badge or pin access and has some power and cooling redundancy to ensure constant temperature
Mid-Tier Data Center: Is the primary server location for an organization that is a large room, but often under
5,000 sq ft. It has superior cooling systems that are probably redundant and is probably protected by two
levels of physical and digital security
Enterprise Class Data Center: Is the primary server location for an organization. Is a very large room often
in excess of 5,000 sq ft and has advanced cooling systems, redundant power and is protected by multiple
levels of physical and digital security
© 2008 IDC 9
Section A
Qualification and
Clarification
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Qualification & Clarification:
Respondents by Number of Employees
Q. How many employees are there in your organization, countrywide?
1000-4999
26%
250-499
16%
500-999
22%
N=405
By design, the survey sample excluded companies with less than 100 employees. 59% of the
sample was in companies with more than 500 employees and 37% above 1000 employees. IDC felt
these to be the target market for datacenter solutions since the bulk of issues lie in the
complexities, inefficiencies and rising management & administration costs that impact the relatively
larger datacenters
© 2008 IDC 11
Qualification and Clarification:
Vertical Industry
Q. What industry classification best represents your organization's principal business
activity?
Vertical Industry
Banking 4.2%
Insurance 3.2% Financial = 11%
Financial Markets 3.2%
Discrete Manufacturing 15.6%
Process Manufacturing 19.0%
Manufacturing = 39%
Construction 2.7%
Resources Industries 1.7%
Retail 6.7%
Distribution = 8%
Wholesale 1.0%
Professional Services 8.9% Professional
Personal & Other Services 4.4% Services = 13%
Transportation & Trans Services 5.9%
Infrastructure
Com m unications & Media 4.9%
Services = 15%
Utilities 3.7%
Healthcare 4.7%
Public
Education 7.4%
Services = 15%
Government 2.7%
© 2008 IDC 12
Qualification and Clarification:
Expertise and Focus Area
Q.Which of the following do you consider to be your areas of expertise or primary focus?
© 2008 IDC 13
Qualification and Clarification:
Expertise and Focus Area – Key Tasks
Q. Which of the following tasks would you be involved in, as part of your job duties?
Identifying any problems or issues around the pow ering and cooling
64%
of your IT operations
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percent of Sample
Note: Multiple response.
© 2008 IDC 14
Qualification & Clarification:
Server & Storage Inventory
Q. How many servers does your organization have currently installed, countrywide?
owned by the
respondent companies. < 24 Server
This was done in order 52.0%
© 2008 IDC 15
Section B
Datacenter Overview
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Overview:
Datacenter Lifespan
Q. Thinking about your Primary Datacenter, how long has it been in operation, and how many
more years do you think your Primary Datacenter will operate before it is closed?
Knows” indicate less than 1 year 1 year to less than 3 years 3 years to less than 5 years
uncertainty
5 years to less than 10 years 10 years or longer Don't Know
© 2008 IDC 17
Datacenter Overview:
Datacenter Pain-Points
Q. Which of the following do you consider to be "pain points" with respect to the operation of
your datacenter?
The uncertainty we were
Current “Pain Points” of datacenter operation inferring in the previous slide
is confirmed as in response to
the current pain-points, end-
Datacenter facility is aging 37% users indicate they are
generally worried about the
future of their operations, and
specifically about cabling
Cabling space and insufficient floor weight load 32%
space and insufficient raised
floor space.
Insufficient raised floor space in the near future 26% Cabling space among server
rooms & localized datacenters,
lack of cooling capacity in
enterprise datacenters and lack
Lack of cooling capacity in the near future 27%
of power in mid-tier
datacenters were the more
specific concerns.
Lack of electric power capacity in the near
24%
future Cramping the datacenter in-
room space with too much
Generally worried about the future operations of cabling, or other design flaws
37%
the datacenter are among the reasons end-
users are finding themselves in
0% 5% 10% 15% 20% 25% 30% 35% 40% this problem. This has been
Percent of Sam ple observed as a pain-point at a
regional level as well
© 2008 IDC 18
Datacenter Overview:
Short-Term Plans
Q. Thinking of your datacenter is your organization considering any of the following changes
over the next 6 months or so?
57.6%
60%
55.3% 63.0%
52.8% We noticed earlier that the
51.7%
50% biggest issue they will need to
resolve will be around the lack
40%
of space, power and cooling
30% issues, which could mean
20.3%
20% 12.8% 10.9% 15.1% rationalizing the IT through
10.9% consolidation or else
10%
14.6% 15.4% 15.3% 15.1% revamping the current design.
12.0%
0% We believe a lot of the
Overall Server Room Localized Mid-Tier Enterprise immediate issues are around
(N=405) (N=201) Datacenter Datacenter Datacenter
(N=92) (N=59) (N=53)
revamping the power and
None cooling provisioning and
efficiency
Enhance - in any way - your datacenter facility to accommodate greater amount of servers,
storage, better cooling design
Refurbshing or retrofitting your datacenter facility to improve Cooling
© 2008 IDC 19
Datacenter Overview:
Are there Power & Cooling Issues?
Q. How would you classify Power and Cooling issues or challenges for the datacenter/s that
your organization has? Today and in FUTURE
68% 68%
65%
Generally more 30% 63%
58%
62%
58%
62%
© 2008 IDC 20
Datacenter Overview:
Addressing Power & Cooling Issues
Q. What is your organization doing - or planning to do - to address any power and/or cooling
issues in your datacenter/s?
Solutions to Resolve Power and Cooling Issues Most ASEAN end-users feel
the need to revamp/retrofit
their datacenters as well as
100%
8.6% 12.1%
4.5%
10.0% consolidate and virtualize
90% to address power and
80% 29.5%
23.3%
36.0% cooling issues.
32.3%
70% 35.4% Enterprise and server room
Percent of Sample
Current Situation in Making Datacenter more Green More than half of the
100% 1.2% 2.6% 2.5% 3.1%
respondents are still
1.8% 0.0% 4.3%
3.5%
1.8%
3.9%
0.0%
2.5% 3.1%
3.1% 8.7%
seeking answers to how
90% 4.7% 9.2% 10.0% 3.1%
8.2%
3.1% 4.3% to make their datacenters
80%
14.5% 15.0% 12.5% 13.0% more green.
70% 14.6%
15% have started to
Percent of Sample
6.6% 12.5%
15.0% 17.4%
60% 8.2%
invest in smarter
50% 7.5%
8.7% software tools while 8%
40% each are measuring
30% 63.2% 59.4%
/assessing datacenters
56.1%
47.5% 43.5%
and being more energy
20%
efficient by design.
10%
Enterprise datacenters
0%
Overall (N=171) Server Room Localized Mid-Tier Enterprise
are also buying more
(N=76) Datacenter Datacenter Datacenter energy efficient
(N=40) (N=32) (N=23)
Other - specify technology, apart from
Putting together an overall Corporate Social Responsibility policy of which green is an integral part
Know what we need and have started work having the most number
Invest in Smarter Software Tools
Become more efficient by buying more energy efficient servers/storage/networking
of respondents who
Trying to be more energy efficient by design
Know what we need and have started re-desinging our datacenter to remove design faults
know what they need and
Started by measuring and assessing our datacenter have started work.
Trying to find out the best way we can become more "green"
© 2008 IDC 22
Datacenter Overview:
The “Green” objective
Q. If your organization were to seek outside help in making your datacenter more "green" -
which vendor do you think would be best suited to help you?
2.3% 1.3%
60% 2.5%
and localized datacenter
4.3%
50% 46.9% respondents.
34.5% 32.9%
32.5%
40% 26.1% Surprisingly Sun that has a
very strong market share in
30%
ASEAN doesn’t come up as
20% choice, and nor do the
31.6%
29.2% 27.5% 28.1% 26.1% power and cooling vendors
10%
like Emerson and APC
0% figure very high in the
Overall Server Room Localized Mid-Tier Enterprise responses.
(N=171) (N=76) Datacenter Datacenter Datacenter
(N=40) (N=32) (N=23)
© 2008 IDC 23
Section C
Datacenter Drilldown:
Current and Future Build Outs and Discontinues
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Taxonomy
Server Room: A secondary computer location that usually is under IT
control, often less than 500 sq ft and has some power & cooling as well as
security capabilities
Localized Data Center: May be a primary or secondary location that is
usually under 1,000 sq ft requiring badge or pin access and has some power
and cooling redundancy to ensure constant temperature
Mid-Tier Data Center: Is the primary server location for an organization that
is a large room, but often under 5,000 sq ft. It has superior cooling systems
that are probably redundant and is probably protected by two levels of
physical and digital security
Enterprise Class Data Center: Is the primary server location for an
organization. Is a very large room often in excess of 5,000 sq ft and has
advanced cooling systems, redundant power and is protected by multiple
levels of physical and digital security
© 2008 IDC 25
Datacenter Drilldown:
Current Number of Datacenters
Q. How many of each of the following currently operate today within your organization?
Percent of Sample
70% 28.3%
datacenters along with
a number of server 60% 13.2%
rooms (220), localized 50% 43.9% 37.7%
(100) and mid-tier (36)
40% 77.4%
datacenters. 50% of 32.1%
© 2008 IDC 26
Datacenter Drilldown:
Discontinue/New Build
Q. How many of each of the following types (or levels) of datacenters does your
organization plan to build or close over the next 3-5 years?
Enterprise datacenter
Overall 48 10
respondents in ASEAN
indicate opening 12.3% new
datacenters as against Server Room 21 2
closing only 2.4% existing
ones in the next 3-5 years.
Localized 13 3
The demand for scale, DR
and inadequacy of existing
New
datacenters seem to be Mid-Tier 7
Discontinue
driving the additional build-
out of datacenters in
Enterprise 7 5
ASEAN
0 10 20 30 40 50 60
No of Datacenters
© 2008 IDC 27
Datacenter Drilldown:
Current Number of Datacenters
Q. How many of each of the following currently operate today within your organization?
Percent of Sample
with 176 localized and 70%
50%
Dominated by 49.2%
manufacturing, financial 40% 78.0%
28.8%
services and distribution 30%
segments, more than 20% 40.7%
half of these 10% 20.3% 20.3%
respondents have more
0%
than 1000 employees. Overall Server Room Localized Mid-Tier
Datacenter Datacenter
© 2008 IDC 28
Datacenter Drilldown:
Discontinue/New Build
Q. How many of each of the following types (or levels) of datacenters does your organization
plan to build or close over the next 3-5 years?
The discontinuation of
Enterprise 2
midrange are especially
high.
0 10 20 30 40 50 60 70 80
No of Datacenters
© 2008 IDC 29
Datacenter Drilldown:
Current Number of Datacenters
Q.How many of each of the following currently operate today within your organization?
Percent of Sample
(329).
60%
37% of the sample has
50%
more than 1000 35.9%
employees, and a 40% 49.5%
majority came from 30% 63.0%
manufacturing and public 20%
sector segment 28.3%
10%
14.1%
0%
Overall Server Room Localized Datacenter
© 2008 IDC 30
Datacenter Drilldown:
Discontinue/New Build
Q. How many of each of the following types (or levels) of datacenters does your organization
plan to build or close over the next 3-5 years?
© 2008 IDC 31
Datacenter Drilldown:
Current Number of Datacenters
Q. How many of each of the following currently operate today within your organization?
Percent of Sample
70%
facilities 9.0%
60%
1) The many remote offices
distributed across the 50%
country due to its vast 40%
geographic expanse
30% 62.7%
2) The scale and maturity of
20%
customers have
restricted them to build 10%
just-enough capacity in
0%
the past Server Room
© 2008 IDC 32
Datacenter Drilldown:
Discontinue/New Build
Q. How many of each of the following types (or levels) of datacenters does your
organization plan to build or close over the next 3-5 years?
boxes.
New
This is again a reflection of Mid-Tier 6
fast growing companies in a Discontinue
rapidly expanding economy.
Enterprise 3
© 2008 IDC 33
Section D
Datacenter Characteristics:
Size, Capacity, Utilization
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Overview:
Location
Q. Thinking about your datacenter , is it shared/standalone?
100%
© 2008 IDC 35
Datacenter Characteristics:
Classification
Q. Datacenters are categorized - by the US-based Uptime Institute - into 4 tiers, depending on
the amount of downtime they experience...which of the following tiers best describes your
datacenter?
34.0%
80%
Tier 4
22.8%
70% 24.9% 28.8%
26.4%
Percent of Sample
Tier 3
60%
Tier 2
50%
35.8%
22.9% 37.0% Tier 1
40% 28.1% 33.9%
30%
20%
33.3% 26.4%
26.4% 27.2%
10% 22.0%
3.8%
0%
Overall (N=405) Server Room Localized Mid-Tier Datacenter Enterprise
(N=201) Datacenter (N=92) (N=59) Datacenter (N=53)
34% of enterprise datacenter owners have facilities that classify under the tier 4 ranking by the uptime
institute. Surprisingly server rooms have tier 4 datacenters that are second to enterprise datacenters.
© 2008 IDC 36
Datacenter Characteristics:
Redundancy
Q. Is your primary datacenter backed up by a redundant site?
60%
highest percentage of
redundancy, while server
50% rooms have the lowest.
40% 81.3% IDC feels that some of
73.9%
67.8% 70.0% these datacenters may not
30% 59.2%
be fully redundant and end-
20% users could be including
data redundancy in the
10%
responses.
0%
Overall Server Room Localized Mid-Tier Enterprise
(N=171) (N=76) Datacenter Datacenter Datacenter
(N=40) (N=32) (N=23)
Yes No
© 2008 IDC 37
Datacenter Characteristics:
Sq. feet and Floor Space Occupied
Q. On average, what percent of floor space is currently being used in the following:
© 2008 IDC 38
Datacenter Characteristics:
UPS Capacity
Q. What is the total UPS (uninterruptible power supply) capacity for your Primary Datacenter?
- Primary & Redundant UPS capacity
© 2008 IDC 39
Datacenter Characteristics:
Average Load Capacity per Rack
Q. What is the average load capacity per rack within your Primary datacenter?
22.9% 10.2%
60% 21.2%
17.4%
15.1% 32% of the enterprise
50%
and 22% of the mid-tier
22.0%
datacenter customers
40% 20.8%
replied as having the
30% average load capacity
53.2% 52.2%
47.7% per rack at more than
20% 37.3%
30.2% 10KW, which explains
10% why blade penetration is
0% among the higher side
Overall Server Room Localized Mid-Tier Enterprise in the region in ASEAN.
(N=405) (N=201) Datacenter Datacenter Datacenter
(N=92) (N=59) (N=53)
© 2008 IDC 40
Datacenter Characteristics:
Power Utilization
Q. What percentage of the power coming into the datacenter is used to power IT equipment (as
opposed to non-IT equipment, like air conditioning, etc..)?
© 2008 IDC 41
Datacenter Characteristics:
Who Pays The Bill
Q. In general, which budget within your company pays for the electric (power) costs
associated with your Primary Datacenter?
60%
Chargeback
respondents don’t see
50% 23.9% 25.4% across Lines of any power and cooling
Business
21.2% 16.9% issues. Of course
28.3%
40% Administrative/C
orporate Budget
ignorance could be
30% prevailing even in the
Facilities Budget higher-end enterprises
20%
35.3% 35.8% 38.0% 37.3% where IT does own the
26.4%
10%
IT Organization
budget, since they are
Budget probably not being
0%
Overall Server Room Localized Mid-Tier Enterprise mandated to measure
(N=405) (N=201) Datacenter
(N=92)
Datacenter
(N=59)
Datacenter
(N=53)
and control it – thus far
© 2008 IDC 42
Section E
Datacenter Power and Cooling
Impact, Challenges and Resolves
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Power and Cooling:
Impact of Current Inefficient Power System
Q.Has your organization experienced any of the following business impacts from issues or
challenges related to power of your datacenter?
outages. Enterprise
37%
Server or Storage
Smaller sites are more likely Downtime
to believe that there are 32% Mid-Tier
fewer business impacts Datacenter Outage
from power and cooling
issues compared to Constrained 31%
Localized
deployment of new
datacenters. This is a servers/systems
challenge for vendors 30%
Lowered Customer
looking to sell into this Satisfaction Server Room
Percent of Sample
© 2008 IDC 44
Datacenter Power and Cooling:
Impact of Current Inefficient Cooling System
Q.Has your organization experienced any of the following business impacts from issues or
challenges related to cooling of your datacenter?
Percent of Sample
© 2008 IDC 45
Datacenter Power and Cooling:
Challenges with respect to Power and Cooling
Q.On a scale of 1-10 (where 1=Not a Challenge and 10=Extremely Challenging), please rate each of
the following issues in terms of the challenge they present to your organization in powering and
cooling your datacenter/s..
© 2008 IDC 47
Datacenter Power and Cooling:
Preferred Specific Solutions
Q. Which of the following actions would your organization take - or consider taking?
Server Room
Use Fans to improve air flow
© 2008 IDC 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 48
Datacenter Power and Cooling:
“Power” Vendor Mindshare
Q. Which vendor primarily comes to mind when you think about power solutions for datacenters?
30%
25%
Percent of Sample
20%
15%
10%
5%
0%
Overall Server Room Localized Datacenter Mid-Tier Datacenter Enterprise Class
Datacenter
Hewlett Packard IBM Sun Microsystems Dell APC/MGE Liebert/Emerson Eaton/Powerware Other Don't know
APC/MGE seems to be enjoying the most recall in ASEAN, when it comes to vendors providing power
solutions across all but mid-tier datacenter category where 32% respondents choose IBM. HP is a close
third overall with customers in mid-tier, enterprise and server rooms. Emerson surprisingly finds very little
recall across almost all types of datacenters.
© 2008 IDC 49
Datacenter Power and Cooling:
“Cooling” Vendor Mindshare
Q. Which vendor primarily comes to mind when you think about cooling solutions for
datacenters?
30%
25%
Percent of Sample
20%
15%
10%
5%
0%
Overall Server Room Localized Datacenter Mid-Tier Datacenter Enterprise Class
Datacenter
Hewlett Packard IBM Sun Microsystems Dell APC/MGE Liebert/Emerson Eaton/Powerware Other Don't know
It seems the visibility of vendors providing cooling solutions is not too strong among the datacenter
operatives, although there maybe a facilities/maintenance department that knows better. Of the vendors
that got called out APC and IBM again have the most recall although IBM doesn’t really sell its own cooling
equipment but has site services that help design and procure cooling systems.
© 2008 IDC 50
Section F
Datacenter Operations
Spending & Solution Partner
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.
Datacenter Operations:
Cap-ex Spending on Datacenter
Q. What was the capital-expenditure (Cap-ex) involved in building your primary datacenter?
If we take away the 9% enterprise
datacenter users who have
Capital Expenditure in Building your Datacenter indicated spending between
100% 1.2%
0.6% 1.3% 3.1%
5-10MUS$, the average
1.8% 2.6%
2.3% 2.6%
15.0%
3.1% 8.7% spend is in the range of 500-
90% 9.4%
15.6% 8.7% 600K for mid-tier and
80% 4.3% enterprise datacenters, and
32.9% 300K for localized and server
27.5% 13.0%
70% 32.7% rooms.
Percent of Sample
© 2008 IDC 53
Datacenter Operations:
Op-ex Spending on Datacenter
Q. Generally speaking, what is the operational-expense (op-ex) for your primary datacenter -
per month? - In-house
© 2008 IDC 54
Datacenter Operations:
Breakdown of Op-ex Spending on Datacenter
Q. For the operational expenditure spent on building your datacenter, can you please provide a
% breakdown of that spending for the following categories..
70%
7.9% 7.8% 7.1% 5.9%
9.3% Enterprise datacenters
60% 9.6% 10.4%
9.7% 9.7% generally seem more
10.6%
50% balanced while mid-tier and
12.2% 13.9% 9.8% 12.5%
12.3%
localized seem to have
40% energy cost issues that
8.3% 7.1% 10.4%
16.9%
30% 7.6% need to be addressed.
9.3%
11.0% 12.2%
20%
9.1% IDC believes there is a
good opportunity for
26.0%
10% 21.0% 19.0%
24.0%
19.0% datacenter solution
vendors to engage ASEAN
0% customers in making their
Overall Server Room Localized Mid-Tier Enterprise datacenters more efficient
(N=171) (N=76) (n=40) (N=32) (N=23)
from a power and cooling
Direct IT electrical cost (IT systems & lighting etc) Cooling electrical costs (cooling system only)
Cooling maintanence costs Networking cost perspective
Labor cost Datacenter faciltiy rent or leasing cost
UPS/Generator maintanence costs IT maintanence costs (ex labor costs)
IT maintanence costs (If outsourced) Other facility overhead costs
© 2008 IDC 55
Datacenter Operations:
Preferred Partner
Q. If your organization were to transform its datacenter (ie, build a next generation
datacenter), would you prefer to...
Talk to experts in different areas, like IT or power or cooling design/layout..since you don’t think one vendor can do it all
Use one major vendor to be your key consultant in helping you transform
© 2008 IDC 56
Datacenter Operations:
Current Engagement
Q. Can you tell us if your organization is currently working with an outside party on...
Percent of Sample
© 2008 IDC 57
Datacenter Operations:
Preferred Attributes in the Partner
Q. What would be the key attributes your organization would look for in a datacenter vendor?
© 2008 IDC 58
Thanks!
Avneesh Saxena, Group VP, Systems, Storage & Software
+852-29054223
[email protected]
Copyright 2007 IDC. Reproduction is forbidden unless authorized. All rights reserved.