NEW QUESTION 1
- (Topic 1)
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A. Checkpoint Report
B. End Stage Report
C. End Project Report
D. Product Status Account
Answer: B
NEW QUESTION 2
- (Topic 1)
How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Answer: D
NEW QUESTION 3
- (Topic 1)
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
Answer: B
NEW QUESTION 4
- (Topic 1)
Which statement about stages is true?
Answer: C
NEW QUESTION 5
- (Topic 1)
What process is used by the Project Board to respond to an Exception Report?
A. Controlling a Stage
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
Answer: D
NEW QUESTION 6
- (Topic 1)
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account
Answer: C
NEW QUESTION 7
- (Topic 1)
Which is a purpose of the Managing Product Delivery process?
A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
B. Provide a controlled link between the Project Manager and the Team Manager(s)
C. Enable the Project Board to requestupdates to the current Team Plan
D. Establish solid foundations for the project
Answer: B
NEW QUESTION 8
- (Topic 1)
Which is a difference between management and technical stages?
Answer: B
NEW QUESTION 9
- (Topic 1)
Which is a purpose of the Controlling a Stage process?
Answer: B
NEW QUESTION 10
- (Topic 1)
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
A. Risk category
B. Risk description
C. Risk response
D. Risk status
Answer: C
NEW QUESTION 10
- (Topic 1)
Which product is NOT created in the Managing a Stage Boundary process?
Answer: A
NEW QUESTION 12
- (Topic 1)
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
Answer: D
NEW QUESTION 16
- (Topic 1)
Which is an objective of the quality review technique?
Answer: C
NEW QUESTION 17
- (Topic 1)
How should the Team Manager report that tolerances are forecast to be exceeded?
D. Grant a concession
Answer: C
NEW QUESTION 22
- (Topic 1)
Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
Answer: A
NEW QUESTION 24
- (Topic 1)
Which principle helps to define what should be included and what should be excluded from a project?
Answer: B
NEW QUESTION 28
- (Topic 1)
Which two roles are linked by the Managing Product Delivery process?
Answer: C
NEW QUESTION 30
- (Topic 1)
Which of the following is NOT a purpose of the Closing a Project process?
Answer: A
NEW QUESTION 33
- (Topic 1)
Which is a purpose of a Project Brief?
Answer: B
NEW QUESTION 37
- (Topic 1)
Which regular report provides the Project Board with a summary of stage status?
Answer: C
NEW QUESTION 41
- (Topic 1)
Which role is responsible for the management of a risk assigned to it?
A. ProjectSupport
B. Risk owner
C. Risk actionee
D. Project Assurance
Answer: B
NEW QUESTION 42
- (Topic 1)
Which is NOT a purpose of the Organization theme?
Answer: B
NEW QUESTION 43
- (Topic 1)
Which statement defines a risk?
A. A certain event occurring in the future that will have a negative impact on the project's objectives
B. An event that has already occurred that the Project Manager must deal with immediately
C. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
D. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
Answer: C
NEW QUESTION 45
- (Topic 1)
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Directing a Project
B. Managing a Stage Boundary
C. Controlling a Stage
D. Starting up a Project
Answer: C
NEW QUESTION 47
- (Topic 1)
Which of the following is NOT part of quality planning?
Answer: B
NEW QUESTION 48
- (Topic 1)
Which is an objective of the Managing Product Delivery process?
Answer: D
NEW QUESTION 52
- (Topic 1)
What is defined as a temporary organization that is created for the purpose of delivering one or more business products?
Answer: B
NEW QUESTION 57
- (Topic 1)
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
A. Enable the Project Board to decide whether or not to authorize the project
B. Justify the continuing viability of the project
C. Enable the Project Board to decide whether or not to authorize project closure
D. Justify the initiation of a project
Answer: B
NEW QUESTION 59
- (Topic 1)
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the
project,
A. Progress
B. Plans
C. Organization
D. Business Case
Answer: C
NEW QUESTION 64
- (Topic 1)
Which is a responsibility of the managing level within the project management team?
Answer: C
NEW QUESTION 66
- (Topic 1)
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
A. Controlling a Stage
B. Closing a Project
C. Directing a Project
D. Managing a Stage Boundary
Answer: D
NEW QUESTION 67
- (Topic 1)
Where should an off-specification be recorded?
A. Risk Register
B. Issue Register
C. Work Package
D. Configuration Management Strategy
Answer: B
NEW QUESTION 68
- (Topic 1)
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Packages for the work performed in the final stage.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 aretrue
D. Neither 1 or 2 are true
Answer: B
NEW QUESTION 72
- (Topic 1)
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a
project.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
NEW QUESTION 75
- (Topic 1)
Which is a responsibility of a risk owner?
Answer: C
NEW QUESTION 79
- (Topic 1)
Which is a type of issue?
A. An expected dis-benefit
B. An off-specification
C. Aproject outcome
D. A scope tolerance
Answer: B
NEW QUESTION 83
- (Topic 1)
Which describes the 'Identify Risks' step within the recommended risk management procedure?
Answer: D
NEW QUESTION 88
- (Topic 1)
Which statement about the Directing a Project process is FALSE?
Answer: C
NEW QUESTION 91
- (Topic 1)
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery
Answer: B
NEW QUESTION 96
- (Topic 1)
When considering risks, which describes an opportunity in a project?
Answer: B
NEW QUESTION 98
- (Topic 1)
Which is part of the PRINCE2 definition of a project?
Answer: D
NEW QUESTION 99
- (Topic 1)
Why is a Project Brief produced?
Answer: C
Answer: C
A. Business Case
B. Plans
C. Progress
D. Quality
Answer: C
Answer: B
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Answer: B
Answer: D
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Answer: A
A. Issue Register
B. Product Status Account
C. Product Description
D. Configuration Item Record
Answer: B
Answer: C
Answer: A
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Answer: A
A. Administrator
B. Chair
C. Producer
D. Reviewer
Answer: C
Answer: D
Answer: C
Answer: B
A. a constraint
B. a deviation from tolerance
C. an off-specification
D. a threat
Answer: C
A. Business Case
B. Communication Management Strategy
C. Project Product Description
D. Quality Management Strategy
Answer: A
A. Assessment
B. Communication
C. Quality control
D. Status accounting
Answer: D
A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B. Project Assurance is independent of the Project; qualityassurance is only independent of the Project Manager
C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Answer: D
Answer:
A. Product Description
B. Team Plan
C. Work Package
D. Stage Plan
Answer: C
Answer: C
Answer: A
Answer: C
Answer: A
A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
B. Provide a fixed reference point at which acceptance for the project product is confirmed
C. Enable the Project Board to be provided with sufficient information to authorize the next stage
D. Enable the organization to understand the work that needs to be done to deliver the project's products
Answer: A
D. business as usual
Answer: A
A. Project mandate
B. Project management team role descriptions
C. Communication Management Strategy
D. Quality Register
Answer: B
A. Ensure that the project organization structure will enable the project to deliver the business benefits in the required time frame
B. Define accountability within the project
C. Identify risk owners for the project
D. Define the quality methods and responsibilities for the management of the project
Answer: B
Answer: D
A. Progress
B. Change
C. Organization
D. Quality
Answer: A
Answer: B
A. Project Brief
B. Benefits Review Plan
C. Project Initiation Documentation
D. Configuration Management Strategy
Answer: C
A. Corporate management
B. Project Board
C. Project Assurance
D. Project Manager
Answer: D
Answer: B
A. How the management and specialist products of the project should be baselined
B. How the method will be tailored for the size and complexity ofthe project
C. Whether the expected benefits have been achieved
D. Who will make decisions on any changes during the project
Answer: C
A. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
C. Identify the actions required to recover from the effect ofa tolerance deviation
D. Define the changes which are within the scope of the change budget
Answer: C
Answer: B
A. The approach that will be used to prove whether the project's products have been completed
B. A measureable improvement resulting from a project outcome
C. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
D. The project controls set up during the process Initiating a Project
Answer: C
Answer: B
Answer: B
A. Summarize progress to enable the Project Board to decide what action to take next
B. Summarize how the project performed against the version of the Project Initiation Documentation used to authorize it
C. Provide the detailed analysis of a deviation and offer options for the way to proceed
D. Provide a plan for the next stage of the project
Answer: A
A. Business Case
B. Project Plan
C. CommunicationManagement Strategy
D. Project Product Description
Answer: A
Answer: A
A. activities
B. processes
C. products
D. quality
Answer: B
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3 ,4
D. 2, 3, 4
Answer: C
A. Executive
B. Senior User
C. Senior Supplier
D. Project Manager
Answer: B
A. Quality
B. Plans
C. Progress
D. Business Case
Answer: D
Answer: A
Answer: D
A. The Project Board is responsible for determining the priority of all issues
B. Direction is required on the best response for preventing the issue from occurring
C. The issue is forecast to cause a deviation beyond stage tolerance and advice is required
D. Escalating issues is a means of providing the Project Board with a regular update on their status
Answer: C
Answer: B
Answer: D
A. Project Plan
Answer: B
Answer: C
Answer: C
Answer: C
Answer: B
A. Increase in agreedscope
B. Increase in agreed scope
C. Increase in agreed scope
D. Handover activities
Answer: A
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Answer: C
Answer: D
A. Quality assurance
B. Risk management
C. Verification and audit
D. Progress reporting
Answer: C
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: D
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan
Answer: B
A. Principles
B. Themes
C. Processes
D. Techniques
Answer: A
Answer: B
Answer: C
A. define a coding system to provide a unique identifier for the products within
B. summarize the results of the quality activities performed on
C. provide a framework to design, develop and maintain
D. define the project benefits to be achieved by each of
Answer: C
A. Project Manager
B. Project Support
C. The authoritydefined in the Product Description
D. Senior Supplier
Answer: C
Answer: B
A. Closing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
Answer: C
A. Describe the risk management techniques and standards to be applied to the project
B. Act as a central record of information relating to the identified risks for the project
C. Act as a repository forinformal issues
D. List the responsibilities for achieving an effective risk management procedure
Answer: B
Answer: B
A. a corporate
B. a temporary
C. an external
D. a technical
Answer: B
Visit Our Site to Purchase the Full Set of Actual PRINCE2-Foundation Exam Questions With Answers.
We Also Provide Practice Exam Software That Simulates Real Exam Environment And Has Many Self-Assessment Features. Order the
PRINCE2-Foundation Product From:
https://www.2passeasy.com/dumps/PRINCE2-Foundation/