ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 OROMIA FINNA BURKUKE DAM 244 Tue 12/21/21 Fri 11/25/22
days
PROJECT
2 1.General Provision 13 days Tue 12/21/21 Thu 1/6/22
3 1.1 Mobilization of contractor's mashinery and 10 days Tue 12/21/21 Mon 1/3/22
equipment
4 1.2 Temporary access and haul roads 3 days Tue 1/4/22 Thu 1/6/22
5 1.3 Survey and Setting out 2 days Tue 1/4/22 Wed 1/5/22
6 2. CAMP CONSTRUCTION 17 Tue 1/4/22 Wed 1/26/22
(Residence,office,kitchen,laboratory,store days
,guard house,toilet and fence)
7 2.1.1 Earth work 5 days Tue 1/4/22 Mon 1/10/22
8 A. Clearing of site to remove top soil 1 day Tue 1/4/22 Tue 1/4/22
9 B. Excavation for stone masonary 2 days Wed 1/5/22 Thu 1/6/22
10 C.Excavation 4m depth for toilet and 2 days Wed 1/5/22 Thu 1/6/22
shower
11 D. Cartaway ofsurplus material 2 days Fri 1/7/22 Mon 1/10/22
12 E. Supply and fill hard core work 2 days Fri 1/7/22 Mon 1/10/22
13 2.1.2 Concrete and Block Work 5 days Fri 1/7/22 Thu 1/13/22
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
14 2.1.2.1 Masonary foundation below and 3 days Fri 1/7/22 Tue 1/11/22
above ground level
15 2.1.2 .2 Mass concrete fill for floor 3 days Tue 1/11/22 Thu 1/13/22
16 2.1.3 Carpentary ,Roofing and walling 8 days Fri 1/7/22 Tue 1/18/22
17 2.1.3.1 Supply,assemle and fixin position 2 days Fri 1/7/22 Mon 1/10/22
euclaptus wall post and purlin
18 2.1.3.2 Fix roof G-32 cover and wall cover 1 day Tue 1/11/22 Tue 1/11/22
19 2.1.3.3 Supply and fix chipwood for internal 3 days Wed 1/12/22 Fri 1/14/22
wall cover and ceiling(only for resident and
office block)
20 2.1.3.4 Supply and fix CIS window and door 3 days Wed 1/12/22 Fri 1/14/22
21 2.1.3.5 Floor Screed and finilizing 3 days Fri 1/14/22 Tue 1/18/22
22 Fence work 4 days Wed 1/5/22 Mon 1/10/22
23 2.1.4 .1 Fence 2m height erected in 0.6m 4 days Wed 1/5/22 Mon 1/10/22
depthplaced every 2m width
24 Camp Facilities 6 days Wed 1/19/22 Wed 1/26/22
25 2.1.5.1 Camp facilities 6 days Wed 1/19/22 Wed 1/26/22
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
26 3. DAM BODY WORK 188 Tue 1/4/22 Thu 9/22/22
days
27 3.1 Earth work and Excavation 25 days Thu 1/6/22 Wed 2/9/22
28 3.1.1 Clearind dam site from bushes,stones 4 days Thu 1/6/22 Tue 1/11/22
etc
29 3.1.2 Bulk Excavation in common soil upto 6 days Wed 1/12/22 Wed 1/19/22
1.5m or to decided depth
30 3.1.3 Cut off trench to described depth fo 15 days Thu 1/20/22 Wed 2/9/22
core foundation
31 3.2 Fill and Compaction work 117 Tue 1/4/22 Wed 6/15/22
days
32 3.2.1 Production of fill and filter material 65 days Tue 1/4/22 Mon 4/4/22
and transportation
33 3.2.2 selected fill with clay material and 90 days Thu 2/10/22 Wed 6/15/22
Compaction of the core section work
34 3.3 Filter(F1 and F2) 45 days Thu 6/16/22 Wed 8/17/22
35 3.3.1 Sand filter-costruction of F-1 with 30 days Thu 6/16/22 Wed 7/27/22
clean washed copncrete sand
36 3.3.2 Gravel filterconstruction of filter F-2 15 days Thu 7/28/22 Wed 8/17/22
with clean screened fine gravel
37 3.4 Down Stream and Toe Drainage 26 days Thu 8/18/22 Thu 9/22/22
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
38 3.4.1 Drainage trench excavation at the toe 6 days Thu 8/18/22 Thu 8/25/22
of the dam
39 3.4.2 Construction of drain 20 days Fri 8/26/22 Thu 9/22/22
40 3.5 Slope Protection 117 Tue 4/5/22 Wed 9/14/22
days
41 3.5.1 Upstream Slope protection supply and 20 days Tue 4/5/22 Mon 5/2/22
spread stone riprap
42 3.5.2 Down stream protection with top soil 20 days Thu 8/18/22 Wed 9/14/22
on the down stream,placing sodding
43 3.5.3 Spread and compaction of selected 30 days Tue 5/3/22 Mon 6/13/22
material to protect of the crest dam
44 4. Dam Instrumentation 12 days Tue 6/14/22 Wed 6/29/22
45 4.1 Supply and install pizometer and 6 days Tue 6/14/22 Tue 6/21/22
deformation monitoring in embankment
46 4.2 Supply and install water level staff,V-Notch 6 days Wed 6/22/22 Wed 6/29/22
and concrete bench mark
47 5. Spill Way Works 149 Tue 5/3/22 Fri 11/25/22
days
48 5.1 Earth Work and Excavation 11 days Thu 6/16/22 Thu 6/30/22
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 4
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
49 5.1.1 Site Clearance of top soil 1 day Thu 6/16/22 Thu 6/16/22
50 5.1.2 Excavation work 5 days Fri 6/17/22 Thu 6/23/22
51 5.1.3 compacted granular backfill 5 days Fri 6/24/22 Thu 6/30/22
52 5.1.4 selected material fill from pits 3 days Fri 6/24/22 Tue 6/28/22
53 5.1.5 cartaway of surplus material 4 days Fri 6/24/22 Wed 6/29/22
54 5.2 Masonary work 66 days Fri 8/26/22 Fri 11/25/22
55 5.2.1 Masonary wall in u/s and d/s floor cut 20 days Fri 8/26/22 Thu 9/22/22
offs upto maximum of 1m depth
56 5.2.2 Masonary work in approach channel 15 days Fri 9/23/22 Thu 10/13/22
floor below concrete
57 5.2.3 Masonary wall in retaining wall in 15 days Fri 10/14/22 Thu 11/3/22
approach channel
58 5.2.4 Cyclopean concrete in ogee wier 10 days Fri 9/23/22 Thu 10/6/22
59 5.2.5 Masonary wall with plastered in wier 16 days Fri 11/4/22 Fri 11/25/22
walls above ground
60 5.2.6 cyclopean concrete in chute floorand 15 days Fri 11/4/22 Thu 11/24/22
stiling basin floor below concrete
61 5.2.7 Masonary wall in retaining wall in 10 days Fri 10/14/22 Thu 10/27/22
chute section
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 5
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
62 5.2.8 Stone riprap in trapizoidal exit channel 15 days Fri 9/23/22 Thu 10/13/22
63 5.3 Concrete Works 124 Tue 5/3/22 Fri 10/21/22
days
64 5.3.1 Blinding concrete 20 days Tue 5/3/22 Mon 5/30/22
65 5.3.2 Fixing steel reinforcement work 3 days Fri 10/14/22 Tue 10/18/22
66 5.3.3 oncrete(C-25) works in top of wier and 3 days Wed 10/19/22 Fri 10/21/22
d/s inclined face
67 5.3.4 fixing water stop PVC 3 days Wed 10/19/22 Fri 10/21/22
68 6 Out-let works 124 Wed 1/12/22 Mon 7/4/22
days
69 6.1 Earth work and excavation 116 Wed 1/12/22 Wed 6/22/22
days
70 6.1.1 Site clearance and excavation 2 days Wed 1/12/22 Thu 1/13/22
71 6.1.2 Fill with selected material from 5 days Thu 6/16/22 Wed 6/22/22
borrow pits
72 6.1.3 Cartaway 2 days Wed 1/12/22 Thu 1/13/22
73 6.2 Masonary work 2 days Thu 6/23/22 Fri 6/24/22
74 6.2.1 Hard core in retaining wall at terminal 2 days Thu 6/23/22 Fri 6/24/22
structurewith plastering
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 6
ID Task Task Name Duration Start Finish Resource
Mode Names
Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
75 6.3 Pipes and Fiting 3 days Thu 6/23/22 Mon 6/27/22
76 6.3.1 Fix in Position of 50 cm steel pipe and 3 days Thu 6/23/22 Mon 6/27/22
butter fly with full accessories
77 6.4 Concrete Work 5 days Tue 6/28/22 Mon 7/4/22
78 6.4.1 In intake tower (C-25) 2 days Thu 6/30/22 Fri 7/1/22
79 6.4.2 Fixing steel reinforcement according 2 days Tue 6/28/22 Wed 6/29/22
to structural drawing
80 6.4.3 installing of trashrack intake tower 1 day Mon 7/4/22 Mon 7/4/22
81 7 Gravel aceess Roadof 6m wide 28 days Thu 6/16/22 Mon 7/25/22
82 7.1 Earth work and Excavation 28 days Thu 6/16/22 Mon 7/25/22
83 7.1.1 Clearing areas 3 days Thu 6/16/22 Mon 6/20/22
84 7.1.2 Excavation cut/fill earth works 10 days Fri 6/17/22 Thu 6/30/22
85 7.1.3 Spreading and c for camber formation 5 days Fri 7/1/22 Thu 7/7/22
86 7.1.4 Fll and compaction workof 15 cm 12 days Fri 7/8/22 Mon 7/25/22
selected gravel wearing material
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: FINNA BURKUKE DAM
Summary Manual Summary Rollup Progress
Date: Fri 12/31/21
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 7