Retrofitting of 6-Storey Paulino Hospital
Retrofitting of 6-Storey Paulino Hospital
Of the Course
College of Engineering
by
LALUYAN, REYCRETZ E.
December 2020
TABLE OF CONTENTS
I. Introduction
A. Introduction ------------------------------------------------------------------4-5
B. Rationale ------------------------------------------------------------------------6
C. Objective ------------------------------------------------------------------------6
C. Recommendations—----------------------------------------------------------34
References-------------------------------------------------------------------------35-36
I. Introduction
A. Introduction
Jacketing is one of those methods and considered as one of the most well-
unlike other methods where steel elements are used, does not have a
During the Earthquake last October and December, 2019 Digos City
was one of the most severely damaged cities because a fault-line lies near the
city proper. Buildings and establishments incurred substantial ruins that left
some already seemingly irreparable. The new yet under construction building
35 meters long, 19 meters wide and about 21 meters high. To assess the
damages and the possible cost of redeeming the building, a certain company
has been asked to carry out a specific structural assessment of the property
After being reviewed for general structural condition, the building has been
elements, calculations and past experience with similar type of buildings. The
increased using the following methods: (1) Placing steel bracings shear wall
and fire protection needs of other techniques where steel is exposed or where
epoxy resins are used. (Julio, E.S., et. al. 2003. Structural Rehabilitation of
Columns with Reinforced Concrete Jacketing. New Jersey: John Wiley & Sons,
Ltd.)
B. Rationale
methodology. That is why the researcher has chosen this topic for it is very
C. Objective
building.
building.
4. To determine the most economical way that the building will be able to
eminently damaged by West Java Earthquake with moderate seismic risk and
structures. Each building had high occupancy during the day with 400
system with shallow foundation, no tie beam, and the soil cover and support
roof system and walls, poor quality of roof truss members and connections,
roof was deformed on top chord. It also has damage on walls with cracks and
on sanitation facility.
columns with footings on corners, they install wire mesh for strengthening
wall elements and they add double tie beams for better foundation system.
were less severe compared to other buildings in the area with similar existing
earthquake loads.
C. Application of Retrofitting Method in Nursing Faculty – Andalas
University Building
University with concrete jacketing and shear wall systems”, which was
authored by Fauzan, Febrin Anas Ismail, Oswin Dezardo, and Zev Al Jauhari
State Polytechnic, retrofitting has been found cost-effective. There are two
types of retrofitting presented in the paper that were conducted in the existing
building, concrete jacketing to the columns (local retrofit) and adding a shear
wall (global retrofit). All the retrofitting methods lead to a more resistant
capacity of the column, by around 165%, 23%, and 132% for bending
In comparison, retrofitting with the shear wall does not increase the
capacity of the column, but it reduces the internal forces in the column by
around 83%, 48%, and 6% for bending moment, shear, and axial forces,
occurred about 84% and 90% in both the X and Y directions, respectively. The
bending capacity of the columns on the 1st floor is not capable of carrying the
working loads from the internal forces when it exceeds the P-M interaction
diagram, while the beam capacity and the inter-story drift are safe from the
modeling and analyzing those columns that had been affected by the recent
earthquakes. Hence, we can plan it precisely and verify the members that
need to be retrofitted.
Second, organize the schedule. As stated from the module, one of the
must be scheduled well so it will not have any losses. An unscheduled event
in the construction site may cause profit-loss. Therefore, all the damaged
will occur.
This retrofitting is effective only in minor cracks. Epoxy sealants are used
to inject inside the cracks and plaster the exterior part of the crack. Thus,
Example photo:
according to the label instructions and apply epoxy over the crack
leaving spaces for the poured installation. Place the ports eight to ten
inches apart.
applied one to two inches wide along the length of the crack.
5. Using a plastic putty knife, apply epoxy underneath the outer half
6. Center the port over the crack face in each gap and attach. Be sure to
seal any pinholes or voids between the ports and the substrate being
8. Insert the cartridge into a dispensing tool. Remove the cap and the end
plug.
flowing equally.
13. Firmly attach the tubing to the nozzle. Attach the opposite end of the
tubing tightly over the tip of the first port that needs to be injected. The
flow clip should always be closed and only open while dispensing material.
14. Start with the lowest port when injecting vertical cracks. Inject until
16. Use the cap to plug the port. Begin injection at the second port
and inject until the epoxy reaches the third port. Repeat until
finished
17. After curing is complete, remove the ports with a hammer. For a
more finished look, the epoxy cap can be ground smooth finish by
Methodology:
Step 1: Prepare the surface of the existing RCC member to receive the
can drill.
Step 3: Drill holes of specified diameter and depth in concrete at locations
Step 4: Clean the drilled hole in dry state with round brushes and by
Step 5: Inject epoxy from the foil pack with the help of epoxy dispenser,
inside the drilled hole to fill it from ends up to the half of the holes.
Step 6: Insert the reinforcing bar and allow the epoxy adhesive to cure.
existing columns.
Step 8: Install and fixing formwork, the form must construct to fit
Step 9: Application of the previous steps for all sides of the column.
Step 10: Drilling a port in the formworks is usually at upper areas to expel
Step 11: To get a strong bonding should take the advantage of (pressure of
water) to clean the pores and saturate the prepared surfaces, existing
cohesion.
Step 12: Mixing the prepackaged repair materials which are designed for
Step 13: Start pumping. Pumping sequence is continued until the cavity is
full.
Methodology:
1. Prepare the surface of the existing RCC member where the additional
4. Clean the drilled hole in dry state with round brushes and by blowing
cartridge holder and disposable PVC mixing nozzle inserted inside the
6. Insert the shear bars and allow the epoxy adhesive to cure.
8. Install and fixing formwork, the form must construct to fit tightly
to clean the pores and saturate the prepared surfaces, existing surfaces
10. Mixing the prepackaged repair materials which are designed for
is full.
SHEARWALL LOCATIONS IN ELEVATION PLAN
SHEARWALL LAY-OUT IN FLOOR PLAN
Added Shear
Walls
Added Shear
Walls
IV. Presentation, Model Formulation and Sensitivity Analysis
A site visit was made on July 16, 2020 to observe the existing
experience with similar buildings, the following key findings are presented:
Existing conditions: The building was found with vast amount of debris
on the floors mainly on the third floor. The debris was mainly composed of
damaged and loose ceilings, partitions, wall and floor coverings, and
broken fixtures as shown in Figures 1-4. Some of the swing glass doors
chippings on stair treads, edges and risers. There were cracks in concrete
Figure 3 Spalling of tiles and concrete cover Figure 4 Spalling of mortar finishing at the
from wall. wall base.
B. Model Formulation - Structural Assessment of Paulino Hospital
of concrete columns, concrete beams with steel wide flange and truss
beams on the 5th and 6th floors only. The floors consist of a profiled steel
Spalling and
exposure of column
rebars on ground
floor.
Spalling of the column
concrete cover and the
exposure of rebars without
buckling or fracture on the
C. Sensitivity Analysis – Non-Structural Assessment of Paulino
Hospital
foundation, acting as partitions, and are 4’’ thick CHB walls. There were
cracks in many walls and fall of fairly large pieces of plaster. Typical
risk.
Figure 11 Extensive damage to interior walls on Figure 12 Spalling and cracking of exterior walls.
third floor.
Figure 15 Concrete crushing in walls. Figure 16 Concrete cracking and spalling in non-
structural walls.
2015 Edition. The tabulated seismic parameters from Section 408 were used
as input data for the structural analysis of the 3D simulation of the structure.
The output from the analysis indicated that the columns of the structure do
conditions.
quality of the existing structure while negating future issues with the building
• Crack repair;
catastrophic for the building; as the inadequate columns can lead to collapse
of the structures, under seismic forces. However, the capacity of the building
C. Recommendations
Public Works Department of Padang City. (2018). Work Unit Price Quarter I
2018. Indonesia.
Ltd.).
& CONSULTING 363, 3rd St., Phase 1 Ecoland Subdivision, Davao City.
January, 2020.
2011.