Assignment 3
Assignment 3
PROJECT MANAGEMENT
(NBO6B)
ASSIGNMENT 3
(Past Year Question)
Prepare by:
Ain Nabilah Binti Jasni
2018879626
Prepare for :
Dr Shatina Binti Saad
JULY 2017
QUESTION 5
a) Discuss any two (2) project closing activities. (5
marks)
Technical reasons
Lack of technical support that involving the sorts of machines, processes, and
materials that are used in industry, transport, and communications.
c) Discuss two (2) concerns for using project information systems. (5
marks)
QUESTION 6
b) Compute the cumulative actual cost (CAC) at the end of week 5. (2 marks)
CV = CEV - CAC
= 1,543k - 550k
= 993k
f) What will be the forecasted cost (FCAC) at the end of week 5? (2 marks)
g) Comment on the overall project cost performance. Support your comment based on
three (3) evidences. (3
marks)
JUNE 2018
QUESTION 4
a) Provide five (5) project closing activities. (5
marks)
Lack of Creativity
Once in a while, venture the board leaves almost no space for imagination. Group
pioneers either centre unnecessarily around the administration procedures or set
tight cut off times, constraining their staff to work inside severe boundaries. This can
demoralize imaginative reasoning and hamper advancement that may profit the task.
It is significant for a task chief to realize when to motivate inventiveness and when to
carefully follow the undertaking plan. An association can develop and make progress
without an undertaking supervisory crew set up. Notwithstanding, employing a
talented expert to deal with these viewpoints can open up new chances and help
your organization arrive at its objectives quicker.
High Costs
These programs can be costly and difficult to implement. Once the PMIS were
implements, they may need training. They may also have to hire subject matter
experts or specialists to help with a project. Often, there will be a push from
stakeholders to include features that were not initially planned. All of these issues
can quickly add up the cost of a project.
QUESTION 6
CV = CEV - CAC
= 1,896.5k - 765k
= 1,131.5k
g) Appraise the overall project cost performance. Support your comment based on three
(3) evidences. (3
marks)
JUNE 2019
QUESTION 4
a) Explain the purpose of change control system in project management. (5
marks)
The change control process in venture the board guarantees that each change
proposed during a task is satisfactorily characterized, inspected and endorsed before
execution. The change control process stays away from pointless changes that may
upset administrations and furthermore guarantees the productive utilization of assets.
This procedure gives the capacity for anybody in the undertaking group the client to
propose a change to the venture. The proposition must incorporate a depiction of the
change and anticipated advantages or other purpose behind the change. The change
is introduced utilizing the Change Request Form and added to the Change Log for
the venture.
b) The time-cost trade-off is used to reduce the project duration incrementally with the
smallest associated increase in cost. Elaborate five (5) assumptions in time-cost
trade-off of project crashing.
(10 marks)
The target of the time-cost exchange off examination is to lessen the first undertaking
term,
decided structure the basic way examination, to comply with a particular time
constraint, with the least expense. Notwithstanding that it may be important to
complete the undertaking in a particular opportunity to:
o Finish the task in a predefined cut off time date.
o Recover early postponements.
o Avoid sold harms.
o Free secret weapons right on time for different tasks
o Stay away from unfriendly climate conditions that may influence profitability.
o Receive an early fruition reward.
o Improve venture income
QUESTION 5
CV = CEV - CAC
= 3,700.5k - 903k
= 2,797.5k
g) Calculate the forecasted cost at completion (FCAC) using two different formulae.
(2
marks)
FCAC = TBC / CPI
= 740k / 2.479
= 298.51K
h) Comment on the overall project cost performance based on all the above costings.
(3
marks)
QUESTION 6
a) Project Management Information System (PMISs) have extensive reporting
capabilities. List five (5) types of reports that PMISs will be able to generate.
(5
marks)
Schedule and Planning - Computes early and late schedule, slack times and the
critical path
Resource Management - Including resource loading, levelling, and allocation.
Budget - Associate cost with individual tasks for more accurate budget estimation
and generation.
Control and Performance - Analyse and control cost and performance, updating
existing plans as actual against planned data changes, provide what-if scenarios for
the project manager.
Reporting and Communication - Creation of graphs and charts of collected and
analysed data that can be shared with stakeholders and team members.
Integration and Ease of Use - Some PMIS will access data from different projects
for multi-project analysis, integrating with other systems, such as payroll and
inventory. The easier a PMIS is to use, the less time and money required to train.
b) Explain four (4) purpose of project lesson learned after project completion. (10
marks)
The lessons learned process involves 5 steps with activities that will capture and use
lessons learned. The steps are:
DECEMBER 2019
QUESTION 5
a) Explain the purpose of the project control process. (5 marks)
Project controls are a sub-capacity and spotlight on only two boundaries which are
cost and timetable. Individuals the executives and quality control, for instance,
doesn't fall under the domain of undertaking controls. The principle target of
undertaking controls is to limit the fluctuation in expenses and calendar based on
what was initially arranged.
Controls goes about as a security outfit to extend the board. Some of the time
venture directors can concentrate exclusively on conveyance, which leaves less
space to inspect costs, deviation from the undertaking plan, and different factors
included. Undertaking controls present a fundamental rude awakening for venture
administrators, giving an additional information grounded perspective on how the
task assets and destinations are drifting after some time.
At its core, project controls are a piece of a checking capacity that investigates
situations and gives proposals. An undertaking controller covers cost and plan and
instructs the venture group with respect to likely issues. The genuine execution of
these proposals isn't finished by the controller, yet rather by the venture chiefs.
Despite the fact that controls are a sub-capacity of undertaking the board, venture
controllers cooperate with something beyond the task chiefs that they report to.
The foundation for a decent undertaking plan is to set up the methods, organization
arrangements, and documentation rules that will oversee your task. The arrangement
for plan the board plots assets accessible for the undertaking and the possibilities
that may emerge. It likewise records venture partners, separates people who must
affirm the calendar, and records other people who need to get a duplicate.
This record likewise builds up who has the position to make plan changes, the
procedure colleagues ought to follow so as to demand a change, and a task
correspondence intend to caution the group of changes made over the span of the
project. Despite the fact that controls is a sub-capacity of task the executives, venture
controllers associate with something other than the undertaking chiefs that they
report to.
This can be as simple as creating a list of tasks that must be completed in order to
deliver your project. In the case of complex projects, it might be useful to arrange
these assignments as at, a diagram imagining undertakings and their sub-errands
and to remain composed at work.
One test in this piece of the project planning process is realizing how to isolate
exercises. In group task the executives, undertakings requiring less than eight hours
could be assembled with others and assignments more than eighty hours are likely
excessively awkward and ought to be separated further. Exercises ought to likewise
be quantifiable, effectively assessed, and identified with both an undertaking
deliverable and a planned expense.
Determine dependencies
Once you have all the project activities listed, thoroughly consider every one
cautiously to recognize which undertakings depend on others to be finished. In case
you're fabricating a house, for instance, you can't put the rooftop on until the casing is
finished. It's imperative to effectively characterize every one of your conditions so you
can plan precisely and maintain a strategic distance from venture delays.
Sequence activity
Once the organizer established the dependencies in project among the activities,
they can sequence them. Now, they aren't relegating whenever to the exercises
regarding work hours or due dates. Rather, they're concentrating on the request
wherein all undertaking exercises ought to be done with the goal that the most
proficient stream is made.
QUESTION 6
CV = CEV - CAC
= 1,471k - 512k
= 959k
g) Calculate the forecasted cost at completion (FCAC) using two different formulae.
(2 marks)
FCAC = TBC / CPI
= 612k / 2.873
= 213.02k
h) Comment on the overall project cost performance based on all the above costings.
(2
marks)