Labour and Materials-Assignmnet (1) - Done
Labour and Materials-Assignmnet (1) - Done
Code(s) Title(s)
Numbe 01
Title Produce labour and material schedule
r
Student Instructions
To successfully complete this Assessment Task, you are required to complete the questions
below and submit the following on Canvas (this is an individual task).
You will be provided with a set of Plans, Contract, specifications, Protection of works
template, Building permit, and Builders variation template. Extension of time request
template, Call Forward sheet template and quote
(1) Prepare the construction schedule for the project (house plan provided by your teacher)( you
can use the Schedule completed in site supervision) which should include the following:
o Contractual requirements (contract provided by teacher)
o List of sub-contractors and suppliers required for this project (they should be have
already been added into you construction schedule)
o Conditions of Approval by local government, council and regulatory bodies (building
Permit)
o Human and physical resources required to complete each activity
o Apply contract rates to materials and labour requirements
o Timeframes required to complete each activity
(2) Using the template provided please complete a protection of works notice for the job (you
can use the protection of works notice completed in Site supervision)
(3) Colour selection of external materials explain the process you would go over with the client
Submission Requirements:
1) Construction Schedule and variation documents
2) Responses to questions
3) Call forward sheet
4) Protection of Works Notice
5) Builders Variation and Extension of Time Request
6) Answers to the below questions
Part C Knowledge Questions
Knowledge Questions
All responses provided for this activity must be demonstrated satisfactorily to achieve this task and have
been assessed as S – Satisfactory or US – Unsatisfactory. A satisfactory outcome must be achieved for all
items/criteria prior to a grading outcome being applied, if applicable.
Base stage
10
11
Evidence Checklist
All items/criteria observed for this activity must be demonstrated satisfactorily to achieve this task and have
been assessed as S – Satisfactory or US – Unsatisfactory. A satisfactory outcome must be achieved for all
items/criteria prior to a grading outcome being applied, if applicable.
Outcome
Submission contained the following aspects
S or US
A. Construction schedule
All contractual requirements noted
Regulations included
Instalment dates payments noted
Timeline nominated
Conditions of approval from local authorities / regulators
Colour selections notated
Suppliers and contractor’s details included
Contract rates for materials and labour applied
Appropriate resources planned and allocated
Overall
Satisfactor Unsatisfactor Grade (if
Assessment Task ☐ y ☐ y applicable)
Result
Assessor
Student
Section 2 – Feedback to Student
<Provide written feedback on the strengths and weaknesses of the student’s’ performance in the activity
National Unit Details
Code(s) Title(s)
Assessment Task
Numbe 02
Title Evaluate materials
r
Student Instructions
To successfully complete this Assessment Task, you are required to complete the questions
below and submit the following on Canvas (this is an individual task).
To complete this assessment activity, you must Identify 2 common building materials used
in low rise residential construction and evaluate them according to the following criteria.
safety
fire resistance
durability
serviceability
15. Where you will source this Getting quality timber as per Ceramic tiles which are
building material? Give supplier construction requirement can be generally used for the interiors
details.
very tedious and thus needs proper of the houses are easily
attention. A renounced supplier in available at any construction
this city has contacts and it material shop and thus it can
imports timber from mills so it be accessed locally.
will help in easy procurement of
timber.
16. What is the unit cost of the In building projects, the unit cost estimation
technique begins by separating a project into
The price varies as per the size
building product? or the quality of the material
different parts or elements for cost estimation
purposes. The price of each timber component or
element of the project will be evaluated and its cost
used. Generally, $ 0.33 to 1
estimate will be calculated. The complete cost of are sufficient for one square
each project element provides the complete project
building cost. For construction purposes, it can cost
unit of ceramic tile to be used
around 10 dollars per square foot. Or 100$ per in houses.
thousand-unit bf.
17. What are the transportation The fundamental variables influencing timber It is essential to avoid knocks and sharp
transport include: the size of the operation; the motions that could have a adverse impact
requirements for the building geographic places of the forest and the mill as well during loading and unloading. Because of its
material?
as the distance between them; the timber assortment size, care must be taken to guarantee that the
circumstances of transport for ceramic
intended for the mill; and the types of transportation
laminate tile are adequate to avoid possible
accessible and appropriate. Full trees with branches,
tension and potential breakage. It is therefore
limbered tree lengths, lengthy logs, brief woods,
recommended that data be provided on the
chips and hog fuel are the primary timber
assortments. In many instances, timber transport is pallet contents and that the appropriate
an incorporated component of the harvesting instructions be given.
procedure, particularly road transport. Any issue
with timber transport can thus prevent the entire
operation of harvesting. Time pressure can result in
demand for overtime job and a tendency to cut
corners that could compromise the safety of the
employees.
18. What naturally occurring and/or There are different kinds of defects Default detection inspection must be
performed at significant rates in the order of
manufactured defects should you as a building material in timber. two tiles per second. The inspection goal is to
look for when inspecting the
building materials on delivery?
These timber failures can be classify tiles based on two parameters, namely
defects and grading of colours. Depending on
caused by natural forces, fungi, the amount of defects and their size, the tiles
insects, and seasoning and are categorized into:-First Class (none or very
few acceptable defects)-Second Class (few
conversion. Defects in wood cause but still acceptable defects)-Waste
primarily due to fungi, seasoning (unacceptable defects) Some of the most
prevalent andanti-esthetic defects discovered
conversion, strain, cracks etc. on both plain and textured tiles can be
Timber is a natural product and classified as cracks, bumps, depressions,
pinholes, dust, falls etc. The inspection
there are some imperfections in method remains with color shade gradation
every natural product. This does after identification of defects to guarantee
not exclude timbers. Most timber consistency of the chromatic characteristics
of the completed item
failures cause weakness or other
kinds of problems. For a particular
sort of job, however, some flaws
may be useful, for instance,
twisted wood is great for creating
a bowl out of wood.
19 Give clear instructions on how Pesticides are used to treat timber to safeguard it Ceramic tiles are capable of carrying peak
against insects such as borers and termites, as well load. Extreme care should therefore be taken
the materials should be as fungi that cause rot and decay. These pesticides in managing large volumes of tiles. Please
handled correctly and safely on can damage individuals and the environment, follow the following rules to prevent
site. however, so it is essential that treated timber is used accidental breakage: 1. When loading or
and disposed of in a safe and legal manner. We need unloading large volumes of ceramic tiles, use
to guarantee that we have a safe working mechanical handling equipment (forklifts,
atmosphere, clear of obstacles and dangers, in terms wheelbarrows, hand trucks). 2. Do not load
of real working methods. Before we work, we
should take the time to perform a risk assessment on and lift more than 1.5 tonnes (1.5 pallet) of
each site. Completion will take a little time, but as ceramic tiles.
with most safety procedures, risk consciousness
20. What are the instructions for In a scheduled and orderly way, Ceramic tile is a very fragile
storing the materials? store materials that do not product and must be placed in
endanger the safety of employees. a region where other objects
For a short time, the wood can be will safely hit it. Tile cases can
stored outdoors in the packaging either be deposited flat or on
their sides. If stored flat, lift it
as long as it is fully protected
off the floor; if stored on its
against precipitation and
sides, lift it off the floor and
absorption of moisture. Use
completely waterproof tarpaulins position other items around it
to cover the wood. Make sure that that will stop it from falling
under the tarpaulin, humidity does over. Leaning tile instances
against a wall is also an
not increase from the floor and
that air can circulate around and efficient storage technique.
over the wood pack. No matter the weather or
Cover the wood to allow the air to temperature, ceramic tiles can
circulate and to prevent too high a be stored. Heat and cold, like
some products, such as slate
resulting temperature or
tile or crushed marble, do not
condensation. For as long as
influence ceramic tile, nor is it
necessary, leave the straps and
subject to the freeze / thaw
packaging on the wood.
cycle.
Ventilate between the wood and
the tarpaulin and make sure it ends
well above the floor. Place spacers
or similar around the wood pack
so that at any stage the tarpaulin
will not touch the wood.
21. Why is it important to maintain
records of testing and materials Efficient material management can lead to significant project cost
purchased for a job? savings. If materials are bought too soon, capital may be kept up
and interest charges on the surplus material inventory may be
incurred. Unless special care is taken, materials may deteriorate
during storage or be robbed. Delays and extras may be incurred if
there is no material needed for specific operations. Ensuring
timely material flow is a major material management problem.
Thus, keeping a record of all the tools, equipment, testing data,
availability of resources in each department etc. becomes very
useful in improving the organizational efficiency. The efficiency
of materials management should be evaluated in order to manage
and control materials efficiently.
Knowledge Questions
All responses provided for this activity must be demonstrated satisfactorily to achieve this task
and have been assessed as S – Satisfactory or US – Unsatisfactory. A satisfactory outcome must
be achieved for all items/criteria prior to a grading outcome being applied, if applicable.
Materials Testing is carried out for a variety of reasons and can provide a
wealth of information on the materials, prototypes or product samples
tested. The data gathered during testing and the final test results can be very
useful for engineers, designers, managers of production and others. Some
common reasons for why material testing is essential includes meeting
regulatory agency criteria, selecting suitable materials and treatments for an
application, Evaluating product design or enhancement specifications. Two
testing methods for ensuring the quality of materials includes physical testing
and laboratory testing.
Knowledge Questions
All responses provided for this activity must be demonstrated satisfactorily to achieve this task
and have been assessed as S – Satisfactory or US – Unsatisfactory. A satisfactory outcome must
be achieved for all items/criteria prior to a grading outcome being applied, if applicable.
Establish a definite plan at the very start of a new partnership for how to
interact with providers. This guarantees an efficient company relationship–
fewer shortages, more timely deliveries, fewer rush delivery expenses and, at
best, fewer headaches for you. There's no space for upgrades, that's not to
say, but make sure our updates are meaningful.
Overall
Satisfactor Unsatisfactor Grade (if
Assessment Task ☐ y ☐ y applicable)
Result
Assessor
Student