Work Method Statement For Structure Erection
Work Method Statement For Structure Erection
CABOT INDONESIA
PT. TRIPATRA ENGINEERS AND CONSTRUCTORS
PT. HASTAKARYA TUNGGAL MANDIRI
FOR INFORMATION
2
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
Contents
1. GENERAL ..................................................................................................... 4
1.1 PURPOSE ..................................................................................................... 4
1.2 SCOPE .......................................................................................................... 4
1.3 DEFINITION .................................................................................................. 4
1.4 REFERENCE DOCUMENT ........................................................................... 4
2. INTRODUCTION.......................................................................................5
2.1 LOCATION .................................................................................................... 5
2.2 MAIN MATERIAL .......................................................................................... 5
2.3 EQUIPMENT AND TOOLS............................................................................ 5
3. BASIC STRUCTURE ................................................................................6
3.1 MANNING PLAN ........................................................................................... 6
3.2 WORK SEQUENCE / PROCEDURE ............................................................. 7
4. SAFETY PRECAUTION ................................................................................ 9
4.1 MAN .............................................................................................................. 9
4.2 METHOD ..................................................................................................... 10
4.3 ENVIRONMENT .......................................................................................... 10
5. EMERGENCY RESPONSE ......................................................................... 11
3
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
1. GENERAL
1.1 PURPOSE
This method statement shows and explains the about Erection Structure activity
and to comply with the specification and scope as well to archive the requirement of
the project.
1.2 SCOPE
b. Detail of drawing shall be clear and already IFC. Preparation material and
tools inspection shall be carry out in accordance with specification.
1.3 DEFINITION
Abbreviation Description
HKTM PT. Hastakarya Tunggal Mandiri
AZN All Zone
DIS Discipline
ED Engineering Deliverable
ELE Electrical
IFC For Construction
MST Method Statement
REV Revision
SEQ Sequence
VND Vendor
4
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
2. INTRODUCTION
2.1 LOCATION
Location of
• Beam
• Rockwool
• Nitrogen
• Paint
• Generator Set
• Hand Tools
• Brush
• Bolt/Nut
• Level
5
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
3. BASIC STRUCTURE
The person of responsible for this work refer to attachment section 8.1
3.1.2 Responsibility
a. Site Manager
b. Site Engineer
c. Quality Controller
Prepare Inspection and Test Plan (ITP) involves to all activities to make
surethat all result complies with standard requirement.
d. Construction Supervisor
e. Scaffolding Supervisor
f. Safety Supervisor
g. Safety Coordinator
Establish JOHAN with engineer for utilize work method. Ensure all
activities and coordinate safety supervisors as far as safety working.
Prepare all safetysign and housekeeping.
h. Material Control
Control the record of project material both in and out material to client.
Prepare the material require to install.
3.2.1 General
7. Ensure that work permits are obtained prior to proceeding with the
work in the area and those are available to the working crew.
7
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
8
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
2.
3. Rafters lifting with 2 cranes on the left and right side, then torque of bolt
and nut after being installed to the column using a man lift every of
connectio
9
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
4. Installation rafter for the next column is the same way as before,
until thethird column. Then, purlin installed every connection of rafter
5. Brasing installation
• Installed between rafters as per drawing approved
4. SAFETY PRECAUTION
4.1 MAN
a. Make sure the mandatory PPE is use correctly
• Safety Helmet complete with Chin Strap
• Arching Suit
• Electrical/Rubber Gloves
10
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
d. Make sure all worker fully understood for their task risk and consequence.
e. All worker for working at height shall be do health check at clinic.
f. Remind worker to take ergonomic position while using hand tools
4.2 METHOD
• Worker must be follow “Working at High” training.
• Work permit already approved from Client.
• Ensure the position of the body is correct.
• Provide safety sign and barricade at work area.
• If working area cannot protect by scaffolding platform, Contractor shall
provide lifeline
4.3 ENVIRONMENT
• All the waste generated from this work will be immediately throw out from site.
11
GENERAL METHOD STATEMENT
FOR ERECTION STRUCTURE
5. EMERGENCY RESPONSE
Immediately
Item Description Reporting What to do
Action
Apply
In case of Report incident to HSE Supervisor Immediately
1
minor cuts and/or Site Manager cure using First
Aid Kit
Flush with
In case of
Immediately go plenty or water
3 chemical Report incident to HSE Supervisor
to eyes wash and bring victim
expose
to clinic
Immediately
stop work. Do
not panic,
In case of
immediately get Assemble at
plant
Report incident to HSE Supervisor out the Red Green Area
4 shutdown
and Site Manager Area and Assembly /
due to gas
assemble at Muster Point
leak
Green Area
Assembly /
Muster Point
12