Feasibility Study - Rewinding of 4MVA Transformer - For Signature
Feasibility Study - Rewinding of 4MVA Transformer - For Signature
Meycauayan Bulacan
FEASIBILITY STUDY
FOR
REWINDING OF 4MVA TRANSFORMER
Civil & Struc : R. B.P. 11-04-2021 Date of Prep.: October 28, 2021
It is hereby certified that the FS Report has been thoroughly and carefully read and recommended to the
Budget Committee for the acceptance of Final Project for the year 2022
Michael T. Marcial
Plant Manager
Jeffry T. Leodones
Department Head
Ramil C. Sulat
Requestor
SteelAsia Head Office: 25 th floor Ore Central Building, 9 th Avenue corner 31st street, Bonifacio Global City, Taguig, Philippines
Tel: (02) 8856-6888 | Fax: (02) 8856-5555
Meycauayan Works: #090 Ciudad Industria, Bahay-Pare Meycauayan City, Bulacan 3020
Tel: (02) 8856-6888 | Fax: (02) 8856-6888
Table of Contents
I. General Information………………………………………………………….1
A. Background of the Study……………………………………………………...1
B. Objectives of the Study...……………………………………………………...1
C. Significance of the Study……………………………………………….……..1
D. Scope & Limitation………………………………………….………………...1
II. Technical Analysis………………….………………………………………...1
A. Specification of the existing 4MVA Transformer for Rewinding……………1
B. Transformer Standard Test Results…………………………………………..3
C. Condition of Existing Operational Transformers……………………........….4
D. Cost Comparison……………………………………………………....….….4
III. Conclusions and Recommendations …………………………………….........5
IV. References ………………………………………………………………........5
Meycauayan Works has an existing transformer with a capacity of 4MVA that is not
currently operational which they are planning to utilize as a spare. This transformer has
been operational from 1995 to 2012 (17 years) and it was replaced last 2012 due to failed
Dissolved Gas Analysis (DGA) and low resistance as per test result. During that time, the
contractor opened the transformer and found out that the insulation had deteriorated. The
recommendation is to subject the transformer for rewinding.
The table below shows the specification of the transformer for rewinding.
Brand EFACEC
Capacity 4000kVA
Primary Voltage 36kV
Secondary Voltage 480V
Temperature Class Insulation A
Cooling Type ONAN
Impedance 5.6%
1
Total Weight 7,400kg
Total Volume of Oil 4,540L
Dimension (L x W x H) 2.5m x 3.5m x 2.8m
This transformer has been operational for 17 years (1995 to 2012). There were no problems
encountered during that time aside from the overloading that happened in 2009 when the
loads of Transformer 3 were transferred to it. During overloading conditions, excess heat
will cause the insulation system to break down, resulting in decreased life expectancy of
the transformer. More information about the average life of a transformer to be discussed
in Section II.C.
It was only in 2012 when it was replaced due to failed Dissolved Gas Analysis Test Result
that falls under Condition 4. Under this condition, continued operation could result in
failure and faults are probably present inside the transformer.
2
Condition 1, it is stated that the transformer is operating satisfactorily but
individual gases exceeding specified level should prompt additional
investigation.
The total CO2 is developed from normal aging, thermal fault involving cellulose
and accumulation from oxidation. A fault in paper (cellulose) is generally
considered as more serious than a fault in oil because paper is placed in HV area
(windings, barriers). A popular ratio to detect fault in a paper is CO2/CO ratio. If
the CO2/CO ratio is <3, this is a strong indicator of a fault in a paper, either a
hotspot or electrical arcing. If the CO2/CO ratio is >11, this indicates cellulose
aging from thermal heating. However, this is only valid when the individual gases
are above 5000/500ppm.
In this case, the CO2/CO is lower than 5000/500ppm. This means that there is no
indication of fault in paper.
3
C. Condition of Existing Operational Transformers
The reason for Meycauayan Works’ request for a spare transformer is due to the
existing condition of the other operational transformers. If ever a problem occurs in one of
the transformers, they would have a back up ready for installation that will avoid long down
time. The usual delivery lead time for a transformer is 6 months.
The table below shows the summary of the ages of the five operational distribution
transformers. Same with the transformer for rewinding, four (4) out of five (5) are already
24 years old. They have been operational since the plant was started in 1995.
The average life expectancy of the transformers operating under ANSI/IEEE (ANSI
C57.96) basic loading condition is between 20-30 years. The ANSI / IEEE basic loading
conditions for Transformer are:
1. The transformer is continuously loaded at rated kVA (kilo Volt Ampere) and rated
voltages (transformer must be operated at the rated voltage and kVA)
2. The average temperature of the ambient air during any 24-hour period is equal to
30°C (86 °F) and at no time exceeds 40°C (104 °F).
3. The height where the transformer is installed is not above 3300 feet or 1000 meters.
This means that the 4 transformers are also near the life expectancy.
The annual test results of these operational transformers for this year showed the
following results:
• For Transformer 1, leak at the top cover was observed. This can be corrected by
retightening.
• All other transformers are within the allowable limits. However, Transformers 1,
2, and 3 already underwent Oil filtering aside from the annual preventive
maintenance to address the failed DGA Test Result on the previous year’s
preventive maintenance tests.
D. Cost Comparison
Part of this study is to also consider the most cost-effective solution to provide a back up
or spare transformer at the plant. The team asked for assistance from the Costing
Department to consider the two options:
Option 1 is to continue the proposed rewinding of the transformer plus the change
oil and replacement of thermal cellulose
Option 2 is to check the cost of a brand new transformer.
4
The table below shows the summary of cost comparison for the two options:
Option 1 Option 2
Reconditioning of the transformer which
Supply of brand new 4MVA
includes: Transformer including hauling,
-Rewinding positioning, testing & commissioning at
-Checking or Replacement of thermal site
Paper insulation
-Changing of oil
Total Cost: P4,450,000.00 Total Cost: P5,500,000.00
The cost difference of the reconditioning should be within the allowable limit. If it is less
than 50%, it is best to purchase new transformer instead of reconditioning. Based on the
table above, the cost difference between supply of brand new transformer is only 21.11%.
This means that the best option for having a spare transformer is by purchasing a brand
new one.
IV. References
https://www.cigre.cl/wp-content/uploads/2017/03/presentacion_12ago.pdf
https://iiee.org.ph:89/uploads/files/917.pdf
5
https://boilerproperty.com/corrosive-sulfur-in-transformer-oil/
http://focuslab.co.th/pdf/coppercorrosion.pdf
https://www.cigre.cl/wp-content/uploads/2017/03/presentacion_12ago.pdf
https://www.electricaltechnology.org/2019/12/average-life-expectancy-
transformer.html