PMP Mock Exam 200 Q A
PMP Mock Exam 200 Q A
A. Hierarchal
B. Authoritarian
C. Charismatic
D. Associative
(2) You are in charge of developing a new product for an organization. Your quality metrics are based on the
80th percentile of each of the last three products developed. This is an example of:
A. Statistical sampling
B. Metrics
C. Benchmarking
D. Operational definitions
(4) During the schedule development process the Project Manager may have to go through several iterations of
the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be
used during this process:
(5) Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the
issue in the long term?
A. Problem solving
B. Withdrawal
C. Forcing
D. Smoothing
(6) The receiver filters messages based on all but the following:
A. Culture
B. Semantics
C. Language
D. Distance
E. Knowledge
(7) How much time does the typical project manager spend communicating both formally and informally?
A. 40-60%
B. 50-70%
C. 60-80%
D. 75-90%
(8) Group brainstorming encourages all of the following except:
A. Team building
B. Analysis of alternatives
C. Convergent thinking
D. Uninhibited verbalization
A. Progress report
B. Project directive
C. Project manager
D. Customer
A. Assuring that the pieces of a project come together at the right time
B. Planning for contingencies that may occur throughout the life cycle of the project
C. The pieces of the project function as an integration unit
D. a and c
A. Functional
B. Cross-functional
C. Matrix
D. Balanced
(13) Which of the following could be an appropriate WBS code for a work package at the fourth level in a
WBS where the top level code is 1.0?
A. 1.4
B. 1.1.1.1
C. 1.2.3.4
D. a and c
E. b and c
(14) Which of the following Project Scope Management processes involves subdividing the major project
deliverables into smaller, more manageable components?
A. Scope Planning
B. Initiation
C. Scope Change Control
D. Scope Definition
E. Create WBS
(15) The review of key deliverables and project performance at the conclusion of a project phase is called:
A. phase exit
B. kill point
C. stage gate
D. a and c
E. all of the above
A. The work that must be done in order to deliver a product with the specified features and functions.
B. The features and functions that are to be included in a product or service.
C. A narrative description of work to be performed under contract.
D. a and b
E. all of the above
(17)The unique identifiers assigned to each item of a WBS are often known collectively as:
A. A formal, approved document used to guide both project execution and project control.
B. A document issued by senior management that provides the project manager with the authority to apply
organizational resources to project activities.
C. A narrative description of products or services to be supplied.
D. A document describing the organizational breakdown structure of the company.
(22) Which of the following is NOT an example of a type of schedule report?
A. Gantt chart
B. Milestone chart
C. Fishbone diagram
D. Network diagram
(23) The most important criteria in selecting project selection method is:
A. Ease of use
B. Cost of using it
C. Available expertise
D. Capability
E. Realism
A. Setting up a team of people with the skills set that are required
B. Sending you project team to a PMI seminar
C. Motivating your project team members
D. Enhancing the ability of stakeholders to contribute as individuals
E. Enhancing the ability of the team to function as a team
A. Planning, organizing, staffing, executing, and controlling the operations of an ongoing enterprise.
B. Business policy, financial management, business economics, contract administration, and legal services
necessary for operating an enterprise.
C. Business strategy, planning and controlling, organizational behavior, procurement, and personnel
administration required for managing the ongoing aspect of a business venture.
D. Organizational development, staffing, marketing and sales, procurement, and contract administration as
part of an ongoing organization.
A. Stakeholder requirements
B. Project performance
C. Schedule progress
D. Cost and schedule
A. A fixed price contract contains the most risk for the buyer.
B. Cost reimbursable contracts offer sellers the highest profit potential.
C. Lump sum contracts offer sellers the greatest profit potential.
D. Unit price contracts are illegal in many jurisdictions.
(34) Herzberg identified factors, which, if present, will lead to increased motivation. A typical factor would be:
A. Good supervision
B. Job security
C. Regular promotions
D. Good salary
E. A dental plan
(35) Your customer ask for a small change in the project, which was not budgeted in the project. It is a small
effort as compared to the total project and you need the goodwill for a multimillion dollar on the pipeline. You
will
A. Replacement of the project manager or key project team members; changes in priorities by senior
management; and contractual difficulties.
B. Changes in the relative importance of time, resources, or cost ; new knowledge about the deliverable;
and technological uncertainty
C. Errors in the initial assessment of how to achieve the goal of the project; new information about the
project deliverable; and a new mandate
D. Unavailability of resources promised by the functional managers; cost overruns; and changes in
customer requirements
(38) The purpose of the review of deliverables and project performance at the conclusion of a project phase is
to:
A. Determine how many resources are required to complete the project according to the project baseline
B. Adjust the schedule and cost baselines based on past performance
C. Obtain customer acceptance of project deliverables
D. Determine whether the project should continue to the next phase
(39) Your project is in the final test stage, the user acceptance test. It meets all the product specs and is under
planned costs. In term of schedule, this project is ahead. Your customer meet you and requested that he will not
accept the product unless you make several changes. What you should do is:
A. Get the list of the changes and estimate all of them. If the total cost is still within the baseline, you just
do it
B. Estimate the costs and send this to your customer requesting contract modification
C. Ask the customer to file a Change request
D. Sit with the customer to review the product specs and tell him/her that you have completed the project.
A. Decision-making
B. Cost Control
C. Overhead rate estimating
D. Team discussions
(41) Which of the following methods is least likely to be used for explaining project planning guidelines to the
team?
A. Stakeholder's pressure
B. Business needs
C. Technological obsolescence
D. All of the above
(43) The party that needs the change resulting from the project, and who will be its custodian on completion is
the:Owner
A. Sponsor
B. Customer
C. Client
(44) A document or tool which describes when and how human resources will be brought onto and taken off the
project team is called a:
A. Functional
B. Projectized
C. Matrix
D. Project expediter
E. Project coordinator
(46) A tool which links the project roles and responsibilities to the project scope definition is called:
(47) Which of the following are outputs from the Communications Planning process?
A. Project records
B. Communications management plan
C. Performance reports
D. Formal acceptance
E. b and c
(48) The receiver filters messages based on all but the following:
A. Culture
B. Semantics
C. Language
D. Distance
E. Knowledge
(49) The sending or conveying of information from one place to another is the process of:
A. Networking
B. Transmitting
C. Encrypting
D. Promoting
A. Memos
B. Verbal circulation of a rumor
C. Videos
D. Body language
E. Inputting data into a spreadsheet
(54) In negotiating with functional department managers, project managers often find themselves using what
two-party conflict management approach?
A. Win-Lose
B. Win-Win
C. Lose-Lose
D. None of the above
(55) A leadership style in which the project manager shares problems with team members and formulates
solutions as a group is called:
A. Autocratic
B. Consultation in a group
C. Consensus
D. One-to-one consultation
(56) A type of organization in which the project manager has little formal authority and basically acts as a staff
assistant to an executive who is ultimately responsible for the project is called:
A. Functional
B. Weak matrix
C. Project coordinator
D. Project expediter
(58) In which of the following organizations is the project manager role likely to be part-time?
A. Weak matrix
B. Functional
C. Balanced matrix
D. a and b
E. All of the above
(59) Project Risk Management includes all of the following processes except:
A. Risk Quantification
B. Risk Identification
C. Risk Analysis
D. Risk Response Development
E. Risk Response Control
(60) Using the PMBOK definition of contingency reserve, which of the following statements about contingency
reserves is false?
A. A contingency reserve is a separately planned quantity used to allow for future situations which may be
planned for only in part.
B. Contingency reserves may be set aside for known unknowns.
C. Contingency reserves may be set aside for unknown unknowns.
D. Contingency reserves are normally included in the project's cost and schedule baselines.
A. The risk can be deflected or transferred to another party through a contract or insurance policy.
B. Pure risks involve the chance of both a profit and a loss.
C. No opportunities are associated with pure risk, only losses.
D. a and c
E. a and b
A. A planned response that defines the steps to be taken if an identified risk event should occur.
B. A workaround
C. A reserve used to allow for future situations which may be planned for only in part.
D. a and c
E. a and b
(63) Deflection or transfer of a risk to another party is part of which of the following risk response categories?
A. Mitigation
B. Acceptance
C. Avoidance
D. Analysis
A. Unknown unknowns
B. Known unknowns
C. business risks
D. pure risks
(65) Which of the following is considered during the Procurement Planning Process?
A. Whether to procure
B. How to procure and how much to procure
C. What and when to procure
D. b and c
E. all of the above
(68) Which of the following is a method for quantifying qualitative data in order to minimize the effect of
personal prejudice on source selection?
A. Weighting system
B. Screening system
C. Selecting system
D. none of the above
E. all of the above
A. Cost-plus-fixed-fee contract
B. Cost plus-incentive-fee contract
C. Fixed-price-incentive contract
D. Firm-fixed-price contract
(71) In which of the following contract types is the seller's profit limited?
A. Cost-plus-percentage-cost contract
B. Cost-plus-fixed-fee contract
C. Fixed-price-plus-incentive
D. b and c
E. none of the above
(72) A cost-plus-percentage-cost (CPPC. contract has an estimated cost of $120,000 with an agreed profit of
10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?
A. $143,000
B. $142,000
C. $140,000
D. $132,000
(73) A fixed-price-plus-incentive-fee (FPI. contract has a target cost of $130,000, a target profit of $15,000, a
target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project
was $150,000. How much profit does the seller make?
A. $10,000
B. $15,000
C. $0
D. $5,000
A. The subcontractor possesses special technical and engineering skills that the contractor does not have.
B. The work to be subcontracted represents almost all of the overall work effort.
C. The subcontractor can perform the work at a lower cost than the contractor.
D. all the above
E. a and c
(75) Which type of bilateral contract is used for high dollar, standard items?
A. Purchase order
B. Request for proposal (RFP.
C. Invitation for bid (IFB.
D. Request for quotation (RFQ.
E. all of them are appropriate
(76) In which stage of the negotiation meeting are points of concession identified?
A. Probing
B. Closure
C. Agreement
D. Scratch bargaining
(77) Which of the following is NOT a method of government procurement?
A. Assistance
B. Sealed Bidding
C. Competitive proposals
D. Acquisition
E. Small purchases
F. No answer provided
(78) The "rule of seven" as applied to process control charts means that :
A. If there are seven points on one side of mean, then an assignable cause must be found.
B. Seven consecutive points are ascending, descending, or the same.
C. At least seven inspectors should be in place for every thousand employees.
D. A process is not out of control even though seven measurements fall outside the lower and upper control
limits.
(79) There is project with CPI of 0.81 and TCPI=1.00001 this project is:
(80) A collection of generally sequential project phases whose name and number are determined by the control
needs of the organization or organizations involved in the project, is called:
(82) Who is responsible for risk identification, risk quantification, risk response development, risk Monitor and
Control?
A. True
B. False
C. Both True and False
D. Neither true nor false
(88) 7. ________ means that every project has a definite beginning and a definite end.
A. Overall
B. Project Chart
C. Temporary
D. Duration
(89) The smallest unit of time used in scheduling the project is known as:
A. Calendar Unit
B. Scope unit
C. Time Measurement
D. All of the Above
A. A reimbursement of allowable cost of services performed plus an agreed upon percentage of the
estimated cost as profit.
B. A reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contract
progresses.
C. The supplier with a fixed price for a delivered performance plus a predetermined fee for superior
performance.
D. None of the above.
(93) Project success depends on a no. of interrelated factors, including time, cost and scope control. The success
of any project depends primarily on:
A. Customer acceptance.
B. Customer satisfaction.
C. Customer compromise in defining its needs.
D. Exceeding customer requirements through gold plating.
(94) Which of the following is the most efficient means of product quality inspection:
A. Acceptance sampling.
B. 100% inspection.
C. Variable lot inspection.
D. A and C.
(96) Pareto Analysis, cause and effect diagrams and flow charts are used in quality.
A. Control.
B. Assurances.
C. Planning.
D. Verification.
A. Conflict of interest.
B. Differentiation in organization
C. Resolved prior conflicts.
D. Both A and B.
E. All of the above.
(99) The contemporary view of conflict is that:
A. Conflict is bad.
B. Conflict is caused by trouble makers.
C. Conflict should be avoided.
D. Conflict is often beneficial.
E. A, B and C.
(101) A project manager has increased project costs by US $75,000, but completed the project six weeks earlier
than planned. What tool is best described here?
A. Resource leveling
B. Duration compression
C. Crashing
D. Fast tracking
A. Lag is the maximum amount of time a task can be delayed without delaying the early start of its
successor.
B. Lag may be determined by making a forward pass.
C. Lag is waiting time.
D. Lag is the maximum amount of time a task can be delayed without delaying the project.
(104) The behavioral responsibilities of a project manager may also include dealing with:
A. Regulatory Personnel
B. The legal environment
C. Environmental Issues
D. All of the above
A. Organize and summarize the information so that all stakeholders were informed
B. Inform upper management of the project problems
C. Inform the client about the changes that have completed
D. Provide information to management and client
(106) Most project management leadership theories focus on all of the following except :
(107) Preliminary Cost estimates are developed during the______ phase of the project:
A. Conceptual
B. Planning
C. Implementation
D. Execution
(108) Historical records during close-out are useful to __________ and ____________ for future projects:
(109) Your client informs that his company has a problem with the current design specs of your product and
how it will interface with the existing systems. If this occurs, it could be a major problem for your project. The
client is coming to your office in one week to discuss the problem and to see what your team can do to
overcome this setback. All previous meetings were informal with this client, but now he wants a formal
meeting. What should you do to prepare for this meeting
A. Update the schedules and assume an active role since the client has not given you the specifics of the
potential problem
B. Make sure that the team has increased productivity so the client can see how efficient your team is
performing
C. Assemble the team and ask them to prepare an agenda for topics to discuss
D. Make sure that each team member has his assignment in preparation for any handouts and needed plans
(110) The definitive terms of a contract are written during which of the following contract phases?
A. Contract phase
B. Post award phase
C. Award phase
D. Pre award phase
E. Requirement phase
A. Gantt Chart
B. WBS
C. Project Charter
D. Scope statement
(112) Some organizations are now using 6 Sigma for quality control compared to the usual:
A. 2 sigma
B. 3 sigma
C. 4 sigma
D. 5 sigma
(113) Reducing the impact of a risk event by reducing the possibility of its occurrence is:
A. Risk avoidance
B. Risk acceptance
C. Risk mitigation
D. Contingency planning
(114) In which of the following project management process groups are the most time and money typically
spent?
A. Initiating
B. Planning
C. Executing
D. Controlling
(115) ______ recognizes that a project or phase should begin and commits the organization to do so:
A. Initiation Process
B. Solicitation Process
C. Scoping Process
D. Planning process
(116) A supplier has withdrawn from your project. A new supplier has been retained. His labor forces are due
to arrive at the job site tomorrow. You should :
A. Meet with the supplier and his forces and establish yourself as the authority in charge.
B. Bring your team in for introductions and establish a communications exchange
C. Bring out the communication management plan
D. Bring out the project plan.
(117) A new project manager is about to begin creating the project's scope of work. One stakeholder wants to
add many items to the scope of work. Another stakeholder only wants to describe the functional requirements.
The project is important for the project manager's company but a seller will do the work. Which of the
following would you advise the project manager to do?
A. The scope of work should be general to allow the seller to make its own decisions.
B. The scope of work should be general to allow clarification later.
C. The scope of work should be detailed to allow clarifications later.
D. The scope of work should be as detailed as necessary for the type of project.
(118) After the kickoff meeting, two team members engage in a casual conversation about the project
objectives and deliverables. It is clear they heard different messages during the meeting. One member is so
adamant that the other member gives up arguing the point. After talking to the project manager, the second
member confirms that the first member is mistaken. At this point, what is the BEST course of action?
A. The second team member should send the other team member an e-mail describing what he discovered.
B. At the next project meeting, the team member should ask the mistaken team member to describe his
interpretation so the project manager can get everyone on the same page.
C. The project manager should send out an e-mail to the team restating the project objectives and
deliverables.
D. At the next project meeting, the project manager should spend time reviewing a documented scope
statement with the goal of identifying this and other false assumptions.
(119) During project execution, a project team delivers a project deliverable to the customer. However, the
customer neither acknowledges the deliverable nor says if it is acceptable, although an approval is required.
What is the BEST thing to do?
A.Continue with the project
B.Document the situation
C.Contact management for help
D.Call a meeting of the team
(120) You are managing a six months project and have held bi-weekly meetings with your project sponsors.
After five-and-a-half months of work, the project is on schedule and budget, but the sponsors are not satisfied
with the deliverables. This situation will delay the project completion by one month. The MOST important
process that could have prevented this situation is:
(121) When you are closing out a project, what must you do?
(122) Financial controls that need to be considered for project plan development do not include:
A. Time reporting
B. Standard contract provisions
C. Process audits
D. Accounting codes
(123) A project manager has been working on a project for six months with the same team yet the team still
shows a lack of support for the project. The best thing for the project manager to do would be to?
A. Re-evaluate the effectiveness of the reward system the project manager has put in place
B. talk to each team member's boss
C. Re-plan the project
D. Tell the team he needs its support
(124) A project has several teams. Team C has repeatedly missed several deadlines in the past causing Team D
to have to crash the critical path several times. As the project leader for Team D, what should you do?
(125) The current update to the schedule performance report shows no schedule variance. Based upon the
reporting, you have told the client that the project is on time. However, your team members know that a major
milestone has just been missed and that the project will not meet its startup date. This is an indication of poor?
(127) An advisor to a new project manager tells the project manager to create lessons learned at the end of a
project. A lessons learned includes?
(128) A project management professional can compare earned value performance data to all of the following
project management tools EXCEPT:
(129) The project is completed and the final deliverable given to the customer but the customer refuses to take
any action to give final acceptance on the project. The project manager should?
(130) Your new product development project has resulted in a highly successful new product. The property,
equipment, materials, and personnel of your project are now being integrated into the functional organization.
Your project is being terminated by:
A. Extinction
B. Addition
C. Integration
D. Starvation
A. has finish-to-start task relationships and provides the flexibility of lead and lag time to the activities;
B. has the activity on the node;
A. Project engineer
B. Purchasing agent
C. Quality manager
D. Team members
(135) You are a project manager for a major information systems project. Someone from the quality department
comes to see you about beginning a quality audit of your project. The team, already under pressure to complete
the project as soon as possible, takes objection to the audit. You should explain to the team that the purpose of a
quality audit is?
(136) You manage a project whose team members have diverse skills and expertise. You want to encourage
your staff to pool its knowledge on project issues to make the best decisions possible. The most appropriate
management style to use is:
A. Laissez-faire
B. Democratic
C. Autocratic
D. Directive
(137) The types of power that have substantial influence on both subordinates and upper management are:
(138) Your preferred resource is not available at the time needed. What is the best thing to do?
(139) An important piece of hardware will be late. What is the first thing to do?
(141) A functional manager wants to make a change to the time associated with a task, but there is not enough
reserve to accommodate the change. Who should authorize the change?
A. Senior management
B. The functional manager
C. The project manager
D. The team member performing the work
(142) During the course of a project you have motivated team members, managed conflict, performed personnel
administrative functions and negotiated for more resources. These are examples of:
A. General Management
B. Project Human Resource Management
C. Project Execution
D. A Projectized organization
(143) You have been promoted to Manager, Continuous Process Improvement. Your new position:
(145) The state of being totally answerable for the satisfactory completion of a specific assignment is called:
A. Authority
B. Accountability
C. Responsibility
D. Fiduciary
(146) You are responsible for the communication controls for the Genesis series of satellites. Your current
assignment is:
A. Project management
B. Functional management
C. Facility management
D. Program management
(147) Work packages are used to :
A. The value of the equipment that has been installed as of the current date
B. The sum of the labor costs that have been incurred on the project date
C. A method of measuring project performance
D. A method of measuring the amount of money that has been spent to date
A. identifying which quality standards are relevant to the project and determining how to satisfy them
B. monitoring specific project results to determine if they comply with relevant quality standards and
identifying ways to eliminate causes of unsatisfactory performance
C. evaluating overall project performance on a regular basis to provide confidence that the project will
satisfy the relevant quality standards
D. taking action to increase the effectiveness and efficiency of the project so as to provide added benefits to
both the performing organization and the project customer
E. assuming the production of goods that meet the highest standards of luxury
A. Quality is free
B. Doing it right the first time
C. Zero defects
D. Process improvement
E. B and C
(154) Quality assurance is:
(156) When appointed, a project manager has the inherent forms of legitimate power conveyed to him. The
three forms of legitimate power are:
(157) The five types of conflict resolution are listed below and represent, in general order of importance, the
methods a project manager should use to manage conflict. The one used most often by project managers to
resolve conflict is:
A. confrontation
B. compromise
C. smoothing
D. forcing
E. withdrawal
(158) The process of getting a group of diverse individuals to work effectively together as a team is the
definition of
A. leadership
B. project management
C. the project manager's responsibilities
D. implementation
E. team building
(159) Which contract type should be used by the owner on a high risk project?
A. Agreement
B. Purchase Order
C. Proposal
D. Memorandum of Understanding
(164) Which of the following situations describes a violation of the PMP. Professional Code of Conduct?
A. Accepting a gift that is within the customary guidelines of the country or province you are currently
working in.
B. Use of confidential information to advance your position or influence a critical decision.
C. Complying with laws and regulations of the state or province in which project management services are
provided
D. Disclosing information to a customer about a situation that may have an appearance of impropriety.
(165) You are working in a country where it is customary to exchange gifts between contractor and customer.
Your company code of conduct clearly states that you cannot accept gifts from any client. Failure to accept the
gift from this client may result in termination of the contract. The action to take in this case would be:
A. Provide the customer with a copy of your company code of conduct and refuse the gifts.
B. Exchange gifts with the customer and keep the exchange confidential
C. Contact your project sponsor and /or your legal office for assistance.
D. Ask the project sponsor or project executive to exchange gifts.
A. As a public official you make a decision about a contract award that will benefit you personally
B. You and a functional manager disagree with a task cost estimate
C. Your sponsor decides to cancel your project because it no longer supports the company strategy
D. Your personality conflicts with that of a key member of your project team.
(167) Your project is running out of cash and significant work remains. You are directed by senior management
to instruct your people to use another project's charge numbers while working on your project. You should:
A. Follow instructions
B. Inform the corporate auditors
C. Understand the background of management's instructions before taking any action
D. Try to close down the project
(168) Project Managers can contribute to their organization's knowledge base and to the profession of project
management most effectively by:
(169) For a festival, you give your government client a leather brief case. You are in violation of the
responsibility to:
(170) You have just changed jobs and discovered that your new employer routinely violates OSHA/EPA and
affirmative action requirements on projects. You should:
(171) During your assignment as project manager you add a new member to your project team. This new team
member was recently hired from a competitor and offers to share a substantial amount of proprietary
information from his previous company. This information could put you and your team in a very strong position
for future business. You are aware of a non-compete clause in the new hire's condition of employment. You
should:
A. Accept the information and agree to keep it confidential between you and the new hire.
B. Review the condition of employment with the new hire and advise her to reconsider the offer.
C. Review the information and only accept only what may have a direct impact on the project's financial
status.
D. Ignore the offer to share and move forward with the project
(172) Before reporting a perceived violation of an established rule or policy the project manager should:
A. Work Item
B. Work Package
C. Workaround
D. Work breakdown structure
(176) The terms "Facilitating Processes" and "Core Processes" are no longer used in new PMBOK. These terms
have been eliminated to ensure that all project management processes in the Project Management Process
Groups have the same level of importance.
A. True
B. False
(177) In a group of 4 members, 1 member has been added. How many communication channels are there now :
A. 5
B. 3
C. 10
D. 20
A. Contract
B. Project Statement of Work
C. Enterprise Environmental Factors
D. Organizational Process Assets
E. Project Management Information System
A. WBS Dictionary
B. Organizational Process Assets
C. Project Scope Statement
D. Work Breakdown Structure
E. Schedule Network Templates
A. Analogous Estimating
B. Work Breakdown Structure Templates
C. Critical Path Method
D. Schedule Network Templates
(184) Crashing, and Fast tracking are techniques used in the following process:
A. Schedule Development
B. Activity Definition
C. Create WBS
D. Resource Allocation
A. Analogous Estimating
B. Bottom-up Estimating
C. Parametric Estimating
D. Vendor Bid Analysis
E. Resource Leveling
A. Cost-Benefit Analysis
B. Benchmarking
C. Design of Experiments
D. Cost of Quality (COQ)
E. Process Analysis
A. Placing many or all of the most active project team members in the same physical location to enhance
their ability to perform as a team.
B. Placing many or all of the most active project team members in the same physical location to reduce the
cost of the project
C. Performing a complete project at a single location
D. Performing a project at various locations.
A. Risk Audits
B. Avoidance
C. Transfer
D. Mitigate
E. Exploit
A. Select Sellers
B. Request Seller Responses
C. Contract Administration
D. Contract Closure
(194) Which of the following definition is not correct:
A. Human Resource Planning - Identifying and documenting project roles, responsibilities, and reporting
relationships, as well as creating the staffing management plan.
B. Acquire Project Team - Obtaining the human resources needed to complete the project
C. Develop Project Team - Improving the competencies and interaction of team members to enhance
project performance
D. Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and
coordinating changes to enhance project performance.
E. Team Building - Forming a team from scratch for a new project.
A. Contract Closure - completing and settling each contract, including the resolution of any open items,
and closing each contract.
B. Plan Purchases and Acquisitions - selecting a buyer to purchase any product or service.
C. Select Sellers - reviewing offers, choosing from among potential sellers, and negotiating a written
contract with a seller.
D. Request Seller Responses - obtaining information, quotations, bids, offers, or proposals, as appropriate
E. Plan Contracting - documenting products, services, and results requirements and identifying potential
sellers
(198) Most schedule simulations are based on some form of which of the following?
A. Delphi
B. PERT
C. CPM
D. Monte Carlo Analysis
(199) What is critical path?
A. The shortest path through the network, which represents the longest amount of time in which a project
can be completed.
B. The path with zero float.
C. The longest path through the network, which represents the shortest amount of time in which a project
can be completed.
D. The path with the most activities with the longest durations.
E. b and c
(200) In the communication process, "noise" is the word used to describe factors and forces inhibiting the
exchange of information between two or more parties. Noise includes all of the following but __________
A. Culture
B. Behavior
C. Language
D. Traditional way of doing things
E. Loud talking
ANSWERS :
(1) Answer:C (51) Answer:E (101) Answer: C (151) Answer: B
(2) Answer: C (52) Answer:D (102) Answer: C (152) Answer: A
(3) Answer: B (53) Answer:B (103) Answer: D (153) Answer: E
(4) Answer:C (54) Answer:C (104) Answer: D (154) Answer: C
(5) Answer:B (55) Answer:C (105) Answer: A (155) Answer: D
(6) Answer: D (56) Answer:D (106) Answer: B (156) Answer: E
(7) Answer: D (57) Answer: B (107) Answer: A (157) Answer: A
(8) Answer: C (58) Answer:C (108) Answer: A (158) Answer: E
(9) Answer: C (59) Answer:E (109) Answer: C (159) Answer: C
(10) Answer: D (60) Answer:C (110) Answer: C (160) Answer: A
(11) Answer: C (61) Answer:D (111) Answer: C (161) Answer: C
(12) Answer:C (62) Answer:A (112) Answer: B (162) Answer: D
(13) Answer:E (63) Answer:A (113) Answer: A (163) Answer: C
(14) Answer:E (64) Answer:A (114) Answer: C (164) Answer: B
(15) Answer:E (65) Answer:E (115) Answer: A (165) Answer: C
(16) Answer:A (66) Answer:A (116) Answer: A (166) Answer: A
(17) Answer:C (67) Answer:E (117) Answer: D (167) Answer: C
(18) Answer: A (68) Answer:A (118) Answer: D (168) Answer: A
(19) Answer: E (69) Answer:E (119) Answer: C (169) Answer: B
(20) Answer:E (70) Answer:D (120) Answer: C (170) Answer: B
(21) Answer:A (71) Answer:D (121) Answer: B (171) Answer: B
(22) Answer:C (72) Answer:A (122) Answer: C (172) Answer: B
(23) Answer:E (73) Answer:A (123) Answer: A (173) Answer: C
(24) Answer:D&E (74) Answer:E (124) Answer: D (174) Answer: B
(25) Answer:B (75) Answer:C (125) Answer: A (175) Answer: C
(26) Answer:C (76) Answer:D (126) Answer: D (176) Answer: A
(27) Answer:A (77) Answer:D (127) Answer: A (177) Answer: C
(28) Answer:D (78) Answer:A (128) Answer: D (178) Answer: D
(29) Answer:B (79) Answer:D (129) Answer: C (179) Answer: E
(30) Answer:A (80) Answer: A (130) Answer: C (180) Answer: B
(31) Answer:D (81) Answer: D (131) Answer: A (181) Answer: E
(32) Answer:C (82) Answer: D (132) Answer: D (182) Answer: D
(33) Answer:C (83) Answer: B (133) Answer: D (183) Answer: A
(34) Answer:C (84) Answer: A (134) Answer: A (184) Answer: A
(35) Answer:D (85) ANSWER: C (135) Answer: C (185) Answer: E
(36) Answer:C (86) ANSWER: D (136) Answer: A (186) Answer: E
(37) Answer:C (87) ANSWER: A (137) Answer: C (187) Answer: D
(38) Answer:D (88) ANSWER: C (138) Answer:B (188) Answer: A
(39) Answer:C (89) ANSWER: A (139) Answer: A (189) Answer: B
(40) Answer:A (90) Answer: E (140) Answer: D (190) Answer: D
(41) Answer:D (91) Answer: C (141) Answer: C (191) Answer: E
(42) Answer:D (92) Answer: A (142) Answer:A (192) Answer: A
(43) Answer:A (93) Answer: B (143) Answer:B (193) Answer: B
(44) Answer:A (94) Answer: A (144) Answer: C (194) Answer: E
(45) Answer:C (95) Answer: C (145) Answer:B (195) Answer: B
(46) Answer:B (96) Answer: A (146) Answer:D (196) Answer: C
(47) Answer:B (97) Answer: B (147) Answer: D (197) Answer: E
(48) Answer:D (98) Answer: D (148) Answer: D (198) Answer: D
(49) Answer:B (99) Answer: D (149) Answer: C (199) Answer: C
(50) Answer:A (100) Answer: D (150) Answer: C (200) Answer: E