Ch9 Project Selection
Ch9 Project Selection
Project Selection
1. Project selection
2. Non-financial methods
3. Financial methods.
9-2
Project Selection
9-3
Project Selection
Comments
Project A: Major competior already has similar product and may reduce price
Project B: New technology may not work as expected.
Project C: Product features may not be accepted in some international markets.
9-4
Non-financial methods
9-5
Non-financial methods
Profile models.
9-6
Non-financial methods
Checklist Model
List of criteria applied to possible projects.
Requires agreement on criteria
Assumes all criteria are equally important
Checklists are valuable for recording opinions and encouraging
discussion.
9-7
Non-financial methods
Checklist Model
Performance on Criteria
Project Criteria High Medium Low
Project Cost X
Profit potential X
Time to market X
Development risks X
Project Cost X
Profit potential X
Time to market X
Development risks X
Project Cost X
Profit potential X
Time to market X
Development risks X
9-8
Non-financial methods
Scoring Models
Each project receives a score that is the weighted sum of its
grade on a list of criteria.
9-9
Non-financial methods
Scoring Models
Criteria weight Project 1Project 2Project 3Project 4
Support key business objectives 25% 90 90 50 20
Has strong internal sponsor 15% 70 90 50 20
Has strong customer support 15% 50 90 50 20
Uses realistic level of technology 10% 25 90 50 70
Can be implemented in one year or less 5% 20 20 50 90
Provides positive NPV 20% 50 70 50 50
10% 20
Has low risk in meeting scope, time, and cost goals 50 50 90
Weighted Project Scores 100% 56 78.5 50 41.5
9-10
Non-financial methods
Scoring Models
100
80
Project 2
60
40 Project 1
Project 3
Project 4
20
0
Projects
9-11
Non-financial methods
9-12
Contents..
1. Project selection
2. Non-financial methods
3. Financial methods
9-13
Financial Models
9-14
Financial Models
Payback Period
• Determines how long it takes for a project to reach a breakeven
point.
• The pay-out period measures the number of years it will take for
the positive net cashflows to repay the investment.
Investment
Payback Period
Annual Cash Savings
9-15
Financial Models
Payback Period
Example: A project requires an initial investment of $200.000
and will generate cash savings of $75.000 each year for the next
three years; what is the payback period?
Solution
Year Cash Flow Cumulative
200.000
0 ($200.000) ($200.000) PP 2.67 years
75.000
1 $75.000 ($125.000) 1
*
rate of return 37%
2 $75.000 ($50.000) 2.67
3 $75.000 $25.000
Advance Disadvance
Simple Do not care the cash flow
Usefull with the high after the payback period.
risk project, need a
fast payback.
Financial Models
Payback Period
0 ($500.000) ($500.000)
1 50.000 (450.000)
2 150.000 (300.000)
3 350.000 50.000
4 600.000 650.000
5 500.000 1.150.000
Payback = 2.857 years
Rate of Return = 35%.
9-19
Financial Models
Payback Period
0 ($500.000) ($500.000)
1 75.000 (425.000)
2 100.000 (325.000)
3 150.000 (175.000)
4 150.000 (25.000)
5 900.000 875.000
Example: r = 10%
Cash flow
pp
0 1 2 3 4 5
(yr)
PV[NCF(A)] -1000 500 300 200 100 60 3
PV[NCF(B)] -1000 200 300 300 400 300 3.5
1/(1+0.1)t 1 0.909 0.826 0.751 0.683 0.621
PVA -1000 454.5 247.8 150.2 68.3 37.26 -41.94
PVB -1000 181.8 247.8 225.3 273.2 186.3 114.4
where
Ft = net cash flow for period t
r = required rate of return
I 0 = initial cash investment
pt = inflation rate during period t
9-22
Financial Models
Net Present Value
Should you invest $60.000 in a project that will return $15.000 per
year for five years? You have a minimum return of 8% and expect
inflation to hold steady at 3% over the next five years.
Solution
Year Net flow Discount NPV
0 -$60.000 1.0000 -$60.000 The NPV column
1 $15.000 0.9009 $13.514 total is negative,
so don’t invest!
2 $15.000 0.8116 $12.174
3 $15.000 0.7312 $10.968
4 $15.000 0.6587 $9.881
5 $15.000 0.5935 $8.902
-$4.562 9-23
Financial Models
r constant
Year 0 1 2 3 4
Net Cash Flow -1000 200 300 350 1440
r 18% 16% 14% 12% 10%
200 300 350 1440
NPV 1000
0
436.91
1.18 (1.18)(1.16) (1.18)(1.16)(1.14) (1.18)(1.16)(1.14)(1.12)
350 1440
NPV 1000(1.18)(1.16) 200(1.16) 300
2
598.04
(1.14) (1.14)(1.12)
Note: All of the transactions are done at the beginning of the year.
Financial Models
r = 10%; NPV?
Cash flow
Year 0 1 2 3 4 5
Bt 900 1500 1500 1500 1700
Ct 2000 500 800 800 800 800
Bt - C t -2000 400 700 700 700 900
1/(1+0.1)t 1 0.909 0.826 0.751 0.683 0.621
PV(NCF) -2000 363.6 587.2 525.7 478.1 558.9
NPV = 459$
a. Reject a projects?
Rule: “Do not accept any project unless it generates a positive
net present value”
Examples
Project A: Present Value Costs $1 million, NPV + $70,000
Project B: Present Value Costs $5 million, NPV - $50,000
Project C: Present Value Costs $2 million, NPV + $100,000
Project D: Present Value Costs $3 million, NPV - $25,000
Result
Only projects A and C are acceptable.
Financial Models
where
ACFt = annual after tax cash flow for time period t
IO = initial cash outlay
n = project's expected life
IRR = the project's internal rate of return
9-31
Financial Models
Sử dụng IRR
(a) Nếu IRR > MARR(Minimum acceptable rate of return), dự
án nên được tiến hành.
(b) Sử dụng IRR để phân hạng dự án. Dự án có chỉ số IRR lớn
nên được chọn.
(c) Lợi thế của IRR là không chỉ sử dụng dữ liệu từ dự án.
3-34
Financial Models
+300
Thời gian
-100
-200
Solution 1
K = 100%; NPV= - 100 + 300/(1+1) - 200/(1+1)2 = 0
Solution 2
K = 0%; NPV= -100 + 300/(1+0) - 200/(1+0)2 = 0
3-35
Financial Models
Vấn đề 3: Dự án có thời gian sống khác nhau và loại trừ lẫn nhau.
Chi phí cơ hội của quỹ đầu tư: 8%.
Dự án A: Chi phí đầu tư: 1000 $ ở năm 0
Lợi nhuận: 3200$ ở năm thứ 5.
Dự án B: Chi phí đầu tư: 1000 ở năm 0.
Lợi nhuận: 5200$ ở năm thứ 10
NPVA0: -1000 + 3200/(1.08)5 = 1177.86
NPVB0: -1000 + 5200/(1.08)10 = 1408.60
Vậy NPVB0 > NPVA0
IRRA: -1000 + 3200/(1 + KA)5 = 0 tức KA = 0.262
IRRB: -1000 + 5200/(1 + KB)10 = 0 tức KB = 0.179
Vậy KA > KB
NPV và IRR đưa ra kết luận khác nhau khi so sánh 2 dự án có
thời gian sống khác nhau. 3-37
Financial Models
Vấn đề 4: Cùng dự án nhưng bắt đầu ở các thời điểm khác nhau.
Dự án A: Chi phí đầu tư = 1000$ ở năm 0
Lợi nhuận = 1500$ ở năm 1
Dự án B: Chi phí đầu tư = 1000$ ở năm 5
Lợi nhuận = 1600$ ở năm 6
NPVA0: -1000 + 1500/(1.08) = 388.88
NPVB0: -1000 + 1600/(1.08)6 = 327.68
Vậy NPVA0 > NPVB0
IRRA: -1000 + 1500/(1 + KA) = 0 tức KA = 0.5
IRRB: -1000 /(1 + KB)5 + 1600/(1 + KB)6 = 0 tức KB = 0.6
Vậy KB > KA
NPV và IRR đưa ra kết luận khác nhau khi thời điểm bắt đầu
của một dự án là khác nhau.
3-38
Home work
r = 12%
Cash flow
Year 0 1 2 3 4 5
NCF(A) -1000 500 300 200 100 60
NCF(B) -1000 200 300 300 400 300
NCF(C) -1000 100 200 300 400 500
9-39