Conc M25 Rate Analysis 2021
Conc M25 Rate Analysis 2021
Code:
5.33.1.1
Providing and laying in position ready mixed or site batched design mix
cement concrete for reinforced cement concrete work; using coarse
aggregate and fine aggregate derived from natural sources, Portland
Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to accelerate / retard setting of
concrete, to improve durability and workability without impairing strength;
including pumping of concrete to site of laying, curing, carriage for all leads;
but excluding the cost of centering, shuttering, finishing and reinforcement
as per direction of the engineer-in-charge; for the
following grades of concrete. Note: Extra cement up to 10% of the minimum
specified cement content in design mix shall be payable separately. In case
the cement content in design mix is more than 110% of the specified
minimum cement content, the contractor shall have discretion to either re-
design the mix or bear the cost of extra cement. 5.33.2.1 All works upto
plinth level .Concrete of M25 grade with minimum cement
content of 330 kg /cum
Providing and laying in position ready mixed or site batched design mix
cement concrete for reinforced cement concrete work; using coarse
aggregate and fine aggregate derived from natural sources, Portland
Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to accelerate / retard setting of
concrete, to improve durability and workability without impairing strength;
including pumping of concrete to site of laying, curing, carriage for all leads;
but excluding the cost of centering, shuttering, finishing and reinforcement
as per direction of the engineer-in-charge; for the
following grades of concrete. Note: Extra cement up to 10% of the minimum
specified cement content in design mix shall be payable separately. In case
the cement content in design mix is more than 110% of the specified
minimum cement content, the contractor shall have discretion to either re-
design the mix or bear the cost of extra cement. 5.33.2.2 All works upto
plinth level .Concrete of M30 grade with minimum cement
content of 350 kg /cum
Providing and laying in position ready mixed or site batched design mix
cement concrete for reinforced cement concrete work; using coarse
aggregate and fine aggregate derived from natural sources, Portland
Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to accelerate / retard setting of
concrete, to improve durability and workability without impairing strength;
including pumping of concrete to site of laying, curing, carriage for all leads;
but excluding the cost of centering, shuttering, finishing and reinforcement
as per direction of the engineer-in-charge; for the
following grades of concrete. Note: Extra cement up to 10% of the minimum
specified cement content in design mix shall be payable separately. In case
the cement content in design mix is more than 110% of the specified
minimum cement content, the contractor shall have discretion to either re-
design the mix or bear the cost of extra cement. 5.33.2.1 All works above
plinth level upto floor V level.Concrete of M25 grade with minimum cement
content of 330 kg /cum
Providing and laying in position ready mixed or site batched design mix
cement concrete for reinforced cement concrete work; using coarse
aggregate and fine aggregate derived from natural sources, Portland
Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to accelerate / retard setting of
concrete, to improve durability and workability without impairing strength;
including pumping of concrete to site of laying, curing, carriage for all leads;
but excluding the cost of centering, shuttering, finishing and reinforcement
as per direction of the engineer-in-charge; for the
following grades of concrete. Note: Extra cement up to 10% of the minimum
specified cement content in design mix shall be payable separately. In case
the cement content in design mix is more than 110% of the specified
minimum cement content, the contractor shall have discretion to either re-
design the mix or bear the cost of extra cement. 5.33.2.2 All works above
plinth level upto floor V level. Concrete of M30 grade with minimum
cement
content of 350 kg /cum
HRC 30 rate
considering rate of
aggretas as Rs 3000/-
per Cum
ost for : 1.00 Cum
Quantity Rate Amount
13991 1.34
Item
Code:
5.33.2.2
Providing and laying in position ready mixed or site batched design mix
cement concrete for reinforced cement concrete work; using coarse
aggregate and fine aggregate derived from natural sources, Portland
Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in
recommended proportions as per IS: 9103 to accelerate / retard setting of
concrete, to improve durability and workability without impairing strength;
including pumping of concrete to site of laying, curing, carriage for all leads;
but excluding the cost of centering, shuttering, finishing and reinforcement
as per direction of the engineer-in-charge; for the
following grades of concrete. Note: Extra cement up to 10% of the minimum
specified cement content in design mix shall be payable separately. In case
the cement content in design mix is more than 110% of the specified
minimum cement content, the contractor shall have discretion to either re-
design the mix or bear the cost of extra cement. 5.33.2.2 All works above
plinth level upto floor V level. Concrete of M30 grade with minimum
cement
content of 350 kg /cum
HRC 30 rate
considering rate of
aggretas as Rs 3000/-
per Cum
ost for : 1.00 Cum
Quantity Rate Amount
Rs 12567.56 1.20
Item Code: 20.2.3
Boring, providing and installation bored cast-in-situ reinforced cement
concrete piles of grade M-25 of specified diameter and length below
the pile cap, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of
boring with bentonite solution and temporary casing of appropriate
length for setting out and removal of same and the length of the pile
to be embedded in the pile cap etc. by percussion drilling using
Direct mud circulation (DMC) or Bailer and chisel technique by tripod
and mechanical Winch Machine all complete, including removal of
excavated earth with all its lifts and leads (length of pile for payment
shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not
be used
8683.80 49080.86 A
2800.00 924.00
2.12 243.80
3000.00 4500.00
3500.00 210.00
3000.00 1140.00
3750.00 1125.00
6000.00 1800.00
784.00 94.08
645.00 1935.00
Total: 61052.74 W
11971.88 119.72
61172.46 X
12091.60 1698.87
62871.33 Y
13790.47 2068.57
64939.90 Z
15859.04 158.59
Cost for 20.00 m 65098.49
Cost for 1 m pile 3254.92
Item Code: 20.2A
Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of
specified diameter and length below pile cap, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and
temporary casing of appropriate length for setting out and removal of same and the length of the pile to
be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete,
including removal of excavated earth with all its lifts and leads (length of pile for payment shall be
measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used.
8683.80 49080.86 A
2800.00 924.00
2.12 233.20
35000.00 26250.00
3500.00 210.00
3000.00 1140.00
6000.00 1800.00
3750.00 1125.00
784.00 94.08
645.00 1935.00
Total: 82792.14 W
33711.28 337.11
83129.25 X
34048.39 4783.80
87913.05 Y
38832.19 5824.83
93737.88 Z
44657.02 446.57
Cost for 20.00 m 94184.45