Method Statement for Formwork, Reinforcement bars and Ready Mix Concrete عام
Method Statement for Formwork, Reinforcement bars and Ready Mix Concrete عام
Site Preparation & temporary site facilities.Three equipped site offices are requires (one for
Owner's engineer, another one for Consultant engineer and last one for Contractor engineer)
with all necessary utilities.
Survey Instruments.
Tower mobile crane.
Mechanical Vibrators / Internal Vibrators
Concrete Pumps.
Transit Mixer Trucks
Batching Plant
Al l necessary Hand Tools
Safety Equipment's
Prior to the commencement of the works, confirm and establish all reference points
and levels.
Locate, confirm and protect control points prior to star ting the site works.
Formwork:
Formworks should support the loads imposed on them by the fresh concrete
together with additional stresses imposed by vibrating equipment and by
construction traffic.
Formwork/Shuttering will be installed as per approved drawings and secured
against lateral force by concrete.
Formwork thus erected and installed will be rigid. water tight and dimensionally
stable.
Formworks release agent material as approved by the consultant will be applied
prior casting to ensure good surfaced finished of concrete.
Before placing concrete, all dirt, debris and other foreign matter shall be removed.
Before concrete placing commences, all wedges and other adjusting devices shall
be secured against movement during concrete placing.
Before placing concrete, make sure all the reinforcement is ready, cover blocks
provided, all MEP installations completed (if any) and all approvals have been
taken.
Concrete Placement Procedure:
The concrete work shall confirm to all requirements of BS 8110, Structural use of
concrete.
No concrete shall be placed in the permanent works until the consultant has approved
the materials.
No concrete shall be placed i n any part of the permanent structure until the consultant
consent has been given in writing.
The concrete shall be deposited as nearly as possible in its final position. It shall be
placed so as to avoid segregation of concrete and displacement of the reinforcement,
other embedded items or formwork.
For the Structures more than 3 meter height, special arrangements will be adopted by
providing the openings at top by cutting one top vertical bar (which can be provided on
later stage with the “U” shape bars with a suitable overlap) at the distance of 1 meter
interval, to accomolate the hose pipe / tremie at the most possible and nearest place of
concrete pouring.
Maximum free fall height / free drop height shall be minimized to 1.5m to avoid
segregation.
The concrete will be placed into layers not more than 600mm. or agreed by the
consultant. (The layer thickness will be controlled by marking on the hose pipe /
tremie).
The layers shall not be placed so that they form featheredges nor shall they be placed
on a previous layer that has taken its initial set. In order to comply with this
requirement, a layer will be started before completion of the preceding layer.
The vibrators shall be operated at regular intervals to produce dense, compact and
homogeneous concrete surface. The size of the vibrating pokers will be decided
considering the layout of reinforcements and will ensure consistent mass is obtained
without segregation.
During concrete placement operations it will be ensured that ambient temperature is
42°C while concrete temperatures 32°C.
Removal of Formwork:
Concrete shall be thoroughly wetted as soon as the forms are first loosened and shall
be kept wet during the removal operation and until the curing media is applied.
The curing process shall commence as soon as the concrete is hard enough to resist
damage from the process.
Curing shall be continued for as long as may be necessary to achieve its objectives but
in any case for at least seven days or until the concrete is covered by the later
construction, whichever is the shorter period.
Method Statement for Formwork, Reinforcement bars and Ready Mix
Concrete
This method statement covers the scope of work including the placement of formwork,
reinforcement bars and ready mixed concrete.
Arrange following equipment before start of the work:
Foundations shall be constructed first and then columns to the tripod beam bottom level.
In the Workshop building, sub-columns and sub-beams system on wall, beam surface
form will be done after the installation of steel framework.
Establish accurate centerline axis and level for the layout of foundations, columns, beams,
and floors, before installing forms.
Form should be adequately supported or braced to avoid movements or displacement
during casting concrete. Bolt connector or any acceptable pre fabricated support system is
essential.
Check the alignment of formwork by stretching a cord along edges of installed forms
For additional supports, Iron and tension cable can be used as supports in the installation
of forms of column footings. Check the establish centerline for accuracy to avoid
deviations.
Staging and scaffolding support system is to be utilized for beams and slab forms, and
they are installed at the same time. During installation regular checking of lines and
grades shall be made to ensure the evenness and straightness of slabs and beams during
construction.
Position Steel and wood joist supports and bracings is utilized for forms of concrete
structures. Jacks are installed at top and base of supports for adjusting height or length, all
bases of support should be propped by a piece of wooden material to prevent settlement.
All supporting columns and bracings should be anchored, hold and connect together to
become stable frame system to secure structures during concreting.
Formwork Procedure شرح آخر للنجارة
Formwork system, which gives an advantage of combining speed and quality of construction,
will be used.
The vertical load carrying members will be made of steel whereas the horizontal members will
be of plywood inserted two wooden beams thereby forming a web flange.
All the formwork and support systems will be designed for the loads coming during the actual
execution stage.
All the members in the formwork and the support system will be designed as per the relevant
codes and standards.
In case of a wall formwork system the H -Beams along with steel components are assembled
to form a very convenient and safe formwork system up to the sub structure levels.
The wall formwork facilitates fixing of working platforms for access, checking of reinforcement
concreting etc.
The formwork panel along with the working platform and alignment systems can be lifted as a
single unit using a crane thus the labor involved in each operation of erection and de-
shuttering is reduced to a minim um.
Formworks shall have adequate bracing and support to carry the concrete load and other
loads foreseen prior to and during concreting.
Proper access (scaffolding, ladders, etc.) and working platforms will be provided for elevated
formworks.
The wall formwork system can handle very large pressures generated due to pumping of
concrete. The interiors of the forms shall be clean and smooth.
All embedded items shall be supported against displacement reinforcement shall be secured
with adequate number and type of spacing.
Columns, Beams, Concrete Walls, Footings and Foundations
Scaffolding system (including wooden shuttering beams, shuttering boards -plywood- and
supporting systems) which shall be erected for foundations, columns, beams and concrete
walls. For footings and grade beams a
sim pler system shall be used which consist of shu ttering boards and supporting systems.
Foundations shall be placed on lean concrete and sub-grade compaction and strength
results shall be obtained prior to lean concrete. Concrete shall be placed in formwork; casting
against soil is not permitted.
Following the concreting of footings/foundations, place formwork and reinforcing bars for the
column and finish concreting for the columns. Wa terproofing will be done as per the
specification.
After the columns are cast, formwork will be placed for the suspended slabs and the beams,
reinforcement will be tied and the concreting will be done.
Slabs
H -Type scaffolding system shall be used in slabs. I t shall be erected near one of the walls as
a single row. The forkheads shall be placed on the top of H-Type system.
Then the shuttering beams in to the forkheads and, the shuttering boards by plywood shall be
erected above them.
Erection of Formwork and Support System
The Table formwork shall be erected using the Crane. All ali gnments & levels shall be
checked & The formwork shall be erected using the mobile crane.
All alignments & levels shall be checked & verified from established da tum on the project
site. Concrete edges shall be chamfered.
Roofing Work:
Roofing material and shop drawing for this type of work shall be submitted to the engineer for
approval.
Installation procedure shall conform to manufacturer's product technical specification on
installation. Precautions against accident shall be well considered for its sensitiveness in
executing this work.
Before placing waterproofing mem brane, the surface shall be thoroughly cleaned and primer
paint shall be applied in dry condition. Apply waterproofing mem brane on primer coated
surface, by pre heating to adhere firmly. Overlapping portion of waterproofing mem brane
shall be carefully bonded with each other to avoid water leakage.
Occupational Health And Safety Control for Steel Structure Work_
Everybody who will carry out the works shall use all the necessary protective or safety gears
and abide by the occupational health and safety control plan of the project to avoid the
occurrence of accident and minimize the potential cause of hazard.
Working areas shall be provided with warning devices signage's or barriers , and frequently
checked by Safety Engineer during work time.
Ensure all vehicles and equipment is safe and fully efficient, guarded and equipped with
safety devices and has been subjected to necessary test.
Make sure that opera tors, drivers and attendants will only concern themselves on the
equipment for which they have been thoroughly trained.
Check working efficiency of equipment for its intended purpose, and its valid registration and
calibration certificates.
Safety lifelines shall be provided to all elevated work areas to enhance connection point
safety harness or belts used by workers, especially to a location where scaffolding
impossible.
All workers working higher than 1.5 meters must wear a safety harness or bel t. The safety
line manufacturer's recommendations for use shall be strictly followed.
Finishing Works
Door & Window Works
Doors, louvers and windows shall be of the approved ones and in compliance with the
specification. Installations shall be made in accordance with the schedule to keep finishing
work in sequence and to avoid lapping of activities that cause delay or damage impact to
other finishing work.
Installed doors, louvers and windows shall be keep protected to avoid damages caused by
other ongoing finishing works and other parties.
Plastering Works
The thickness and mix proportion of mortar for Plastering or rendering shall be in accordance
with the specification and the mixing and kneading process is to be done manually or by
portable mixer.
Cement shall be of the standard ordinary Portland cement and sand, sourced out from land or
river and shall be approved by the Engineer.
Tiling Works
Tile material and shop drawing for tile layout or arrangement shall be submitted to engineer
for approval. Prior to tile laying concrete surface where tile is laid shall be cleaned, free from
dust oil, grease and other elements that would affect quality of tile bed mortar.
Bed mortar of specified mix proportion (1:3) is placed and spread evenly with a minimum
thickness of 1Om m over the area to be tiled. Tiles are then laid over the evenly applied bed
mortar until it adhere firmly in place.
Tile gaps shall be filled up with grout of approved type or as specified in the plan. After
grouting tiled area shall be cleaned from excess grout to keep the work clean as specified.
Painting Works
Paint material shall be of the approved one in accordance with specification. Surface
preparation before Painting shall conform to the manufacturer's instruction to each kind of
pain t material.
Number of coat dry film thickness shall comply with the approved paint schedule. Where
required, final coat shall be carried out after or almost all of the work nearby is completed to
minimize damage.
Ceiling Work
The material for ceiling work shall be submitted to the engineer for approval. Shop drawing for
ceiling layout and arrangement plan shall be approved by the consul tan t. And proper
coordination to MEP works shall be made to avoid lapping of works that cause delay in
executing the work.
Hangers shall be installed, fastened and fixed properly under the concrete slab or steel
structural members. Then thin gauge and light steel frame is installed to enhance level
adjustments' required. MEP works above ceiling shall
be completed before installing the ceiling frame.
Deflections or damage on the T-runner frame shall be repaired prior to installation of the
gypsum board.
Mechanical Electrical & Plumbing Work
Air Conditioning and Ventilation Works
Air Conditioning and Ventilation system including shop drawing plans and all schema tic
layouts for these works shall be submitted to the Engineer for approval.
All slots in exterior walls intended for pipe crossing shall be made impervious. Shop drawings
of ceilings and walls shall reflect location of air conditioner, ventilator and ducts, to account
for the balance distribution of other equipment.
Installation of air conditioner, ventilator, air inlet and outlet including pipes, ducts and other
related fittings shall conform as indicated in the shop drawings. Exhaust pipe/duct shall
sloped downward from inside to outside.
Plumbing Works
Material and equipment for Plumbing work and shop drawings shall be submitted to the
engineer for approval.
Excavation and trenching of soil, preparation of sleeves on floor, wall and beam where there
are necessary in structures shall be well considered.
Before being installed, all pipes shall be thoroughly cleaned, free from any scales, burrs, rusts
and obstructions.
Prefabrication, installation and join ting of pipes (including fittings) with adhesive for PVC
material, including valves, strainers, and flexible joints shall be done carefully.
Adequate pipe supports, hanging steel bars and anchorage shall be provided.
Sealing of pipe sleeves shall be done properly.
Pressure test for water supply pipes and flushing test for drainage pipes shall be performed.
Back-fill and compaction of soil for underground piping shall be done carefully.
Electrical Works
Material and equipment for electrical works and shop drawings shall be submitted to the
Engineer for approval.
Preparation for efficient wire or cable laying such as confirmation of the exact locations where
they are to be laid, cleaning the trenches or ducts, scraping/brushing inside of the duct bank,
pipes or conduits and so on shall be done.
All cable connections shall be made inside distribution board; pull box and outlet box etc. and
the connection shall never be exposed or inside of conduits.
Cable alignment binding, fixing, wall penetration sealing, cable marking, cable penetration into
conduits between cable trays, ducts and Job-site junction boxes and similar shall be made
properly.
Adequate press-save coupling, wire connector or press com bine terminal etc. will be used as
a principle for the connection of wires and/or cables.
In the case of line pipe exceeding 30m for one section or where leading in is difficult pull box
shall be used.
Fixing method of distribution boards etc. shall be specified on the construction drawing, and
shall be fixed accordingly.
The position of lighting apparatus shall be indicated on ceiling allotted sketch in advance,
taking balance with other facilities apparatus.
Fixing height of switch and socket outlet shall be shown on the shop drawing securing the
approval of the consultant and shall be fixed accordingly.
Testing and Commissioning (Trial Run)
After installation of Mechanical and Electrical equipment test and inspection including their
record reports will be done. Trial operation shall be proceeded to adjust and check the
function of equipment.
Formworks should support the loads imposed on them by the fresh concrete together with
additional stresses imposed by vibrating equipment and by construction traffic.
Formwork/Shuttering will be installed as per approved drawings and secured against
lateral force by concrete.
Formwork thus erected and installed will be rigid. water tight and dimensionally stable.
Formworks release agent material as approved by the consultant will be applied prior
casting to ensure good surfaced finished of concrete.
Before placing concrete, all dirt, debris and other foreign matter shall be removed.
Before concrete placing commences, all wedges and other adjusting devices shall be
secured against movement during concrete placing.
Before placing concrete, make sure all the reinforcement is ready, cover blocks provided,
all MEP installations completed (if any) and all approvals have been taken.
Reinforcing Rebar Works
The reinforcing bars in conformity with the valid drawings shall be used in the construction.
Steel workers shall bend all rebar under supervision of the foremen.
These foremen have to organize bending works according to the valid revision of related
project. After that steel fixers shall install all reinforcing steel.
Erection of rebar shall take place in layers from bottom to top, and the embedded items (if
exist) shall be installed at the required level.
Concrete Placement Procedure:
The concrete work shall confirm to all requirements of BS 8110, Structural use of
concrete.
No concrete shall be placed in the permanent works until the consultant has approved the
materials.
No concrete shall be placed i n any part of the permanent structure until the consultant
consent has been given in writing.
The concrete shall be deposited as nearly as possible in its final position. It shall be placed
so as to avoid segregation of concrete and displacement of the reinforcement, other
embedded items or formwork.
For the Structures more than 3 meter height, special arrangements will be adopted by
providing the openings at top by cutting one top vertical bar (which can be provided on
later stage with the “U” shape bars with a suitable overlap) at the distance of 1 meter
interval, to accomolate the hose pipe / tremie at the most possible and nearest place of
concrete pouring.
Maximum free fall height / free drop height shall be minimized to 1.5m to avoid
segregation.
The concrete will be placed into layers not more than 600mm. or agreed by the consultant.
(The layer thickness will be controlled by marking on the hose pipe / tremie).
The layers shall not be placed so that they form featheredges nor shall they be placed on
a previous layer that has taken its initial set. In order to comply with this requirement, a
layer will be started before completion of the preceding layer.
The vibrators shall be operated at regular intervals to produce dense, compact and
homogeneous concrete surface. The size of the vibrating pokers will be decided
considering the layout of reinforcements and will ensure consistent mass is obtained
without segregation.
During concrete placement operations it will be ensured that ambient temperature is 42°C
while concrete temperatures 32°C.
Casting Water Tank Walls
During concrete placement, care shall be taken not to lose any ingredients from the concrete,
any type of segregation, and the displacement of the reinforcement.
Concrete shall be deposited in uniform layers from the bottom to the required level and shall
be consolidated using vibrators and pokers. Care shall be taken to avoid segregation. The
maximum depth of each layer shall be restricted to 300 mm.
Removal of Formwork:
Once the concrete has set curing shall be started and shall be maintained for 7 days
Concrete shall be thoroughly wetted as soon as the forms are first loosened and shall be
kept wet during the removal operation and until the curing media is applied.
The curing process shall commence as soon as the concrete is hard enough to resist
damage from the process.
Curing shall be continued for as long as may be necessary to achieve its objectives but in
any case for at least seven days or until the concrete is covered by the later construction,
whichever is the shorter period.
Casting of Roof slab
The roof slab of water tank shall be cast with the basemen t roof slab
Water Proofing
Once the curing period of walls is completed, The waterproofing system shall be applied to
the external face of the water tank in accordance with the manufacturer's recommendations
and the applicator's approved method statement
Internal Finishing
Internal finishing (Epoxy painting) shall be applied as per the Specification and manufacturer's
recommendations and the applicator's approved method statement.
Testing of Tank for Water Tightness
The water tank shall be tested for the water tightness as per the specification requirements
and procedures.
Backfilling
Once the waterproofing of external face of water tank is inspected and approved by consul
tant the backfilling around water tank shall be carried in 250m m thick layers and its density
shall be tested. The backfilling shall carry out up to the required grade level as per the
drawing. During backfilling the anti termite chemical shall be sprayed. After every 1 meter
layer of backfilling (if applicable).