ITP For Block Work
ITP For Block Work
Tests will be
Mortar Compressive Section ASTM Approved
2.2 R As Specification performed for 400 R R
Strength 042000 C270 m2 of wall area Submittal
3 INSPECTION
Check axis as Conforms to Approved
Section Proir to work
3.1 Offsets of Axis Location N.A per approval approved
progress
inspection H H
042000 shop drawing shopdrawing request
visual Approved
Conforms to
First Course with starter Section inspection and Proir to work
3.2 N.A dimension
specification/drawin
progress
inspection H H
bars of posts&accessories 042000 g
check request
visual Approved
Check Verticallity,
Section inspection and Proir to work
3.3 Full Height N.A dimension
all joints between
progress
inspection H H
042000 blocks
check request
PROJECT
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
Employer
Engineer
CONSTRUCTION SUPERVISION
1
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 2 of 7
CONTENTS
CONTENTS .................................................................................................................................
2.0 REFERENCES...................................................................................................................
4.0 STORAGE………………………………………………………………………………………….
5.0 METHODOLOGY...............................................................................................................
2
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 3 of 7
1.0 SCOPE
This method statement is to outline the general specifications & methodology of block work installation
for all masonry walls to achieve surface matching the correctness to receive plaster.
2.0 REFERNCE
3.0 RESPONSIBILITES
Project manager :-
Emphasis on all the teams associated with this task need to follow the project specifications and
standards necessary to perform this task perfectly.
Emphasis on the need for the availability of raw materials and equipment for the performance of this
crisis, the process in an appropriate manner.
The need to follow the instructions of the industrial security and take preventive measures to preserve
the lives of individuals and Prevention diagnosed without any damage to the course of their work.
Construction Manager : -
The Construction Manager shall be responsible for the overall implementation of this Method
statement, and for ensuring that Site and Section Engineers are well informed of its requirements.
Assigning site engineers to specific task and ensuring that tasks are performed according to the projects
plans and specifications.
Site Engineers:-
3
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 4 of 7
QC Manager:-
Reviewing all relevant documentation and test reports and prepare all handing over reports.
Clearing all non-conformances relevant to the activity.
Ensuring that the Engineer’s Representative / Inspector clears all discipline activities that must be
inspected and tested.
Organizing and allocation of inspection works to Quality Control Inspectors.
Ensuring all inspection are performed and recorded as per project specifications.
Ensuring inspections are carried out in a timely manner and documented as per project inspection plan
QC Engineers:-
Inspect the work as per approved project inspection plan and approved shop drawings and make sure
the work is ready for Consultant inspection if required.
Preparing, Signing and obtain signatures from Consultant according to IR stages.
Informing Consultant Engineer’s Representative by works Inspection Request as and when his
presence is required to carry out inspections as per the approved project inspection plan.
The Surveyor: -
The surveyor is responsible for setting out the coordinates and the levels for all project works.
4.0 Storage/Handing
4
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 5 of 7
5.0 METHODOLGY
5.2 Installation :
Blocks shall be well soaked before using.
Full and half CMU units only should be used.
Full mortar bed to be spread well with the trowel ensuring plenty of mortar under the bottom
edges of the first course.
Installing first course taking into consideration location of openings, intersections.
For intersections in the first layer putting the block match with the perpendicular wall and in
the second layer the block will be parallel to wall direction and vice versa.
During construction all embedded conduits or plumping pipes to be installed and keep
cavities and air spaces clean of mortar, also all electrical boxes will be saw cut in place after
building the wall.
Concrete mortar shall be used for filling hollow cells, under concrete lintels and at opening
jambs.
5.5 Lintels :
Provide minimum bearing at each jamb of 100 mm for opening less than 1.5m and
of 200mm for wider openings.
5
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 6 of 7
5.7 Curing :
All walls shall be cured by sprinkling water twice a day for period not less
than 5 days.
6
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-10 Rev 00
CONCRETE MASONRY UNITS Date 22/11/2020 Page 7 of 7
Plumb
Straight edge
Strain lines for maintaining horizontal alignment between corners and piers
Mason trowels for applying and removing excess mortar
7.0 MATERIALS
Hollow block and solid block
Cement, sand
9.0 Safety:
All safety and health regulations shall be strictly followed and any case disregarding
the safety.
7
Ref MS-03 Rev 00
Date 31 May 2011 Page 8 of 8