600mw Coal Fired Power Plant Group 10 5201 Bamba Aldea Villanueva J.
600mw Coal Fired Power Plant Group 10 5201 Bamba Aldea Villanueva J.
BULACAN,
MABINI BATANGAS
In Partial Fulfillment
by
ALDEA, JENUEL
PetE-5201
May 2021
i
TABLE OF CONTENTS
Page
TITLE PAGE i
TABLE OF CONTENTS ii
LIST OF FIGURES v
CHAPTER
Introduction 1
Products 4
Demand Outlook 7
Market Share 12
Design Objectives 15
Plant Process 16
Definition of Terms 17
Plant Layout 21
ii
III TECHNICAL ASPECTS
Equipment Functions 26
IV ECONOMIC ANALYSIS
Building Cost 63
Vehicle Cost 66
Pipeline Construction 68
Equipment Cost 69
Installation/Commissioning 71
Engineering Cost 72
Labor Cost 73
Other Utilities 77
Product Prices 78
iii
Hazardous Chemical Control Activities 91
Conclusion 103
Recommendation 104
iv
LIST OF TABLES
v
and Heat Balance for each State Point
18 Coal Composition 48
19 Project Schedule 53
20 Project Schedule 54
21 Cost of Buildings 56
22 Vehicle cost 60
24 Equipment Cost 61
vi
36 Total Annual Operating Cost 70
vii
LIST OF FIGURES
viii
14 Piping and Instrumentation Diagram: Turbine 19
15 Coal 20
17 Belt Conveyor 22
18 Condenser 24
19 Turbine 26
20 Flash Tank 27
21 Pump 28
22 Separator/Evaporator 30
23 Economiser 31
25 Air Separation 33
26 Generator 35
27 Coal Burner 36
28 Coal Boiler 37
29 Coal Pulvurizer 39
x
and Heat Balance for each State Point
64 Coal Composition 48
65 Project Schedule 53
66 Project Schedule 54
67 Cost of Buildings 56
68 Vehicle cost 60
70 Equipment Cost 61
xi
79 Operating Labor Cost for Maintenance Department 68
xii
CHAPTER I
A. Introduction
As the economy of the country grows. Its energy consumption grows too.
Philippines has rural population of 53% of the total population and 94% of the total
population have access to electricity. (energypedia) The country’s total peak
demand in 2019 was recorded at 15,581 MW, which is 799 MW or 5.4% higher
than the 14,782 MW in 2018 (DOE). The distinctive feature of the energy demand
structure in the Philippines is that the transport sector consumes more than 50%
of the country’s energy demand, and that three quarters of the latter is used for
road transportation. In addition to the fact that transportation fuel accounts for large
portion of energy consumption, oil has been widely used by industrial users. Thus,
petroleum products accounts for about 70% of the primary energy requirement,
and one quarter is borne by electricity.(jicareport) As social modernization
progresses, demand for electricity and gas may increase in future. Considering the
importance of power industry in the overall development of the country, power
sector has been given high priority in the country’s development plans. Everyone
experience brownout or the drop in voltage in an electrical power supply system.
These outages have wide-ranging effects on the economy. Households would
experience no electricity for a few minutes or even for hours, causing great
inconvenience; businesses would have higher costs by way of lost revenue and
reduced productivity; and investors would be hesitant to do business, leading to
reduced investments. This scenario could have been avoided had there been more
power plants available to compensate for those undergoing unscheduled
shutdowns or maintenance. Data from the Department of Energy (DoE) showed
there are 126 power plants in Luzon grid alone as of end-2018 with installed and
1
dependable capacities of 16,133.06 MW and 14,641.76 MW, respectively
(bworldonline,2019). However, results of a study from the Energy Regulatory
Commission (ERC) released in May showed that up to 72% of these power plants
are at least 16 years or older, which may have contributed to the grid’s power
deficiency. Older plants require more frequent maintenance and repairs and may
be more prone to unscheduled outages. Building more efficient, high tech power
plant will help solve this problem.
2
Figure 1. Summary Table of Coal in Philippines
C. Products
The Philippines produces 100 to 130 million tons of combustion wastes annually
at coal-fired power plants. Regulations control the handling of solid wastes from the
boiler and pollution-control equipment at coal-fired power plants. In most cases, these
materials are disposed of in landfills. However, reuse of coal combustion wastes as
byproducts is permitted and 40 to 60 million tons (10 to 15%) are recycled annually
according to the American Coal Ash Association.
Boiler slag is produced in coal-fired power plants that use wet-bottom boilers. It
forms from melted minerals left over from coal combustion. This molten ash is
quenched with water to form a solid, black, glassy waste product, called slag. Boiler
slag is commonly re-purposed as a useful combustion byproduct. The slag material
can be ground into particles which are used as roofing granules and blasting grit, and
for snow and ice control (like sand) (Kalyoncu and Olson, 2001; American Coal Ash
Association, 2016).
3
Bottom ash is produced in dry-bottom boilers, which are the most common types
of boilers in coal-fired power plants. Bottom ash consists of the melted minerals left
over from coal combustion. The ash settles on the walls and at the base of the boiler
as a gray, sandy material. The ash is periodically removed and disposed of in landfills
or re-purposed as a useful coal-combustion byproduct. Approximately 15 million tons
of bottom ash are produced annually in the United States, and 10 to 15% is recycled
as useful byproducts. Bottom ash is used in many ways but mostly (1) as road base;
(2) for snow and ice control (like sand); (3) in structural fills; (4) in cement and grout;
and (5) in mining applications such as mine fills, where permitted (Kalyoncu and
Olson, 2001; American Coal Ash Association, 2016).
Fly ash is the fine particulate (including ash, dust, soot, and cinders) material
produced from coal combustion. It consists of the mineral matter in the coal which did
not combust in the furnace, and did not settle to the bottom of the boiler as bottom
slag or bottom ash. It is carried upward with gaseous by-products from the furnace
into the flue gas. Fly ash can be captured in an electrostatic precipitator or filter
baghouses. Between 50 and 70 million tons of fly ash are produced in the United
States annually. A little more than half of the fly ash is disposed of in landfills, but 40
to 45% (more than 20 million tons) is re-cycled as useful byproducts. Fly ash is used
in many ways but mostly (1) to make concrete and grout; (2) for use in structural fills;
(3) for waste stabilization (thickening, solidifying); (4) in cement production; and (5) in
mining applications such as mine fills, where permitted (Kalyoncu and Olson, 2001;
American Coal Ash Association, 2016).
4
Figure 3. Location of Propose Site
5
Its population as determined by the 2015 Census was 1,351. This represented
2.92% of the total population of Mabini. The site is near the highway where
transportation of personnel and equipment will be much easier; it is also near the
sea so jetty can be constructed and can be source of water supply for some
applications. The site also is far from active faults.
E. Demand Outlook
The following data necessary for the load projection were gathered from the
Department of Energy (DOE) distribution utility profile particularly the distribution utilities
operating in Batangas Province: BATELEC I, BATELEC II, FBPC, and IEEC. The Manila
Electric Company (MERALCO) was also added to the load projection. The data were
gathered to determine the forecast of the electrical consumption of the target locations.
6
Figure. 5 Seismic map of the Proposed Location
The data gathered from DOE showed the projected load from 2015- 2029 for
BATELEC I, BATELEC II, IEEC, and MERALCO. At 2019 the total projected load is equal
to 7622.7MW and after 10 years the projected load will increase to 10470MW. The power
demand has an average growth rate of 9.64% starting from 245.65 MW to 327 MW
averaging 309.21 MW for 10 years.
Assuming no other power plants will provide the additional demand, the proposed
600 MW power plant will reach its capacity within the next 2 years of operation upon the
finishing of construction within the next 10 years.
F. Market Share
As economies in Asia Pacific grow rapidly, so does the demand for power. At the
same, there is increasing urgency to limit the impact of power generation to the
environment. Yet, structural changes must be well planned and based on long-term
visions with tangible milestones. Therefore, critical to the energy transition process is
upgrading existing power plants and their controls to provide cleaner and more flexible
power, in part to address the intermittent nature of power generation renewables.
7
G. Design Objective
The main objective of this project is to design a coal-fired power plant having a
plant capacity of 600 MW located at Brgy. Bulacan, Mabini Batangas. Specifically, the
designers aim to come up with the desired plant wherein the following objectives must be
met.
1. Present and evaluate the design and development of the projected 600 MW coal
fired power plant taking into account of the following considerations:
2. Provide technical design specifications for the different components of the coal
fired power plant, presenting the proper data for the plant calculations,
schematic diagrams, process flow diagrams, plant lay-out, and particular type
of plant components considering the required engineering codes, standards and
appropriate specifications to be utilized as a part of the advancement of the
proposed coal-fired power plant.
3. Evaluate the economic viability of the three proposed design options as well as
the comparison of equipment through calculations of economic indicators:
Coal is shipped to the port area where it will be conveyed in the coal yard for
storage prior to being transported to the main power generating units. The first process
8
of this power plant is where the pulverized coal is fed into the boiler and it is burnt in the
furnace. The flue gasses and ash formed during combustion will be treated accordingly.
The water present in the boiler drum changes to high pressure steam. From the boiler the
high-pressure steam passed to the super heater where it is again heated up to its dryness.
This super-heated steam strikes the turbine blades with a high speed and the turbine
starts rotating at high speed. A generator is attached to the rotor of the turbine and as the
turbine rotates it also rotates with the speed of the turbine. The generator converts the
mechanical energy of the turbine into electrical energy. The electrical energy will be
amplified by a transformer and will then be transferred to the switch yard. After striking on
the turbine the steam leaves the turbine and enters into the condenser. The steam gets
condensed with the help of cold water from the cooling tower. The condensed water with
the feed water enters into the economizer. In the economizer the feed water gets heated
up before entering into the boiler. This heating of water increases the efficiency of the
boiler. The exhaust gases from the furnace pass through the super heater, economizer
and air pre-heater. The heat of this exhaust gases is utilized in the heating of steam in
the super heater, feed water in the economizer and air in the air pre-heater. After burning
of the coal into the furnace, it is transported to ash handling plant and finally to the ash
storage. The electricity produced by the generator are then stored at transformers before
distributing it to the consumers
I. Definition of terms
9
Generator - a generator is a device that converts motive power into electrical
power for use in an external circuit.
Reserves - Natural gas reserves refer to large deposits of natural gas which,
based on geological surveys and engineering studies, are thought to exist to a very
high degree of certainty.
Steam - Steam is water in the gas phase. This may occur due to evaporation, to
due to boiling, where heat is applied until water reaches the enthalpy of
vaporization
Steam turbine - is a device that extracts thermal energy from pressurized steam
and uses it to do mechanical work on a rotating output shaft
Voltage - Voltage is the pressure from an electrical circuit's power source that
pushes charged electrons (current) through a conducting loop, enabling them to
do work such as illuminating a light
10
Chapter II – Process Design Layout
11
Figure 7. : Process Flow Diagram - Flue Gas Desulphurisation system
12
Figure 8. Process Flow Diagram - Deashing system
13
Figure 9. Process Flow Diagram - Raw and Demineralised Water system
14
B. Piping and Instrumentation Diagram
15
Figure 11. Piping and Instrumentation Diagram: Polishing Plant
16
Figure 12. Piping and Instrumentation Diagram: Feedwater Tank
17
Figure 13. Piping and Instrumentation Diagram: Boiler
18
Figure 14. Piping and Instrumentation Diagram: Heat Exchanger
19
Figure 15. Piping and Instrumentation Diagram: Turbine
20
Chapter III – Technical Aspects
Source: geology.com
20
b. Location
The Semirara Mining and Power Corporation is a mining company based in the
Philippines. The company, a subsidiary of DMCI Holdings, operates its main coal
mine in Semirara Island and is the biggest coal producer in the Philippines
accounting for 92 percent of the total national production as of 2015. SPMPC’s
primary mining site is in Semirara Island where it has operated numerous coal
mines. It operated the Unong Pit in Semirara Island until 2000 and the Panian Pit
until 2016. It opened the Narra and Molave Pit in the islands as replacements.
Source:http://www.semiraramining.com
A. Belt Conveyor
Belt conveyors help in the transportation of large volumes of coal over long
distances. They come with an endless rubber, balata or canvas belt running over pulleys
or a pair of end drums, with rollers (idlers) at regular intervals for support. The return idlers
that help in the support of the empty belt are plain and fall widely apart.
21
Figure 17. Belt Conveyor
Source: Alibaba
Design Specification
Equipment Category Transportation
Requirement 1000kg
22
Size 1600*520*1000mm
B. Heat Exchanger
Heat exchangers are devices designed to transfer heat between two or more fluids—
i.e., liquids, vapors, or gases—of different temperatures. Depending on the type of heat
exchanger employed, the heat transferring process can be gas-to-gas, liquid-to-gas,
or liquid-to-liquid and occur through a solid separator, which prevents mixing of the fluids,
or direct fluid contact.
23
Design Specification
Equipment Category Treatment
C. Condenser
24
Condensers are employed in power plants to condense exhaust steam from
turbines and in refrigeration plants to condense refrigerant vapours, such as ammonia
and fluorinated hydrocarbons. The petroleum and chemical industries employ
condensers for the condensation of hydrocarbons and other chemical vapours. In distilling
operations, the device in which the vapour is transformed to a liquid state is called a
condenser. All condensers operate by removing heat from the gas or vapour; once
sufficient heat is eliminated, liquefaction occurs.
Design Specification
Equipment Category Treatment
Size 3 m W / 12 m L
D. Turbine
A turbine is a device that harnesses the kinetic energy of some fluid – such
as water, steam, air, or combustion gases – and turns this into the rotational motion
of the device itself. These devices are generally used in electrical
generation, engines, and propulsion systems and are classified as a type of
25
engine. Coal-fired plants produce electricity by burning coal in a boiler to produce
steam. The steam produced, under tremendous pressure, flows into a turbine,
which spins a generator to create electricity. The steam is then cooled, condensed
back into water and returned to the boiler to start the process over.
Design Specification
Equipment Category Process
Capacity 60 MW
Size 15 m Diameter
26
E. Flash Tank
A flash tank serves as a collection system for a variety of condensate drain lines.
Flash tanks receive high pressure condensate which is then exposed to a low pressure
steam source. When this occurs, a certain percentage of condensate will “flash” to steam
at the lower pressure. This steam can be “recycled” on other low pressure steam heat
transfer devices. Smaller in size than traditional flash tanks, flash separators utilize
cyclonic action to instantly separate steam and condensate.
Design Specification
Equipment Category Collection
Capacity 5000-7000 L
27
Manufacturer/ Model Qingdao Inc/ Hammer
F. Pumps
Pumps collect saturated water from the condenser hot well and pumps it either to
a deaerating heater or back into the boiler feed pump. It operate at extremely low suction
pressures. For this reason these pumps are often located at the lowest level of any pump
in the power plant and installed in a suction can that is below ground level.
Design Specification
Equipment Category Transportation
Requirement 1000 Pa
28
Capacity 1000-3000 Pa
G. Separator/Evaporator
Design Specification
Equipment Category Treatment
Requirement 50m3 /h
Capacity 80 m3/h
29
Size 10x20 m
H. Economiser
30
Design Specification
Equipment Category Process/Treatment
Size 10x15x8 m
31
I. Feed Water Tank
Design Specification
Equipment Category Treatment
32
Size 10x15 m
An air separation plant separates atmospheric air into its primary components,
typically nitrogen and oxygen, and sometimes also argon and other rare inert gases.
The most common method for air separation is fractional distillation. Cryogenic air
separation units (ASUs) are built to provide nitrogen or oxygen and often co-produce
argon. Other methods such as membrane, pressure swing adsorption (PSA) and vacuum
pressure swing adsorption (VPSA) are commercially used to separate a single
component from ordinary air. High purity oxygen, nitrogen, and argon, used
for semiconductor device fabrication, require cryogenic distillation. Similarly, the only
33
viable source of the rare gases neon, krypton, and xenon is the distillation of air using at
least two distillation columns.
Design Specification
Equipment Category Process
Size 13x13x10 m
K. Generator
34
Figure 26. Generator
Design Specification
Equipment Category Electrical
Requirement 500kVA
Capacity 25 to 800kVA(60Hz)
Size 10 x 8 meters
35
L. Coal Burner
A coal burner (or pulverized coal burner) is a mechanical device that burns pulverized
coal (also known as powdered coal or coal dust since it is as fine as face powder in
cosmetic makeup) into a flame in a controlled manner. Coal burner is mainly composed
of pulverized coal machine, host of combustion machine (including combustion chamber,
automatic back and forth motion system, automatic rotation system, the combustion air
supply system) control system, ignition system, the crater and others.
Design Specification
Equipment Category Treatment
36
Size 12x 16 meters
M. Coal Boiler
The basic idea of a firing system using 37ulverized fuel is to use the whole volume of
the furnace for the combustion of solid fuels. Coal is ground to the size of a fine grain,
mixed with air and burned in the flue gas flow. Biomass and other materials can also be
37
added to the mixture. Coal contains mineral matter which is converted to ash during
combustion. The ash is removed as bottom ash and fly ash. The bottom ash is removed
at the furnace bottom.
Design Specification
Equipment Category Treatment
38
N. Coal Pulvurizer
Pulverizers (coal pulverizer) are used to pulverize pieces of coal into fine particles
(100μm) before placing into a boiler, to ensure efficient combustion. Pulverizers have
three functions, pulverization, drying and classification. The classification function plays
the important role of ensuring that only fine particles of the pulverized coal are sent to the
boiler. Within a rotating-type classifier, fine particles are passed through while coarse
particles are eliminated by utilizing the relative balance of centrifugal force and centripetal
force produced by a blade rotating at several dozen rpm and the flow of air.
Design Specification
Equipment Category Treatment
39
D. Mass Balance and Energy Balance Computations
Mass(Steam) Pressure
State Point Enthalpy kJ/kg Temp °C
kg/s (bar a)
3 200 126.6531 30 10
4 200 126.6531 30 10
5 60 129.3848 30 40
6 140 129.3848 30 40
7 140 129.3848 30 40
8 60 633.8126 150 30
9 200 129.3848 30 40
10 80 125.7458 30 0.05
17 55 3069.2941 350 50
Table 16. Mass Balance Calculations: Mass and Heat Balance for each State Point
40
Diagrams Calculations
m1 = m2
m2 = m3
Pump P-101
200 kg/sec = 200 kg/sec to
m2 m3
Polishing Plant
m3 = m4
m4 = m5 + m6
m6
200 kg/sec = 60 kg/sec to Air
Pump P-102 Separator unit + 140 kg/sec to
m4 m5
E-102
m6 = m7
41
Air Separator Unit m5 = m8
m5 System m8
60 kg/sec = 60 kg/sec to Low
Pressure Heat Exchanger E-103
m7 + m8 = m9
140 kg/sec to 60 kg/sec = 200
m10 kg/sec to Heat Exchanger E-103
Heat Exchanger
m9 E-103
m11 m9 + m10 = m11
200 kg/sec + 80 kg/sec = 280
kg/sec to Feed Water
Tank
m11 = m12
280 kg/sec = 280 kg/sec to Boiler
Feed water tank
Feed water Pump
m11 m12
Tank
m12 = m13
Boiler Feed water
280 kg/sec = 280 kg/sec to
m12 Pump m13
High Pressure Heater
Pump
Tank
42
m17
Tank
m14 = m15
Boiler m15
335 kg/sec = m16
= 335 kg/sec to High
m14 m15 Pressure Turbine
370 kg/sec = 370 kg/sec to
High Pressure Turbine
Tank
m16
m15 = m16 + m17
High Pressure
335 kg/sec = 55 kg/sec to E-
m15 Turbine m17
104 + 280 kg/sec to Reheater
E-105
Tank
m16 = m18
280 kg/sec = 280 kg/sec to
Heat exchanger
m16 m18 Intermediate Pressure Turbine
E-105
Tank
43
m18 = m19
Intermediate
Pressure Turbine 280 kg/sec = 280 kg/sec to
m18 m19
Low Pressure Turbine
Tank
m20 = m11 + m1
Low Pressure
Turbine 280 kg/sec = 80 kg/sec + 200
m19 m1
kg/sec to condenser
Tank
m10
44
Energy Balance
= 0.18146 MW Wp1 h3
= 0.18146 MW
Wp2 h5
h12
Wp = W p1 + W p2 + W p3
Wp = 114.859076 MW
45
Turbine Work h15
= 278.136095 MW h16 W T1
h18
Turbine
WT2 = (h18 – h17)*(m18)
= 360.666936 MW
WT = W T1 + WT2
= 278.136095 MW + 360666.936 MW
WT = 638.803031 MW
= -0.18146 MW Qcondenser h2
46
Heat Added by Heat exchangers
Total Heat Added = (h5 - h3)*(m6) + (h11 - h10 - h9)*(m9 + m10) + (h14 -h13 - h19)*
Parameters Design
Heat Added 1408.372007 MW
Work of Turbine 600 MW
Work of Pump 114.859076 MW
Net Work 485.140924 MW
Thermal Efficiency 0.344469303
The work produced by the turbine is 600MW and the total mass of steam required
to produce the output is 335 kg/s. The calculations show that design has the thermal
efficiency of 34.4469303%.
47
Fuel Computations
Coal Composition
Hydrogen 4.4100%
Carbon 58.2900%
Nitrogen 1.0000%
Sulfur 0.7300%
Oxygen 16.5000%
Ash 19.0700%
Table 18. Coal Composition
Heat Added
Fuel Consumption = HHV
23166.9739
= 23166.9739
Emission Calculation
= 0.5829 * 75.99028757
48
Mcox = 162.4140416 kg/sec
= 0.0100 * 75.99028757
= 0.0073 * 75.99028757
Ash Disposal
= 0.1907 * 75.99028757
Air-Fuel Ratio
𝑂
A/F = 11.5C + 34.5( H - 2 ) + 4.3S
0.1650
= 11.5 (0.5829 + 34.5(0.0441- ) + 4.3S
2
= 7.54 kgair/kgfuel
49
Pulverized coal fired boilers run with an average of 20% excess air to burn the fuel
completely:
= 7.54 * 0.2
= 7.74 kgair/kgfuel
50
Chapter IV
ECONOMIC ANALYSIS
This chapter presents all the required calculations and data regarding the
financial aspects of the proposed 600MW Coal-Fired Power Plant Located at Brgy.
Bulacan, Mabini Batangas. These calculations and data will be used to know if the plant
is economically viable.
51
Timeline of Construction Plant
PROJECT SCHEDULE
YEAR
Planning of Plant
Design and
Feasibility Study
Approval of Loan
from Banks
Acquisition of
Land
Registration of
Corporation and
Securing of the
52
Required Permit
Canvassing and
Selection of
Machinery
PROJECT SCHEDULE
YEAR
Procurement
and
Construction
Stage
53
Commissionin
g and Dry-run
Stage
Hiring and
Training of
Employees
Operation
Stage
54
B. Building Cost
According to the Philippine Statistics Authority (PSA), the current cost per square
meter estimate is Php 9,000 in the region of CALABARZON and Php 4,200 in
Mabini, Batangas.
Source: https://estimationqs.com/building-costs-per-square-metre-in-the-
philippines/#:~:text=The%20region%20of%20Calabarzon%20comes%20in%20at%
209%2C000%20per%20m2
1. Plant Utilities
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (600m2) (Php 4,200 / m2)
Building Cost = Php 2,520,000.00
2. Production Building
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (1300m2) (Php 4,200 / m2)
Building Cost = Php 5,460,000.00
3. Administration Building
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (400m2) (Php 4,200 / m2)
Building Cost = Php 1,680,000.00
4. Warehouse Building (Raw Materials Storage)
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (700m2) (Php 4,200 / m2)
Building Cost= Php 2,940,000.00
5. Laboratories
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (400m2) (Php 4,200 / m2)
Building Cost= Php 1,680,000.00
55
6. Maintenance Building
Building Cost = (Total m2 of the building) (Php 4,200 / m2)
Building Cost = (450m2) (Php 4,200 / m2)
Building Cost= Php 1,890,000.00
7. Fire House
Building Cost = (Total m2 of the building) (Php4,200/ m2)
Building Cost = (300m2) (Php 4,200/ m2)
Building Cost= Php 1,260,000.00
8. Canteen
Building Cost = (Total m2 of the building) (Php 4,200/ m2)
Building Cost = (250m2) (Php 4,200/ m2)
Building Cost= Php 1,050,000.00
9. Gymnasium
Building Cost = (Total m2 of the building) (Php 4,200/ m2)
Building Cost = (400m2) (Php 4,200/ m2)
Building Cost= Php 1,680,000.00
10. Clinic
Building Cost = (Total m2 of the building) (Php 4,200/ m2)
Building Cost = (200m2) (Php 4,200/ m2)
Building Cost= Php 840,000.00
56
Plant Utilities 600 2,520,000.00
57
C. Vehicle Cost
1. Trailer truck
The cost assumption of one (1) Trailer Truck from Hebei Chenyang
Source: www.alibaba.com
2. Tanker Truck
The cost assumption of one (1) Tanker Truck from Qingdao Transauto
Source: www.alibaba.com
58
3. Forklift
The cost assumption of one (1) Forklift from Jiangsu Jingxin Lifting
Source: www.alibaba.com
4. Fire Truck
Source: www.alibaba.com
59
Forklift 2 354,855.00 709,710.00
D. Pipeline Construction
Pipeline construction follows once the design is completed and all approvals are
granted. The construction includes the process of landholder engagement and
access approvals, surveying and fencing, clear and grade, stringing, bending,
welding and nondestructive testing, joint coating, trenching, lowering in and
padding, backfilling, hydrostatic testing, restoration and signage.
This includes cost for fittings, pipe, valves supports, piping covers labor and other
terms involved in the complete construction of all piping used directly in the process.
According to the table of piping costs, the total pipeline construction cost follows the
formula: Total Pipeline Construction Cost = Material Cost + Labor Cost
60
Material Cost 9% 233,596,514.75 21,023,686.3275
E. Equipment Cost
8 23923000.00 191,384,000.00
Pumps
1 3,225,090.00 3,225,090.00
Separator/Evaporator
61
Economiser 1 3,588,750.00 3,588,750.00
F. Installation/Commissioning
62
Php1,230,121,336.00 47% 578,157,027.90
G. Engineering Cost
Engineering Cost should be 30% of total purchased equipment cost. For the
estimation,
63
H. Fire and Safety Cost
System
(Set)
Equipment (Set)
I. Labor Cost
Operating Labor
For every payroll period, employers must withhold (i.e. deduct) taxes from
the payroll of their employees. Withholding tax is a mandatory tax on the gross
64
value of an employee’s salary. “Gross” means the value before any payroll
deductions have been made
Table 28. Operating Labor Cost for Technical Department
65
Production 1 80,000.00 960,000.00 198,219.00 761,781.00
Manager
Production 35 23,000.00 276,000.00 12,671.00 9,216,515.00
Operators
Process 5 30,000.00 360,000.00 32,011.00 1,639,945.00
Engineer
Process 5 23,000.00 276,000.00 12,671.00 1,316,645.00
Technicians
TOTAL 46 156,000.00 1,872.000.00 255,572.00 12,934,886.00
66
Position Number of Monthly Annual Annual Tax Total Annual
Employees Salary Salary (Php) Deduction Operating Cost
(Php) (Php) (Php)
Human
Resource 1 80,000.00 960,000.00 198,219.00 761,781.00
Manager
Human
Resources 6 23,000.00 276,000.00 12,671.00 1,579,974.00
Officers
Medical 5 18,000.00 216,000.00 5,339.00 1,053,305.00
Officer/Staff
TOTAL 12 121,000.00 1,452,000.00 210,890.00 3,395,060.00
461,353.00
67
Position Number of Monthly Annual Annual Tax Total Annual
Employees Salary (Php) Salary (Php) Deduction Operating
(Php) Cost (Php)
Maintenance 1 80,000.00 960,000.00 198,219.00 761,781.00
Manager
Maintenance 10 23,000.00 276,000.00 12,671.00 2,633,290.00
Technician
TOTAL 11 103,000.00 1,236,000.00 210,890.00 3,395,071.00
68
Logistic 1 30,000.00 360,000.00 32,011.00 327,989.00
Supervisor
TOTAL 4 166,000.00 1,992,000.00 291,536.00 1,700,464.00
The annual maintenance costs for plants are high, typically 5 to 15 per cent
of the installed capital costs according to Design and Calculation of Chemical
Engineering Projects.
69
Table 37. Total Maintenance and Repair Cost
Php1,230,121,336.00 5% 615,060,668.70
K. Other Utilities
This cost category covers other utilities needed in the operation process.
These will normally be supplied from a central facility and this will include water, coal
and compressed air and electricity. According to Design and Calculations of Chemical
Engineering Projects, utility costs amount to 10 to 20 percent of the total purchased
equipment cost. For the estimation of Utility Cost, Let Utility Cost = (20%) (Total
Purchased Equipment Cost).
70
L. Product Prices
The target plant production for the proposed 600 MW Coal-Fired Power Plant is
12.8M tons per year.
Selling Price per Plant Capacity Annual Plant Annual Total Product
MW per day (MW) Capacity (MW) Price of Coal
Equipment Cost)
Pipeline Construction Cost 37,375,442.36
71
Table 41. Total Indirect Cost
(Php)
CAPITAL (Php)
72
Equipment Cost 1,230,121,336.00
Variable Cost:
TOTAL 24,011,367,336.00
MANUFACURING
73
Table 45. Total Variable Cost
Materials)
74
Insurance = Php 2016567975.00
Total Investment = Total Variable Cost + Total Fixed Capital Investment + Taxes
75
Price per MW: Php 8,118,000.00
• Payback Period
Building 21,630,000.00
Engineering 369,036,400.80
Equipment 1,230,121,336.00
76
Installation/Commissioning 578,157,027.90
Labor 35,226,961.00
Vehicle 14,154,078.00
CHAPTER V
a. Air Emission
Main Stack emissions from coal-fired power plant are sulphur dioxide, nitrogen
dioxide, carbon dioxide and traces of other gases that are present in insignificant
concentrations.
The NOx emissions are controlled by the low Nox firing system and the Selective
Catalytic Reduction System (SCR), using anhydrous ammonia. The purpose of the SCR
is to reduce the Nox in the flue gas by mixing vapour ammonia with flue gas at the boiler
outlet. The SCR System is composed of three layers of catalyst within a catalyst chamber.
77
The reduction reaction takes place as the gases pass through the catalyst chamber with
the Nox being reduced to nitrogen and water vapour.
Particulate Matter
Electrostatic Precipitator cleans the flue gas from the dust/fly ash released during
the combustion process in the boiler. The flue gas is routed to the ESP through ductwork
and an inlet nozzle. At the inlet of the ESP, gas distribution screens are provided to ensure
uniform distribution of the flue gas over the entire cross section of the ESP. While the dust
loaded flue gas passes through the ESP, the dust is precipitated by charging the dust
particles under the influence of high voltage electric field created by the transformer
rectifier sets. The collected dust is then rapped off from the electrodes through the rapping
mechanism.
The purpose of the de-ashing system is to remove and collect the ash produced
by the coal combustion in the boiler furnace. There are two types of ash: bottom ash; and
fly ash.
Bottom ash
For bottom ash, the heaviest and largest ash is collected at several locations:
bottom ash from the furnace, ash collected under the economizer and ash collected under
the inlet duct to the SCR. A submerged scraper conveyor is provided under the furnace
78
bottom hopper section for the removal of the furnace bottom ash. This uses a drag chain
and flight conveyor of heavy construction submerged in a water trough below the furnace.
The ash is evacuated mechanically on a continuous basis so there is no long-time storage
in the water impoundment beneath the furnace. After discharge from the submerged
scraper conveyor in a dewatered condition, ash is dumped into the diverter grizzly screen
for further particle size reduction. Finally, the bottom ash is transported by conveyors to
an elevator. From the top of the elevator a conveyor delivers the ash into the Bottom Ash
Silo. The silo is emptied by truck.
Fly ash
Fly Ash Fly ash is driven within the flue gas is collected and removed in the ESP
and collected in the ESP hoppers. From the hoppers, the fly ash is transported by the fly
ash handling Fly ash is delivered in the fly ash silo.
Waste Water Treatment systems shall be designed and installed to treat all
industrial waste generated from the plant during operation. The waste water treatment
plant shall be designed to cater to regular waste during operation and irregular waste
during outages.
Discharge water quality from each of the treatment system shall be monitored for key
constituents of concern in accordance with constituents treated and the regulatory
requirements. Waste water shall be rerouted back to the waste water treatment system
for further treatment should the treated water quality fail to meet the required limits.
The waste water treatment system shall cater to all oily and chemical waste water from
the entire Plant including but not limited to the boiler, steam turbine, transformers, pumps,
tanks, fuel and chemical unloading facilities, vessels drainage and heat exchangers
drainage, onsite and external ash pond leachate and ash pond rain runoff.
79
The treated waste water monitoring location should be selected with the objective of
providing representative monitoring data. Effluent sampling stations shall be located at
the final discharge, as well as at strategic upstream points prior to merging of different
discharges.
The company will provide information on this, confirming that solid wastes will be
sent to landfills of appropriate design for the materials concerned, and that monitoring to
guard against environmental harm.
Any industrial effluent generated from the Plant shall be treated to comply with
DENR Administrative Order No:2016-08 on Water Quality Guidelines and General
Effluent Standards (Class SC) IFC 2008 EHS Guideline for Thermal Power Plants) before
discharging downstream the treatment facility. For surface waters three types of
monitoring are required by the company:
• Operational – to help classify those water bodies which are at risk of failing to meet good
status; and
• Investigative – to ascertain the cause and effects of a failure to meet ‘good status’ where
it is not clear
• Hydro-morphology;
80
• Priority and priority-hazardous substances.
The Plant design shall comply with the following requirements for effluents:
Effluent Treatment
Chemical effluents that mainly arise from the demineralized water production plant
and the polishing plant are neutralized before being discharged to the Waste water
treatment plant (WTP).
81
In the WWTP the chemical and industrial effluents are combined and their pH
raised through the addition of hydroxide.
The effluents are then sent to the precipitation tank where sulphide addition along
with the raised pH leads to the conversion of soluble heavy metal salts to insoluble
salts which precipitate.
The precipitation process generates very fine particles which are hard to remove,
so the stream is sent to the flocculation tank where the addition of chemical coagulants
in conjunction with low-sheer mixing promotes contact between the particles, and
allows them to clump together into larger heavier particles which can settle at a faster
rate. The mixture is sent to a sedimentation tank where the heavy metal containing
floc settles to the bottom and can be removed as a sludge. The sludge is sent to a
filter press to recover the solids which are sent for off-site treatment.
The liquid from the sedimentation tank passes to a buffer tank before the biological
treatment section where the ammonia in the effluent is treated in a two-step process.
Liquid from the buffer tank passes through a heat exchanger and undergoes pH
adjustment with acid addition before entering the Nitrification basin. Here the ammonia
is converted to nitrite and then to nitrate – the nitrification process. This process is
mediated by bacteria which require oxygen for growth and the metabolism of nitrogen,
and so must proceed under aerobic conditions.
Following the denitrification process a Flotation basin separates the organic solids
generated in the process from the effluent as a sludge which is sent to a filter press
for solid separation. Clear effluent is released to the water discharge point.
82
Treated water is mixed with cooling water effluents (mainly the cooling tower
blowdown) before being discharged to the Drax water discharge system. The sludge
are removed by truck.
Safety
83
The layout design of the detection systems was informed by a scenario based
identification of potential hazards. The layout design process included:
Identification of CO2 process hazard areas (internal and external) and non-
process fire and utility hazard areas;
Determination of the hazard characteristics; and
Determination of required detector type, principle of operation and location.
Diverse detector types will be provided including for detection of gas leak, gas
migration and smoke (instrument building). Primary emergency communication to
personnel will be through the local alarm system. Audible alarms will be provided
including separate alarm tones for fire (smoke) detection, CO2 detection and
evacuate facility. Audible alarms are supplemented by visual alarms at process
piping areas. Personnel will have UHF hand portable radios. Communications with
third parties will be facilitated by the analogue telephone located in each instrument
building.
84
Off-site Emergency Plan
The external emergency plan details the roles to be carried out by emergency
services, local authorities and other external organisations in the event of a major
accident. This includes the arrangements established to help with the emergency
response on site. The degree of planning should be proportionate to the probability
of a major accident and consequences of the accident occurring. The responsibility
for the Off-site emergency lies with the Local Authority. However the facility
operator has to liaise with the local authority and provide information to support the
off-site emergency plan.
The 1982 United Nations Convention on the Law of the Sea (Article 1.1.4)
defines marine pollution as “the introduction by man, directly or indirectly, of
substances or energy into the marine environment, including estuaries, which
results or is likely to result in such deleterious effects as harm to living resources
and marine life, hazards to human health, hindrance to marine activities, including
fishing and other legitimate uses of the sea, impairment of quality for use of sea
water and reduction of amenities” (Nordquist & Nandan, 2011). Besides, “marine
contamination changes the physical, chemical, and biological characteristics of the
oceans and coastal zones, and potentially threatens marine organism,
ecosystems, and biodiversity and affects thus the quality and productivity of marine
ecosystems” (Wilhelmsson, Thompson, Holmström, Lindén, & Eriksson-Hägg,
2013). In this regard, the contamination causing damage or negative impact on
marine ecosystems is called pollution. The final impact of pollution on marine
resources depends on the intensity (acute or chronic), form and location of the
contamination. Likewise, some species, ecosystems and marine environments are
more sensitive to pollution than others. “Coal is an organic sediment that contains
inorganic constituents such as heavy metals, which can be very toxic to marine
85
organisms” (Siboni, Fine, Bresler, & Loya, 2004). Therefore, it could be
hypothesized that unburnt coal could be a marine pollutant. For example, a study
carried out at the contiguous coal shipping terminal at the Lambert’s Point Docks
in Norfolk, Virginia confirmed that “along with the particulate coal, arsenic
associated with the coal is also enriched in these soils by 2 to 20 times over upper
crustal abundances, and by ∼five times over estimated background soil As
concentrations” (Bounds & Johannesson, 2007). It has long been recognized that
“arsenic is one of the most toxic elements and has serious effects on plants,
animals and human health” (Kucuksezgin, Gonul, & Tasel, 2014).
For protection of the plant against fire, all yards and plant will be protected by any
one or a combination of the following systems:
Hydrant system
Automatic high velocity and medium velocity sprinkler system
Existing fire fighting facilities would be integrated with the proposed system
to ensure central control from the existing fire station
Portable and mobile chemical extinguishers
In view of vulnerability to fire and its importance in the running of the power station,
effective measures are to be taken to tackle fire in the following susceptible areas:
For containment of fire land preventing it from spreading in cable galleries, unitwise
fire barriers with self-closing fire resistant doors will be provided. The ventilation systems,
86
if provided in the cable galleries, would be so interlocked with the fire alarm system that
in the event of a fire the ventilation system is automatically switched off. Also to avoid
spreading of fire, all cable entries/openings in cable galleries, tunnels, channels, floors,
barriers etc. would be sealed with non-inflammable/fire resistant sealing material.
a. Safety – prevention
Personnel Safety
All easily accessible moving parts in the plant will be securely fenced.
There will be arrangement for prompt power cut from transmission
equipment, if necessary.
Every hoist, crane etc. will be properly maintained and examined at intervals
All working places will have safe means of access and exit.
Emergency fresh water bath will be provided in the hazardous chemical
handling areas e.g. storage areas and operating unit areas
All personal safety equipment like gloves, helmet, goggles etc. will be worn
in the required place.
Boilers will be examined in proper manner by proper authority as per
statutory requirement
87
c) Asbestos safety boots Striking by objects, fall of
objects and stepping on
sharp or hot objects
Heat radiation, stepping hot
or sharp objects and
stepping on sharp or hot
objects
EYE a) Spectacle type goggles Foreign bodies entering the
with plain shatter proof lens eyes and reflected arc rays
HEAD a) Fibre Helmet Fall of objects/hitting
against objects during
construction, maintenance
etc
EAR a) Ear plugs or muffs High noise level
NOSE a) Dust protection mask Fine dust particles
Table 46. Personnel Safety
C. Health – exposures
Occupational exposures
88
turbine and boiler areas were found to be the heated zone in the plant, besides
furnace operations.
The following measures will be adopted for protecting health and ensuring
safety of workers.
89
CHAPTER VI
PROJECT MANAGEMENT
This chapter contains the management of the proposed project plant as well as the
time frame of the project plant and the necessary measures to maintain and assure the
quality of the electricity produced.
I. PRELIMINARIES
a. Planning Stage
The planning stage is one of the most crucial aspects of deciding how a
project will be carried out and operated. All necessary planning, materials,
equipment, and contrast will be addressed during this stage. The selection
of the planning team and plant projects would be based on the design as
well as the plant's feasibility.
The site preparation is also included in the planning stage. The necessary
legal documentation for the proposed plant location property, as well as
the legal permits required before the plant can be built, are part of the site
planning stage. It would be easier for the plant to operate in the long run if
the rules are followed and adequate environmental protection is given
ahead of time.
Another aspect of the planning stage is the calculation of the plant's time
schedule and expense in order to identify the tasks that must be
completed. As well as identifying the deliveries of the plant's necessary
equipment. It will also assist in having a logical sequence of events and
maximizing the allotted time on the construction time frame once it begins.
b. Basis of Design Stage
The design stage will be built around the process's optimal efficiency. This
will include the production volume and pace. Benefit maximization can be
greatly enhanced by optimizing the efficiency of the process flow. The
design stage also takes into account the plant's feasibility, ease of access
to each site, and the operation. The area can be reduced and the plant's
protection ensured by providing an open venue. Provided that the plant
90
should have an assured danger and health protection, the safety and
comfort of the plant employees should also be considered as the basis of
the design. A facility is available for the employees' health conditions as
well as any potential injuries that might occur.
A facility for an office, a guard house, and parking space is also included
in the design layout. The water supply and treatment waste water
collection plant is situated near the seashore. This can also be used to
move raw materials, machinery, and finished goods.
c. Design stage layout
At this stage, there is a proposed design layout for the plant, that can be
used as a guide in selecting the best design layout to be provided by the
selected team. Bidding will be used to pick the winning team.
The requirements for choosing a design layout are determined by the
plant's efficiency and the cost. The first step in construction management
is to complete the design stage layout. The building will begin after the
final design stage layout is completed.
91
This stage also includes the requirements for the process
equipment that will be installed in the plant, as well as the reliability,
volume, and dimensions of the equipment.
Quality Assurance
Quality Assurance (QA) will be undertaken to ensure that project activities are
planned, controlled, performed, verified and documented in such a way that all specified
contractual requirements are met.
All project activities scope will comply with the relevant codes and standards in
force with safety, legal and other regulations (local and national), acts and legislation in
force in the Philippines.
92
The plant will be designed in accordance with Good Industry Practice (GIP) to
enable it to be constructed, installed, commissioned, operated and maintained in a
prudent and safe manner, compliant with Philippine regulations and legislation.
The project activities will ensure that a safe and operationally robust design is
achieved that allows the project to be executed in accordance with the project
programme, within budget and to meet its operational performance objectives.
Quality Control
Quality requirements should be clear and verifiable, so that all parties in the project
can understand the requirements for conformance.
93
CHAPTER VII
SUMMARY OF FINDINGS, CONCLUSION AND RECOMMENDATION
This chapter presents the summary of findings, conclusion and
recommendation on the design for the proposed 600 MW Coal-Fired Power Plant.
Summary of Findings
After the analysis and evaluation of all the data gathered. The proposed
location of 600 MW Coal-Fired Power which is at Barangay Bulacan, Mabini,
Batangas was to be feasible and advantageous for the construction and operation
of the proposed power plant. The transmission of the generated electricity of the
proposed power plant for the Luzon Grid will be the responsibility of the National
Grid Corporation of the Philippines (NGCP) and this company will distribute the
generated electricity to the customers of the Batangas province electric
cooperatives namely; BATELEC I, BATELEC II, First Bay Power Corporation
(FBPC) and Ibaan Electric Engineering Corporation (IEEC) will transmit the
generated electricity to within reach provinces.
Conclusion
Recommendation
94
1. Further research and evaluation of the present technologies, equipment, and
operation of existing power plants are essential for more advanced and progressive
design.
2. The proponents should be more familiar with each of the equipment specifications
and it’s functions which are important in designing and constructing a power plant.
4. Additional information through consultation with the concerned person helps the
proposed power plant to enhance the design and make it possible and presentable
for the actual plant construction.
5. Economic analysis must be done for the designed power plant for a better
presentation of profits to attract more investors.
95
Republic of the Philippines
BATANGAS STATE UNIVERSITY
Gov. Pablo Borbon Main Campus II, Alangilan, Batangas City
College of Engineering, Architecture and Fine Arts www.batstate-u.edu.ph Telefax: (043) 300-4404 locs. 106-118
96