Method of Statement For Concrete Repair
Method of Statement For Concrete Repair
PROJECT
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
Employer
Engineer
CONSTRUCTION SUPERVISION
1
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
2 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
Method Statement
:SCOPE
The RME seeks through this method statement of this documents is to identify and clarify
the mode of action for the repairing surface of structural elements from cracks and honey
combs and resist any harmful effect, also determine the ideal way and appropriate to deal
with the repairing material and how their implementation and use trained person to deal
with it so be optimally implemented after.
:SPECIFICATION REFERENCES
- Egyptian code of practice for design and construction reinforced concrete ECP 203-
2017.
- ACI 304, 318.
- All approved repairing material data sheets
- Project specification volume III, division 3, section 033000
- Contract /IFC drawings.
- Manufacture’s recommendation according to approved Material Submittals.
RESPONSIBILITIES
The direct personnel responsible for the works are Section Engineers; the section engineer is responsible
for compliance by his subordinates with the contents of this method statement, for ensuring that all
.parties involved in supervision of the works are in receipt of all relevant information
The section engineer will ensure the required degree of safety to personnel and protection to property
.is maintained at all times
2
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
3 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
3
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
4 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
4
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
5 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
o Assigning site engineers to specific task and ensuring that tasks are performed
according to the projects plans and specifications.
Laboratory Technician: -
Site Engineers: -
1.0 METHODOLGY
A- Cracks appears in concrete surface
o All defective areas will be delineated and marked out on site by the
site supervisor.
o The first steps are to clean the cracks that have been
contaminated; to the extent this is possible and practical.
Contaminants such as oil, grease, dirt or fine particles of concrete
prevent grouting penetration and bonding, and reduce the
effectiveness of repairs. Preferably, contamination should be
removed by vacuuming or flushing with water or other especially
effective cleaning solution.
5
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
6 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
o Putting the grout in the bucket and adding the water slowly until the
basis be elastic and suitable to be stretched.
o The grout should be putted in stages for defective areas with more
than 5cm.
o For less than 5cm the grout shall be done in one stage.
6
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
7 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
1.3 Final:
o According to previous steps (RME) cover all steps of the job works
and achieved its goals in repairing concrete surface from honey
combs and cracks and showed the ideal way to protect the work
and repair it in safety manners.
7
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
8 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR
3.0MATERIALS
Basf products for concrete repair MS-0036
Verification Point
Contractor Process Step S/N
Consultant
Q/C construction
5.0Safety:
All safety and health regulations shall be strictly followed and any case
disregarding the safety.