Method of Statement For Concrete Repair

This document provides a method statement for concrete repair works on the ZED Towers Project in Sheikh Zayed City, Egypt. It outlines responsibilities for the project manager, construction manager, engineers, supervisors, HSE officer, and QA/QC engineer to ensure repairs are conducted safely and per specifications. The methodology section describes implementing cracks repairs by delineating defective areas, cleaning cracks, applying epoxy injection, and finishing repairs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
793 views9 pages

Method of Statement For Concrete Repair

This document provides a method statement for concrete repair works on the ZED Towers Project in Sheikh Zayed City, Egypt. It outlines responsibilities for the project manager, construction manager, engineers, supervisors, HSE officer, and QA/QC engineer to ensure repairs are conducted safely and per specifications. The methodology section describes implementing cracks repairs by delineating defective areas, cleaning cracks, applying epoxy injection, and finishing repairs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

ZED Towers PROJECT‐PHASE 01B

SHEIKH ZAYED CITY‐EGYPT


01 Rev MS-07 Ref METHOD STATEMENT
1 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

PROJECT
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT

Employer

Engineer

CONSTRUCTION SUPERVISION

1
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
2 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

Method Statement

CONCRETE REPAIR Works


(Cracks appears in concrete surface, Honeycomb in concrete repair& Broken concrete edges)

:SCOPE

 The RME seeks through this method statement of this documents is to identify and clarify
the mode of action for the repairing surface of structural elements from cracks and honey
combs and resist any harmful effect, also determine the ideal way and appropriate to deal
with the repairing material and how their implementation and use trained person to deal
with it so be optimally implemented after.

:SPECIFICATION REFERENCES
- Egyptian code of practice for design and construction reinforced concrete ECP 203-
2017.
- ACI 304, 318.
- All approved repairing material data sheets
- Project specification volume III, division 3, section 033000
- Contract /IFC drawings.
- Manufacture’s recommendation according to approved Material Submittals.

- Project HSE Plan and Procedures.

RESPONSIBILITIES
The direct personnel responsible for the works are Section Engineers; the section engineer is responsible
for compliance by his subordinates with the contents of this method statement, for ensuring that all
.parties involved in supervision of the works are in receipt of all relevant information

The section engineer will ensure the required degree of safety to personnel and protection to property
.is maintained at all times

The Project Manager / Construction Manager shall be responsible to:

o Communicate this method statement to all Engineers, Senior Surveyor,


Surveyors, supervisors and employees.
o Provide them with the information they need to carry out their responsibilities.

2
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
3 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

o Enforce the application of this document once it has been effectively


communicated to employees.
o Responsible for the safe execution of the works.
o Project Engineer shall be responsible to:
o Implement and maintain a successful completion of the work.
o Ensure that this method statement is being implemented correctly.
o Ensure that sufficient resources are allocated to enable full compliance with this
document.
o Ensure that all construction works are being carried out as per project
specifications and IFC drawing.
o Keep all his personnel fully aware of the quality control principles and he shall
provide all support to the project Quality Control Department.
o Responsible for the safety and the quality of work carried out by all site
personnel under his control including sub-contractors and suppliers.
o Interpreting contract drawing and specifications and being familiar with all
provisions of the contract and any revisions or amendments.
o Records and control of production documentation.
o Ensure that staff under his control areas are experienced and trained in their
relevant disciplines.
o Designate the competent person to carry out or himself carry out jointly with the
HSE Officer of the area the daily excavation inspection and complete the
checklist and co-sign it with the HSE officer of the area.

Supervisor / Foremen shall be responsible to:


o Directly be in charge in the execution of activities.
o Takes instruction from the Superintendent and communicates directly to
Foreman, Workforce and drivers.
o Ensure also that the working area is safe for the workers and equipment.
o Daily and for each task conduct a STARRT briefing to his work crew to ensure
that the task is properly explained, the hazards associated with each step are
identified and the control measures for these hazards are identified and
implemented.
o Conduct daily Toolbox talks to his workers.

3
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
4 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

HSE officer shall be responsible to:


o Ensure that toolbox talks are conducted as per HSE plan by the activity
supervisor.
o Monitor against the implementation of the requirements of this Method
Statement.
o Provide the required training for the site personnel involved.
o Advise the construction personnel regarding compliance with the project HSE
Plan and Procedures.
o Monitor to ensure compliance with procedures with respect to equipment’s and
related certifications and permits. Stop work activities in case non compliances
are observed and notify the engineer in charge to rectify.

QA / QC Engineer shall be responsible to:


o Discuss inspection schedule and the result with those responsible for works and
recommended necessary corrective actions if applicable.
o Discard or reject products, material and equipment not meeting specifications.
o Inspect test and sample materials or assembled parts or products for defects
and deviations for specifications.
o Observe and monitor production operations and equipment’s to ensure
conformance to specifications and make order necessary process or assembly
adjustment.
o To check and ensure that the work is done as per project specification, method
statement and as per approved shop drawing.
o To ensure that all approved and inspected materials are used.
o To raise NCR and initiate corrective actions if the work done is not as per
approved specification, method statement or as per approved shop drawing.
o Witnessing of all site inspections within their discipline.
o Coordinate all site inspection with the sub-contractors designated site engineer
or section engineer.

4
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
5 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

o Ensure all work is correctly prepared prior to inspection being undertaken.


o Review all inspection reports for compliance.

Senior Site Engineer: -

o Assigning site engineers to specific task and ensuring that tasks are performed
according to the projects plans and specifications.

Laboratory Technician: -

o Sampling of fresh concrete samples as applicable.


o Maintenance of materials prior to testing.
o Testing of hard concrete specimens and reporting of results.

Site Engineers: -

o Notifying Quality Control Engineer when work is ready for


inspection Liaison with Mechanical, Electrical and Plumbing trades
foremen for marking out and installation of embedded items.

1.0 METHODOLGY
A- Cracks appears in concrete surface

1.1 Implementation Steps:

o All defective areas will be delineated and marked out on site by the
site supervisor.

o The first steps are to clean the cracks that have been
contaminated; to the extent this is possible and practical.
Contaminants such as oil, grease, dirt or fine particles of concrete
prevent grouting penetration and bonding, and reduce the
effectiveness of repairs. Preferably, contamination should be
removed by vacuuming or flushing with water or other especially
effective cleaning solution.

5
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
6 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

o All defective concrete will be removed by using appropriate tools


and equipment.

o Putting the grout in the bucket and adding the water slowly until the
basis be elastic and suitable to be stretched.
o The grout should be putted in stages for defective areas with more
than 5cm.

o For less than 5cm the grout shall be done in one stage.

o Tool is used for individual grout on the early stages of one or


several stages by spraying with water first element of cleanliness
and to prevent absorption of water by the concrete.

B- Honeycomb in concrete repair

o Remove loose concrete or loosened aggregate by hammer or


wire brush.
o Prevent the application by large forces such as electrical chippers
to avoid sound concrete damage around the honey comp area.
o Clean any dirt or loose material from the area.
o Wet the cleaned area before applying the repair material.
o Fill small voids and cracks with suitable material as approved non
shrinkage grout.
o If honeycomb covers a large area, you may need to create a
patch hole to ensure proper bonding.
o Place formworks if necessary, and pour the grout.

6
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
7 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

o The filling process should be on a 15mm thickness layer if the


depth of honeycombing is grater than 5cm its recommended to
wait for a while 30min before applying the next layer.
o Repair material strength should match the virgin concrete of the
structural element.

C- Broken concrete edges


o Drill a hole into the center of the break into which you can insert
a steel dowel.
o Clean the broken edges of the concrete element and blow out
the hole, coat the rod and the hole with bonding material, and
pound it in, leaving half its length sticking out.
o Apply approved bonding agent to the broken edges.
o Place formwork for broken edges.
o Filling process by approved non shrinkage grout match with
thickness.
o After 24hrs remove formwork

1.2 Inspection of Isolation:

o Making first inspection after finishing the cleanness of the surface


and make the preparation to accept the material of the repair
(approved grout).
o Making the final view after finishing the repair with the material and
curing of it and the surface should be homogeneous with concrete
surface.

1.3 Final:

o According to previous steps (RME) cover all steps of the job works
and achieved its goals in repairing concrete surface from honey
combs and cracks and showed the ideal way to protect the work
and repair it in safety manners.

2.0PLANT AND EQUIPMENTS


 Wire Bruch.

7
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
8 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

 Hammer & Chisel.


 Application trowels.
 Smoothing floats.
 Mixing container.
 Drill and mixing

3.0MATERIALS
 Basf products for concrete repair MS-0036

 All approved materials submittals from other manufacture.

 Masteremaco 466 MS-008

 Sikacrete 114 MS-009

 Sika rep from (0.5cm till 3.0cm) MS-94

 Sika rep fine from (0.5mm till 5mm) MS-94

 Novo grout 60 S (1cm) MS-79

4.0INSPECTION AND TEST PLANS

Verification Point
Contractor Process Step S/N
Consultant
Q/C construction

Hold Hold Surveillance Material delivery (MIR) 1

Hold Hold Hold Surface preparation before repairing (Civil IR) 2

Hold Hold Hold Final surfaces after repairing (Civil IR) 3


8
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
01 Rev MS-07 Ref METHOD STATEMENT
9 of 8 Page 28/11/ 2020 Date FOR CONCRETE REPAIR

5.0Safety:
 All safety and health regulations shall be strictly followed and any case
disregarding the safety.

 procedures to be immediately reported to safety office and construction


manager.

 Risk assessment will be submitted separately.