Drilling, Completion & Workover Time Definition Guide
Drilling, Completion & Workover Time Definition Guide
1. INTRODUCTION
3. SET UP INFORMATION
4. JOB TYPES
- 4.1 Mobilize/Demobilize Operations
- 4.2 Drilling Operations
- 4.3 Completion Operations
- 4.4 Workover Operations
5. CHANGE OF SCOPE
6. TIME CATEGORIES
7. EXAMPLES
8. LIST of ACRONYMS
1. INTRODUCTION
Critical path activities are those which are necessary to mobilize, drill, complete or
workover a well.
Note: Critical path activity, category types, should focus on what work is being
done and not why the work is being done.
Drill, run string in hole, circulate or pump, run casing, cement, BOP test, log etc.
Run string in hole, circulate or pump, run tubing, place sand control, perforate etc.
Problem events include all problems that occur during mobilization, drilling, completion
and workover operations. Problems should be reported as they occur and may overlap
each other or be nested within other problems. There are two types of problem events:
Examples include:
Rev: 1.0 Issue date: 11/16/04 Time Definitions Document
ExxonMobil Use Only
mud pumps/fluids system repairs during wireline logging, crane repairs which
do not effect drilling operations.
• Problem events which interrupt or delay the planned critical path - non-
productive time (NPT)
Examples include:
Top drive system problem while drilling, weather or environment problem, well
control problem, stuck pipe, string or BHA failure.
Note: Problem events must be created to record NPT. A well will appear to be
problem free unless NPT events are reported. NPT duration is reconciled in
performance analysis reports to allow for overlapping events.
2.3 Milestones
Major points reached during well operations are called milestones. Examples include:
began sidetrack, began out-of-scope work, reached total depth, released rig
Example:
The following illustrates critical path activities with associated problem events. Note that
multiple problem events can occur simultaneously.
Activity
Category Type Problem NPT?
MOB Move or tow rig in or out No
Rig up or rig down rig (or reconfigure)
TRIP Pick up or make up string, BHA or tools
Run string in hole RIG ROV problem
DRLG Drill cement, plugs etc. to clean-out
CIRC Circulate or pump
DRLG Directional survey
Drill (new hole)
CIRC Circulate or pump CIRC Lost circulation Yes
3. SET UP INFORMATION
Information for each well is provided by the engineer in the well program. This
information includes:
Well ID, country, surface location, water depth, rotary height, field name, etc.
The four job types performed on wells are defined below. Each job must be assigned
to one of these types. A well may have more than one job of a particular type, but jobs
may not overlap.
• Mobilize/demobilize - special job type for capturing rig mobilization time and cost
• Drilling - all work to drill to target(s) and prepare well for completion
• Completion - all work subsequent to drilling job to bring well online
• Workover - any other well operations not previously mentioned
Information for each job is provided by the engineer and is found in the well program.
This information includes:
AFE number, AFE cost, rig contractor, target depth, formal well name, etc.
4. Job Types
Use when:
When mobilizing for work on multiple wells, it is recommended that the mobilization job
belong to the first well in the program. The demobilization job may then belong either
to the same well or to the last well in the program.
Note: Dummy or fictitious wells should rarely if ever be utilized. All time and costs
should be associated with a real well.
Start when:
• Charges commence for the Drilling stewarded portion of the well until the original
objective of the well is accomplished and the well is ready to complete.
Note: Drilling around junk or lost hole will usually be included with the current drilling
job unless a regulatory authority requires that the sidetrack receive a new wellbore
identifier. Sidetracking to a new objective will usually trigger the creation of a new
drilling job. Any sidetrack should trigger a sidetrack milestone.
The split between drilling and initial completions jobs is determined as follows:
Example 1
Example 2
The completion job would revert back to a drilling job after the final zone is
suspended or abandoned if the TP&A or P&A is part of the drilling portion of the
AFE.
A workover job includes all activities that are performed on a well other than
mobilization/demobilization, drilling and completion. Operations conducted without a rig
will be recorded under this system if an Operations Supervisor is responsible for the
operation.
Time should commence when charges are incurred by ExxonMobil. The time should
continue until the original objective of the well is accomplished.
5. CHANGE OF SCOPE
The purpose of the Change of Scope classification is to identify time associated with
work not covered under the original well AFE (excluding trouble time to reach original
objective).
When Change of Scope time begins, the "Began out-of-scope work" milestone marks
the associated start time and depth. When the work is complete the "Began in-scope
work" milestone is created. It is the well engineer's responsibility to inform the
Operations Supervisor when work is to be classified as Change of Scope.
After the original objective for which the well was approved has been achieved or once
Drilling Management has changed the original scope of the well, time and costs will be
recorded as Change of Scope.
Examples:
Many times these changes in scope occur before the actual work begins. In these
situations, time and costs can be included in the AFE. In such cases, these operations
should be included in the In Scope activities.
The basic criteria for determining whether a Change of Scope should occur are:
• All changes in scope for completion and workover operations which occur
before operations begin and the AFE is approved should not be considered
as a Change of Scope.
6. TIME CATEGORIES
6.3 Milestones
Milestones
MILE Began in-scope work
(Default milestone - also marks in-scope operations resume)
Began out-of-scope work
(Marks when out-of-scope operations begin - e.g. unplanned
logs, drill deeper, target changes, etc.)
Began sidetrack
(Marks time and depth of wellbore sidetrack)
Began suspension activities
(Marks when suspension operations begin - e.g. after drilling
well and evaluating logs)
Began day work
(Default milestone - also marks when AFE charges on day
work operations resume)
Began footage work
(Marks when rig changes to a footage rate)
Reached total depth
(Marks time and depth when total well depth is reached)
Released rig
(Marks time when rig goes off payroll)
7.0 EXAMPLES
The following section provides examples for common coding problems experienced by
Operations Supervisors.
Generally, a problem event encompasses all time required to resolve the problem and
return the well to the point where the problem occurred. However, not all problems
result in NPT. Therefore, the Operations Supervisor must decide whether a problem
event should be reported as NPT.
While drilling ahead, the MWD fails. After consultation with management, the decision is
made to continue drilling without the MWD and take surveys with single shots as
required.
How should the surveys be coded? Code single shot survey time as DRLG-Directional
Survey. An NPT event should be opened and
coded as DRLG – MWD problem and NPT flag
activated.
Is this problem NPT? YES – Select NPT flag since critical path activities
are impacted.
Note: Start event at first sign of loss and end after circulation is established sufficiently to
continue drilling.
B. Lost returns are experienced in an area where losses are common and planned for in
the well program. The plan calls for treating the losses while drilling ahead.
C. Lost returns are experienced in an area where losses are common and planned for in
the well program. The plan calls for treating the losses via the ‘Fracture Closure
Stress’ – Technique.
OR
A. Mud pump 3 fails when only two pumps are needed to continue drilling.
B. Mud pumps 1 and 2 fail and two pumps are needed to continue drilling.
NPT events may be interrupted to account for certain planned critical path activities.
Example:
While trying to resolve an ongoing equipment problem, a decision is made to to drill ahead.
How should this be coded?
Since drilling ahead is a planned critical path activity, the time spent drilling should
"interrupt" (close out) the repair NPT. If the equipment problem continues to impact drilling
progress, the NPT should reinitiated (open new repair NPT).
This results in more than one NPT event for the same problem. However, the amount of
NPT will reflect only lost critical path time.
Critical path activities should focus on what work is being done and not why the work is
being done.
• Planned wait includes any critical path wait activity which has been built into the well
plan such as:
• Unplanned wait is the critical path activity used when no other activity (tripping,
drilling, circulating, etc.) can be performed. It includes all other waiting in the critical
path and in almost all cases should trigger the creation of an NPT event such as:
8. LIST of ACRONYMS