0% found this document useful (0 votes)
112 views67 pages

Control Center and Data Exchange Requirements: PJM Manual 01

Uploaded by

lisused
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views67 pages

Control Center and Data Exchange Requirements: PJM Manual 01

Uploaded by

lisused
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 67

PJM Manual 01

Control Center and Data


Exchange Requirements

Revision: 26
Effective Date: April 11, 2014

Prepared by
System Operations Division

© PJM 2014

PJM © 2014 1
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Table of Exhibits

PJM Manual 01

Control Center Requirements


Table of Contents
Table of Contents..................................................................................................... ii
Table of Exhibits ..................................................................................................... iv
Approval ................................................................................................................... 1
Current Revision ...................................................................................................... 1
Introduction .............................................................................................................. 2
ABOUT THIS MANUAL ......................................................................................................... 2
Intended Audience .............................................................................................. 2
References ......................................................................................................... 3
USING THIS MANUAL .......................................................................................................... 3
What You Will Find In This Manual ..................................................................... 3
Section 1: PJM Systems .......................................................................................... 4
1.1 ENERGY MANAGEMENT SYSTEM (EMS) ................................................................... 5
1.2 GENERATION MANAGEMENT SYSTEM (GMS) ........................................................... 6
1.3 DATA HISTORIAN SYSTEM ....................................................................................... 6
1.4 ENHANCED ENERGY SCHEDULER (EXSCHEDULE) ..................................................... 6
1.5 TWO SETTLEMENT SYSTEM (EMKT) .............................................................................. 7
1.7 DISPATCH MANAGEMENT TOOL (DMT) .................................................................... 8
1.8 OPEN ACCESS SAME-TIME INFORMATION SYSTEM (OASIS) ...................................... 8
1.9 OTHER ESUITE TOOLS (POWER METER, INSCHEDULES, ELRS, EFTR) ...................... 8
1.10 PLANNING SYSTEMS ............................................................................................... 9
Section 2: Member Control Center Requirements .............................................. 10
2.1 PJM CONTROL CENTER CATEGORIES.....................................................................10
2.2 PJM MEMBER DATA EXCHANGE .............................................................................11
2.3 COMPUTER SYSTEM REQUIREMENTS ......................................................................12
2.3.1 Transmission Monitoring Capability .................................................... 12
2.3.2 Data Backup & Archiving .................................................................... 13
2.3.3 Computer System Security ................................................................. 13
2.3.4 System Maintenance .......................................................................... 13
2.3.5 Expansion Capability .......................................................................... 13
2.3.6 Data Integrity ...................................................................................... 14
2.4 COMMUNICATIONS REQUIREMENTS ........................................................................15
2.5 FACILITIES REQUIREMENTS ....................................................................................15
2.5.1 Environmental Characteristics ............................................................ 16
2.5.2 Power Supply & Conditioning ............................................................. 16
2.5.3 Area Access Security ......................................................................... 17
2.5.4 Information Flow to Control Room Personnel ..................................... 17
2.5.5 Smoke & Fire Protection..................................................................... 17
2.5.6 Recovery Procedures ......................................................................... 17
2.5.7 Disclosure of EMS Data to Transmission Owners .............................. 20

PJM © 2014 ii
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Table of Contents

2.6 CONTROL CENTER STAFFING .................................................................................20


2.6.1 Staffing Upon Loss of an EMS or a 765 kV, 500 kV, or 345 kV RTU . 21
2.7 PJM MEMBER BACK UP CAPABILITY REQUIRED TO SUPPORT PJM IN ITS TOP ROLE 21
Section 3: Data Exchange Requirements ............................................................ 23
3.1 INTRODUCTION ......................................................................................................23
3.2 ENERGY MANAGEMENT SYSTEM (EMS) DATA EXCHANGE .......................................24
3.2.1 EMS Communications System ........................................................... 24
3.2.2 PJM EMS Communication Protocols .................................................. 24
3.2.3 EMS Data Exchange .......................................................................... 24
3.2.4 PJMnet Communications System ....................................................... 26
3.3 OASIS INFORMATION EXCHANGE ...........................................................................27
3.3.1 Transmission Customer Communications .......................................... 27
3.3.2 Transmission Provider Communications ............................................ 28
3.4 EMS BACKUP COMMUNICATIONS ...........................................................................28
3.5 REAL-TIME ANALYSIS MONITORING REQUIREMENTS FOR SYSTEM SECURITY ............28
3.6 DISPATCHING REQUIREMENTS ................................................................................29
Section 4: Voice Communications ....................................................................... 30
4.1 DISPATCH VOICE & FACSIMILE COMMUNICATIONS ...................................................30
4.1.1 All Call System ................................................................................... 30
4.1.2 Ring Down Circuits ............................................................................. 30
4.1.3 Manual Dial ........................................................................................ 31
4.1.4 Facsimile Communications ................................................................. 31
4.2 ALTERNATIVE VOICE COMMUNICATIONS .......................................................................31
4.2.1 Business Voice System ...................................................................... 31
4.2.2 Cellular Telephones............................................................................ 31
4.2.3 Satellite Telephones ........................................................................... 31
4.2.4 Three Part Communications ............................................................... 32
Section 5: Metering Requirements ....................................................................... 35
5.1 PURPOSE & CRITERIA ............................................................................................35
5.2 GENERAL GUIDELINES ...........................................................................................35
5.3 PRIMARY METERING REQUIREMENTS ......................................................................36
5.3.1 Accuracy............................................................................................. 37
5.3.2 Backup Metering Requirements ......................................................... 37
5.3.3 Location of Meter Points ..................................................................... 37
5.3.4 Alternative Approach .......................................................................... 38
5.3.5 Tie Line Telemetry Specification ........................................................ 38
5.3.6 Geographically Non-Contiguous Load ................................................ 40
5.3.7 Maintenance ....................................................................................... 41
5.4 METER ACCURACY STANDARDS .............................................................................41
5.4.1 Purpose .............................................................................................. 41
5.4.2 General Guidelines ............................................................................. 42
5.4.3 Primary Metering Accuracy ................................................................ 42
5.5 SYSTEM CONTROL MONITORING REQUIREMENTS ....................................................42
5.5.1 System Control Data .......................................................................... 43
5.5.2 Area Regulation .................................................................................. 43
5.5.3 Dispatch Data ..................................................................................... 43

PJM © 2014 iii


Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Table of Contents

5.5.4 Reserve Data ..................................................................................... 44


Attachment A: Information Access Matrix ........................................................... 45
Attachment B: Schedule of Data Submittals ....................................................... 54
Attachment C: Notification of Member Company System Outages .................. 56
Revision History..................................................................................................... 58

Table of Exhibits
Exhibit 1: Primary Transducer Accuracy Guideline ..............................................................42
Exhibit 2: Generation Scheduling Services ..........................................................................46
Exhibit 3: EMS Services ......................................................................................................47
Exhibit 4: Historical EMS Data Services ..............................................................................48
Exhibit 5: Transmission Maintenance Planning Services .....................................................49
Exhibit 6: Transmission Services .........................................................................................50
Exhibit 7: Energy Transaction Services ...............................................................................51
Exhibit 8: Long-term Planning Services ...............................................................................52
Exhibit 9: PJM Administration Services ...............................................................................53

PJM © 2014 iv
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Approval and Current Revision

Approval
Approval Date: 04/11/2014
Effective Date: 04/11/2014

Chantal-Aimee Hendrzak, Executive Director


Operations Support

Current Revision
Revision 26 (04/11/2014):
 Two of the eSuite Applications have been renamed. Moving forward EES will be
known as ExSchedule and eMTR will be known as Power Meter.

PJM © 2014 1
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Introduction

Introduction
Welcome to the PJM Manual for Control Center Requirements. In this Introduction, you will
find the following information:
 What you can expect from the PJM Manuals in general (see “About PJM Manuals”).
 What you can expect from this PJM Manual (see “About This Manual”).
 How to use this manual (see “Using This Manual”).
About PJM Manuals
The PJM Manuals are the instructions, rules, procedures, and guidelines established by the
PJM Interconnection, L.L.C. for the operation, planning, and accounting requirements of the
PJM RTO and the PJM Energy Market. The manuals are grouped under the following
categories:
 Transmission
 PJM Energy Market
 Generation and transmission interconnection
 Reserve
 Accounting and Billing
 PJM administrative services
For a complete list of all PJM Manuals, go to www.pjm.com and select “Manuals” under the
“Documents” pull-down menu.

About This Manual


The PJM Manual for Control Center Requirements is one of a series of manuals within the
Transmission Owners manuals. This manual focuses on the requirements for control centers
of signatories to the Operating Agreement of PJM Interconnection, L.L.C. The manual
describes the telecommunication linkages to the PJM Interconnection, L.L.C. and the
recommended characteristics of these control center computer systems and the buildings
housing these systems. It also summarizes the computer services and systems at the PJM
Interconnection, the standards for billing quality MWh meters, and meter accuracy
standards.
PJM staff will review and update this manual on an annual basis and review the updates
with PJM control center operators.
The PJM Manual for Control Center Requirements consists of five sections and two
attachments. These sections are listed in the table of contents beginning on page ii.
Intended Audience
The intended audiences for the PJM Manual for Control Center Requirements are:
 Applicants to the Operating Agreement of PJM Interconnection, L.L.C.
 All PJM Members Company Control Rooms

PJM © 2014 2
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Introduction

 PJM staff
References
There are some other reference documents that provide both background and detail. The
PJM Manual for Control Center Requirements does not replace any of the information in
these reference documents. These documents are the primary source for specific
requirements and implementation details.

Using This Manual


Because we believe that explaining concepts is just as important as presenting the
procedures, we start each section with an overview. Then, we present details and
procedures. This philosophy is reflected in the way we organize the material in this manual.
The following paragraphs provide an orientation to the manual’s structure.
What You Will Find In This Manual
 A table of contents that lists two levels of subheadings within each of the sections
 An approval page that lists the required approvals and a brief outline of the current
revision
 Sections containing the specific guidelines, requirements, or procedures including
PJM actions and PJM Member actions
 Attachments that include additional supporting documents, forms, or tables in this
PJM Manual
 A section at the end detailing all previous revisions of this PJM Manual
 PJM Operations Manager will review this manual on a minimum of an annual basis
for updates and changes and review with the PJM Systems Operation
Subcommittee.

PJM © 2014 3
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

Section 1: PJM Systems


Welcome to the PJM Systems section of the PJM Manual for Control Center Requirements.
In this section you will find the following information:
 Descriptions of the PJM control centers systems (see “PJM Systems”).

PJM Systems
PJM operates several functional systems that directly interface with PJM Members. Systems
that are wholly internal to PJM and have no direct PJM Member interface are not listed.
The following systems are used to operate the PJM RTO and support the Energy Market:
 Energy Management System (EMS)
 Generation Management System (GMS)
 PJM SCADA System
 Data Historian System
 Enhanced Energy Scheduler (ExSchedule)
 Two Settlement System (eMKT)
 Dispatch Management Tool (DMT)
 Regulation Market
 Synchronized Reserve Market
 Operations Planning Tools
 Available Transfer Capability (ATC) Program
 Open Access Same-Time Information System (OASIS)
 Dispatcher Analysis and Reporting Tool (eDART)
 Other eSuite Tools (Power Meter, InSchedules, eFTR, eLRS)
 PJM Voice Communications
 Reliability Coordinator Information System (RCIS)
 Security Constrained Economic Dispatch (SCED)
The following systems are used for planning purposes:
 Generator Availability Data System (eGADS)
 Capacity Reporting Program (eRPM)
 Central Planning Database
 Transmission Planning Tools

PJM © 2014 4
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

1.1 Energy Management System (EMS)


The PJM EMS performs the real-time monitoring, security analysis, and generation control
functions for the entire PJM region. The EMS major subsystems:
 Real-Time EMS — the Real-time EMS is responsible for monitoring, analysis, and
real-time coordination of the PJM region. It includes a full complement of monitoring,
generation control, state estimation and security analysis software. PJM Members
supply telemeter data to the PJM real-time EMS and may receive data and control
signals from the PJM real-time EMS.
o Communications Front End (CFE)
o The EMS Communications Front End processors communicate to the field via
Distributed Network Protocol (DNP). This allows PJM to communicate directly
with individual generators or smaller Control Centers.
o The CFE system allows transfer of both generation and revenue data to PJM as
well as Automatic Generation Control (AGC), set point, device control, and other
functions to the data concentrator (e.g. Remote Terminal Unit, Generator Control
System, etc.) at the Member's site,
 DTS — The Dispatcher Training Simulator (DTS) system is used to train PJM
dispatchers. Member company operators participate in Fall Restoration Drills using
PJM’s DTS.
 Development System — The Development System allows the PJM staff to develop
software, database, and displays for the Real-Time EMS, and DTS systems, without
interfering with the operation of those systems. There is no direct interaction
between PJM Members and the Development System.
 Test System — The Test System provides an independent test environment to
validate changes developed on the Development System, prior to installing them on
the Real-Time EMS. PJM Members may exchange telemetry with the Test System
to verify telemeter points, to test data communications, to test communications
failover capabilities and to test application programs.
 Process Control Test (PCT) System — The PCT system is a parallel test system with
access to live data used to test and verify software and database changes prior to
promoting those changes to the on-line production EMS. There is no direct
interaction between PJM Members and the PCT system.
 EMS Reliability Configuration
 For reliability purposes, each of the Real-Time EMS systems described above is
configured in a redundant or fault tolerant manner (depending on the nature of the
subsystem) at each site (Valley Forge and Milford). In addition, the two sites are
synchronized and operated from continuously staffed Control Centers at the
respective locations.
 The Core elements of the Real-Time EMS systems (ICCP, SCADA, and AGC) are
operated in a Dual Primary mode (both sites have these elements of the EMS as
primary), with either site having the functionality of continuing to operate the grid by
itself in the event of failure of the other.

PJM © 2014 5
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

 The Transmission Network Applications are operated in a Primary/Secondary mode


with the configuration updates synchronized to the secondary so that it can either be
slaved off of the primary or operate independently and still be ready to take over for
the primary in the event of a primary failure or routine switchover.
 In the event of a catastrophic failure of systems at both sites, rapid recovery
procedures are in place to recover the systems. While that recovery is occurring,
Transmission Operating Authority would be temporarily turned over to the
Transmission Owners and the GMS System would be used by PJM Dispatchers to
provide the Balancing Authority function.
 EMS Support Systems
 The functionality as well as reliability requirements of each support system dictate its
configuration:
 Test is site redundant/fault tolerant at each site and has a presence at each site as
well as operates in modes (e.g. Dual Primary) like the Real Time EMS in order to
support testing of new functionality.
 PCT is configured for a single system at each site that operates in modes (e.g. Dual
Primary) like the Real Time EMS to support testing of (for example) new model
functionality.
 Development as well as DTS are single systems. Development is located at Valley
Forge, DTS is located at Milford

1.2 Generation Management System (GMS)


PJM has retained and repurposed the GMS to be a BA Emergency Backup system for the
PJM EMS. PJM Members with frequency sources and external tie connections continuously
provide data to the GMS system. This data, in conjunction with Frequency Standards and
constantly updated Scheduling information provide an ongoing checkpoint for the ACE
calculation as well as a Balancing Authority Emergency Backup System.

1.3 Data Historian System


The Data Historian System serves as a data archive for operational data in near-real-time. It
provides visualization tools for presenting data to operators and provides a permanent
archive of data for post-event study and analysis. Telemeter data is archived from EMS and
other operational data is imported from other sources, including Market Systems.

1.4 Enhanced Energy Scheduler (ExSchedule)


The Enhanced Energy Scheduler (ExSchedulerecords customer requests for interchange
transactions, the bulk power scheduled between PJM and neighboring regions. PJM
personnel use ExSchedule to process and schedule these transactions. The ExSchedule
validates PJM ramp, use of transmission reservation rights, and other PJM scheduling
business rules as described in the PJM Manual for Scheduling Operations.

PJM © 2014 6
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

1.5 Two Settlement System (eMKT)


The Two-Settlement system consists of two markets, a day-ahead market and a real-time
balancing market. The Day-ahead Market is a forward market in which hourly clearing prices
are calculated for each hour of the next operating day based on generation offers, demand
bids Increment offers, Decrement bids and bilateral transaction schedules submitted into the
Day-ahead Market. The balancing market is the real-time energy market in which the
clearing prices are calculated every five minutes based on the actual system operations
security-constrained economic dispatch. Separate accounting settlements are performed for
each market, the day-ahead market settlement is based on scheduled hourly quantities and
on day-ahead hourly prices, the balancing settlement is based on actual hourly (integrated)
quantity deviations from day-ahead scheduled quantities and on real-time prices integrated
over the hour. The day-ahead price calculations and the balancing (real-time) price
calculations are based on the concept of Locational Marginal Pricing.
The Day-ahead Market enables participants to purchase and sell energy at binding day-
ahead prices. It also allows transmission customers to schedule bilateral transactions at
binding day-ahead congestion charges based on the differences in LMPs between the
transaction source and sink. Load Serving Entities (LSEs) may submit hourly demand
schedules, including any price sensitive demand, for the amount of demand that they wish
to lock-in at day-ahead prices. Any generator that is a PJM designated capacity resource
must submit a bid schedule into the day-ahead market even if it is self-scheduled or
unavailable due to outage. Other generators have the option to bid into the day-ahead
market. Transmission customers may submit fixed, dispatchable or 'up to' congestion bid
bilateral transaction schedules into the day-ahead market and may specify whether they are
willing to pay congestion charges or wish to be curtailed if congestion occurs in the Real-
time Market. All spot purchases and sales in the day-ahead market are settled at the day-
ahead prices. After the daily quote period closes, PJM will calculate the day-ahead schedule
based on the bids, offers and schedules submitted, using the scheduling programs
described in section 2 of this manual, based on least-cost, security constrained unit
commitment and dispatch for each hour of the next operating day. The day-ahead
scheduling process will incorporate PJM reliability requirements and reserve obligations into
the analysis. The resulting Day-ahead hourly schedules and Day-ahead LMPs represent
binding financial commitments to the Market Participants. Financial Transmission Rights
(FTRs) are accounted for at the Day-ahead LMP values (see the PJM Manual for Financial
Transmission Rights (M-06)).
The Real-time Energy Market is based on actual real-time operations. Generators that are
designated PJM capacity resources that are available but not selected in the day-ahead
scheduling may alter their bids for use in the Real-time Energy Market during the Generation
Rebidding Period from 4:00 PM to 6:00 PM (otherwise the original bids remain in effect for
the balancing market). Real-time LMPs are calculated based on actual system operating
conditions as described by the PJM state estimator. LSEs will pay Real-time LMPs for any
demand that exceeds their day-ahead scheduled quantities (and will receive revenue for
demand deviations below their scheduled quantities). Generators are paid Real-time LMPs
for any generation that exceeds their day-ahead scheduled quantities (and will pay for
generation deviations below their scheduled quantities). Transmission customers pay
congestion charges based on Real-time LMPs for bilateral transaction quantity deviations
from day-ahead schedules. All spot purchases and sales in the balancing market are settled
at the Real-time LMPs.

PJM © 2014 7
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

1.7 Dispatch Management Tool (DMT)


The Dispatch Management Tool (DMT) is a software tool that is designed to enable the PJM
dispatchers to manage generating unit and transmission constraint information and
administer the Real-Time Regulation Market. Since many of the current dispatcher logging
activities are position independent, the DMT allows each dispatcher position to view the
same generation and transmission constraint information simultaneously. This real-time
sharing of logging information provides the PJM dispatchers with an efficient communication
vehicle to help them perform their job functions more effectively.
The DMT is used by the PJM dispatchers to:
 View and record real-time unit generation information
 View and record unit generation scheduling information
 Review the chronological log of generation events
 Analyze system resources
 Record and calculate regulation assignment information
 Record and calculate Synchronized Reserve assignment information
 View and record real-time transmission constraint information

1.8 Open Access Same-time Information System (OASIS)


The PJM OASIS system maintains transmission and ancillary services information for PJM
Members. OASIS operates on a collection of PJM and PJM Member computers linked by
private and public networks. For additional information, see the PJM Manual for PJM
OASIS Operation (M-04).

1.9 Other eSuite Tools (Power Meter, InSchedules, eLRS, eFTR)


The other eSuite tools are all Web-based tools that PJM members use to facilitate the
exchange of information with PJM and support various PJM market activities.
a. Curtailment Service Providers will retrieve PJM real time Energy market dispatch
instructions, PJM emergency event notifications and PJM synchronized reserve
event notifications on a 1 minute basis from PJM eLRS system through published
Web Service standards in eLRS web service User Guide. PJM will post dispatch
instructions in eLRS based on economic demand response registration or economic
demand response dispatch group that has been dispatched in the real time energy
market. PJM will post in eLRS emergency event notifications and instructions when it
calls an emergency demand response event. PJM will post in eLRS synchronized
reserve event notifications when it calls a synchronized reserve event.
CSP must maintain communication link and continuously check for dispatch
instructions and event notifications and provide PJM an acknowledgment for receipt
of each dispatch instruction and notification. PJM can provide generic and
unsupported software client to perform the required requests and
acknowledgements. This is offered as an aid for CSPs that currently do not have
web service capabilities.

PJM © 2014 8
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 1: PJM Systems

1.10 Planning Systems


PJM operates several planning systems which are used to run studies for reliability and
capacity planning and for transmission planning. Reliability and capacity planning includes
the Generating Availability Data System (GADS) database and eRPM are computer
programs and databases used for entering, storing, and reporting generating unit data
concerning outages, unit performance, and fuel performance. In addition, PJM Members
provide information to the PJM Central Planning Database, a database containing planning
information relating to generation production costs, load flow analyses, short circuit and
system dynamics studies, and LSE load data. Additional details about these planning
functions may be found in the PJM Manual for Load Forecasting and Analysis (M-19),
and the PJM Manual for PJM Resource Adequacy Analysis(M-20).
PJM also performs transmission planning studies. For example, PJM Members staffs
provide transmission planning capacity and load data to the PJM Transmission Planning
Tool which generates performance adequacy and reliability assessments (see the PJM
Manual for Transmission Service Request (M-02)).

PJM © 2014 9
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

Section 2: Member Control Center Requirements


Welcome to the Control Center Requirements section of the PJM Manual for Control Center
Requirements. In this section you will find the following information:
 A description of the different categories of control centers (see “PJM Control Center
Categories”).
 An overview of PJM Member responsibilities (see “PJM Member Data Exchange”).
 Computer system requirements for Control Centers (see “Computer System
Requirements”).
 Communications requirements (see “Communications Requirements”)
 Requirements for control center physical facilities (see “Facilities Requirements”).
 Control center staffing recommendations (see “Control Center Staffing”).

2.1 PJM Control Center Categories


PJM Members may be involved with transmission ownership, generation ownership, load
service operations, and/or PJM Energy Market participation. Depending upon the functions
they perform and the services they require from PJM, the control center for each PJM
Member will fall into one or more of the designations defined below. The specific functions,
systems, and communications capabilities of that control center depend upon the
responsibilities of the PJM Member:
 Local Control Center — An entity that participates in the Operating Agreement of
PJM Interconnection, L.L.C. (Agreement) and assists PJM in operating and
controlling Designated Transmission Facilities establishes a Local Control Center
(LCC) to facilitate its responsibilities regarding the security of the PJM RTO.
 Market Operations Center — An entity that participates in the Agreement and assists
PJM in operating and controlling generation within the PJM RTO establishes a
Market Operations Center (MOC) to facilitate its responsibilities regarding the
security of the PJM RTO.
 Load Service Center — any entity that participates in the Agreement and operates
and controls load (but without generation or Designated Transmission Facilities)
establishes a Load Service Center (LSC) to facilitate its responsibilities for its load in
the PJM RTO. Entities responsible for load that also assist PJM in operating or
controlling transmission and/or generation may not need an LSC, as they can
discharge these responsibilities from an LCC or MOC.
 Marketing Center — a participant in the Agreement as a Power Marketer, Wholesale
System User, Other Supplier, or Transmission Customer establishes a Marketing
Center to facilitate communications with PJM concerning its participation in the PJM
Energy Market.
Many PJM Members are involved in more than one of the four areas of responsibility
discussed above. Each member is obligated to be in compliance with the Code of Conduct
requirements established in FERC Order 2004. Entities participating in the PJM Energy

PJM © 2014 10
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

Market may establish a separate MOC. All of these four categories of control centers are
referred to collectively in this manual as “control centers”.

2.2 PJM Member Data Exchange


PJM Members support a variety of PJM functions appropriate to their business requirements
and level of participation requirement in PJM. For each of the PJM services described in this
section, data is exchanged between PJM and one or more of the categories of PJM Member
control centers. The following PJM services are further defined in Attachment A, Information
Services Matrix. In this attachment, the references to “Member Type” translate to control
center category as follows:
 Regional Transmission Owner — Local Control Center (LCC)
 Generating Entity — Market Operations Center (MOC)
 Load Serving Entity — Load Service Center (LSC)
 Marketer — Marketing Center
 Generation Scheduling Services — MOCs input generation, pre-scheduling,
scheduling, Synchronized Reserve bids, and regulation bids, and outage data to
PJM, and PJM output hourly and daily generation scheduling information to LCCs,
MOCs, and LSCs (see the PJM Manual for Pre-Scheduling Operations (M-10)
and the PJM Manual for Energy & Ancillary Services Market Operations (M-11)).
 EMS Services — LCCs, MOCs and LSCs input real-time transmission and
generation information plus generator regulation and availability data and PJM
outputs real-time transmission status, generation status, generation dispatch and
regulation signals, and operations & emergency information (see the PJM Manual
for Balancing Operations (M-12)).
 Transmission Maintenance Planning Services — LCCs input transmission
maintenance schedules which are confirmed by PJM to all PJM Members (see the
PJM Manual for Transmission Operations (M-03)).
 Transmission Services — OASIS is used at LSCs and Marketing Centers to input
transmission reservations and by PJM to output Available Transmission Capacity,
energy transactions, transmission congestion information, approved transmission
reservation requests, and other market information to all categories of control centers
(see the PJM Manual for Transmission Service Request (M-02) and the PJM
Manual for PJM OASIS Operation (M-04)).
 Energy Transaction Services — bilateral energy transactions are input from all
categories of control centers and are confirmed by PJM (see the PJM Manual for
Energy & Ancillary Services Markets Operations (M-11) and the PJM Manual for
Balancing Operations (M-12)).
 Long-term Planning Services — LCCs, MOCs, and LSCs input capacity, load,
system characteristics information, generator events, production costs, outage
reports and long-term planning information and PJM outputs the results of studies
and assessments to all categories of control centers (see the PJM Regional
Transmission Planning Process Manuals (14 Series))

PJM © 2014 11
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

 PJM Administration Services — PJM outputs general administrative information and


FERC filings to all PJM Members via the PJM Web site.

2.3 Computer System Requirements


Each PJM Member’s control center serves as the primary operating link to the PJM control
centers and includes computer system hardware and software that supports their
responsibilities under the Agreement.
2.3.1 Transmission Monitoring Capability
Transmission Owners shall provide transmission monitoring at their Local Control Centers
including monitoring of circuit loading, voltages, limit violations and contingency analysis.
Basic software should include State Estimation and Security Analysis functions to monitor
actual and contingency conditions. This should include functionality to bring to the attention
of operating personnel important deviations in operating conditions.
In the event that PJM’s monitoring systems are unavailable, PJM may notify Transmission
Owners that they are the sole monitor for their portions of the bulk power transmission
system. In that scenario, PJM will communicate the situation via the All-Call. PJM is
expecting that the Transmission Owner(s) will use their monitoring systems to (1) assess the
reliability of their portions of the bulk power transmission system via contingency analysis
and SCADA; (2) communicate any contingency or limit violations on any bulk electric system
facility to PJM as soon as possible. If the Transmission Owner determines that corrective
actions are necessary to preserve system reliability, then PJM shall approve the corrective
action, unless immediate action is necessary. If immediate action is necessary, the TO shall
implement the action and report to PJM any actions taken. If the various PJM real time
analysis tools are not functioning for the present operating state (possibly because of an
EMS outage), PJM shall coordinate with the appropriate Member Transmission Owner to
determine if their tools are functioning. If neither the Member Transmission Owner nor the
PJM EMS are functioning, then PJM will work with the Transmission Owner to return the
system to a known operating condition.

Note: PJM Transmission Owners that own BES facilities and serve load
greater than 300 MW must have a real-time analysis package or have their
BES facilities be observable within another TO analysis package. Any
exceptions to this requirement must be formally approved by PJM.

Should the PJM RTO at any time enter into an unknown operating state due to a
catastrophic failure of the ICCP links or loss of EMS analysis tools, it will be considered an
Emergency and operations shall be restored to respect proven reliable power system limits
within 30 minutes in accordance with NERC standards. PJM relies on Transmission Owners
to serve as a back-up to PJM, monitoring BES facilities, when the PJM EMS is inoperable
(TOP-007-1). PJM Transmission Owners shall notify PJM dispatch within 15 minutes when
their TO analysis packages are unavailable (TOP-004-2 R4).. In general, PJM may be in an
unknown state when both PJM and TO analysis packages are unavailable.
The continuous calculation and monitoring of post-contingency voltages for nuclear power
plants (for the loss of the nuclear unit) is an important requirement to ensure that adequate

PJM © 2014 12
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

voltage is always available for the operation of the nuclear safety systems. Given this
requirement, the nuclear power plant(s) shall be notified in cases where the transmission
monitoring capability (at PJM and the Transmission Owner) becomes unavailable and the
ability to calculate the post-contingency voltages is lost. [There may be situations where the
calculations are only being performed at PJM. In this case, loss of the PJM capability shall
trigger the notification to the nuclear power plant(s) within 30 minutes.] The notification will
go via the All-Call from PJM to the Transmission Owner(s) who will then communicate with
the applicable nuclear power plant(s).
System Availability
The computer hardware and software at each control center shall achieve a long-term
99.95% availability level for those reliability functions directly affecting the successful
operation of PJM. Any application that supplies operational data to PJM, accepts
generation control signals from PJM, or otherwise links to the real-time operational aspects
of the PJM control system is considered vital to reliability. Other applications may be
considered to be vital to a PJM Member’s operations and therefore, shall also achieve
99.95% availability. Redundant hardware configurations with either automatic or rapid
manual failover schemes are generally necessary to achieve 99.95% availability.
2.3.2 Data Backup & Archiving
All PJM Members shall prepare and implement a backup and archiving plan which
minimizes the loss of vital data upon the occurrence of any hardware failure or a
catastrophic system loss.
2.3.3 Computer System Security
Control centers with electronic data links to the PJM computer systems require rigorous
computer system security provisions to prevent unauthorized access and unintentional
operation. Due to the sensitive nature of both operational and financial data, control center
computer systems shall include appropriate techniques such as password log-on for internal
users, hardware and software security controls for external users, and on-line virus detection
capabilities. Telecommunication circuits connected to any control center computer system
shall utilize firewall technology to prevent unauthorized access from external sources.
2.3.4 System Maintenance
Due to the operational requirements and economic benefits of a PJM Member’s control
center computer system, a computer system (hardware, software, and network)
maintenance service arrangement with 24-hour, 7 day/week call-out provisions or on-site
staff, is required to ensure appropriate levels of system availability to implement database
changes, and to modify user interface displays.
2.3.5 Expansion Capability
PJM Member computer system hardware, software, and network shall be expandable to
accommodate growth in their system and operations and to accommodate future changes to
the organization and responsibilities of the PJM RTO and the PJM Energy Market. PJM
services and marketing activities are all expected to increase and the control center
computer systems shall be expandable to accommodate this expected growth. System
design shall provide for orderly addition of computer hardware, software, and network
through adherence to accepted system standards and Good Utility Practice.

PJM © 2014 13
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

2.3.6 Data Integrity


PJM maps quality codes sent by member companies into four quality codes:
1. Good (valid data);
2. Manually Substituted by company;
3. Telemetry Failure; and
4. Suspect (usually indicating value is bad).
Details on quality code translations are given in the following documents:
 PJM ICCP Network Interface Control Document, Version 1.1, March 27, 2000.
 PJM ICCP Communications Workbook, Version 1.1, March 27, 2000.
 Running list of updates to the PJM ICCP NICD and Workbook, Version 1.1 January
30, 2001.
Member companies should only send valid quality codes. In particular, companies with
front-end data servers should insure that the front-end server does not initiate data transfers
with PJM until the front-end server has begun receiving valid and current data from the
company EMS or other data source. Sending even a single scan with zero values or other
bad data for analog or switch statuses can cause massive alarm generation and improper
operation of State Estimator and other vital functions.
PJM provides new members and existing members the testing requirements for system
commissioning and on-going support. When commissioning a new system, members
should request the latest copy of the PJM ICCP Testing Requirements document from PJM.
The required tests include:
For new members:
1. Server to server communication verification over PJMNET
2. Exchange of NERC ICCP Association Information Exchange Form
3. Exchange of client and server data points needed before ICCP Association
testing
4. Ability to initiate an ICCP Association with PJM
5. Ability to support an ICCP Dual direction Client-Server Association
6. Ability to provide real-time SCADA data during testing along with the ability to
change values and quality codes
7. Ability to participate in testing with the designated PJM TEST system
8. Participation in Failover testing to verify required network, server, and
communication redundancy
For existing members:
1. All of the above (1 to 8). New members testing requirements
2. The ability to test with the designated PJM TEST system while supporting the
real time PJM EMS system

PJM © 2014 14
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

3. The ability to test changes with the PJM designated TEST system before putting
the changes in production with the real time PJM EMS system
4. The ability to support Failover testing to verify required network, server, and
communications redundancy for existing member changes while still supporting
the real time PJM EMS system
5. PJM Member companies are required to successfully complete the PJMNET
ICCP Communications Failover Test before going into production with the PJM
real time EMS system. The purpose of this test is to verify redundancy from
company ICCP servers to PJM ICCP servers. In the process of doing this ICCP
server to server Failover testing all network hardware components such as:
routers, firewalls, and PJMNET communication lines will have their redundancy
validated.
6. In order to accomplish site to site failover between PJM GMS and PJM EMS
(depending on member company situation), member company ICCP systems
must be able to support up to four IP addresses in their ICCP association start up
sequential server hunt list.

2.4 Communications Requirements


Telecommunications (voice and data) circuits, which must be reliable and secure, shall be
tested regularly and/or monitored on-line, with special attention given to emergency
channels. These communications will include:
 Voice communications between Transmission Owners and neighboring
Transmission Owners both internal to and external to PJM.
 Data communications between Transmission Owners and neighboring Transmission
Owners both internal to and external to PJM (either directly or through PJMnet).
 Provisions to monitor communications 24 x7
 Use predetermined communication paths (phone numbers, etc.) to talk to
neighboring Transmission Owners internal and external to PJM
 Testing of voice communications with all neighboring Transmission Owners both
internal and external to PJM

2.5 Facilities Requirements


This section discusses the control center facility considerations for a PJM Member, including
the physical space housing operations staff and, if appropriate, a computer room,
communications room, and power supply area. While these considerations apply to all PJM
Member categories, the specific implementation of control center facilities considerations
shall be appropriate for the nature of the computer systems and communications equipment
installed.

PJM © 2014 15
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

2.5.1 Environmental Characteristics


In order to ensure the PJM Member’s computer system availability and data reliability
discussed in the previous section, its control center facilities shall provide an environment
that is suitable for its equipment and personnel during the hottest and coldest outdoor
temperatures that can be anticipated.
 The range of control center temperature and humidity shall be controlled
appropriately for the installed computer systems and communications equipment.
The most restrictive temperature and humidity characteristics of any item of
equipment in each room of the control center, the total heat load of that equipment,
and the projected growth shall establish the design criteria for the heating,
ventilating, and air conditioning systems provided.
 Control room operators, technical staff, and maintenance personnel should be able
to function comfortably.
 Where feasible, heating, and air conditioning equipment shall be backed up with
redundant or auxiliary systems to allow operations to continue indefinitely following
the failure of any single temperature controlling device or motor control center.
 If the control center is located in the proximity of a polluting atmosphere , a positive
pressure shall be maintained in the computer room using filtered air to minimize the
accumulation of airborne contaminants on the computer system circuit boards and
components.
2.5.2 Power Supply & Conditioning
Because of the importance of non-stop operation of the PJM RTO and the sensitivity of
computer equipment to minor power disturbances, a stable and secure supply of AC power
for the equipment in the control room, computer room, and communications room shall be
provided and installed in compliance with current National Electric Code provisions.
 An uninterruptible power supply (UPS) (i.e., battery charger, battery, and inverter)
and a backup generator is necessary to supply power to operator display equipment,
computer systems and communications equipment. A completely redundant power
supply with dual UPS may also be utilized.
 K-rated transformers and oversized neutral conductors shall be employed as
necessary to mitigate the effects of harmonic distortion created by non-linear loads.
 The UPS battery shall have sufficient capacity to operate the computer system, and
communications equipment until stable emergency generation can be achieved.
Periodic maintenance and testing of the battery cells and inter-cell connections shall
be performed.
 The backup generator shall be tested periodically under load to ensure its availability
under loss of power conditions. Fuel supply for the backup generator should be
sufficient for a five-day period. If applicable, redundant backup generators should be
considered.
 An emergency lighting system should be provided with adequate battery capacity for
several hours.

PJM © 2014 16
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

 The heating, cooling, and ventilation equipment shall also be powered by the backup
generator (but not by the UPS).
 A high quality, common earth ground shall be provided, in accordance with IEEE
standards, for the computer system and communications equipment to provide a low
impedance path for rapid clearing of electrical faults and to reduce electromagnetic
interference.
 If UPS power is not provided, TVSS protection for power and communications
circuits shall be provided to mitigate the effects of lightning strikes and AC power
excursions.
 Where warranted, external power to the control center shall be supplied from two
sources, such as two distribution feeders that follow diverse routing from separate
electric substations.
2.5.3 Area Access Security
Access to PJM Member control rooms should be restricted. For example, access could be
controlled by means of a single entry point monitored by office personnel during business
hours and, at other times, either by control room personnel via closed-circuit TV monitors
and remotely controlled locks or by a cipher/key/badge-reader lock. Emergency
exits/entrances should be sealed and alarmed in conformance with local fire regulations.
2.5.4 Information Flow to Control Room Personnel
A protocol shall be established concerning information transfer from PJM Member staff to
the appropriate staff members and their supervisor responsible for coordinating and
directing work in the PJM Member’s control center. Topics covered shall include the
following:
 Inquiries to the shift team and their on-shift supervision.
 Access control to the control room.
 Approvals for Computer outages.
 The PJM shift supervisor and Support Center shall be notified of any computer
system outages.
 In case of implementation of PJM Emergency Procedures, all non-essential
personnel shall leave the control center and non-essential computer system
hardware and software maintenance should be terminated.
2.5.5 Smoke & Fire Protection
Smoke and fire detection equipment shall be installed to detect smoke and fire, warn
personnel to hand-extinguish the fire or evacuate the facility, and, where warranted,
automatically extinguish the fire. Smoke and fire protection equipment shall conform to the
current version of NEC, local, state, and national codes.
2.5.6 Recovery Procedures
In accordance with BAL-005-0, “Automatic Generation Control,” PJM, as the Balancing
Authority, provides adequate and reliable backup power supplies and performs weekly tests
(system conditions permitting) at both control center locations to ensure continuous

PJM © 2014 17
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

operation of AGC and vital data recording equipment during loss of the normal power
supply.
The AGC program is monitored by a function called the “Multi-Computer System (MCS)
function.” This function monitors all vital EMS programs, including AGC, and initiates a
failover to the backup server if a problem is detected with the application. Data links to each
member company are also monitored such that any interruption in data feed is indicated via
alarm messages and an indicator on the main menu and by individual quality codes on all
data affected by the link outage. In addition, the generation dispatcher has graphic
presentations of ACE and other AGC data in front of them at all times so any interruption in
the program or its calculations are readily apparent as a flat-line on the graphs.
PJM Members shall comply with PJM recovery procedures. For PJM Members that interface
with the PJM EMS, all the necessary backup voice and data circuits must be provided
between the Local Control Center and PJM. Generation owners should design their
generation control systems with the capability to accept alternate control inputs from PJM
AGC systems (i.e. AC1, AC2, and GMS) including manual operation as directed by PJM
operations personnel.
Each Member TO must have a plan for loss of control center functionality that
includes procedures and responsibilities for providing annual training to ensure that
operating personnel are able to implement the plans.
All PJM Members shall develop a backup recovery plan to cover various contingencies,
including maintaining an off-site storage location for updated copies of all software and data
files necessary to restore control center functions. The backup recovery plan is subject to
review by PJM.
PJM systems provide multiple levels of redundancy in order to mitigate various levels of
Control Center functionality degradation. This redundancy and the associated Business
Continuity Plans developed by PJM ensure that PJM can meet its responsibilities under the
PJM Operating Agreements as well as NERC standards. The following descriptive material
provides a high level view of key areas included in the Business Continuity Plan and in
detailed PJM operating procedures.
Portions of the PJM Control Center capability are housed in diverse physical locations. The
PJM campus in Valley Forge, PA houses one control center and a second control center is
located in Milford Township, PA. Each control center has access to the both AC1 and AC2
EMS’s and maintains redundant communications capability for data and voice. Generation
Control: PJM is capable of calculating Area Control Error (ACE) via AC1, AC2 or the GMS.
AC1 and AC2 are physically located at different sites to increase redundancy. The PJM
Operator has the ability within each tool to select alternative tie sources to correct for poor
data quality.
PJM Actions:
 PJM Dispatcher verifies accuracy of ACE calculation.
 PJM Dispatcher controls to appropriate ACE by manually correcting any inaccurate
data inputs.
 PJM Dispatcher notifies support personnel of data quality issue.

PJM © 2014 18
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

 PJM Dispatcher switches to alternative system in the event of a widespread data


quality issue.
 PJM returns to normal operations when data/ACE calculation issues are resolved.
Transmission Analysis: PJM is capable of performing transmission analysis via either
Primary EMS.). System Operators have the ability to switchbetween EMS’s in real time.
Testing is scheduled on a weekly basis. Transmission Owners are responsible to
monitor/control their transmission system in the event that both PJM primary EMS’s are
unavailable.
PJM Actions:
 PJM Dispatcher verifies the accuracy of the Network Applications (NA) results.
 PJM Dispatcher attempts to resolve inaccurate NA results by troubleshooting data
inputs and manually over riding incorrect device statuses, tuning parameters, etc.
 PJM Dispatcher notifies support personnel of issue.
 If appropriate, PJM Dispatcher switches to alternateEMS.
 PJM Dispatcher notifies companies via the All–Call of NA status.
 PJM Dispatch notifies Transmission Owners and external systems via RCIS if unable
to monitor system via alternateEMS.
 PJM returns to normal operations when appropriate.
Data Integrity: PJM is capable of failing ICCP links from AC1 to AC2 communication servers.
System Operators have the ability to switchservers in real time. Testing is scheduled on a
weekly basis.
PJM Actions:
 PJM Dispatcher verifies the accuracy/status of the data links.
 PJM Dispatcher notifies support personnel of data quality issue.
 PJM Dispatcher, if appropriate, will switchservers in real time on p EMS’s.
 PJM Dispatcher, if appropriate, will switch EMS’s if communication problems exist on
both primary and stand by communication servers on either EMS.
Voice communication: Voice communications are available from either control room. Within
each site there are multiple levels of redundancy, including dedicated ring-downs, manual
dial, business voice systems, cellular, satellite, all-call and facsimile communications.
Testing is conducted on a periodic basis.
PJM Actions:
 PJM Dispatcher will utilize the appropriate phone system, based on availability,
following this hierarchy: British Telecom (BT), Tradenet, office phone, cell, satellite.
These plans and procedures for maintaining PJM Control Center functionality are integrated
into the PJM Business Continuity Plan. Periodic training on the plan elements and specific
actions required by System Operators is included in PJM’s normal operating training
curriculum. The Business Continuity Plan is tested on a semi-annual basis via drills and
procedural exercises. System Operators are responsible for conducting the periodic tests,

PJM © 2014 19
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

participating in the Business Continuity Exercise and participating in debriefing activities


designed to identify and implement improvements to the overall process. Detailed operating
procedures are documented in the Business Continuity Plan.
2.5.7 Disclosure of EMS Data to Transmission Owners
PJM will implement a technical solution to provide Transmission Owners with read-only
access to PJM’s EMS system. In order to ensure that this solution is implemented in a
secure, protected manner, members are required to implement the following:
 Procedural controls to ensure that this information is viewed only from a location
within the member’s control center.
 Provide PJM’s Network Infrastructure department configuration information needed
for establishing and authenticating connections.
 Limit access to the workstation utilized in viewing PJM’s EMS screen to those with
authorized access to the member’s control center.
 Share credentials for this access only with individuals who have authorized access to
the member’s control center. This should be documented in accordance with the
member’s controls for CIP 004 R4.
 Report to PJM immediately any incidents leading to loss, theft or destruction of the
authentication devices.
 Data Security: Protect the information displayed in accordance with PJM’s OA
section 18.17, as well as member’s own policies, standards and procedures.
 PJM may request evidence for any or all of these steps during PJM’s TO Audit.

2.6 Control Center Staffing


PJM Member control centers must be staffed with competent personnel trained (reference
PJM Manual 40) for all normal and emergency situations that might be anticipated. Control
room operator staffing levels should be prudently determined based upon the impact of the
PJM Member’s operations. Possibilities for control room staffing include combinations of the
following:
 One or more operators in the control room 24 hours a day, 7 days a week
 One or more operators in the control room during business hours or hours of
operation
 Responsible personnel not in the control room but able to be contacted by the PJM
dispatcher within one minute
While staffing guidelines cannot cover all situations, the following general guidelines may be
useful:
 Transmission Owners, Generation Owners, and other Load Serving Entities that
participate in the operation and security of the PJM RTO and/or that must respond to
generation adjustment or load shedding during normal or emergency conditions must
staff their control center 24 hours a day, 7 days a week, with 100% availability of
staff.

PJM © 2014 20
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

 Owners of generation which operates infrequently may require continuous control


center staffing only during the hours of their units’ operation. They must be able to
answer telephone questions and directions within one minute of a call initiation by
PJM.
 Market Participants must be able to respond to telephone questions about their
scheduled transactions within one minute of a call initiation by PJM.
2.6.1 Staffing Upon Loss of an EMS or a 765 kV, 500 kV, or 345 kV RTU
If a PJM Member’s EMS becomes unavailable, some PJM Members move their dispatchers
to a backup control center while others send staff to man their vital operational facilities.
PJM Members should continue to stay in contact with and provide as much information as
possible to PJM. If an EHV substation RTU becomes unavailable, the respective
Transmission Owner may be required to send staff to that substation to telephone
information to the LCC and to PJM.

2.7 PJM Member Back Up Capability Required to Support PJM in


its TOP Role
If a PJM member primary EMS capability becomes unavailable, PJM will need back up
capability (may include backup EMS or backup functionality or staffing critical substations,
etc.) from the Transmission Owner to be available (within 1 hour) from that member so that
PJM can continue to perform its obligations as the TOP during such interruptions.
Specifically, PJM requires the following from the PJM members during the loss of the
transmission owner EMS:
 NERC Standard TOP-004, R1 requires the TOP to operate within the limits of its
IROLs and SOLs. If the data for monitoring the IROLs and SOLs passes through the
PJM member EMS and that capability becomes lost, then the PJM member is
required to have a backup capability to ensure that the necessary data continues to
be provided to PJM.
o During the TO transition to its back up facility, PJM will continue to monitor the
TO Transmission System to the extent data quality permits.
 NERC Standard TOP-004, R6 requires the TOP to have formal policies and
procedures to ensure transmission reliability. If the PJM member is unable to
execute operating procedures that may be implemented by PJM, such as switching
or load shedding, due to the unavailability of its EMS or other operational tools, then
the PJM member is required to have a backup capability to be able to execute these
actions.
 NERC Standard TOP-006, R1, R2, R5-7, requires data to be provided to PJM to
ensure reliability. If such data is interrupted by unavailability of the PJM member
EMS, then the PJM member is required to have a backup capability to ensure that
the necessary data continues to be provided to PJM.
 NERC Standard TOP-008, R1-4 requires PJM to take immediate action to mitigate
potential and actual IROL or SOL violations. Many of those actions require the PJM
member to execute actions requested by PJM. If the unavailability of the PJM
member EMS or other tools prevents the execution of those actions, then the PJM

PJM © 2014 21
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 2: Member Control Center Requirements

member is required to have back up capability to ensure that it can execute PJM-
requested actions.

PJM © 2014 22
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

Section 3: Data Exchange Requirements


Welcome to the Communications & Data Exchange Requirements section of the PJM
Manual for Control Center Requirements. In this section you will find the following
information:
 Data exchanges with new PJM Members (see “Introduction”).
 Data exchanged between PJM and PJM Member’s EMS systems (see “Energy
Management System (EMS) Data Exchange”).
 Information available to Market Participants (see “OASIS Information Exchange”).
 Data exchanged over telephone and facsimile machines (see “Dispatch Voice and
Facsimile Communications”).
 Usage of backup communications systems (see “Alternative Voice
Communications”).
 Requirement to support both PJM dispatch centers (see “EMS ”).

3.1 Introduction
Communications between PJM Members and PJM depend upon a combination of electronic
data, dispatch and business voice links, facsimile, Internet communications (e.g., to OASIS),
and floppy disk and paper reports sent by courier or US mail.
 PJM Members (and PJM) may require additional time after signing the Operating
Agreement to establish electronic data links.
 PJM Members with real-time data to be exchanged with PJM and with a significant
participation in the supply of information to the PJM RTO require electronic
communications via the EMS and eSuite data exchanges.
 New PJM Members with a small amount of data to be exchanged and that do not
require real-time links to PJM should use facsimile and voice communications for
their PJM communications.
 New PJM Members already communicating with PJM through another PJM
Member’s electronic communications systems should arrange to continue using
those communications systems where this is feasible; separate electronic
communications links can be planned and installed subsequently if necessary.

PJM © 2014 23
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

3.2 Energy Management System (EMS) Data Exchange


Energy Management System (EMS) information is exchanged between PJM EMS
computers and the EMS systems of PJM Members primarily to support real-time functions
such as PJM RTO network monitoring, generation control, and security analysis as well as
non-real time functions, such as generation scheduling, accounting information, messages,
and reports. The information exchange occurs periodically, by exception, and upon demand.
3.2.1 EMS Communications System
PJM and PJM Members exchange EMS information between their respective EMS
computer systems via PJMnet, which is a dual redundant MPLS (Multiprotocol Label
Switching) network using the Inter-control Center Communications Protocol (ICCP).
3.2.2 PJM EMS Communication Protocols
The EMS utilizes a communication protocol based on the Inter-control Center
Communications Protocol (ICCP) standard. PJM supports block 1 (scanned data), block 2
(exception data) and block 4 (messages) of this protocol. PJM requires that members
support blocks 1 and 2.
ICCP is a comprehensive, international standard for real-time data exchange within the
electric power utility industry. It is intended to support inter-utility real-time data exchange
which is vital to the operation of interconnected systems.
A detailed description of the format and content of the ICCP Conformance Blocks as
adapted to PJM needs may be found in the following documents:
 PJM ICCP Network Interface Control Document (NICD) Version 1.1, dated March 27,
2000.
 PJM ICCP Communications Workbook Version 1.1, dated March 27, 2000.
 Running list of updates to the PJM ICCP NICD and Workbook, Version 1.1, January
30, 2001.
The appropriate documents will be supplied to applicant PJM Members to describe data
types and message structures and to supply detailed information on network protocol and
line discipline.
3.2.3 EMS Data Exchange
EMS data is exchanged between each PJM Member’s EMS and the PJM EMS computer
system periodically on one of several fixed cycles, as well as on demand, by exception, and
interactively.
 The EMS data sent cyclically from PJM Members to PJM includes the following types
of information sent with associated data quality codes:
o data needed for the PJM control programs
o data needed for monitoring generation
o data needed for monitoring transmission
o data needed for monitoring interchange

PJM © 2014 24
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

 The EMS data sent cyclically from the existing PJM EMS to each PJM Member’s
EMS includes the following types of information:
o System control data
o Generation and transmission information required for monitoring and security
analysis programs
o Area Regulation data
 Cyclic data exchanged at the fast scan rate (i.e., two seconds) is used to develop the
PJM Area Control Error (ACE) and associated individual PJM Member Area
Regulation megawatt values. Cyclic data exchanged at a slower scan rate (i.e., every
ten seconds) is used to develop dispatch control values, security monitoring, and
data tracking.
 Cyclic data may also be sent hourly from PJM Members which define the
accumulated energy values.
 PJM Members are responsible for the accuracy of the data they send to PJM. A
maximum of 2% overall inaccuracy in the repeatability of data from transducers or
potential transformers/current transformers (PTs/CTs) is allowed for instantaneous
monitored values (see Section 5, Meter Accuracy Standards). Hourly MWh readings
data must be provided to PJM daily to ensure accurate billing. Regular calibration of
PJM Member metering is necessary to keep the data as accurate as possible (see
Section 4, Billing Metering Standards).
 Data exchanged either by exception, on demand, or interactively between PJM
Member’s and the PJM EMS systems include the following:
o Breaker, disconnect, and line status changes, with associated data quality code
information (integrity scans for exception data shall be at 30 minute intervals)
o Emergency messages in text format
Each PJM Member is responsible for determining data quality indicators for all data
transmitted to PJM. Both failed individual values and any value calculated using a failed
point must be flagged. At times, state estimated values may suffice for an interim period.
However, when a point fails for an extended period, a manual update of the point’s value is
necessary to keep the data as accurate as possible.
PJM member systems will report to PJM the outage of any equipment which handles
telemeter 345 kV or higher and tie data sent to PJM. This equipment includes remote
terminal units (RTU), data links, etc., which telemeter 345 kV and higher voltage facilities
and tie line values, megawatt flows, megavar flows, and voltage. Scheduled outages should
be reported one day in advance, and again prior to switching the equipment out of service.
The loss of any of this equipment should be reported immediately after such an occurrence.
The PJM control room should be notified when the outaged equipment is returned to
service.
When data communication outages occur, the following data must be kept manually (or
electronically should manually prove impractical) updated:
 Megawatt line flows for 345 kV or higher lines and all tie lines. If megawatt values
cannot be given, provide the best data available, i.e. MVA, state estimated data, etc.

PJM © 2014 25
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

 Bus voltages for all 345 kV or higher stations.


Affected data must be updated:
 After the loss of a major generator or transmission line;
 When the data value has a detected change of more than 100 MW on a 500 kV or
higher line, or more than 50 MW on a 345 kV and below;
 At least every 30 minutes, and more frequently as determined by PJM.
 Whenever changes occur, 500/345/230 kV tap changes and 345 kV or higher
breaker positions should be manually updated. MVAR values for the 345 kV or
higher lines will be updated only when requested by PJM.
3.2.4 PJMnet Communications System
PJMnet is a dual-redundant MPLS network that PJM utilizes as the primary wide-area
network for communicating Control Center data to and from PJM. PJMnet will support:
 Inter-Control Center Communications Protocol (ICCP) data links to Control Centers.
 SCADA links to plants via remote terminal units (RTUs) using Distributed Network
Protocol (DNP).
PJMnet connects member Local Control Centers (LLCs), Market Operations Centers
(MOCs) and generating plants to PJM's Control Centers. The number of physical interfaces
and their capacity will be determined by the impact of your facilities on overall PJM
Operations. LCCs, MOCs and generating plants are expected to install metering and use
their own EMS/GMS/SCADA or equivalent system to collect data. PJM will provide ICCP
network connections and router(s) at the member company location.

PJM © 2014 26
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

Exhibit 5 in Manual 14D


(http://www.pjm.com/documents/~/media/documents/manuals/m14d.ashx) shows the types
of equipment necessary for exchanging generation data with PJM.
PJM will supply a PJMnet connection to LCCs and generation sites per customer eligibility
as indicated in manual 14D. This will include installation of the frame relay connections
(local loop, PVC’s, etc.) and routers as well as ongoing Network Operations Support and
maintenance of the PJMnet components. If dual circuits are provided, PJM will route them
as diverse from each other as practicable within the existing infrastructure. Installation will
be completed within 90 calendar days of the completion of the site survey contingent upon
timely completion of the member supplied items. The member company will be responsible
for the following:
 AC power within five (5) feet of equipment site.
 Power outlet(s) will be quad box outlet on a separate breaker for each router.
 Adequate cooling.
 Mounting location for PJMnet router and modem equipment.
 An environment clean and free from excessive dust or debris, dry (5 to 95%
humidity, non-condensing), of moderate temperature (32 to 104 degrees F), well-
ventilated and well-illuminated.
 Adequate station ground.
 Dial up modem lines for out of band router access by NOC.
 Return of the “Welcome Letter” either agreeing to PJM assigned IP address scheme
or providing specific member requirements in this area.

3.3 OASIS Information Exchange


PJM is responsible for providing the Open Access Same-time Information System (OASIS)
for PJM RTO Transmission Providers and Customers (see the PJM Manual for PJM OASIS
Operation (M-04)). The information on the OASIS network includes Available Transfer
Capability and other important transmission and ancillary services data. Market Participants
are responsible for establishing Market Operations Centers which implement the necessary
communications with OASIS.
3.3.1 Transmission Customer Communications
Transmission Customers use the public Internet to access PJM OASIS. OASIS Customers
must register with PJM before they access the PJM OASIS system and login each time a
connection is established. The primary interface to request transmission or ancillary service
and to provide information to PJM OASIS is on-line data entry forms available on the OASIS
display pages. These forms are used to request the purchase of services and to offer
products for sale, as well as to post other transmission-related information. Instructions on
how to interface with OASIS are available on the OASIS display pages or from the PJM
OASIS Account Administrator. If a Transmission Customer enhanced OASIS connections, a
direct connection is available, at additional cost.

PJM © 2014 27
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

3.3.2 Transmission Provider Communications


Transmission Providers may connect to the PJM OASIS system via the Internet and it is
possible for them to use SQL*NET protocol and ORACLE Forms user interface software to
display and post information to the OASIS. ORACLE Forms are used to post and modify
data, approve purchase requests, offer products for sale, and post “Want” ads. PJM is
responsible for administering and posting information associated with the provision of
transmission service as required by FERC.

3.4 EMS Backup Communications


PJM utilizes two systems (AC1 and AC2) for PJM EMS control information as backups for
one another. PJM requires all ICCP members to send identical sets of data to both systems
by use of two ICCP Links. Members may also use these links to receive identical PJM ICCP
data from both systems, or utilize a third ICCP Links that will be used to receive data from
PJM. This third link must have the ability to connect to AC1 and AC2 to receive data.
PJM Transmission Owners with Ties to transmission systems external to PJM will provide tie
information to the PJM GMS system as a backup to the PJM AC1 and AC2 systems.

3.5 Real-Time Analysis Monitoring Requirements for System


Security
PJM analyzes the system security of the PJM system using information telemetered from
PJM Members. Phase and line-end location of metering is as mutually agreed between the
two connected systems, must be consistent with established system metering, and must be
coordinated with PJM. The following analog and status information is required for this
analysis:
 Required Analog Data:
o Voltages for buses at 34 kV and above (or 69 kV and above, if lower voltage
equipment is not monitored), MW and MVAR values for generating units greater
than 1 MW including steam, nuclear, hydro and combustion turbine units and
non-utility generator units (usually individual unit generation but total station
generation may be telemetered in special circumstances) if connected directly to
the transmission system.
o MW and MVAR values (both ends) for designated transmission lines at 69 kV
and above (if single-phase metering is employed, the B-phase is preferred)
o Transformer phase angle regulator (PAR) tap positions for modeled and
controlled transformers (high side metering or low side with a loss calculation)
o MVAR values for synchronous condensers
o MVAR injection on 34 kV buses (or 69 kV if lower voltage equipment is not
monitored)
o Selected station frequencies
o Frequency of Acquisition — <10 seconds
 Required Status Data:

PJM © 2014 28
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 3: Data Exchange Requirements

o Circuit breaker status for each modeled facility at 69 kV and above


o Breaker and disconnect statuses as modeled
o Transformer fixed tap settings (change in no-load tap setting)
o Frequency of Acquisition — Upon change of status.
PJM Members have the capability to validate data and send accurate manually adjusted
data until inaccurate metering is corrected if state estimated data will not suffice. In case of a
computer failure or outage, all data should be sent once the computer reinitializes. See the
PJM Manual for Transmission Operations (M-03) for more information.

3.6 Dispatching Requirements


The following requirements are intended to assure reliable dispatch and operation of the
PJM system:
 All tie line MW and MWH data are telemetered to PJM and the neighboring Control
Area and emanate from a common agreed upon terminal using common primary
metering equipment. Daily billing MWH data can be submitted via Power Meter.
 Tie-line MWH metering is not submitted on an hourly basis per NERC Standard BAL-
005-0, however, this data is submitted on a daily basis via Power Meter.. PJM
Dispatch utilizes an EMS alarming process to compare State Estimator data to tie-
line telemetry in order to detect data accuracy issues on a more frequent basis than
hourly intervals.
 Combustion turbines supply accurate real-time status information and report failure-
to-start situations.
 500 kV and significant 345 kV and 230 kV locations require disturbance recording
equipment for post-disturbance analysis. These devices should have the capability to
retain historical data for future analysis.
 PJM Members participate in the payback of the accumulation of inadvertent
interchange as directed by PJM.
 The amount of generator regulating capacity reported to PJM is accurate and
committed to the system.
 The amount of generator reserve capacity reported to PJM is accurate and
committed to the system.
PJM Members, generating stations, and fault recorders are time synchronized to assure
accurate recording times for system events.

PJM © 2014 29
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 4: Voice Communications

Section 4: Voice Communications

4.1 Dispatch Voice & Facsimile Communications


The dispatch voice system provides high-priority voice communications between PJM and
various PJM Members, as described below. The dispatch voice system hardware consists of
the All Call system, Ring Down circuits, and manual dial circuits. Equipment at PJM includes
a British Telecom (BT)) / BT digital switch and a Nortel Meridian PBX. Access and
interfacing to the communications service providers is configured so that either switch can
operate in stand-alone mode, but economy and performance are optimized when they are
operating together.
Communications via facsimile machines is another redundant means of exchanging
information between PJM operations, accounting, and planning personnel and all categories
of PJM Members.
PJM and PJM Members shall use English as the language for all
communications between them and shall issue directives in a clear,
concise, and definitive manner. These communications shall ensure the
recipient of the PJM Directive repeats the information back correctly and
the initiator shall acknowledge the response as correct or repeat the
original statement to resolve any misunderstandings (i.e., 3-Part
Communications) per NERC COM Standards.
4.1.1 All Call System
The All Call system is used by PJM operators to contact Local Control Centers (LCCs),
Market Operations Centers (MOCs), and Load Serving Centers (LSCs), either individually or
simultaneously for information exchange under both normal and emergency situations. The
All Call is based on the Dialogic Communications Corp. Communicator, an emergency
notification system that provides PJM system operators the ability to broadcast voice, text or
fax messages. The All Call operates over PSTN (Public Switched Telephone Network). The
system is capable of sending messages to 72 numbers simultaneously. If the more than 72
locations must be contacted the system will dial the additional numbers as lines become
available. Continuous retry logic ensures 100% of the facilities are contacted by cycling
through primary, secondary, and tertiary numbers until positive confirmation of message
receipt. Both real-time displays and reports of response status are available to PJM System
Operators.
Each control facility is required to have a dedicated PSTN line for the primary All Call
number. Secondary and tertiary do not have to be dedicated to the All Call System; they
may be PBX or cellular, not pager. Acknowledgement of message receipt by each
participant is required. Logs of responses and response times are provided to PJM’s
Performance Compliance department for analysis.
4.1.2 Ring Down Circuits
Private Lines with automatic ringing (PLAR) or dual central office (DCO) lines are used to
provide Ring Down or simulated Ring Down capability to LCCs, some Market Operations
Centers (MOCs), and Load Service Centers (LSCs). These circuits provide virtually
instantaneous point to point access between PJM and PJM Members.

PJM © 2014 30
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 4: Voice Communications

4.1.3 Manual Dial


In addition to private line capability, the PJM BT switch also interfaces with both the PJM
Meridian PBX and Central Office (CO) Lines to provide manual dial capability to all
categories of PJM Members via the Public Switch Telephone Network (PSTN). Manual dial
serves as backup to the Ring Down system in case that system fails.
4.1.4 Facsimile Communications
Facsimile communications is widely used in the PJM Control Center to communicate with all
PJM Members. Facsimile machines support energy marketing, energy scheduling, unit
scheduling, accounting, dispatch operations, and system restoration. These facsimile
machines are connected to either the PJM Nortel Meridian PBX or CO Lines.

4.2 Alternative Voice Communications


The dispatch voice system (All Call, Ring Down, and manual dial PBX) is designed to
provide voice communications during normal circumstances. Should the PJM primary All
Call System, Ring Down, Manual Dial, and Facsimile Communication fail, the following
systems provide alternative communication capabilities in the event the normal system is not
effective for some reason:
4.2.1 Business Voice System
Each dispatch position is provided with a standalone phone set, configured with speed dial
using CO Lines, which serve as a backup for the PJM BT switch to provide communication
between the PJM control center and all PJM Members in the event of BT switch failure.
4.2.2 Cellular Telephones
Cellular telephones are used by PJM dispatchers as an alternate method of voice
communication. Cellular phones can be used to coordinate activities while physically moving
personnel to the PJM emergency dispatch center.
4.2.3 Satellite Telephones
Satellite telephones are used by PJM dispatchers as an alternate method of voice
communication. These telephones are used to protect against loss of common carrier
services.
Transmission Owners shall have satellite phone capabilities at both their primary and back-
up facilities. Satellite phones are required for all Generation Operator (GO) control centers
which control one or more units totaling 500 MW or greater.
Functional Requirements for Satellite Phones:
 Compatible with PJM satellite network
 Ability to receive dedicated all-call
 Ability to bypass the ground phone (PSTN) network
Additional Notes:
 If the emergency plan for a generator control center is to co-locate with a
transmission control center which has a satellite phone, this will meet the

PJM © 2014 31
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 4: Voice Communications

requirement, however, companies need to examine the availability of these systems


for both transmission and generator communications during an emergency.
 Companies need to also provide similar (radio, satellite, etc.) redundant
communications from their control centers to their plants.
 PJM may also require specific vital generation units to maintain a satellite phone.
4.2.4 Three Part Communications
All operators should use their name and company name when answering a phone call. This
will ensure that the caller has the correct party prior to communication beginning.
PJM system operators and member transmission and generation operators should always
practice three-part communications to avoid errors and miscommunications.
Three-part communications consists of the sender delivering the message to the receiver.
The receiver repeating back the information to the sender while questioning for clarification.
The original sender will confirm if the receiver has the message correct.
Three-part communications is required when the operators are exchanging important
operational information. A partial list of these situations is presented below. If there is a
question about whether the situation warrants the use of three-part communication, it should
be used.
Examples of generation operations utilizing three-part communications:
 Unit starts
 Unit trips or releases
 Requests from PJM for additional generation
 Outages (eDART ticket numbers and unit designations)
 Synchronized Reserve or Regulation assignments
 Manual dispatch of generation
 Emergency operations related information
Examples of transmission operations utilizing three-part communications:
 Transmission switching
 Capacitor switching
 Outages (eDART ticket number and line numbers, not every circuit breaker)
 PCLLRW issuance and cancellation
 TLR curtailments in transactions
 Market to Market redispatch
 Emergency operations related information
In addition, it would be expected that anytime information is exchanged that is not
thoroughly understood (whether it be due to speech impediment, accent, or because
information was not clearly articulated, etc.), a repeat back should be requested and
followed up on, constituting three-part communications. The use of the term “directive”

PJM © 2014 32
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 4: Voice Communications

should be used if additional clarification is needed - either by the issuer or the receiver of the
critical communication.
In order to facilitate the clear communication of Transmission Operations instructions to field
personnel, there is also a requirement for Transmission Owner operators to use three-part
communications to communicate switching instructions associated with BES facilities.
PJM All call messages do NOT require repeating as the receiver can repeat the message
via telephone keypad selection. It is the responsibility of any party receiving information via
an all call to follow up with the initiator of the information if there is not a clear understanding
of the message. PJM receives confirmation of member confirmation through electronic
means and will follow-up with individual companies if appropriate.
PJM also performs communication audits of operator conversations to ensure that three-part
communication is being consistently utilized.
In addition, it is possible for PJM to issue directives in each of its operational roles (as the
RC, TOP, or BA). PJM Directives are defined as instructions from PJM to its members to
take actions to control Inter Regional Operating Limits (IROL) or initiate load dump
measures for capacity or transmission emergencies as described in PJM Manual 13,
Section 2 and Section 5. These Directives could be issued through a PJM All Call or
through direct voice communications to the applicable member companies. The following
are examples of communications which could be considered Directives by PJM (PJM
Directives require 3 part communication):
 PJM as Reliability Coordinator:
o Direct actions to implement load dump plans to control IROLs
 PJM as Transmission Operator:
o Directing Generation to manually lower or increase unit output outside of
automated dispatch signals to control IROLs
o Directing selected generation to trip off-line to control IROLs
o Direct actions to implement load dump plans for the purposes of transmission
control
 PJM as Balancing Authority:
o Directing Generation to deploy synchronous reserves to restore DCS after a unit
trip to control an IROL
o Direct actions to implement load dump plans to rectify capacity deficiencies.
 All operators must be cognizant of the time constraints associated with system
operations such as limits over emergency ratings, load dumps, IROLs, DCS events,
etc. It will often be necessary to quickly confirm status, ratings, output, options, etc.
prior to initiating the directive or operational instruction. Once this is complete, the
PJM operator will initiate the instruction by:
o Restating the desired action
o Receiving and or requesting the repeat back by the receiver
o Acknowledging the correct repeat back

PJM © 2014 33
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 4: Voice Communications

o From this point on, the receiving operator should be focused on implementing the
directed actions.
NOTE: PJM members are obligated to follow all operational instructions or
Directives as described in the PJM Operating Agreement, NERC Standards
and PJM Manuals. If a PJM member is unable to comply with PJM
instructions, the member should notify PJM of the restriction (based on
safety, loss of life, or damage to equipment) so PJM is able to implement
other actions to alleviate the operation problems.

PJM © 2014 34
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

Section 5: Metering Requirements


Welcome to the Metering Requirements section of the PJM Manual for Control Center
Requirements. In this section you will find the following information:
 A general description of the purpose of having billing metering standards (see
“Purpose & Criteria”).
 The overall requirements for the billing metering (see “General Guidelines”).
 The basic metering requirements in terms of accuracy, backup, location, alternative
installation methodology, tie circuits, non-contiguous load, and maintenance (see
“Primary Metering Requirements”).

5.1 Purpose & Criteria


All electricity recording metering equipment is operated and maintained to assure, to the
maximum extent possible, that the equipment provides an accurate record of the quantities
supplied to and received by all parties. Each PJM Member is responsible for properly
maintaining its metering and telemeter equipment in accordance with applicable ANSI
standards.
This section provides the minimum standard requirements for the billing metering for new
meter installations to be used in transactions with PJM. The standards apply to new meter
installations, replacement meter installations, or upgrades to existing installations.
The standards in this section are a minimum requirement and do not supersede more
restrictive agreements. In cases in which standards differ, the most restrictive criteria take
precedence. More specific standards may be required by local, state, or federal regulations,
host utilities, service providers, or as are mutually agreed upon.

5.2 General Guidelines


All PJM Members involved with any interface with PJM shall abide by the following general
guidelines for Billing Meter Standards:
 Reliable and compliant operational metering equipment is in place for any metered
service that is billed.
 Meter information is automatically and electronically communicated to PJM by the
producer, host utility, or transmitter in order to ensure timely accounting and billing.
This enables PJM to identify and resolve erroneous information and to account and
bill for services. Communication between PJM Members other than PJM may utilize
any method, such as voice notification or paper document if mutually agreeable.
 Billing metering systems are capable of collecting and storing bi-directional
information for intervals as determined by the parties involved. The expense and
practicality of reporting information for small data intervals may not be cost effective
or prudent. The average of instantaneous values can be used, provided that a
mutually agreed upon accuracy is obtained and applicable standards are achieved.
Meter intervals can be of lesser duration for some services, but common intervals
are fifteen minutes, thirty minutes, and sixty minutes. Collected meter information

PJM © 2014 35
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

may be transmitted to the appropriate parties with a different frequency than it is


collected, as communications systems permit.
 The megawatt-hour (MWh) is the standard unit of service measurement. Service
may be measured in kilowatt-hours (kWh) if required by specific services, local or
state regulations, host utilities, service providers, or as are mutually agreed upon by
the parties involved. kWh information may be used by the parties involved but must
be converted to MWh information before transmission to PJM.
 All metered generator data values are to be supplied to the required parties in “net”
form. “Net” shall be defined as “gross” output minus unit station light and power
components. When metering limitations require “gross” values to be used, the
“gross” to “net” calculation method must be approved by the PJM Operating
Committee for use by PJM Members in the calculation of “net” data values.
 All meter records and associated documentation is retained for a period of seven
years for independent auditing purposes.
 Any dispute involving any aspect of the billing metering standards or their application
are resolved as described in the PJM Manual for Administrative Services for the
PJM Interconnection Agreement (M-33).

5.3 Primary Metering Requirements


The primary metering requirements are:
 For billing purposes, watt-hour meters are recognized as the official source of meter
information.
 Metering devices must be capable of collecting and storing information for intervals
required by the service provided, and as mutually agreed upon by the parties
involved.
 Any generation unit participating in the PJM Energy Market is required to have
independent metering devices that are capable of recording generation net MWh
output. When metering limitations require variance from this standard, the metering
system must be mutually agreed upon by the parties involved.
 All manual or additional meter reading or comparisons required to ensure consistent
valid meter information (“true-up”), are performed prior to the billing cycle, as
mutually agreed upon by the parties involved. Current billing cycles are monthly.
Each meter must follow the specific metering requirements associated with:
 Accuracy
 Backup Metering Requirements
 Location of Meter Points
 Alternative Approach
 Tie Line Telemetry Specification
 Geographically Non-Contiguous Load
 Maintenance

PJM © 2014 36
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

5.3.1 Accuracy
The minimum metering accuracy for each measuring device is defined by prevailing ANSI
and NERC standards. The standards in this attachment are a minimum requirement, and do
not supersede more restrictive agreements. In cases in which standards differ, the most
restrictive criteria take precedence.
The manufactured accuracy class of all energy interchange billing devices should be
accurate within ±0.3% of full scale.
An individual metering system at a metering point location includes all components from the
meter location through to the system operator destination. The accuracy of the total energy
interchange billing metering system, at each generator or transformer location, is to be
within 1.0%. More restrictive standards may be required by local or state regulations, host
utilities, service providers or as are mutually agreed upon by the parties involved.
Each individual metering system at each metering point location used for billing is tested by
the owner of the equipment at intervals of two years and its accuracy of registration
maintained in accordance with good practice. At the request of any party, an individual
meter system will be tested, but, if an error of less than 1.0% is observed, the requesting
party will pay for the test. PJM is to be notified of the error for auditing purposes.
5.3.2 Backup Metering Requirements
The backup metering system is of sufficient accuracy to serve as a replacement for the
primary metering system. The average of instantaneous values may be used as a backup
source, provided mutually agreed upon accuracy is obtained and applicable standards are
achieved.
The backup metering system is capable of collecting interchange data and logically
comparing data with the primary meter system so that material differences may be detected
in a reasonable time.
If any test of an individual metering system discloses an error of greater than 1.0%, the
accounts of the parties shall be adjusted for no more than two months for which the
inaccuracy is estimated to have occurred. Longer correction periods, if confirmed by
recorded information or defined as a result of the dispute resolution process, may be
mutually agreed upon by the parties involved. All errors of the above magnitude shall be
reported to PJM and documented for auditing purposes.
5.3.3 Location of Meter Points
Interchange billing metering is provided on the system as follows:
 Transformers: Through-Transmission — EHV interchange metering points are
provided from the secondary side of all through-transmission transformers connected
to the 500 kV EHV system. For example, interchange metering is provided on the
230 kV side of a 500/230 kV through-transmission transformer.
 Generators and Transformers Radially Tapped — Generators and transformers that
are not through transmission (including unit station service transformers) and that are
tapped directly on the 500 kV EHV system are provided with interchange metering
on the primary side (500 kV) of the step-up, station service or radial transformer. For
instance, a generator connected to the EHV system has an interchange metering
point on the 500 kV side of the unit step-up transformer. All other generators and

PJM © 2014 37
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

transformers not connected to the 500 kV system provide information as received


from the high side or the low side of the unit transformer.
5.3.4 Alternative Approach
In lieu of providing interchange billing metering, a PJM Member may elect to install a watt-
hour metering system on the opposite side of the transformer than directed above (the 500
kV side of the through-transmission transformer or the 230 kV side of the radial
transformers) provided that a compensation system is included to capture and adequately
adjust interchange values to account for transformer losses. Any design for alternative
metering approaches shall be documented and made known to PJM and all parties
involved. Any alternative approach must be approved by PJM.
For through-transmission transformers, interchange values may be determined from the 500
kV side if compensation is installed which subtracts transformer losses when power is
imported to the PJM Member or adds transformer losses for exported power.
5.3.5 Tie Line Telemetry Specification
Following are the telemetry requirements for monitoring PJM Ties with any neighboring
external Balancing Authority (BA) (See Figure 1). These requirements are also applicable to
ties defined between Transmission Zones internal to PJM (eg: AEP-DEOK etc.) (See Figure
2) This will apply to any existing tie lines that get modified.

From the primary metering BA/Transmission Operator (TO):


1. Primary Meter Reading (Required) – this value must be revenue quality and reflect
the value that originates from the meter that has been agreed upon with the
neighboring BA/TO as the Primary meter.
2. Secondary Source Secondary Meter Reading – this value represents the through
pass of the tie line secondary meter measurement by the BA/TO that has the primary
metering and should be sent to PJM if available. (Same value as received from the
TO having the Secondary Meter Reading (4), via a different data communication
path).
3. If the PJM TO is the primary metering end of the line for external tie-lines then PJM
will need to send that value to the neighboring BA.

PJM TO/BA PJM TO/BA


2

1
4

P S P Tie Line A S P S
3
5
Primary Meter Secondary
Meter

PJM

Figure1: Telemetry Requirement for External Tie-lines

PJM © 2014 38
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

TO Zone TO Zone

1
4

P S P Tie Line A S P S

5
Primary Meter Secondary Meter

PJM

Figure 2: Telemetry Requirements for PJM Internal Tie-Lines between Transmission Zones

Required
Optional
If PJM TO is Primary end, need to send primary metering to BA

From Secondary BA/TO Control Zone;


4. Secondary Meter Reading (Required) – the tie line secondary meter that can be
used during primary meter outages or maintenance; the value for this meter should
be sent to PJM.
5. Secondary Source Primary Meter Reading – this value if available must reflect the
value that originates from the meter that has been agreed upon with the neighboring
PJM BA/ TO Control Zone as the Primary meter (same value as received in the TO
Primary Meter Reading (1), via a different data communication path).

Tie line notification:


The TO is required to submit all new tie lines requests before the 1st of the month prior to
the month of the requested tie line being energized at the PJM SOS meeting. The TO who
does the notification should know which end is the primary metering point and expected
date the line is to be energized.

Dynamic Schedule/ Pseudo Tie Telemetry Specification:


Following are the telemetry requirements for monitoring PJM Dynamic Schedules/ Pseudo
Ties with any neighboring external Balancing Authority (BA).

From the primary metering BA/Transmission Operator (TO):


1. Primary Meter Reading (Required) – this value must be revenue quality and reflect
the value that originates from the meter that has been agreed upon with the
neighboring BA/TO as the Primary meter.

PJM © 2014 39
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

2. Secondary Source Primary Meter Reading – this value must reflect the value that
originates from the meter that has been agreed upon with the neighboring PJM BA/
TO Control Zone as the Primary meter (same value as received in the Primary Meter
Reading, via a different data communication path).
3. For PJM Members any dynamic schedule over 10 MW the data link that the values
are sent over must be setup to use a PJM-NET connection.
Any exception to the required telemetry will be reviewed on a case by case basis at PJM’s
discretion.

Dynamic Schedule notification:


PJM must be notified as soon as possible of new Dynamic Schedules and PJM will
determine if the time line is achievable.

Tie Line and Dynamic Schedule/ Pseudo Tie Telemetry Specification:

Time line to receive telemetry:


All required telemetry shall be available 2 weeks in advance of the tie line being energized.

Telemetry accuracy:
All tie line telemetry shall be scanned at a periodicity of equal to or less than 4 seconds (2
seconds is preferred) and 2 % accuracy for entire range. Metering issues/outages impacting
accuracy of available telemetry should be brought to PJM’s attention by TO/ Generation
Company owning the metering along with an estimate on when the issues will be resolved.

Telemetry Link Requirements:


Type of
AGC input type Redundancy Data Link Type
Tie Line voltage greater than or equal to 69 redundant point Dual PJM Net
KV source Connection
DNP over internet or
Tie Line voltage less than 69 KV existing ICCP
single point source connection
Dynamic Schedule/ Pseudo Ties greater redundant point Dual PJM Net
than or equal to 100 Mw source Connection
Dynamic Schedule/ Pseudo Ties greater
than or equal to 10 Mw and less than a 100 redundant point single PJM Net
MW source Connection
DNP over internet or
Dynamic Schedule/ Pseudo Ties less than
existing ICCP
10 MW
single point source connection

5.3.6 Geographically Non-Contiguous Load


Any PJM Member serving a load which is geographically non-contiguous to its defined
service area documents and makes known to PJM, and all other parties involved, any
metering and system conventions implemented in order to meter the load. Metering devices

PJM © 2014 40
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

may be met by contractual arrangement with any party involved. Any alternative approach
must be approved by PJM prior to implementation. This enables PJM to monitor and control
the transmission system, to identify and resolve erroneous information, to account and bill
for services and to take appropriate action for reliability concerns.
5.3.7 Maintenance
The accuracy of all recording meters, as required to transact energy services, is verified by
tests conducted by the equipment owner once every two years. If such test identifies, or
other indications show, a recording meter is out of service or inaccurate, the owner must
take action to restore the meter to correct operation within a reasonable time. In the interim,
backup metering may be used as mutually agreed by the parties involved. All equipment
must be restored to correct operation within the period of 30 days from the date of
discovery, or a date mutually agreed upon by all parties. If equipment installation or
replacement is required to resolve the inaccuracy, all equipment must be correctly operating
at a date mutually agreed upon by all parties. PJM is notified of the inaccuracy, interim
procedures, and resolution for auditing purposes.
Periodic accuracy compliance testing may be requested by PJM Member agreement
groups, as required. Authentication of current meter testing and validation of newly installed
or repaired meter systems may also be required.
The results of all accuracy testing are reported to PJM. As a minimum, PJM maintains a
metering database documenting the test results for all PJM Member metering tests that
show errors of greater than 1% for auditing purposes.

5.4 Meter Accuracy Standards


Welcome to the Meter Accuracy Standards section of the PJM Manual for Control Center
Requirements. In this section you will find the following information:
 A general description of the purpose and applicability of metering standards (see
“Purpose”).
 The overall requirements for telecommunications metering (see “General
Guidelines”).
 The overall requirements for metering accuracy (see “Primary Metering Accuracy”).
 Requirements for data needed for system control data (see “System Control
Monitoring Requirements”).
 Requirements for data used in system security monitoring (see “Real-Time Analysis
Monitoring Requirements for System Security”).
 A description of the requirements intended to assure reliable dispatch (see
“Dispatching Requirements”).
5.4.1 Purpose
This section provides the minimum standard requirements for telecommunications metering,
such as MW, MVAR, and kW values, to be used when communicating information to PJM.
The standards apply to new meter installations, replacement meter installations, or
upgrades to existing installations. The requirements for billing meters are covered in Para
5.3.1.

PJM © 2014 41
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

These standards are a minimum requirement and do not supersede more restrictive
agreements. In cases in which standards differ, the most restrictive criteria take precedence.
More specific standards may be required by local, state, or federal regulations, host utilities,
service providers, or as are mutually agreed upon.
5.4.2 General Guidelines
All PJM Members involved with any interface with PJM abide by the following general
guidelines for telecommunications metering:
 All electric measurement equipment is operated and maintained so as to assure, to
the maximum extent possible, that it provides an accurate record of the quantities
supplied to and received by all parties.
 Each PJM Member is responsible for properly maintaining its metering and telemeter
equipment in accordance with applicable ANSI standards.
 Metered information is automatically electronically communicated to PJM by the
producer, host utility or transmitter in order to ensure system security and reliability.
 It is important to recognize the importance of accurate data as well as the need to
meet deadlines associated with updating this data, since the failure to provide
accurate and timely data affects reliable system operations.
5.4.3 Primary Metering Accuracy
For all new metering installed since December 1, 1997, the following primary transducer
accuracy guidelines are followed:
Primary Transducer Accuracy
Guideline
Frequency Transducers 0.001 Hz
Potential Transformers 0.30% of Full Scale
Current Transformers 0.50% of Full Scale
MW/MVAR/Voltage 0.25% of Full Scale
Transducers
Remote Terminal Units (A/D) 0.25%of Full Scale

Exhibit 1: Primary Transducer Accuracy Guideline


This accuracy guideline results in an overall metering accuracy better than 2% and satisfies
the NERC BAL standards. Billing accurate telemeter data values should be supplied
whenever possible.

5.5 System Control Monitoring Requirements


Data required for system control monitoring provides PJM dispatcher with the necessary
information to meet the continuous requirement of matching the generation with the load
demand and to assure that system security is maintained. There are four classes of system
control data:
 System control data
 Area regulation data
 Dispatch data

PJM © 2014 42
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

 Reserve data
The frequency and accuracy of data transmission, unless otherwise noted, applies to the
primary source of telemeter data, the backup source when the primary is unavailable and
backup source for tie line and frequency data.
5.5.1 System Control Data
System control data is required to match the load demand with the available generation.
This is accomplished by measuring the actual tie-flow values and the actual frequency and
using them in a calculation with the scheduled total tie-line value and the scheduled
frequency. PJM Members that control generation participate in time error control by raising
or lowering frequency schedules by 0.02 Hz at the direction of PJM (see the PJM Manual
for Balancing Operations (M-12)).
System control data is also required to facilitate system restoration (see the PJM Manual
for System Restoration (M-36)). Specifically, a system frequency measurement is required
to be transmitted to PJM from each Transmission Zone. Frequency of Acquisition — <4
seconds, Metering Accuracy — 2%
Balancing Authority (PJM) Control Room Time Error and Frequency devices will be checked
and calibrated against a common reference at least annually. The Balancing Authority shall
adhere to the minimum accuracy values for measuring devices as follows:
 Digital frequency transducer, ≤ 0.001 Hz
 MW MVAR, and voltage transducer, ≤ 0.25 % of full scale
 Remote terminal unit, ≤ 0.25 % of full scale
 Potential transformer, ≤ 0.30 % of full scale
 Current transformer, ≤ 0.50 % of full scale
5.5.2 Area Regulation
Area regulation data is required to ensure that the instantaneous mismatches of load and
generation are corrected by sending a generation control signal to those plants/stations/PJM
Members scheduled to provide this ancillary service. PJM calculates the desired area
regulation signal and the signal is transmitted to the designated provider of this service.
 Frequency of Acquisition — <4 seconds
 Metering Accuracy — 2%
PJM Members must have the ability to receive a regulation signal and must have the ability
to adjust generation manually to maintain scheduled interchange if automatic generation
control becomes inoperative.
5.5.3 Dispatch Data
The plant/station/PJM Member provides to PJM the individual generation availability by
providing the necessary information to dispatch the generation. For PJM dispatchable
generation, the appropriate operating data points are provided to PJM either through an
EMS data link or through the eMarket interface whenever the data changes. For self-
scheduled generation, the self-scheduled value is transmitted twenty minutes prior to any
changes. PJM uses its Security Constrained Economic Dispatch (SCED) to determine the

PJM © 2014 43
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Section 5: Metering Requirements

appropriate generation output which is then sent to each plant/station/PJM Member in the
form of an individual unit MW base point, to be used as the dispatch signal, and an
individual unit dispatch lambda, used for informational purposes only. PJM Members with
generation notify PJM of any actual or potential changes in unit status or capacity.
 Frequency of Acquisition — <10 seconds
 Metering Accuracy — 2%
5.5.4 Reserve Data
The availability of generation reserve is transmitted to PJM from the individual
plant/station/PJM Member. This data is used to determine the reliability of the PJM RTO.
 Frequency of Acquisition — <10 seconds
 Metering Accuracy — 2%

PJM © 2014 44
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

Attachment A: Information Access Matrix


The following Information Access Matrix lists each of the major PJM services that affect PJM
Members. It differentiates these services by PJM member type and by information access
method. This Information Access Matrix should be considered as a rough approximation
only. The PJM Customer Relations and Training Department is available to provide more
specific information concerning PJM services and access methods.

A: Generation Scheduling Services


PJM
PJM Member PJM
Member PJM
Regional Member Neighboring
Information Services Load Member
Transmission Generating Control Areas
Serving Marketer
Owner Entity
Entity
Inputs to PJM
Hydro Constraint Information (pool
A.1 scheduled resources) [submitted daily by 2
hydro plants] via eDART
Generator Outage Information [submitted
A.2 1 4
daily] via eDART
Daily Generator Bids (cost, availability, etc.)
A.3 3
[submitted by noon for next day] via eMKT

A.4 Daily Area Regulation Bids via eMKT 7

A.5 Daily Synchronized Reserve Bids via eMKT 3

Outputs from PJM

Daily Hydro Schedules (hourly generation


A.6 2
and capacity) [read only] via eDART
A.7 Daily Hydro Schedule Updates via eDART 2

Daily Managers Report on Joint Owned


A.8 5
Units [reported to joint plant owners]
Daily Load Forecasts (peak loads,
A.9 congestion) via eDADA, Operational Data O O O O
page on pjm.com
Reliability Information (Forecasted Load via
A.1 eDATA, Minimum Generation Problems,
O X
0 Outages, Available Capacity) via eDART
and Emergency Procedures
A.1 Daily Generator Bid Confirmations (cost,
2
1 availability, etc.) via eMKT
Selected Generators (next day
A.1
schedule)[distributed to selected generator 2
2
owners] via eMKT
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

PJM © 2014 45
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

Exhibit 2: Generation Scheduling Services

B: EMS Services
PJM
PJM Member PJM
Member PJM
Regional Member Neighboring
Information Services Load Member
Transmission Generating Control Areas
Serving Marketer
Owner Entity
Entity
Inputs to PJM
CT Generator Availability Updates
B.1 1
via eMKT, eDART
Confirmed Regulation MWs via
B.2 7
eMKT
Telemetry Status & Analog Values
B.3 X X 6 4
[real-time] via SCADA or ICCP
B.3.
MW on BES Facilities X X
1
B.3.
MVAR on BES Facilities X X
2
B.3.
Voltages on BES Facilities X O
3
B.3.
Tap Position on BES Transformers X
4
B.3.
Frequency X X
5
B.3.
Status of BES Circuit Breakers X X
6
B.3. Phase Shifter Tap Position (if in
X
7 Zone)
B.3. Static VAR Compensator status (if in
X
8 zone)
B.3.
Status of some BES Disconnects O
9
B.,3.
Temperatures O
10

B.4 AVR/PSS Excitation Control 1

B.5 Black Start Test Data X

Outputs from PJM

B.6 CT On/Off Times for PJM Units Only 1

Requests for Regulation MWs via


B.7 7
SCADA , ICCP
Real-time Transmission Status (Line
Outages, etc.) [PJM dispatcher
B.8 X 4
communication to other CCs] via
SCADA, ICCP, and eDART
Real-time Generation Status
(Generation Inquiries, etc.) PJM
B.9 X 4
dispatcher communication to other
CCs, MOC

PJM © 2014 46
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

B: EMS Services
PJM
PJM Member PJM
Member PJM
Regional Member Neighboring
Information Services Load Member
Transmission Generating Control Areas
Serving Marketer
Owner Entity
Entity
Real-time Informational, Operational,
and Emergency Messages
B.10 X
[broadcast to all LCCs] via ICCP,
Emergency Procedures
Generation Dispatch [relayed < 10s,
B.11 X
or manually] via SCADA, ICCP
Generation Regulation Control
B.12 7
[relayed < 10s] via SCADA, ICCP
Real-time Telemetry (status & analog
B.13 values) [relayed to other CCs] via X X 6 4
SCADA, ICCP
AVR/PSS Excitation Control via
B.14 X
eDART
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 3: EMS Services

PJM © 2014 47
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

C: Historical EMS Data Services

Information Services PJM Member PJM PJM PJM Neighboring


Regional Member Member Member Control Areas
Transmission Owner Generating Load Marketer
Entity Serving
Entity
Inputs to PJM
C.1 Historical EMS Information X 4
Requests [submitted per
request to PJM for
processing]
Outputs from PJM
C.2 Historical EMS Information X 4
[distributed to requesting
parties]
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 4: Historical EMS Data Services

PJM © 2014 48
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

D: Transmission Maintenance Planning Services


PJM
PJM Member PJM
Member PJM Neighboring
Regional Member
Information Services Load Member Control
Transmission Generati
Serving Marketer Areas
Owner ng Entity
Entity
Inputs to PJM
3-4 Day Ahead Transmission
Maintenance Schedules [planned
D.1 X
outages, submitted by transmission
providers per Manual 03] via eDART
3-4 Day Ahead Neighboring Control
Area Transmission Maintenance
D.2 Schedules (planned outages) X
[submitted by neighboring control
areas] via phone and eDART
Outputs from PJM
3-4 Day Ahead Transmission
Maintenance Schedules (planned
D.3 X X
outages) [confirmation of D.1] via
eDART
3-4 Day Ahead Neighboring Control
Area Transmission Maintenance
D.4 X
Schedules (planned outages)
[confirmation of D.2]
Transmission Maintenance Schedule
(planned outages) [monthly report sent
D.5 X X
to all transmission providers] via
eDART
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 5: Transmission Maintenance Planning Services

PJM © 2014 49
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

E: Transmission Services
PJM
PJM Member PJM
Member PJM Neighboring
Regional Member
Information Services Load Member Control
Transmission Generating
Serving Marketer Areas
Owner Entity
Entity
Inputs to PJM
Transmission Reservations [reserved through
E.1 O X X
OASIS]

E.2 Network Transmission Services X

Outputs from PJM


Available Transmission Capacity [posted on
E.3 X X
OASIS]
Actual Energy Transactions [posted on OASIS
E.4 X X X X
7 days later]
E.5 Informational Messages [posted on OASIS] X X X X

E.6 Ancillary Services [posted on OASIS] X X X X

Approved Transmission Reservation Requests


E.7 X X
via OASIS
Summary of Month End Transactions via
E.8 X
billing, OASIS
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 6: Transmission Services

PJM © 2014 50
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

F: Energy Transaction Services


PJM
PJM Member PJM
Member PJM Neighboring
Regional Member
Information Services Load Member Control
Transmission Generating
Serving Marketer Areas
Owner Entity
Entity
Inputs to PJM

F.1 External Energy Transactions via ExSchedule X X


Non-PJM Energy Transactions (Wheels, etc.)
F.2 [submitted by neighboring control areas] via X
ExSchedule
Updates / Additions to Energy Transaction
F.3 X X X
Schedule via ExSchedule and NERC tag

F.4 Internal Energy Transactions via InSchedules X

Outputs from PJM


External Energy Transactions [collectively
F.5 confirmed by PJM & communicated to X X X
neighboring control areas] via ExSchedule
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 7: Energy Transaction Services

PJM © 2014 51
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

G: Long-term Planning Services


PJM
PJM Member PJM
Member PJM Neighboring
Regional Member
Information Services Load Member Control
Transmission Generating
Serving Marketer Areas
Owner Entity
Entity
Inputs to PJM
G.1 Capacity Information (spreadsheets) X
G.2 Load Information (spreadsheets) X
G.3 Load Flow Information X
G.4 Short Circuit Information X
G.5 Dynamics Information X 1
G.6 LAS Load Information X
Generator Events Information (GADS dataset)
G.7 X 1
[submitted by plant operations]
PROMOD information File (Generation Production
G.8 Cost Information) [submitted by generation X 1
planning into central planning database]
Generation Planning Maintenance Outage Reports
G.9 X 1
[compiled from transmission planning tools]
Long-term Capacity Planning Information
G.10 X
[submitted by transmission planning]
Performance Adequacy Assessments (financial
G.11 X X X X
Studies)
Generator Planning Study [distributed to
G.12 X O O O
committee members]
Supplemental Agreement (Forecast Obligation)
G.13 X O O O
[distributed to committee members]
G.14 LAS Report [submitted to Reliability Committee] X O
G.15 GORP Reports [distributed to generation planning] X O
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 8: Long-term Planning Services

PJM © 2014 52
Revision 26, Effective Date: 04/11/2014
Manual 01: Control Center Requirements
Attachment A: Information Access Matrix

H: PJM Administration Services

Information Services PJM Member PJM PJM PJM Neighboring


Regional Member Member Member- Control
Transmission Generating Load Marketer Areas
Owner Entity Serving
Entity
Outputs from PJM
H.1 PJM Information [on PJM Web site] X X X X X

H.2 RTO Information [on PJM Web site] X X X X X

H.3 FERC Filings [on PJM Web site] X X X X X

H.4 Training Information [on PJM Web site] X X X X X

H.5 Emergency Information [on PJM Web site] X X X X X

H.6 General Administration Information X X X X X


[distributed via fax to all participants]
H.7 Regulatory Reporting (FERC 714, 715; EIA X X X X
411)
Key:
X - Required Service
O - Optional Service
1 - Mandatory For All Generation Within the PJM RTO
2 - Mandatory For Unit Specific Generation Bidding
3 - Mandatory For All Capacity Resources
4 - System Reliability Information Only
5 - Mandatory For Joint-Owned Unit Owners
6 - Mandatory If Not Attainable From Existing Telemetry
7 - Mandatory For Generators Offering Regulation

Exhibit 9: PJM Administration Services

PJM © 2014 53
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Attachment B: Schedule of Data Submittals

Attachment B: Schedule of Data Submittals


In order for PJM to provide satisfactory evidence to demonstrate compliance, PJM members
are required to provide the following information to PJM on a frequency noted below

Standard Reference To be Submitted Frequency and Date


TOP–006-2R6 Tie line meter accuracy for each tie line. (Annual)Recommend
Submittal to be provided via PERCS September 30
website.
EOP-003-1 UFLS data (similar to current process for (Annual)
R2 annual request of information). Submittal to Recommend
be provided via PERCS website.
May 1
EOP-003-1 How each TO plans to implement load (Annual)
R8 reduction in sufficient time and amount if Recommend
directed by PJM. Submittal to be provided
March 1
via PERCS website.
EOP-005-2 Assurance that their personnel have been (Annual)
R10 trained annually in the implementation of Recommend
the Restoration Plan and that they have
December 31
participated in restoration exercises with
auditable records that could be obtained
upon request by PJM. Response can just
be an affirmative confirmation. Assurance
could be made by TOs via submittals
provided via PERCS website
EOP-005-2 Submit TO Restoration Plan, Ensure (Annual)
R3 Annual Review is noted in plan revision Within Annual
history section. Submittal to be provided Definition of last
via eDART Black Start application. submittal – per table 1
of Attachment G of M-
36
EOP-005-2 Submit TO changed System Restoration Within 90 days of
R4 Plan via eDART Black Start application if unplanned changes or
conditions of EOP-005, R4 are met before planned
changes that affect
System Restoration
Plan
EOP 008-1 Coordinate and submit a TO backup test (Annual)
R7 with PJM and provide evidence of its Recommend
performance. Submittal to be provided via
September 30
PERCS website.
EOP-008-1 Certification to PJM that the TO Operating (Annual)
R5 Plan for backup functionality has been Recommend
reviewed in its entirety and updated
December 31
appropriately. Such review effort should
be noted in plan revision history section.

PJM © 2014 54
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Attachment B: Schedule of Data Submittals
Response can just be an affirmative
confirmation. Submittal to be provided via
PERCS website.
EOP-008-1 Certification to PJM of changes to the TO Within 60 days of any
R5.1 Operating Plan for backup functionality. changes
Submittal to be provided via PERCS
website.

PJM © 2014 55
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Attachment C: Telecommunication Outages

Attachment C: Notification of Member Company System Outages


1. Members and PJM should provide an email coordination notice *24 business hours
in advance of significant system changes that could affect ICCP data link
communications or the data exchange with PJM.
a. Data Set Switches (this does not include database updates, editing data
exchange lists, etc. unless they include an outage)
b. Significant Software Enhancements
c. Communication line outages
d. Backup center testing
e. Failovers to alternate sites
f. ICCP server failovers.
g. Network and Firewall maintenance
h. RTU outages or changes to RTU data sent to PJM for RTUs connected to EHV
(345kv and above) facilities.
i. 1 day notice required.
2. The PJM EMS Networking group will coordinate any technical details, additional
support, etc. with the member company.
3. Members providing notification should send it to the following email address
([email protected] ). In an emergency, call the PJM Support Center at 610-666-
8886 or the Dispatch Supervisor at 610-666-8806.
4. The notification should include:
 The action being taken by the member company (see 1 above)
 Planned length and expected time of the outage
 Potential impact to PJM
 Member contact information
5. Member Company System Operator should coordinate final outage with the PJM
Dispatch Supervisor (610-666-8806) 15 minutes prior to the event.
 PJM will communicate any additional system conditions which would cause the
outage to affect system reliability even if the conditions are not directly related to the
requesting company. This communication can be through either a PJM Dispatcher or
a member of the EMS Networking group working with the impacted member
company. The communication will not contain any information that can identify
another member company but will contain enough information to let the affected
member company understand the severity of the situation.
 PJM fully understands the logistics and economic effect a delay or postponement
can have on a member company. If the member company wishes to challenge or
contest the delay or postponement, they should contact the PJM Shift Supervisor.

PJM © 2014 56
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Attachment C: Telecommunication Outages
6. PJM will notify member companies of PJM initiated outages via an email list at least
24 business hours in advance through a self-subscribing alias Exchange list.
Note: In order for a Member Company to receive an email alert of a PJM
generated outage, the company must have a permanent email address for
this purpose. PJM will send outages to that email address, not the address of
an individual person, since people can be re-assigned and change
responsibilities. Additionally, the member company must subscribe to the
outage list at [email protected].
7. PJM will follow-up significant outages with an All Call message 15 minutes prior to
the outage.

Emergency System Outages and Unscheduled System Outages


1. Member Company System Operator should immediately notify PJM when an event
has occurred to include EMS and State Estimator outages.
2. The member company should attempt to provide input into the expected length of the
outage.
3. Member Company should notify PJM when system has returned to normal.
4. The PJM Manual 13, Emergency Operations, should be followed for all Emergency
System Outages.

Outage Tracking

1. All outages (planned and unplanned) causing link reliability to drop below 99.8% in a
24 hour period will be reported and tracked with a cause code by PJM.
2. In the event that PJM detects a member outage of one hour or greater, PJM will
immediately email the appropriate SIS representative in order to alert that
representative and facilitate determination of outage details.
3. The following information items will be tracked for outages:
a. Company Identifier (3 letter)
b. Outage length (in minutes)
c. Cause code (see table below):
Code Description
PTV PJM Telecom Vendor
MTV Member Telecom Vendor
PPO PJM Planned Outage
MPO Member Company Planned Outage
PUO PJM Unplanned Outage
MUO Member Company Unplanned Outage
OTH Other

PJM © 2014 57
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

Revision History
Revision 25 (09/26/2013):
 Major changes to Section 5.3.5 Tie Line Telemetry Specification to provide more
detailed requirements for Tie Line Telemetry.
 Miscellaneous changes to support Section 5.3.5 (minor change to 5.3, deleted 5.3.7)
 Changed numbering for sections 5.5 through 5.7 to make them subsections under
Section 5.4 Meter Accuracy Standards.
 Major changes to Attachment B to remove redundant text and streamline table. EOP-
005-2 and EOP-008-1 requirements updated in the table.
Revision 24 (08/01/2013):
 Added Section on 2.5.7 - Disclosure of EMS Data to Transmission Owners
 3.2.3 Modified to clarify if manual approach is impractical
 4.2.4 Modified keypad selection
 Attachment A - added reference for PJM related applications to inputs and outputs;
added additional items per member input

Revision 23 (06/01/2013):
 Revisions for Curtailment Service Provider (CSP) dispatch instruction two way web
service communications. (Section 1.9)

Revision 22 (2/28/2013):
 Administrative Change: Updated all references of “eSchedules” to “InSchedules”

Revision 21 (04/26/2012):
 Removed references to BUCC throughout the Man.
 Section 1 – Added eLRS, SCED, and removed UDS and HIS due to AC2
Implementation
o Added CFE (Communications Front End)
o HIS is still in the AC2 EMS, but it will not be used due to PJM’s preference to PI
for visualizations.
o Modes of Operation Options listed
o EMS Support Systems Listed
 1.1 Changes due to BUCC Elimination and AC2 Implementation
 1.2 Removed SCADA, added GMS
 1.3 Data Historian replaced with PI due to AC2 implementation
 1.9 Added eLRS

PJM © 2014 58
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

 2.2 Added ref for Planning section


 2.3.1 Clarified unknown state to match Man 3.
 2.5.1 Removed reference to Coal Pollution
 2.5.6 Removed references to BUCC and added AC1 and AC2
o Clarified Gen Owners design (removed “multiple” and added AC1, AC2, Man,
and GMS)
 2.7 Added PJM requirement to monitor system during transition to B/U facility
 3.2.1 Changed Frame Relay to MPLS
 3.2.4 Added MPLS and removed ref to Back Up
 3.3.2 Added MPLS
 3.4 AC2 Clarity for “Backup”
 4.2.3 Removed references to Customer Relations Dept.
 5.5 Changed para ref for Billing Meters
 5.8.3 Replaced UDS with SCED
 Attch “B” – Added EOP 008 R1.5 to Table,
 Attch “B” – Changed ref for TO Backup Capability Plan
 Attch “C” – Clarified RTU outage reporting (24 hrs to 1 day for consistency)

Revision 20 (03/15/2011):
 2.3.1 – Added 30 minute time limit to notification.
 2.5.6 – Added Member TO training responsibilities and EMS configuration changes
 5.8.1 – Added requirement for BA annual check of Fqcy and Time Error meters
 Attch B – Added months for submittals and changed Ref’s for Tie Line meter checks.
Reference cleanup.
 3.5 – corrected typo for acquisition frequency
 5.7 – added clarity to percentages
 Changed “Self Certification” to Submittals Attch “B”
 Added Table to Attch “B”

Revision 19 (03/15/2011):
 Sections 1 & 2 – Updated references to Manuals
 2.3.1 – Clarified member TO requirements for security analysis capability
 2.4 – Clarified 3 part communication
 2.7 – Clarified back up capability

PJM © 2014 59
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

 4.2.4 – Clarified 3 part communication


 5.8.1 – Updated references to Manuals
 Attch A, H2 – Removed MAAC
 Attch C5 – Clarified process.

Revision 18 (01/24/2011):
 Added reference to Manual 40 in section 2.6
 Revision to 2.7 – changed 2 hours to 1 hour (EOP-008)
 Revisions to 4.2.4 for 3 part communications

Revision 17 (01/01/2010)
 Corrected section 2.7 from PJM EMS to transmission owner EMS and clarified timing
requirement – within 2 hours
 Updated Section 3.2.3 changing 500 kV to 345 kV
 Updated language in section 4.2.4 to include a PJM definition of Directives
 Updated section 5.3.3 – generators (less than 500 kV) can be metered from high
side or low side of GSU.
 Updated tables in Attachment A
 Added Attachment C – notification for system outages affecting telecommunications
to include EMS and State Estimator outages.
Correction made January 4, 2010 to fix subsection numbering in section 4.2 and the table of
contents.

Revision 16 (10/05/2009)
 Removed Attachment B – Nuclear Protocols – will be contained in M39 to be
published 10/1/09
 Added Attachment B – Annual Data Submissions for Transmission Owners
 Added Section 2.7 – Backup Capability Requirements for Transmission Owners
 Updated language in Section 4.2.3 for 3 part communications and use of the term
“directives”

Revision 15 (06/01/2009)
 PJM has conducted the 2009 annual review and update based on this effective date

Revision 14 (05/09/2008)

PJM © 2014 60
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

 3 part communications guidance


 Annual review and update of complete manual for 2008.

Revision 13 (05/15/07)
Section 2: Control Center Requirements
Moved Training and Certification requirements to new Manual M40 Certification and
Training Requirements.
Section 3: Communications & Data Exchange Requirements
 Provided language related to data communication outages and reporting.
 Provided additional clarity regarding satellite phone requirements.
Attachment C: PJM System Operator Training Requirements
Moved to new Manual M40 Certification and Training Requirements
Attachment D: Continuing Education Hour (CEH) Tracking Process
Moved to new Manual M40 Certification and Training Requirements.
Introduction trimmed to eliminate redundant information.
List of PJM Manuals exhibit removed, with directions given to PJM Web site where all the
manuals can be found.
Section 4: Meter Accuracy Standards permanently moved to the end of the manual.

Revision 12 (09/13/06)
Section 2: Control Center Requirements
 Provided additional clarity regarding “Backup Recovery Procedures.”
Attachment C: PJM System Operator Training Requirements
 Added more details to compliance monitoring, levels and process for noncompliance.
Attachment D: Continuing Education Hour (CEH) Tracking Process
 Made revisions to reporting forms.

Revision 11 (06/19/06)
Attachment C: PJM System Operator Training Requirements
 Added Training Requirements for Demand Resources providing Ancillary Services.
 Deleted obsolete paragraph on page 79 regarding certification of incumbent system
operators.
Section 1 (PJM Systems), Page 8: Removed word “analog”.

PJM © 2014 61
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

Revision 10 (02/07/06)
Added Attachment D: Continuing Education Hour (CEH) Tracking
Added provision to maintain PJM System Operator Certification through CEH’s to
Attachment C.
Miscellaneous minor revisions to correct current naming of Member Training offerings, and
references to NERC policies.
Revisions were made on the following pages: 20-22, 27, 39, 54, 57, 62, 69, 80-83, 86-89, 91
and 102-118.

Revision 09 (9/01/05)
Added Attachment C: PJM System Operator Training Requirements.
Added Nuclear Power Plant voltage notification.

Revision 08 (1/01/05)
Miscellaneous member comments and reflect the retirement of the Back Up Analog Control
System.

Revision 07 (5/15/04)
Miscellaneous member comments, not incorporated in Revision 6
Updated PJM List of Manuals
Revision 06 (3/31/04)
Added descriptions of the Generation Management System (GMS), the Process Control
Test (PCT) System, the Back-Up Control Center () System, the PJM SCADA System, the
OSI PI Data Historian System and clarified member obligations for ICCP communications
including data integrity requirements and transmission monitoring requirements.

Revision 05 (12/31/03)
Added Attachment B: Nuclear Plant Communications Protocol, December 17, 2003

Revision 04 (05/01/03)
Revised Section 3: Communications & Data Exchange Requirements. Updated to include
satellite phone requirements for generation operator control centers.

Revision 03 (04/04/03)
Complete revision of manual to reflect PJM Standards and Systems.

PJM © 2014 62
Revision 26, Effective Date: 04/11/2014
Manual 01: Data Management Modeling
Revision History

Revision 02 (12/31/00)
Removed Attachment A: Definitions and Abbreviations. Attachment A is being developed
into a ‘new’ PJM Manual for Definitions and Acronyms (M35).

Revision 01 (04/01/98)
Attachment B: Information Access Matrix
Exhibit B.7: Grid Accounting Services revised to change "Market Clearing Price" to
"Locational Marginal Price."

Revision 00 (07/30/97)
This revision is the preliminary draft of the PJM Manual for Control Center Requirements.

PJM © 2014 63
Revision 26, Effective Date: 04/11/2014

You might also like