Concerete Report

1) The document provides a concrete progress report from January 24th to January 30th 2021 for a construction project. 2) It lists 38 structures along with the required quantity of concrete, quantity poured up to January 23rd and 30th, and percentage of work completed. 3) Most structures have over 95% of the concrete work completed, with a few structures between 40-65% completed and total concrete work over 97% completed as of January 30th.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views4 pages

Concerete Report

1) The document provides a concrete progress report from January 24th to January 30th 2021 for a construction project. 2) It lists 38 structures along with the required quantity of concrete, quantity poured up to January 23rd and 30th, and percentage of work completed. 3) Most structures have over 95% of the concrete work completed, with a few structures between 40-65% completed and total concrete work over 97% completed as of January 30th.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

CONCERETE REPORT

From 24
Comp. Qty. Comp. Qty.
th Jan to
Sr.No Structure Name Unit Req. Qty upto 23th 30th upto 30th
Jan 2021 Jan 2021
Jan2021

1 LimeStone Crusher House Cum 2233 2230.1 2230.1


2 LimeStone Storage & Transport Cum 1811 1810 1810
3 Additive & Coal Storage & Transport Cum 4055 4198.15 4198.15
4 Raw Mill Feed Hopper Cum 350 374.3 34.5 408.8
5 Raw Mill building Cum 3004 3100.3 3100.3
6 Coal mill Buildng Cum 1165 1167.2 52 1219.2
7 Raw Mill Silo Cum 1746 1845.2 1845.2
8 Preheater Cum 3238 3217.7 3217.7
9 Kiln Pier Cum 634 661.7 661.7
10 Alkali Bypass Cum 218 255 255
11 Clinker Cooler Cum 1877 1800.4 1800.4
12 Clinker & low Alkali Silo Cum 5626 5486.7 5486.7
13 Cement Mill Feed Hopper Cum 957 945 945
14 Gypsum Intake & Crusher Cum 613 606.5 606.5
15 Cement Mill building & Bag House Cum 1695 1676 1676
16 Cement Silo Cum 3040 3004 3004
17 Packing Plant Cum 1478 1524.7 1524.7
18 Switch Yard Cum 112 205.6 205.6
19 MRSS Building Cum 242 331.2 14.2 345.4
20 LC-1 Cum 162 186.9 186.9
21 LC-4 Cum 432 459.5 459.5
22 LC-5 Cum 162 178 178
23 CCR Building Cum 1183 1280.5 1280.5
24 Cable gallery Cum 445 438 438
25 TT-1 Cum 61 66 66
26 TT-2 Cum 56 58.2 58.2
27 TT-3 Cum 120 121 121
28 TT-4 Cum 146 154 154
29 TT-5 Cum 144 143 143
30 Conveyor Cum 744 930 930
31 WHRS (PH Boiler) Cum 447 407.3 407.3
32 WHRS (Cooler Area) Cum 164 164 164
33 TG Building Cum 757 882.6 882.6
34 Water Tank Cum 369 323 323
35 Raw Water Tank Cum 3100 2023.5 2023.5
36 Compressor Room Cum 165 199.8 8 207.8
37 Cooling Tower Cum 452 244.3 3.8 248.1
38 Weigh Bridge Cum 20 20 20
39 Workshop & Store Cum 670 201.3 70.9 272.2
40 Centeen Cum 160 61 2 63
Total 44053.00 42800.25 185.40 43167.05
% of work % of work
Completed Completed
Balance on on
23.01.2021 16.01.2021

10.2 99.87 99.54


1 99.94 99.94
(+)135.55 100.00 100.00
(+)58.8 100.00 100.00
(+)95.3 100.00 100.00
(+54.2) 100.00 100.00
(+) 99.2 100.00 100.00
43.9 99.37 99.37
(+) 14.7 100.00 100.00
(+) 37 100.00 100.00
76.6 95.92 95.92
139.3 97.52 97.04
12 98.75 98.75
6.5 98.94 98.94
19 98.88 98.88
36 98.82 98.82
(+)46.2 100.00 100.00
(+)83 100.00 100.00
(+)83.5 100.00 100.00
(+)69.1 100.00 100.00
(+)27.5 100.00 100.00
(+)38 100.00 100.00
(+)97.5 100.00 100.00
7 98.43 98.43
(+)5 100.00 100.00
2.2 103.93 103.93
(+)1 100.83 100.83
(+) 8 100.00 100.00
1 99.31 99.31
(+)42 100.00 100.00
39.7 100.00 100.00
0 100.00 100.00
(+)206.2 100.00 100.00
46 87.53 87.53
1076.5 65.27 65.27
(+)69.3 100.00 100.00
203.9 54.89 37.35
0 100.00 100.00
397.8 40.63 22.01
97 39.38 27.00
878.10 97.321 96.84
Miscellaneous manpower
Present Manpower at Site