Open navigation menu
Close suggestions
Search
Search
en
Change Language
Upload
Sign in
Sign in
Download free for days
0 ratings
0% found this document useful (0 votes)
74 views
2 pages
NEC3 Cl60
NEC3 Cl60
Uploaded by
Brian Ernest Regalado
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download
Save
Save NEC3 Cl60 For Later
0%
0% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
0 ratings
0% found this document useful (0 votes)
74 views
2 pages
NEC3 Cl60
NEC3 Cl60
Uploaded by
Brian Ernest Regalado
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Carousel Previous
Carousel Next
Download
Save
Save NEC3 Cl60 For Later
0%
0% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
Download now
Download
You are on page 1
/ 2
Search
Fullscreen
Core Clauses NEC3 Compensation events Cost are alculateg ‘amounts s for al Compensation events 60 60.1 The following are compensation events. (1) The Project Manager gives an instruction changing the Works Information except * a change made in order to accept a Defect or * @ change to the Works Information provided by the Contractor for his design which is made either at his request or to comply with other Works Information provided by the Employer. (2) The Employer does not allow access to and use of a part of the Site by the later of its access date and the date shown on the Accepted Programme. (3) The Employer does not provide something which he is to provide by the date for providing it shown on the Accepted Programme, (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date. (5) The Employer or Others ‘+ do not work within the times shown on the Accepted Programme, '* do not work within the conditions stated in the Works Information or ‘* carry out work on the Site that is not stated in the Works Information, (6) The Project Manager or the Supervisor does not reply to a communication from the Contractor within the period required by this contract. (7) The Project Manager gives an instruction for dealing with an object of value or of historical or other interest found within the Site. (8) The Project Manager or the Supervisor changes a decision which he has previously communicated to the Contractor. (9) The Project Manager withholds an acceptance (other than acceptance of ‘@ quotation for acceleration or for not correcting a Defect) for a reason not stated in this contract. (10) The Supervisor instructs the Contractor to search for a Defect and no Defect is found unless the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection, (11) A test or inspection done by the Supervisor causes unnecessary delay. (12) The Contractor encounters physical conditions which * are within the Site, * are not weather conditions and * an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreason- able for him to have allowed for them. Only the difference between the physical conditions encountered and those {for which it would have been reasonable to have allowed is taken into account in assessing a compensation event. (43) A weather measurement is recorded * within a calendar month, ‘+ before the Completion Date for the whole of the works and ** at the place stated in the Contract Data the value of which, by comparison with the weather data, is shown to occur on average less frequently than once in ten years, contract seccontract.com © copyright nec 2013 15, a f msnCao Coes main option clauses ‘secondary option clauses cost components contract, data = NEC Engineering and Construction Contract Notifying compensation events 60.2 603 61 614 61.2 613 Only the difference between the weather measurement and the weather whic ‘the weather data show to occur on average less frequently than once in te years is taken into account in assessing a compensation event. (14) An event which is an Employer's risk stated in this contract. (15) The Project Manager certifies take over of a part of the works befor both Completion and the Completion Date. (16) The Employer does not provide materials, facilities and samples for test and inspections as stated in the Works Information. (17) The Project Manager notifies a correction to an assumption which he he stated about a compensation event. (48) A breach of contract by the Employer which is not one of the othe compensation events in this contract. (19) An event which ‘+ stops the Contractor completing the works or ‘+ stops the Contractor completing the works by the date shown on th Accepted Programme, and which * neither Party could prevent, * an experienced contractor would have judged at the Contract Date © have such a small chance of occurring that it would have been unreaso able for him to have allowed for it and * is not one of the other compensation events stated in this contract. In judging the physical conditions for the purpose of assessing a compens= tion event, the Contractor is assumed to have taken into account * the Site Information, * publicly available information referred to in the Site Information, * information obtainable from a visual inspection of the Site and * other information which an experienced contractor could reasonably & expected to have or to obtain. If there is an ambiguity or inconsistency within the Site Information (include ‘the information referred to in it), the Contractor is assumed to have taken i account the physical conditions more favourable to doing the work. For compensation events which arise from the Project Manager or the Super sor giving an instruction, issuing a certificate, changing an earlier decision correcting an assumption, the Project Manager notifies the Contractor of @ compensation event at the time of that communication. He also instructs ® Contractor to submit quotations, unless the event arises from a fault of © Contractor or quotations have already been submitted. The Contractor 0. the instruction or changed decision into effect. The Project Manager may instruct the Contractor to submit quotations for proposed instruction or a proposed changed decision. The Contractor does. put a proposed instruction ar a proposed changed decision into effect. The Contractor notifies the Project Manager of an event which has happen or which he expects to happen as a compensation event if ‘= the Contractor believes that the event is a compensation event and ‘+ the Project Manager has not notified the event to the Contractor. If the Contractor does not notify a compensation event within eight weeks becoming aware of the event, he is not entitied to a change in the Prices, Completion Date or a Key Date unless the event arises from the Project M ‘ager or the Supervisor giving an instruction, issuing a certificate, changing earlier decision or correcting an assumption. 16 copyright nec 2013, www.neccontract.c
You might also like
NEC4 Assessment
PDF
No ratings yet
NEC4 Assessment
21 pages
NEC4 Compensation Event and Delay Analysis
PDF
No ratings yet
NEC4 Compensation Event and Delay Analysis
16 pages
NEC4 Compensation Event Template
PDF
100% (1)
NEC4 Compensation Event Template
8 pages
6. Compensation Events_revised
PDF
No ratings yet
6. Compensation Events_revised
74 pages
Full Set - CV04 - Nec3
PDF
No ratings yet
Full Set - CV04 - Nec3
258 pages
NEC4 Stage 2 Question 2 Final
PDF
50% (2)
NEC4 Stage 2 Question 2 Final
6 pages
Tested Areas Model Questions & Answers- New
PDF
No ratings yet
Tested Areas Model Questions & Answers- New
73 pages
Contract Changes Management Nov.2016
PDF
No ratings yet
Contract Changes Management Nov.2016
24 pages
Pre-reading CE Workshop 2022 HANDOUTS
PDF
No ratings yet
Pre-reading CE Workshop 2022 HANDOUTS
18 pages
NEC 3 Clauses
PDF
No ratings yet
NEC 3 Clauses
53 pages
Question 3
PDF
100% (1)
Question 3
2 pages
Schedule Impact Analysis
PDF
No ratings yet
Schedule Impact Analysis
39 pages
Lecture 5
PDF
No ratings yet
Lecture 5
32 pages
NEC 3 Engineering and Construction Contract - Grupo 4
PDF
No ratings yet
NEC 3 Engineering and Construction Contract - Grupo 4
2 pages
Contract Changes Management
PDF
No ratings yet
Contract Changes Management
29 pages
NEC4 Stage 2 Question 1 Final
PDF
No ratings yet
NEC4 Stage 2 Question 1 Final
5 pages
Chapter 4 Issues During Construction Phase F23
PDF
No ratings yet
Chapter 4 Issues During Construction Phase F23
28 pages
NEC 3 Comp Events
PDF
No ratings yet
NEC 3 Comp Events
27 pages
Contract Administration and Supervision
PDF
No ratings yet
Contract Administration and Supervision
40 pages
Nec4 Ecc Practice Note 1 1 - Web
PDF
No ratings yet
Nec4 Ecc Practice Note 1 1 - Web
2 pages
NEC3 Cl61 64
PDF
No ratings yet
NEC3 Cl61 64
4 pages
NEC101-Compensation-Events-Webinar-Slides
PDF
No ratings yet
NEC101-Compensation-Events-Webinar-Slides
17 pages
Healthy buildings - unhealthy contract_ _ Simmons & SimmonsSS
PDF
No ratings yet
Healthy buildings - unhealthy contract_ _ Simmons & SimmonsSS
8 pages
Pricing Compensation Events Under Nec3
PDF
No ratings yet
Pricing Compensation Events Under Nec3
3 pages
Dadcic 61972 077
PDF
No ratings yet
Dadcic 61972 077
6 pages
Insight - June - 2022 - Accepted Programmes
PDF
No ratings yet
Insight - June - 2022 - Accepted Programmes
9 pages
NEC4 - Part 2 - Ling (W Ans) Q5
PDF
100% (2)
NEC4 - Part 2 - Ling (W Ans) Q5
6 pages
All Change in The Change Clause: NEC3 To NEC4 Comparison of Core Clause 6 Compensation Events
PDF
No ratings yet
All Change in The Change Clause: NEC3 To NEC4 Comparison of Core Clause 6 Compensation Events
20 pages
5-Myths-Misconceptions-and-Misunderstandings-Glenn-Hide
PDF
No ratings yet
5-Myths-Misconceptions-and-Misunderstandings-Glenn-Hide
13 pages
NEC Course Questions
PDF
100% (3)
NEC Course Questions
5 pages
NEC3 ECC Compensation Events workflow
PDF
No ratings yet
NEC3 ECC Compensation Events workflow
10 pages
PRO-FAT-0124 Rev02 Notification of Compensation Event
PDF
No ratings yet
PRO-FAT-0124 Rev02 Notification of Compensation Event
7 pages
Compensation Events and Claims: Presented by Prof. Khem Dallakoti
PDF
No ratings yet
Compensation Events and Claims: Presented by Prof. Khem Dallakoti
19 pages
Ce 6.1.3
PDF
No ratings yet
Ce 6.1.3
9 pages
Fafc Nec3 When Is The PM Obliged To Notify A Ce and Consq of His Failure To Do So April2011 Rev02
PDF
No ratings yet
Fafc Nec3 When Is The PM Obliged To Notify A Ce and Consq of His Failure To Do So April2011 Rev02
5 pages
A Practical Guide To Compensation Events - Chris Holden
PDF
No ratings yet
A Practical Guide To Compensation Events - Chris Holden
65 pages
Wtaccalb41 Leg 5
PDF
No ratings yet
Wtaccalb41 Leg 5
12 pages
NEC4 Early Warnings v Compensation Events 1748212765
PDF
No ratings yet
NEC4 Early Warnings v Compensation Events 1748212765
8 pages
Insight September 2024
PDF
No ratings yet
Insight September 2024
7 pages
NEC4 Q5
PDF
No ratings yet
NEC4 Q5
5 pages
CE Process Map
PDF
No ratings yet
CE Process Map
1 page
Compensation Events Explained
PDF
No ratings yet
Compensation Events Explained
2 pages
NEC4 Q4
PDF
No ratings yet
NEC4 Q4
4 pages
Compensation Events
PDF
No ratings yet
Compensation Events
4 pages
Compensation Events
PDF
No ratings yet
Compensation Events
2 pages
NEC4 Stage 2 Question 5 Final
PDF
No ratings yet
NEC4 Stage 2 Question 5 Final
4 pages
NEC Core Clause
PDF
No ratings yet
NEC Core Clause
24 pages
NEC 3 Engineering and Construction Contract - Grupo 1
PDF
No ratings yet
NEC 3 Engineering and Construction Contract - Grupo 1
3 pages
Request For Information Log: Return To Table of Contents
PDF
No ratings yet
Request For Information Log: Return To Table of Contents
5 pages
07 ECS NOTIFICATION OF COMPENSATION EVENT Templates
PDF
No ratings yet
07 ECS NOTIFICATION OF COMPENSATION EVENT Templates
1 page
Contract 12 - NEC3 - Early Warning and Compensation Events
PDF
100% (1)
Contract 12 - NEC3 - Early Warning and Compensation Events
5 pages
CE
PDF
No ratings yet
CE
2 pages
A Practical Guide To Compensation Events
PDF
No ratings yet
A Practical Guide To Compensation Events
2 pages
CECA NEC4 Bulletin No.4 Pricing Compensation Events and The Use of Assumptions April 2021
PDF
No ratings yet
CECA NEC4 Bulletin No.4 Pricing Compensation Events and The Use of Assumptions April 2021
4 pages
NEC 3 - When Is The Project Manager Obliged To Notify A Compensation Event, and What Are The Effects of His Failure To Do So
PDF
No ratings yet
NEC 3 - When Is The Project Manager Obliged To Notify A Compensation Event, and What Are The Effects of His Failure To Do So
3 pages
Question 4
PDF
No ratings yet
Question 4
2 pages
Question 2
PDF
No ratings yet
Question 2
2 pages
Questions 1
PDF
No ratings yet
Questions 1
4 pages