100% found this document useful (1 vote)
478 views4 pages

BOQ of Drain Wall and Septic Tank

The document provides a bill of quantities (BOQ) for a 10 meter surface drain. It includes 6 items describing the excavation, brickwork, concrete work, plastering, and their quantities in cubic meters or square meters. It then provides a rate analysis with unit rates and totals. The estimated cost per meter is Rs. 67.81.

Uploaded by

Uzair Mukhtar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
478 views4 pages

BOQ of Drain Wall and Septic Tank

The document provides a bill of quantities (BOQ) for a 10 meter surface drain. It includes 6 items describing the excavation, brickwork, concrete work, plastering, and their quantities in cubic meters or square meters. It then provides a rate analysis with unit rates and totals. The estimated cost per meter is Rs. 67.81.

Uploaded by

Uzair Mukhtar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Prepare an estimate of a surface drain for 10meter length from the given

drawing

BOQ (Bill of Quantity)


Sr. Description No Length Width Height Quantity Unit
. (m) (m) (m) (m) (m3)
1. Excavation 1 10 0.4 0.28 1.12 m3
2. Brickwork in 1:6 2 10 0.1 0.2 0.4 m3
cement mortar
3. Concrete 1:4:8 in 1 10 0.4 0.08 0.32 m3
foundation
4. Concrete 1:2:4 in semi- 1 10 0.2 0.1 0.2 m3
circle
5. Deduction semi-circle 1 10 1/2xΠx(0.1)2 0.157 m3
Tota 0.04 m3
l
6 12mm cement plaster 1 10 2(0.1 + 0.1) Πx0.1 1.26 m2
1:4 =0.4 =0.314
RATE ANALYSIS

Sr. Description Unit Quantity Rate Amount


1. Excavation Cu.m 1.12 Rs. 350 Rs. 392
2. Concrete 1:4:8 Cu.m 0.32 Rs. 300 Rs. 96
3. Concrete 1:2:4 Cu.m 0.043 Rs.450 Rs. 19.35
4. Brick work Cu.m 0.4 Rs.320 Rs. 128
5. Plaster 1:4 Sq.m 1.26 Rs.83 Rs. 10.45
Total Rs. 645.8

5% Contingencies = 5/100x645.8 = Rs. 32.29


Total = Rs. 678.09
Per meter cost = Rs. 67.81 per meter
Prepare a BOQ of Septic tank from given drawing
BOQ
Sr. Description No. Length Breath Height Quantity Unit
1. Excavation 1 11.5 5.5 5.67 358.63 Cu.ft
2. P.C.C in foundation bed 1 11.5 5.5 0.67 42.378 Cu.ft
3. Brickwork outer wall 1 29.55 0.375 5 55.133 Cu.ft
4. Brickwork baffle wall 1 4 0.375 4 6 Cu.ft
5.A Plaster ½” 1:4 outer wall inner 1 27.25 - 5 136.25 Sq.ft
face
B. Baffle wall plaster 2 4 - 4 16 Sq.ft
6. Sludge chamber P.C.C (1:2:4) 1 6 4 0.125 3 Cu.ft
7. R.C.C slab (1:2:4) 1 10.75 4.75 0.33 16.85 Cu.ft
8. Deduction for wash out cover 1 Π/4x22=Π 0.33 1.03 Cu.ft
9. Man hole cover 1 1 Cu.ft