Prepare an estimate of a surface drain for 10meter length from the given
drawing
BOQ (Bill of Quantity)
Sr. Description No Length Width Height Quantity Unit
. (m) (m) (m) (m) (m3)
1. Excavation 1 10 0.4 0.28 1.12 m3
2. Brickwork in 1:6 2 10 0.1 0.2 0.4 m3
cement mortar
3. Concrete 1:4:8 in 1 10 0.4 0.08 0.32 m3
foundation
4. Concrete 1:2:4 in semi- 1 10 0.2 0.1 0.2 m3
circle
5. Deduction semi-circle 1 10 1/2xΠx(0.1)2 0.157 m3
Tota 0.04 m3
l
6 12mm cement plaster 1 10 2(0.1 + 0.1) Πx0.1 1.26 m2
1:4 =0.4 =0.314
RATE ANALYSIS
Sr. Description Unit Quantity Rate Amount
1. Excavation Cu.m 1.12 Rs. 350 Rs. 392
2. Concrete 1:4:8 Cu.m 0.32 Rs. 300 Rs. 96
3. Concrete 1:2:4 Cu.m 0.043 Rs.450 Rs. 19.35
4. Brick work Cu.m 0.4 Rs.320 Rs. 128
5. Plaster 1:4 Sq.m 1.26 Rs.83 Rs. 10.45
Total Rs. 645.8
5% Contingencies = 5/100x645.8 = Rs. 32.29
Total = Rs. 678.09
Per meter cost = Rs. 67.81 per meter
Prepare a BOQ of Septic tank from given drawing
BOQ
Sr. Description No. Length Breath Height Quantity Unit
1. Excavation 1 11.5 5.5 5.67 358.63 Cu.ft
2. P.C.C in foundation bed 1 11.5 5.5 0.67 42.378 Cu.ft
3. Brickwork outer wall 1 29.55 0.375 5 55.133 Cu.ft
4. Brickwork baffle wall 1 4 0.375 4 6 Cu.ft
5.A Plaster ½” 1:4 outer wall inner 1 27.25 - 5 136.25 Sq.ft
face
B. Baffle wall plaster 2 4 - 4 16 Sq.ft
6. Sludge chamber P.C.C (1:2:4) 1 6 4 0.125 3 Cu.ft
7. R.C.C slab (1:2:4) 1 10.75 4.75 0.33 16.85 Cu.ft
8. Deduction for wash out cover 1 Π/4x22=Π 0.33 1.03 Cu.ft
9. Man hole cover 1 1 Cu.ft